MONTHYEARML20216E6051999-09-0707 September 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1,safety Features Actuation Sys Instrumentation & Associated Bases 3/4.3.1 & 3/4.3.2,reactor Protection Sys & Safety Sys Instrumentation ML20210H0631999-07-28028 July 1999 Application for Amend to License NPF-3,revising TS 3/4.7.5.1, Ultimate Heat Sink, by Allowing Plant Operation in Modes 1-4 with Water Temp Less than or Equal to 90 F ML20210G4131999-07-27027 July 1999 Application for Amend to License NPF-3,changing TSs 6.4, Training, 6.5.2.8, Audits, 6.10, Record Retention, 6.14, Process Control Program & 6.15, Odcm ML20210G8831999-07-26026 July 1999 Application for Amend to License NPF-3,revising TSs 3/4.3.3.1, Radiation Monitoring Instrumentation, 3/4.3.3.2, Instrumentation - Incore Detectors & 3/4.3.3.9, Instrumentation - Waste Gas Sys Oxygen Monitor ML20210G5251999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs for Implementation of 10CFR50,App J,Option B for Type B & C Containment Leakage Rate Testing ML20210G4631999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1, Safety Features Actuation Sys Instrumention & Associated Bases 3/4.3.1 & 3/4.3.2, Reactor Protection Sys & Safety Sys Instrumentation ML20195F9121999-06-10010 June 1999 Application for Amend to License NPF-3,changing TS 3/4.6.4.4 Hydrogen Purge Sys, TS 3/4.6.5.1, Shield Bldg Emergency Ventilation Sys & TS 3/4.7.6.1, Crevs ML20207E7861999-05-21021 May 1999 Application for Amend to License NPF-3,allowing Use of Expanded Spent Fuel Storage Capability ML20205E4961999-03-19019 March 1999 Application for Amend to License NPF-3,requesting Withdrawal of Proposed New Action B to TS 3.6.5.2,previously Submitted in 981027 Application ML20204F1691999-03-0909 March 1999 Application for Amend to License NPF-3,adopting Changes in Frequency & Scope of Volumetric Exams Justified by W TR WCAP-14535A ML20196F3791998-11-30030 November 1998 Supplemental Application for Amend to License NPF-3, Proposing Changes to License Conditions 2.C(6) & 2.E by Transferring Operating Authority for DBNPS from Toed & Centerior Svc Co to Firstenergy Nuclear Operating Co ML20155E3181998-10-28028 October 1998 Application for Amend to License NPF-3,revising Various Sections of TS 6.0, Administrative Controls, Including Relocation of Contents of 6.11 to Plant Ufsar,Per NUREG-1430,Rev 1 ML20155E0701998-10-27027 October 1998 Application for Amend to License NPF-3,revising TSs 3/4.3.1.1 Re RPS Instrumentation & 3/4.3.2.3 Re ARTS Instrumentation by Providing Potential Reduction in Spurious Trip Rate to Provide Cost Savings in Excess of $50,000 ML20155D7731998-10-27027 October 1998 Application for Amend to License NPF-3,relocating Existing TS SR 4.6.5.1.d.4 Re Evs Negative Pressure Testing to TS 3/4.6.5.2,deleting TS Definition 1.24 & Making Related Changes Associated with Deletion of Subject Definition ML20155D8481998-10-27027 October 1998 Application for Amend to License NPF-3,revising Existing TS SRs 4.8.2.3.2.d,4.8.2.3.2.e,4.8.2.3.2.f & Table 4.8-1 Re Testing of 125 Volt DC Station Batteries & Applicable TS Bases ML20151W2811998-09-0808 September 1998 Application for Amend to License NPF-3,permitting Use of Framatome Cogema Fuels M5 Advanced Alloy Fuel Rod Cladding & Fuel Assembly Spacer Grids ML20151W2851998-09-0808 September 1998 Application for Amend to License NPF-3,revising TS Section 3/4.7.6, Plant Systems - CREVS & Associated Bases ML20236G6461998-06-29029 June 1998 Application for Amend to License NPF-3,transferring Operating Authority for DBNPS from TE & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Marked Up License,Safety & Environ Assessments Included ML20236R2301998-06-29029 June 1998 Resubmitted Application for Amend to License NPF-3, Transferring Operating Authority for DBNPS from Teco & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Safety Assessment & EA Included ML20217P8671998-04-24024 April 1998 Application for Amend to License NPF-3,modifying Existing TS 3/4.3.1.1,3/4.3.2.1,3/4.3.2.2 & Associated Bases by Relocating Tables of Response Time Limits from TS to Plant USAR Technical Requirements Manual ML20217P8251998-04-24024 April 1998 Application for Amend to License NPF-3,clarifying Discussion of Margin Between RPS High Pressure Trip Setpoint & Lift Setting for Pressurizer Code Safety Valves ML20203L0861998-02-26026 February 1998 Application for Amend to License NPF-3 to Revise TS 3/4.4.5 & TS 3/4.4.6.2,incorporating New Repair Roll Process for SG Tubes W/Defects in Upper Tube Sheet ML20197J2511997-12-23023 December 1997 Application for Amend to License NPF-3.Amend Changes TS Definitions 1.12,TS 3/4.9.5 & New TS 3.0.6 ML20197J5861997-12-23023 December 1997 Application for Amend to License NPF-3,revising TS Surveillance Requirements for ISI Requirements of Internal Auxiliary Feedwater Header,Header to Shroud Attachment Welds & External Header Thermal Sleeves ML20217R2801997-08-26026 August 1997 Application for Amend to License NPF-3,clarifying LCO 3.6.1.3.a & Revising Surveillance Requirement 4.6.1.3.c ML20217R2831997-08-26026 August 1997 Application for Amend to License NPF-3,modifying TS 3.2.5 Action Statement to Require Power Reduction to Less than 5% of Rated Thermal Power within Four Hrs If RCS Flow Rate Is Less than Specified Limit for Greater than Two Hrs ML20217G5931997-07-29029 July 1997 Suppl 950929 to Application for Amend to License NPF-3, Change TS 3/4.4.3 Re Safety Valves & Pilot Operated Relief valve-operating & Associated Bases 3/4.4.2 & 3/4.4.3 ML20141F1051997-06-24024 June 1997 Application for Amend to License NPF-3,deleting Requirements for Safety Features Actuation Sys Containment High Radiation Monitors ML20138A3201997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Conversion to 24-month Fuel Cycle ML20138C3131997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Rev to TS 3/4.7.6 to Include New Required Actions in Event That One or Both Channels of Radiation Monitoring Instrumentation Becomes Inoperable ML20137M1061997-03-31031 March 1997 Application for Amend to License NPF-57,revising TS to Improve Consistency Between TS & Plant Configuration, Operation & Testing & Complete Required CA to Resolve TS Discrepancies Identified in CA Program ML20138M1251997-02-14014 February 1997 Application for Amend to License NPF-3,requesting Delay of Heat Removal Sys Valve Pit Surveillance Requirements ML20134D7461997-01-30030 January 1997 Application for Amend to License NPF-3,revising SR Intervals from 18 to 24 Months Based on Results of DBNPS Instrument Drift Study & TS 2.2, Limiting Safety Sys Settings, Based on Results of Revised Framatome RPS Instrument String Error ML20134B0561997-01-20020 January 1997 Application for Amend to License NPF-3,involving TS 3/4.5.3 Re ECCS Subsystems ML20132C7771996-12-13013 December 1996 Application for Amend to License NPF-3,authorizing Transfers of Control ML20132B6871996-12-11011 December 1996 Application for Amend to License NPF-3,revising TS Definitions,Instrumentation TS & ECCS TS for Conversion to 24 Month Fuel Cycle ML20134F1851996-10-28028 October 1996 Application for Amend to License NPF-3,requesting Revisions to 3/4.8.1.1,3/4.8.1.2,3/4.8.2.3,3/4.8.2.4 & 3/4.8 Re Electrical Power Systems ML20117P5301996-09-17017 September 1996 Application for Amend to License NPF-3,supporting Conversion of DBNPS from 18 Month to 24 Month Fuel Cycle ML20117N8441996-09-12012 September 1996 Application for Amend to License NPF-3,revising Reactivity Control Systems & Emergency Core Cooling Systems ML20117M1971996-09-0404 September 1996 Application for Amend to License NPF-3,App A,Modifying TS 6.2.3 by Removing Specific Overtime Limits & Working H from TS Consistent W/Nrc Recent Determination,On Generic Basis, That Limits Need Not Be Specified ML20116K2601996-08-0707 August 1996 Application for Amend to License NPF-3,changing Tech Specs 1.0, Definitions, Bases 3/4.0, Applicability & 3/4.6.2.1, Containment Sys - Depressurization & Cooling Sys - Containment Spray Sys ML20117K1871996-05-28028 May 1996 Application for Amend to License NPF-3,revising TS 3/4.3.1.1 RPS Instrumentation & TS 3/4.3.2.2 - Anticipatory RTS Instrumentation to Increase Trip Device Test Interval ML20107L3541996-04-18018 April 1996 Application for Amend to License NPF-3,requesting NRC Review & Approval to Use Alternate Electrical Lineup.Station Blackout DG as Standby Emergency Power Source to Supply Loads Normally Supplied by EDG 1,while Being Reworked ML20101M1601996-03-29029 March 1996 Application for Amend to License NPF-3,App A,Re Surveillance Requirements for Charcoal Filter Lab Testing to Revise Testing Methodology Used to Determine Operability of Charcoal Filters in ESF Air Handling Units ML20101C6911996-03-0606 March 1996 Application for Amend to License NPF-3,revising TS 3/4.5.2 to Allow Deferment of SR 4.5.2.b for ECCS Flowpath Containing HPI 1-2 Pump Until 10th Refueling Outage, Scheduled to Begin 960408 ML20100E0051996-02-0505 February 1996 LAR 93-0003 to License NPF-3,revising Table 3.3-3 of TS 3/4.3.2.1 Re Safety Features Actuation Sys Instrumentation to More Accurately Reflect Design & Actuation Logic of Plant Sequencers & Undervoltage Relays ML20095F5861995-12-12012 December 1995 Application for Amend to License NPF-3,revising TSs Re Containment Sys ML20098C5131995-10-0202 October 1995 Application for Amend to License NPF-3,revising TS Section 5.0,design Features & Adopting Improved STS for B&W Plants Format & Content ML20098C1071995-09-29029 September 1995 Application for Amend to License NPF-3,modifying TS 3.4.3 & Associated Bases for Pressurizer Code Safety Valve Lift Setpoint Tolerances ML20098C3931995-09-29029 September 1995 Application for Amend to License NPF-3,revising Tech Spec 3/4.1.2.8, Reactivity Control Sys - Borated Water Sources - Shutdown, Tech Spec 3/4.1.2.9, Reactivity Control Sys - Operating & TS 3/4.5.1, ECCS - Core Flooding Tanks 1999-09-07
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML20216E6051999-09-0707 September 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1,safety Features Actuation Sys Instrumentation & Associated Bases 3/4.3.1 & 3/4.3.2,reactor Protection Sys & Safety Sys Instrumentation ML20210H0631999-07-28028 July 1999 Application for Amend to License NPF-3,revising TS 3/4.7.5.1, Ultimate Heat Sink, by Allowing Plant Operation in Modes 1-4 with Water Temp Less than or Equal to 90 F ML20210G4131999-07-27027 July 1999 Application for Amend to License NPF-3,changing TSs 6.4, Training, 6.5.2.8, Audits, 6.10, Record Retention, 6.14, Process Control Program & 6.15, Odcm ML20210G8831999-07-26026 July 1999 Application for Amend to License NPF-3,revising TSs 3/4.3.3.1, Radiation Monitoring Instrumentation, 3/4.3.3.2, Instrumentation - Incore Detectors & 3/4.3.3.9, Instrumentation - Waste Gas Sys Oxygen Monitor ML20210G5251999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs for Implementation of 10CFR50,App J,Option B for Type B & C Containment Leakage Rate Testing ML20210G4631999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1, Safety Features Actuation Sys Instrumention & Associated Bases 3/4.3.1 & 3/4.3.2, Reactor Protection Sys & Safety Sys Instrumentation ML20195F9121999-06-10010 June 1999 Application for Amend to License NPF-3,changing TS 3/4.6.4.4 Hydrogen Purge Sys, TS 3/4.6.5.1, Shield Bldg Emergency Ventilation Sys & TS 3/4.7.6.1, Crevs ML20207E7861999-05-21021 May 1999 Application for Amend to License NPF-3,allowing Use of Expanded Spent Fuel Storage Capability ML20205E4961999-03-19019 March 1999 Application for Amend to License NPF-3,requesting Withdrawal of Proposed New Action B to TS 3.6.5.2,previously Submitted in 981027 Application ML20204F1691999-03-0909 March 1999 Application for Amend to License NPF-3,adopting Changes in Frequency & Scope of Volumetric Exams Justified by W TR WCAP-14535A ML20196F3791998-11-30030 November 1998 Supplemental Application for Amend to License NPF-3, Proposing