MONTHYEAR2CAN012401, U.S. Additional Protocol2024-01-17017 January 2024 U.S. Additional Protocol 2CAN012403, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42024-01-11011 January 2024 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN012401, Registration of Cask Use2024-01-10010 January 2024 Registration of Cask Use 1CAN122301, Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037)2023-12-14014 December 2023 Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037) 2CAN112302, Submittal of Amendment 31 to Safety Analysis Report2023-11-16016 November 2023 Submittal of Amendment 31 to Safety Analysis Report 0CAN102303, Registration of Cask Use2023-10-24024 October 2023 Registration of Cask Use 0CAN102302, (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 32023-10-11011 October 2023 (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 3 0CAN102301, Evacuation Time Estimate (ETE) Study2023-10-0404 October 2023 Evacuation Time Estimate (ETE) Study 1CAN092301, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-09-21021 September 2023 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN092302, Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002)2023-09-14014 September 2023 Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002) 2CAN092301, Reply to a Notice of Violation2023-09-0808 September 2023 Reply to a Notice of Violation 0CAN092301, Emergency Plan Implementing Procedure Revision2023-09-0505 September 2023 Emergency Plan Implementing Procedure Revision 0CAN082301, Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 03412023-08-17017 August 2023 Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 0341 2CAN082301, Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29)2023-08-10010 August 2023 Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29) 0CAN072301, Registration of Cask Use2023-07-18018 July 2023 Registration of Cask Use 1CAN062304, Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2023-06-29029 June 2023 Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 0CAN062301, Status of Actions to Return to Compliance2023-06-26026 June 2023 Status of Actions to Return to Compliance 0CAN062302, Submittal of Revision 22 of the ANO Fire Hazards Analysis2023-06-20020 June 2023 Submittal of Revision 22 of the ANO Fire Hazards Analysis 1CAN062301, Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037)2023-06-0808 June 2023 Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037) 0CAN052303, Annual 10 CFR 50.46 Report for Calendar Year 20222023-05-24024 May 2023 Annual 10 CFR 50.46 Report for Calendar Year 2022 0CAN052302, Emergency Plan Rev. 482023-05-11011 May 2023 Emergency Plan Rev. 48 0CAN052301, Units 1 and 2 - Annual Radiological Environmental Operating Report for 20222023-05-0909 May 2023 Units 1 and 2 - Annual Radiological Environmental Operating Report for 2022 2CAN052301, Cycle 30 Core Operating Limits Report (COLR)2023-05-0303 May 2023 Cycle 30 Core Operating Limits Report (COLR) 0CAN042302, Annual Occupational Radiation Exposure Report for 20222023-04-27027 April 2023 Annual Occupational Radiation Exposure Report for 2022 0CAN042301, Radioactive Effluent Release Report for 20222023-04-14014 April 2023 Radioactive Effluent Release Report for 2022 2CAN042301, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-04-0505 April 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN032301, License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure2023-03-30030 March 2023 License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure 2CAN032303, Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032304, Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032305, 03 Post Examination Analysis2023-03-23023 March 2023 03 Post Examination Analysis 1CAN032302, Inspection Summary Report for the Thirtieth Refueling Outage (1R30)2023-03-20020 March 2023 Inspection Summary Report for the Thirtieth Refueling Outage (1R30) 1CAN012301, Responses to Request for Additional Information for Request for Relief ANO1-ISI-0352023-01-30030 January 2023 Responses to Request for Additional Information for Request for Relief ANO1-ISI-035 2CAN012303, U.S. Additional Protocol2023-01-23023 January 2023 U.S. Additional Protocol 2CAN012302, Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-01-20020 January 2023 Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 1CAN122201, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42022-12-22022 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN122202, Registration of Cask Use2022-12-21021 December 2022 Registration of Cask Use 0CAN122201, Reply to a Notice of Violation; EA-22-0992022-12-0808 December 2022 Reply to a Notice of Violation; EA-22-099 0CAN112201, Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002)2022-11-10010 November 2022 Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002) 1CAN102202, Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2022-10-31031 October 2022 Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 1CAN102203, Cycle 31 Core Operating Limits Report2022-10-24024 October 2022 Cycle 31 Core Operating Limits Report 1CAN102201, Supplement to Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations2022-10-13013 October 2022 Supplement to Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations 0CAN092201, Supplement to License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements2022-09-29029 September 2022 Supplement to License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements 1CAN092201, Supplement to Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period2022-09-0808 September 2022 Supplement to Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period 0CAN082201, License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements2022-08-30030 August 2022 License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements 1CAN082201, Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period2022-08-24024 August 2022 Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period 2CAN072201, Response to Request for Additional Information Requests for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fourth 10-Year Interval, Second and Third Periods2022-07-20020 July 2022 Response to Request for Additional Information Requests for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fourth 10-Year Interval, Second and Third Periods 0CAN072201, Registration of Cask Use2022-07-14014 July 2022 Registration of Cask Use 0CAN062202, Registration of Cask Use2022-06-0909 June 2022 Registration of Cask Use 1CAN062201, Response to the Request for Additional Information Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations2022-06-0202 June 2022 Response to the Request for Additional Information Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations 1CAN052201, Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Augmented Examination Requirements ANO1-ISI-0352022-05-31031 May 2022 Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Augmented Examination Requirements ANO1-ISI-035 2024-01-17
[Table view] |
Text
Entergy Operations, Inc.
