Forwards Public Version of Summary Evaluation of Evacuation Time Estimates.Adverse Weather Conditions (Rain) Should Be Considered for Summer Scenario
ML20024D977
Person / Time
Site: 05000128
Issue date: 06/21/1983
From: Urbanik T
TEXAS A&M UNIV., COLLEGE STATION, TX
To: Robinson P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
Shared Package
ML20024D973 List:
References
NUDOCS 8308080657
Download: ML20024D977 (2)


Text

$ .

THE TEXAS A&M UNIVERSITY SYSTEM TEXAS TRANSPORTATION INSTITUTE

~

COLLEGE STATION TEXAS 77843-3135 TRANSPORT OPERATIONS PROC %M (713) g45.gs35 June 21, 1983 Perry D. Robinson ,_ -

U.S. Nuclear Regulatory Commission Ed ~ / - O Emergency Preparedness Branch Office of Inspection & Enforcement Washington, D.C. 20555

Dear Mr. Robinson:

A review of the Perry ETE dated July 1982 has been made using Appendix 4 of NUREG-0654, Revision 1. As indicated on the attached summary, two defi-ciencies were noted.

The Summer Sunday evacuation time estimate does not include an adverse weather estimate. Although a summer peak scenario with adverse weather is a remote possibility, wet roads due to a summer thunderstorm is nevertheless possible. It is, therefore, appropriate to have a Summer Sunday scenario con-sidering adverse weather (rain).

No reference in the report is made to having had the estimates reviewed by the appropriate state and local officials. A statement or reference to ,

state / local review is necessary to remove the deficiency regarding state and local review.

If you have any questions, please call me at (409) 845-1535.

Sincerely,

^Q.

Thomas Urbanik II Assistant Research Engineer TV/kab I l 8308080657 830729 PDR ADOCK 05000128 F PDR TRANSPORTATION RESEARCH ANO DEVELOPMENT

6 .

EVALUATION OF EVACUATION TIME ESTIMATE

, Perry Item Adequate Deficient Poor None

=

I. General A. Maps X B. Report Format 1 II. Demand Estimation A. Permanent Residents X B. Transient Populations X _ _

C. Special Facility Population X _

D. EPZ Sub-areas X III. Traffic Capacity A. Evacuation Roadway Network X B. Roadway Characteristics X C. Adverse Weather Considered X _

IV. Analysis A. Assumptions X _

B. Methodology X _,__

C. Carless X _

V. Other Requirements A. Confirmation Time X B. State and Local Review 1 VI. Overall X Date of Report: July, 1982 i

)