Changes to License Conditions 2.C(6) & 2.E by Transferring Operating Authority for DBNPS from Toed & Centerior Svc Co to Firstenergy Nuclear Operating Co ML20155E3181998-10-28028 October 1998 Application for Amend to License NPF-3,revising Various Sections of TS 6.0, Administrative Controls, Including Relocation of Contents of 6.11 to Plant Ufsar,Per NUREG-1430,Rev 1 ML20155E0701998-10-27027 October 1998 Application for Amend to License NPF-3,revising TSs 3/4.3.1.1 Re RPS Instrumentation & 3/4.3.2.3 Re ARTS Instrumentation by Providing Potential Reduction in Spurious Trip Rate to Provide Cost Savings in Excess of $50,000 ML20155D7731998-10-27027 October 1998 Application for Amend to License NPF-3,relocating Existing TS SR 4.6.5.1.d.4 Re Evs Negative Pressure Testing to TS 3/4.6.5.2,deleting TS Definition 1.24 & Making Related Changes Associated with Deletion of Subject Definition ML20155D8481998-10-27027 October 1998 Application for Amend to License NPF-3,revising Existing TS SRs 4.8.2.3.2.d,4.8.2.3.2.e,4.8.2.3.2.f & Table 4.8-1 Re Testing of 125 Volt DC Station Batteries & Applicable TS Bases ML20151W2811998-09-0808 September 1998 Application for Amend to License NPF-3,permitting Use of Framatome Cogema Fuels M5 Advanced Alloy Fuel Rod Cladding & Fuel Assembly Spacer Grids ML20151W2851998-09-0808 September 1998 Application for Amend to License NPF-3,revising TS Section 3/4.7.6, Plant Systems - CREVS & Associated Bases ML20236G6461998-06-29029 June 1998 Application for Amend to License NPF-3,transferring Operating Authority for DBNPS from TE & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Marked Up License,Safety & Environ Assessments Included ML20236R2301998-06-29029 June 1998 Resubmitted Application for Amend to License NPF-3, Transferring Operating Authority for DBNPS from Teco & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Safety Assessment & EA Included ML20217P8671998-04-24024 April 1998 Application for Amend to License NPF-3,modifying Existing TS 3/4.3.1.1,3/4.3.2.1,3/4.3.2.2 & Associated Bases by Relocating Tables of Response Time Limits from TS to Plant USAR Technical Requirements Manual ML20217P8251998-04-24024 April 1998 Application for Amend to License NPF-3,clarifying Discussion of Margin Between RPS High Pressure Trip Setpoint & Lift Setting for Pressurizer Code Safety Valves ML20203L0861998-02-26026 February 1998 Application for Amend to License NPF-3 to Revise TS 3/4.4.5 & TS 3/4.4.6.2,incorporating New Repair Roll Process for SG Tubes W/Defects in Upper Tube Sheet ML20197J2511997-12-23023 December 1997 Application for Amend to License NPF-3.Amend Changes TS Definitions 1.12,TS 3/4.9.5 & New TS 3.0.6 ML20197J5861997-12-23023 December 1997 Application for Amend to License NPF-3,revising TS Surveillance Requirements for ISI Requirements of Internal Auxiliary Feedwater Header,Header to Shroud Attachment Welds & External Header Thermal Sleeves ML20217R2801997-08-26026 August 1997 Application for Amend to License NPF-3,clarifying LCO 3.6.1.3.a & Revising Surveillance Requirement 4.6.1.3.c ML20217R2831997-08-26026 August 1997 Application for Amend to License NPF-3,modifying TS 3.2.5 Action Statement to Require Power Reduction to Less than 5% of Rated Thermal Power within Four Hrs If RCS Flow Rate Is Less than Specified Limit for Greater than Two Hrs ML20217G5931997-07-29029 July 1997 Suppl 950929 to Application for Amend to License NPF-3, Change TS 3/4.4.3 Re Safety Valves & Pilot Operated Relief valve-operating & Associated Bases 3/4.4.2 & 3/4.4.3 ML20141F1051997-06-24024 June 1997 Application for Amend to License NPF-3,deleting Requirements for Safety Features Actuation Sys Containment High Radiation Monitors ML20138A3201997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Conversion to 24-month Fuel Cycle ML20138C3131997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Rev to TS 3/4.7.6 to Include New Required Actions in Event That One or Both Channels of Radiation Monitoring