Letter to R. Beedle Status Report on Study of Risk-Informed Changes to the Technical Requirements of 10 CFR Part 50 (Option 3) and Recommendations on risk-informed Changes to 10 CFR 50.44 (Combustible Gas Control)
ML003775521
Person / Time
Issue date: 12/08/2000
From: Thadani A
Office of Nuclear Regulatory Research
To: Ralph Beedle
Nuclear Energy Institute
References
SECY-00-0198
Download: ML003775521 (3)


Text

December 8, 2000 Ralph E. Beedle Senior Vice President and Chief Nuclear Officer, Nuclear Generation Nuclear Energy Institute 1776 I Street, NW Suite 400 Washington, DC 20006

SUBJECT:

STATUS REPORT ON STUDY OF RISK-INFORMED CHANGES TO THE TECHNICAL REQUIREMENTS OF 10 CFR PART 50 (OPTION 3) AND RECOMMENDATIONS ON RISK-INFORMED CHANGES TO 10 CFR 50.44 (COMBUSTIBLE GAS CONTROL)

Dear Mr. Beedle:

Your letter of November 17, 2000, to Chairman Meserve has been referred to me for response.

Your letter provided perspectives on several issues discussed in SECY-00-0198. These issues include:

  • selective implementation
  • the framework for risk-informing technical requirements
  • the inclusion of new special treatment requirements in Option 3.

The first two issues, backfit considerations and selective implementation, are currently under consideration by the Commission, including the views expressed in your letter. In regard to the remaining two issues, the framework provides the staff guidance for identifying and developing risk-informed changes to the technical requirements so that this effort is performed in a uniform, consistent and defensible manner. It is essentially complete and will only be refined based upon experience. Thus, we believe it is not detracting from OPTION 3, but rather providing consistency and direction. In SECY-99-264, risk-informed alternatives to the technical aspects of special treatment requirements is part of the scope of Option 3 which the Commission approved. This effort is being closely linked and integrated with the work being performed under Option 2.

We will continue to hold public meetings and public workshops as we move forward so that all stakeholders are informed of our progress and have the opportunity to provide input in a timely manner. If you have any questions, please do not hesitate to call me or contact Mary Drouin (301 415-6675, email mxd@nrc.gov).

Sincerely,

/RA MVFederline for/

Ashok C. Thadani, Director Office of Nuclear Regulatory Research

  • Previously concurred.

OFFICE PRAB/DRAA/RES PRAB/DRAA/RES DRAA/RES NAME *MDrouin *MCunningham mxd for *TKing DATE 12/01/00 12/01/00 12/01/00 OFFICE NRR NRR D/RES NAME *DMatthews *SCollins bws for AThadani mvf for DATE 12/05/00 12/06/00 12/07/00 / /00 NAME: g:\marys letter to nei on secy-198 dec 00.wpd Distribution: DRAA Chron PRAB r/f M. Drouin r/f M. Drouin M. Cunningham T. King D. Matthews S. Collins A. Thadani RES number ________,EDO Number G20000547 OAR in ADAMS? (Y or N) Y ADAMS ACCESSION NO.: TEMPLATE NO. RES-006 Publicly Available? (Y or N) Y DATE OF RELEASE TO PUBLIC SENSITIVE? No (RES File Code) RES

PARALLEL CONCURRENCE ROUTING AND TRANSMITTAL SLIP DATE:12/01/00 LETTER TO: Ralph Beedle FROM: A. Thadani

SUBJECT:

STATUS REPORT ON STUDY OF RISK-INFORMED CHANGES TO THE TECHNICAL REQUIREMENTS OF 10 CFR PART 50 (OPTION 3) AND RECOMMENDATIONS ON RISK-INFORMED CHANGES TO 10 CFR 50.44 (COMBUSTIBLE GAS CONTROL)

ORIGINATOR/SECRETARY: ROOM NO./BLDG: T10 C 24 Patty Nielsen PHONE NO.: 415-6189 SIGN AND/OR CONCUR DATE

1. MDrouin / /
2. MCunningham / /
3. TKing / /
4. D. Matthews / /
4. SCollins / /
5. AThadani / /

DUE TO RES 12/14/00 ACTION: CIRCULATED: FOR YOUR INFO:

APPROVAL: COMMENT: SEE ME:

AS REQUESTED: NOTE & RETURN: PREPARE REPLY: