JOSEPH M. FARLEY NUCLEAR PLANT UNIT 1 NARRATIVE
SUMMARY
OF OPERATIONS OCTOBER There were no unit shutdowns or significant power reductions during the month of October.
The following major safety-related maintenance was performed in the month of October:
1.
Performed miscellaneous corrective and preventive maintenance on diesel generators.
2.
Completed re-racking of Unit I spent fuel pool. High density storage racks have been installed to increase the capacity to 1407 fuel assemblies.
l 0
ck y
k
DOCKET NO.
50-348
~
UNIT 1
November 6, 1984
^
DATE COMPLETED BY J. D. Woodard TELEPHONE (205) 899-5156 M0ffill October. 1984 DAY AVERAGE DA!LY POWER LEVEL '
DAY
- VERACE DAILY POWER LEVEL (MWe Net)
(MWe Net) 826 806 g,
g7 2
829 gg 708
~3 829 19 nna 828 811 4
20 5
826 21 R09 821 809 6
g 819 7
23 810 8
818 24 811 9
770 812 818 10 26 814 819 11 27 814 0
12 3
807 i
820 13
- 9 gio 14 819 30 811 811 687 33 16 810 l
l 2 G UCDONS On this form:. list the aversge daily unit puwer levelin MWe-Net for e:ch d:y in the reporting month. Compute to
, the neste:t whole rnepwast.
(997) 1 l
l l
I I
OPERATING DATA REPORT DOCKET NO.
sn_1ag DATE 11 A RA l
COMPLETED BY J. D. Woodard TELEPHONE (?nsi R99-5156 OPERATING STATUS Joseph M. Farley - Unit 1 Notes
- 1. Unit Nm.
- 2. Reporting Period: noenhar 1996 (1) Cumulative data since
- 3. Licensed Thermal Power (MWt):
2652 12-1-77, date of 860 commercial operation.
- 4. Nameplate Rating (Gross MWe):
829
- 5. Design Electrical Rating (Net MWe):
- 6. Maximum Dependable Capacity (Gross MWe):
Rat R
- 7. Maximum Dependable Capacity (Net MWe):
797 1
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:
N/A N/A
- 9. Power Level To which Restricted.If Any (Net MWe):
- 10. Reasons For Restrictions. If Any:
N/A i
Cumulative This Month Yr..to-Date
- 11. Hours In Reporting Period 745 7.320 60,648
- 12. Number Of Hours Reactor Was Critical 745.0 5,541.8 40,665.0 0.0 3,650.0
- 13. Reactor Reserve Shutdown Hours nn
- 14. Hours Generator On-Line 745.0 5.457.0 lo.560.4
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Thermal Energy Generated (MWH) 1,949,788 14,001,907 100,103.433 632,706 4,514,896 31,857.906
- 17. Gross Electrical Energy Generated (MWH) 399'734 4.255.466 -
29,956,528.
- 18. Net Electrical Energy Generated (MWH)
- 19. Unit Service Factor 100.0 74.5 65.2 100.0 74.5 65.2
- 20. Unit Availability Factor 101.0 72,9 62.0
- 21. Unit Capacity Factor (Using MDC Net) 97*I
- 22. Unit Capacity Factor (Using DER Net) 70.1 59.6
- 23. Unit Forced Outage Rate 0.0 1.4 13.6
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration,.of Each):
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
- 26. Units In Test Status t Prior to Commercial Operation):
Forecast Achieved a
08-06-77 08-09-77 INITIAL CRITICALITY j
l INITIAL ELECTRICITY nn-?n_77 08-18-77 COMMERCIAL OPERATION 12-01-77 12-01-77 i
(4[77 )
)
i
L
)s J
s'
'.[
5d-348-UNITSilU1 DOWNS AND POWER REIM)CilONS DOCKET NO.
.J,M.
Farley - Unit.1 UNIT NAME DATE 6-84 D-'W" U #d CU#*-*- * "' '
REPORT MON 111 October. 1984 TELErilONE _"G.Q5) 899-5156 i
"r 5 s4 'E E
c re i
.E E g
5g Licenser Ev.
g4 Cause & Cussective 7,gx Event u 'l r]
Acti.us to N.e.
Date g
Eg g
h3 5
,C o
i8 h R*E'"' #
p,gy,,,g,c,,,,,,,
2 6
THERE WERE N0 la IT SI UTDOW ;S OR SIGNIFICANT PO.IE 1 REDUCTIC NS DURING THE MONTH OF OCTOBER, 4
t l
l t
i 3
3 4
F: Forced Reason:
Method:
Exhibit G -lasitucesons S: Stheduled A Equipmens Failure (Explain)
I Manual for Prepasasiam of Data u Maintenance e,iTest 2 Manual Scram.
Enisy Sheets for Licensee -
C Refueling 3 Autuniatic Scram.
Event Rep w (i.ER) File INURI G-D.Regulasiuy Resisiction 4 0 hcr (Emplaise) 0161) 4 E4)pesaius Tsaining A license Exandnasion F-Adminisisasive 5
G Opcaatiimal Essur (limplain)
Exhibit I - Same Sousee 19/77)
II Othe: (Emplain)
& m
f; Malling Address f
- Alabama Power Cornpany
' 600 North 18th Strsot Post Office Box 2641 f-Btrmingham, Alabma 35291 Telephone 205 783-6090 tff(
R. P. Mcdonald
[-
Senior Vice President
[
Flintridge Building AlabaritaPower ce s zwwe~ sa:..
November 9, 1984-Docket No. 50-348 Director, Office of Resource Management U. S. Nuclear Regulatory Commission -
Washington, D.C.
20555
Dear Sir:
RE: Joseph M. Farley Nuclear Plant Unit 1 Monthly Operating Data Report Attached are two (2) copies of the October 1984 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Unit 1, reouired by Section 6.9.1.10 of Appendix A of the Technical Specifications.
As requested by letter from Mr. John F. Stolz to Mr. Alan R. Barton, dated October 21, 1977, a " Narrative Summary of Operating Experience" is included in the attached report.
If you have any questions, please advise.
Yours very trul,
N f
f/
R. P. Mcdonald RPM /KWM: sam Enclosures xc: Director, IE (10 copies)
Director, RII (1 copy)
+o