Instrumentation Becomes Inoperable ML20137M1061997-03-31031 March 1997 Application for Amend to License NPF-57,revising TS to Improve Consistency Between TS & Plant Configuration, Operation & Testing & Complete Required CA to Resolve TS Discrepancies Identified in CA Program ML20138M1251997-02-14014 February 1997 Application for Amend to License NPF-3,requesting Delay of Heat Removal Sys Valve Pit Surveillance Requirements ML20134D7461997-01-30030 January 1997 Application for Amend to License NPF-3,revising SR Intervals from 18 to 24 Months Based on Results of DBNPS Instrument Drift Study & TS 2.2, Limiting Safety Sys Settings, Based on Results of Revised Framatome RPS Instrument String Error ML20134B0561997-01-20020 January 1997 Application for Amend to License NPF-3,involving TS 3/4.5.3 Re ECCS Subsystems ML20132C7771996-12-13013 December 1996 Application for Amend to License NPF-3,authorizing Transfers of Control ML20132B6871996-12-11011 December 1996 Application for Amend to License NPF-3,revising TS Definitions,Instrumentation TS & ECCS TS for Conversion to 24 Month Fuel Cycle ML20134F1851996-10-28028 October 1996 Application for Amend to License NPF-3,requesting Revisions to 3/4.8.1.1,3/4.8.1.2,3/4.8.2.3,3/4.8.2.4 & 3/4.8 Re Electrical Power Systems ML20117P5301996-09-17017 September 1996 Application for Amend to License NPF-3,supporting Conversion of DBNPS from 18 Month to 24 Month Fuel Cycle ML20117N8441996-09-12012 September 1996 Application for Amend to License NPF-3,revising Reactivity Control Systems & Emergency Core Cooling Systems ML20117M1971996-09-0404 September 1996 Application for Amend to License NPF-3,App A,Modifying TS 6.2.3 by Removing Specific Overtime Limits & Working H from TS Consistent W/Nrc Recent Determination,On Generic Basis, That Limits Need Not Be Specified ML20116K2601996-08-0707 August 1996 Application for Amend to License NPF-3,changing Tech Specs 1.0, Definitions, Bases 3/4.0, Applicability & 3/4.6.2.1, Containment Sys - Depressurization & Cooling Sys - Containment Spray Sys ML20117K1871996-05-28028 May 1996 Application for Amend to License NPF-3,revising TS 3/4.3.1.1 RPS Instrumentation & TS 3/4.3.2.2 - Anticipatory RTS Instrumentation to Increase Trip Device Test Interval ML20107L3541996-04-18018 April 1996 Application for Amend to License NPF-3,requesting NRC Review & Approval to Use Alternate Electrical Lineup.Station Blackout DG as Standby Emergency Power Source to Supply Loads Normally Supplied by EDG 1,while Being Reworked ML20101M1601996-03-29029 March 1996 Application for Amend to License NPF-3,App A,Re Surveillance Requirements for Charcoal Filter Lab Testing to Revise Testing Methodology Used to Determine Operability of Charcoal Filters in ESF Air Handling Units ML20101C6911996-03-0606 March 1996 Application for Amend to License NPF-3,revising TS 3/4.5.2 to Allow Deferment of SR 4.5.2.b for ECCS Flowpath Containing HPI 1-2 Pump Until 10th Refueling Outage, Scheduled to Begin 960408 ML20100E0051996-02-0505 February 1996 LAR 93-0003 to License NPF-3,revising Table 3.3-3 of TS 3/4.3.2.1 Re Safety Features Actuation Sys Instrumentation to More Accurately Reflect Design & Actuation Logic of Plant Sequencers & Undervoltage Relays ML20095F5861995-12-12012 December 1995 Application for Amend to License NPF-3,revising TSs Re Containment Sys ML20098C5131995-10-0202 October 1995 Application for Amend to License NPF-3,revising TS Section 5.0,design Features & Adopting Improved STS for B&W Plants Format & Content ML20098C1071995-09-29029 September 1995 Application for Amend to License NPF-3,modifying TS 3.4.3 & Associated Bases for Pressurizer Code Safety Valve Lift Setpoint Tolerances ML20098C3931995-09-29029 September 1995 Application for Amend to License NPF-3,revising Tech Spec 3/4.1.2.8, Reactivity Control Sys - Borated Water Sources - Shutdown, Tech Spec 3/4.1.2.9, Reactivity Control Sys - Operating & TS 3/4.5.1, ECCS - Core Flooding Tanks 1999-09-07
[Table view] |
Text
. .