oftEntergy 1448 S.R. 333 Russellville, AR 72802 Tel 479-858-4601 Thomas A. Marlow Director.
Nuclear Safety Assurance 2CAN090602 September 26, 2006 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
Supplement to Amendment Request to Allow One-Time Extension of Containment Spray System Allowable Outage Time Arkansas Nuclear One, Unit 2 Docket No. 50-368 License No. NPF-6
REFERENCES:
- 1. Entergy Letter to the NRC dated September 19, 2005 License Amendment Request to Allow One-Time Extension of Containment Spray System Allowable Outage Time (2CAN090502)
- 2. Entergy Letter to the NRC dated February 28, 2006 Supplement to Amendment Request to Allow One-Time Extension of Containment Spray System Allowable Outage Time (2CAN020602)
- 3. Entergy Letter to the NRC dated May 31, 2006 Supplement to Amendment Request to Allow One-Time Extension of Containment Spray System Allowable Outage Time (2CAN050603)
Dear Sir or Madam:
By letter (Reference 1), Entergy Operations, Inc. (Entergy) proposed a change to the Arkansas Nuclear One, Unit 2 (ANO-2) Technical Specifications (TSs) to amend TS 3.6.2.1 "Containment Spray System." The proposed change will allow a one-time extension of the allowable outage time (AOT) for the Containment Spray System from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to a maximum of 7 days.
On September 25, 2006, Entergy and members of your staff held a call to discuss the method of handling the supporting commitments. The NRC requested that the commitments be maintained in the TS bases. A markup of the TS bases for ANO-2 TS 3.6.2.1 is included in Attachment 1.
A-001
2CAN090602 Page 2 of 2 There are no technical changes proposed. The original no significant hazards consideration included in Reference I is not affected by any information contained in the supplemental letter. There are no new commitments contained in this letter.
Ifyou have any questions or require additional information, please contact Dana Millar at 601-368-5445.
I declare under penalty of perjury that the foregoing is true and correct. Executed on September 26, 2006.
Sincerely, TAM/DM Attachments:
- 1. Markup of Technical Specification Bases Pages (For Information Only) cc: Dr. Bruce S. Mallett Regional Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Resident Inspector Arkansas Nuclear One P. O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Drew Holland MS 0-7 D1 Washington, DC 20555-0001 Mr. Bernard R. Bevill Director Division of Radiation Control and Emergency Management Arkansas Department of Health and Human Services P. 0. Box 1437 Slot H-30 Little Rock, AR 72203-1437
Attachment 1 To 2CAN090602 Markup of Technical Specification Bases Pages (For Information Only)
CONTAINMENT SYSTEMS BASES 3/4.6.2 DEPRESSURIZATION, COOLING, AND PH CONTROL SYSTEMS 3/4.6.2.1 CONTAINMENT SPRAY SYSTEM The OPERABILITY of the containment spray system ensures that containment depressurization and cooling capability will be available in the event of a LOCA. The pressure reduction and resultant lower containment leakage rate are consistent with the assumptions used in the accident analyses.
