NOC-AE-06002094, Results of Reactor Head Penetration Inspection Pursuant to Revision 1 of Order EA-03-009

From kanterella
Revision as of 12:12, 23 November 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Results of Reactor Head Penetration Inspection Pursuant to Revision 1 of Order EA-03-009
ML063530479
Person / Time
Site: South Texas STP Nuclear Operating Company icon.png
Issue date: 12/12/2006
From: Rencurrel D
South Texas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-03-009, G25, NOC-AE-06002094
Download: ML063530479 (6)


Text

Nuclear Operating Company South Texas Tro/ect Electric GeneratingStation PO Box 289 Wadsworth, Texs 77483 December 12, 2006 NOC-AE-06002094 File No.: G25 10 CFR 50.55a U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 South Texas Project Unit 1 Docket No. STN 50-498 Results of Reactor Head Penetration Inspection Pursuant to Revision 1 of Order EA-03-009 Pursuant to Revision 1 of NRC Order EA-03-009, STP Nuclear Operating Company (STPNOC) provides the results of volumetric examinations of the South Texas Project Unit 1 reactor pressure vessel head penetrations. The revised Order requires that, within 60 days after returning a ,unit to operation, licensees provide a description of the inspection performed in accordance with the Order. The inspection was performed during South Texas Project Unit 1 refueling outage 1 RE13; the unit was returned to operation on November 4, 2006.

The Order requires the following inspections:

" A bare metal visual examination every third refueling outage or five years, whichever is shorter;

" A non-visual, non-destructive examination (NDE) prior to February 11, 2008; and

" A visual inspection to identify boric acid leak paths during every refueling outage.

A bare metal visual examination of the Unit 1 reactor vessel head was most recently performed during the Spring 2003 refueling outage (1RE11). The results were reported to the NRC by correspondence dated August 18, 2003 (accession number ML032330260). The inspections in 1RE13 addressed the NDE requirement and the visual examination for boric acid leaks; the results are reported here.

Non-visual nondestructive volumetric examination was performed on all 76 reactor head penetration tubes with J-groove welds, including the head vent penetration and the degas penetration. The examination detected no discontinuities or indications of boric acid leak paths, and no flaws needing disposition or corrective action were identified. In addition, a visual inspection to identify potential boric acid leaks from the pressure-retaining components above the reactor pressure vessel head found no indications. Details are provided in the attachment.

A list of commitments is provided as an attachment to this letter.

ST 32097806 4 t01

NOC-AE-06002094 Page 2 of 3 If there are any questions, please contact either Philip L. Walker at (361) 972-8392 or me at (361) 972-7867.

v r.Rencurrel Vice President, Engineering

& Strategic Programs PLW

Attachment:

1. Response to NRC Order EA-03-009 for South Texas Project Unit 1 - 1 RE13 Examination Results
2. List of Commitments

NOC-AE-06002094 Page 3 of 3 cc:

(paper copy) (electronic copy)

Regional Administrator, Region IV A. H. Gutterman, Esquire U. S. Nuclear Regulatory Commission Morgan, Lewis & Bockius LLP 611 Ryan Plaza Drive, Suite 400 Arlington, Texas 76011-8064 Mohan C. Thadani U. S. Nuclear Regulatory Commission Richard A. Ratliff Steve Winn Bureau of Radiation Control Christine Jacobs Texas Department of State Health Services Eddy Daniels 1100 West 49th Street NRG South Texas LP Austin, TX 78756-3189 Senior Resident Inspector J. J. Nesrsta U. S. Nuclear Regulatory Commission R. K. Temple P. O. Box 289, Mail Code: MN116 E. Alarcon Wadsworth, TX 77483 City Public Service C. M. Canady C. Kirksey City of Austin City of Austin Electric Utility Department 721 Barton Springs Road Jon C. Wood Austin, TX 78704 Cox Smith Matthews

Attachment 1 NOC-AE-06002094 Page 1 of 2 South Texas Project Unit 1 Response to NRC Order EA-03-009 for South Texas Project Unit 1 -