APPLICATION FOR AMENDMENT TO FACILITY OPERATING LICENSE NO. NPF-3 FOR DAVIS-BESSE NUCLEAR POWER STATION UNIT NO. 1 Enclosed are forty-three (43) copies of the requested changes to the Davis-Besse Nuclear Power Station Unit No. 1 Facility Operating License No. NPF-3, together with the Safety Evaluation for the requested change.
The proposed changes include Section 3.7.7, Table 3.7-3 and Bases.
By [/
Vice President, Nuclear Sworn and subscribed before me this / day of h I, , 19 RF .
Ik$ kWk11h4 Notary Public ,
C ;f. L' GU.
.% .l OLi. -
H1, C ;,, ,.p , 9 b'b O b 8309090427 830901 PDR ADOCK 05000346 p PDR J
Docket No. 50-346 License No NPF-3 Serial No. 984 September 1, 1983 Attachment I I.
Changes to Davis-Besse Nuclear Power Station Unit 1, Appendix A Technical Specifications Section 3.7.7, Table 3.7-2 and Bases.
A. Time required to Implement. This change is to be effective upon MRC approval.
B. Reason for Change (Facility Change Request 83-080 Rev. A). In Response to Mr. D. G. Eisenhut's letter of November 20, 1980 (Log No. 638) concerning Technical Specification Revision for Snubber Surveillance.
C. Safety Evaluation (See Attached)
D. Significant Hazard Consideration (See Attached) 9 Y
l l
e i
a
Safety Evaluation This Technical Specification Amendment to 3/4.7.7 and B3/4.7.7 embodies several changes to the requirement for snubber surveillance. The revised surveillance program includes visual inspections, and functional testing for both hydraulic and mechanical snubbers. New and/or upgraded inspection and testing acceptance criteria are also proposed by this change.
The safety function of all affected snubbers is that they are required operable to ensure that the structural integrity of the reactor coolant system and all other safety-related systemsois maintained during the following seismic or other events initiating dynamic loads. The amendment request for inspection and functional testing will increase the probability of locating inoperable snubbers without testing 100% of the '
snubbers each inspection period by testing 10% each period and 100% over a period of 10 refueling outages. The additional inspection and testing ~
requirements will increase the total man-rem exposures at Davis-Besse. ,
The requirements for mechanical snubbers alone may result in an estimated additional 30 man-rem exposure per year. In order to reduce this figure *-
whenever practical, visual inspection of snubbers that are inside
- containment or are in high radiation exposure zones will be performed i
~
during plant shutdowns or when radiation levels are lowest. Snubbers located in low radiation areas may be chosen preferentially over those id higher radiation areas when selecting snubbers for additional testing. 2 This sampling program will detect common failures without having to manually test all of the snubbers and, therefore, will aid in keeping radiation exposure ALARA.
The snubber functional testing program must be conducted such that the ;
Technical Specifications regarding system or train operability are not -
violated. Functional testing of the snubbers will require unpinning of at least one end, which in turn renders the snubber temporarily inoperable.f.