The containment spray system and the containment cooling system provide post accident cooling and mixing of the containment atmosphere; however, the containment cooling system is not redundant to the containment spray system. The containment spray system also provides a mechanism for removing iodine from the containment atmosphere and therefore the time requirements for restoring an inoperable spray system to OPERABLE status have been maintained consistent with that assigned other inoperable ESF equipment.
- INSERT 1 -
3/4.6.2.2 TRISODIUM PHOSPHATE (TSP)
A hydrated form of granular trisodium phosphate (TSP) is employed as a passive form of pH control for post LOCA containment spray and core cooling water to ensure that iodine, which may be dissolved in the recirculated reactor cooling water following a loss of coolant accident (LOCA), remains in solution. TSP also helps inhibit stress corrosion cracking (SCC) of austenitic stainless steel components in containment during the recirculation phase following an accident. Baskets of TSP are placed on the floor of the containment building to dissolve from released reactor coolant water and containment sprays after a LOCA. Recirculation of the water for core cooling and containment sprays then provides mixing to achieve a uniform solution pH.
Fuel that is damaged during a LOCA will release iodine in several chemical forms to the reactor coolant and to the containment atmosphere. A portion of the iodine in the containment atmosphere is washed to the sump by containment sprays. The emergency core cooling water is borated for reactivity control. This borated water causes the sump solution to be acidic. In a low pH (acidic) solution, dissolved iodine will be converted to a volatile form. The volatile iodine will evolve out of solution into the containment atmosphere, significantly increasing the levels of airborne iodine. The increased levels of airborne iodine in containment contribute to the radiological releases and increase the consequences from the accident due to containment atmosphere leakage.
After a LOCA, the components of the core cooling and containment spray systems will be exposed to high temperature borated water. Prolonged exposure to the core cooling water combined with stresses imposed on the components can cause SCC. The SCC is a function of stress, oxygen and chloride concentrations, pH, temperature, and alloy composition of the components. High temperatures and low pH, which would be present after a LOCA, tend to promote SCC. This can lead to the failure of necessary safety systems or components.
Adjusting the pH of the recirculation solution to levels above 7.0 prevents a significant fraction of the dissolved iodine from converting to a volatile form. The higher pH thus decreases the level of airbome iodine in containment and reduces the radiological consequences from containment atmosphere leakage following a LOCA. Maintaining the solution pH above 7.0 also reduces the occurrence of SCC of austenitic stainless steel components in containment. Reducing SCC reduces the probability of failure of components.
ARKANSAS - UNIT 2 B 3/4 6-3 Amendment No. 82,94,22-6,246,
Insert 1 When applying the extended 7-day AOT, the following actions shall be satisfied:
- 1. While performing maintenance on the CSS train components, do not disable other components that are used for the containment heat removal.
- 2. Prior to performing maintenance on one CSS equipment train, assure that the backup train is properly aligned and would be expected to perform its function if required.
- 3. Conduct a briefing with appropriate plant personnel to ensure that they are aware of the impact associated with unavailable components and flow paths.
- 4. Ifa maintenance action or repair is to be performed, pre-stage parts and tools to minimize outage time.
- 5. Consider actions which could be taken to return the affected train to functional use, if not full operability, if the need arises or plan for backup systems (e.g., containment fan coolers) to be available.
- 6. In repairing and/or testing components (particularly valves), define the appropriate valve position (open/closed) that provides the greater level of safety and "if practical" establish that position for the repair.
- 7. Do not commence maintenance activities on the CSS for an extended AOT if any of the following conditions exist:
- Seismic Event (earthquake) as indicated by the earthquake trigger or noticeable abnormal vibrations in major structures
- Tornado watch or warning for Pope, Yell, Logan, or Johnson counties is in effect
- Tornado is sighted locally
- Loss of Dardanelle Reservoir is forecast
- 8. When performing maintenance activities on either train of the CSS, the redundant CSS train and the containment cooling system (CCS) will be protected (i.e., no testing or maintenance activities will be allowed).
- 9. Ensure the ignition source probability is as low as possible in the Turbine Building to maintain the availability of off-site power by posting an houdy roving fire watch in that area.
- 10. Post a roving fire watch in other risk significant areas which include: the operable CSS train, the CCS, the high pressure safety injection (HPSI) system, both emergency feedwater (EFW) trains, and the auxiliary feedwater (AFW) system.