1RE13 Examination Results Pursuant to Revision 1 of NRC Order EA-03-009, STP Nuclear Operating Company (STPNOC) calculated the susceptibility of the South Texas Project (STP) Unit 1 reactor pressure vessel head to pressurized water stress corrosion cracking (PWSCC), as represented by effective degradation years (EDY) at the end of each operating cycle. Unit 1 was determined to have an EDY of 6.9 EDY when the 1RE13 refueling outage began in October 2006. The Order Inspection Category, determined in accordance with Section IV.A, is "low." Therefore, STPNOC was required to perform an inspection in accordance with NRC Order EA-03-009, Sections IV.C(5)(b)(i) and IV.D.

RequirementsSection IV.C(5)(b)(i) requires ultrasonic testing of the reactor head penetration nozzle volume from two inches above the highest point of the root of the J-groove weld to one inch below the lowest point of the toe of the J-groove weld, including all penetration nozzle surfaces below the J-groove weld having an operating stress level of 20 ksi or greater. The Order also requires an assessment to determine if there has been leakage into the annulus between the head penetration nozzle and the head low-alloy steel.

Examination Parameters During 1 RE1 3, STPNOC performed a non-visual nondestructive volumetric examination of the reactor head penetration tubes in compliance with Section IV.C.(5)(b)(i) of Revision 1 of the Order. Of the 79 penetrations present, 75 were examined from the underside of the reactor vessel head using ultrasonic test equipment maneuvered into place using a remote positioning manipulator. One penetration was examined using both automated ultrasonic testing and manual eddy current testing. Three penetrations were not included because they were not attached to the head with "J-groove" welds.

Examination Results The affected penetrations were scanned starting from the taper-to-cylinder transition at the bottom of each nozzle up to at least two inches above the highest point of the J-groove weld.

STPNOC performed an analysis which supports limiting the examination zone to 1-inch below the lowest point of each J-groove weld. UT coverage of most of the penetrations with J-groove welds addressed at least the specified one inch. However, one Control Rod Drive Mechanism penetration had examination coverage less than one inch because the penetration length only allowed examination to 0.73-inch below the weld toe. With the exception of the degas penetration nozzle, an inside diameter chamfer on the end of each nozzle precludes coverage to the very end of the nozzle below the J-groove weld. The de-gas penetration was found to have an unchamfered extension leading 0.67-inch below the lowest point of the J-groove weld.

Because it was unchamfered, scanning coverage extended to the end of the degas penetration nozzle. No recordable indications were found. Please note that the one penetration that received less coverage than required by the NRC Order will be addressed in a relaxation request to the NRC in a separate submittal consistent with the schedule requirements of the Order.

The head vent line was examined with both ultrasonic testing (UT) and eddy current testing (ET) to satisfy the requirements of the Order. The vent line penetration was scanned starting from

Attachment 1 NOC-AE-06002094 Page 2 of 2 the taper-to-cylinder transition at the bottom of the weld to at least two inches above the highest point of the J-groove weld. The vent line is flush with the inside contour of the head and the chamfer on the corner of the vent prevents full coverage to the very end of the nozzle.

Consequently, the configuration of the weld at the base of the vent line is not suitable for examination by UT. The J-groove weld surface was examined using ET. No recordable indications were found using either method.

The examinations detected no discontinuities or indications of boric acid leak paths.

Attachment 2 NOC-AE-06002094 Page 1 of 1 List of Commitments The following table identifies the actions in this document to which the STP Nuclear Operating Company has committed. Statements in this submittal with the exception of those in the table below are provided for information purposes and are not considered commitments. Please direct questions regarding these commitments to Philip Walker at (361) 972-8392.

Commitment Expected CR Action No.

Completion Date The one penetration that received less coverage than required by the NRC Order will be addressed in a 12/31/2007 05-15733-20 relaxation request to the NRC in a separate submittal consistent with the schedule requirements of the Order.