Therefore, system operability may be affected by functional testing of the snubbers unless an evaluation shows that the system or train is operable,-
without the snubber. Various systems are required by the Technical ,
- Specifications to have one or two trains operable during Modes 1 through<
i 6. The Action 3.7.7b footnote 2 also now allows snubber removal for 72 ,
I hours for normal surveillance testing without declaring the system -
inoperable.
Functional testing of 10 percent of the snubbers is required every 18 .
months, which means testing can be performed during refueling cutages for
~
. inaccessible snubbers. Functional testing may also be performed just prior to maintenance being done on snubbers in order to reduce the time .
! when safety-related systems are unavailable. In this manner, through the use of accurate and proper administrative controls, functional testing of the snubbers can be accomplished without violating the existing Technical Specifications. ,q The proposed change upgrades the surveillance inspection and testing of ,
snubbers and therefore will increase the confidence level that snubbers on safety-related systems will perform as required to restrain movements e
during earthquakes, pipe ruptures and other accident loadings, and still allow normal movements due to thermal expansion. This confidence level will be offset slightly due to the fact that portions of safety-related systems may be inoperable during functional testing of the snubbers.
However, the proposed change will not introduce any new adverse consequences or affect the consequences of previously analyzed transients.
Therefore, this change does not constitute an unreviewed safety question.
i a
Is I
T
, -- - . . - - . - _ - - - _ . , . _ . , , - - . . , , ,,,,.,_...,c. . , , _ - - , , , . , , , _ , , , - , . . , . . , , - - . ,
Significant Hazard Consideration The attached amendment represents a change to the " Limiting Condition for Operation" and " Surveillance Requirements" and the requested change does not contain a significant hazard. The amendment provides schedules, actions and acceptance criteria for sample testing snubbers.
The proposed request is:
- 1. To add mechanical snubbers and hydraulic snubbers to the surveillance schedule by reference to the applicable surveillance test specification (s).
- 2. To add engineering evaluation as means of: -
- a. Determining how snubber inoperability affects a safety related system or component to assure no adverse significant effect or degradation has occurred.
- b. Verifying system operability with the snubber inoperable.
- 3. To permit surveillance testing without requiring further engineering evaluation if the time constraints of system operability are met and if visual and functional failure are not involved.
- 4. To provide a schedule for performing " ACTIONS" in response to inoperability and for performing surveillance visual and functional tests.
The purpose of the surveillance test is to assure that safety-related snubbers are operable. This will in turn ensure that the structural l integrity of the reactor coolant system, and other safety-related systems, is maintained during and following seismic or other events initiating dynamic loads.
The proposed revision will allow all safety related snubbers to be tested
- on a timely basis. Snubbers shall be inspected on a schedule which l assures a 95% confidence level that 90 to 100% of all snubbers in the plant will be operable. The revision also permits inspection during normal operation of all accessible snubbers.
The proposed revision would grant an exemption to the functional testing of snubbers greater than 50,000 pounds capacity which are installed in high radiation zones or are in especially difficult to remove locations.
In order to functionally test the 8" or 20" snubbers, structural steel must be removed, special scaffolding must be installed and special arrangements are made for use of the overhead polar crane. Also there is increased risk of damage to other pipe and components because of the close proximity of all equipment. In order to be exempt, these units must have operability demonstrated at either the completion of their fabrication or at a subsequent date, e.g. , major repairs which require removal.
e L
This new amendment will not sacrifice any safety margin presently existing in current procedures and specifications. Instead, this revision will increase reliability of existing snubbers and thereby, also increase reliability of safety related systems.
The granting of the request would not:
- 1. Involve a significant increase in the probability or consequences of an accident previously evaluated 10 CFR 50.92 (c)(1).
The revision would provide data as requested in NUREG 0103 for prevention of snubber failure. The increase in the number of snubbers to be inspected will decrease the probability or consequences of a previously evaluated accident.
- 2. Create the possibility of a new or different kind of accident previously evaluated 10 CFR 50.92 (c)(2).
All accidents are still bounded by previous evaluations and no new accidents are involved.
- 3. Involve a significant reduction in a margin of safety 10 CFR 50.92 (c)(3).
The margins of safety assumed in the accident analysis are unaffected by the request.
Therefore, based on the attached safety evaluation and the above, the requested amendment does not contain a significant hazard.