MONTHYEARML18212A0442018-07-30030 July 2018 Letter to R. Boyle Application for the Model No. TNF-XI Transport Package Supplemental Information Needed (W/Enclosure) Project stage: Other ML19071A1492019-02-21021 February 2019 Enclosure 2: Contents Pictures (Rsi Supplement 2 (Letter Dated 2/21/19) Model No. TNF-XI (Docket No. 71-3092) Project stage: Other ML19071A1432019-02-21021 February 2019, 26 February 2019 Package: Letter Dated 2/26/19, Rsi Supplement 2, Model No. TNF-XI (Dkt No. 71-3092) Project stage: Request ML19091A0552019-03-29029 March 2019 Letter to R. Boyle Application for Revising the Model No. TNF-XI Transport Package - Accepted for Review Project stage: Other ML19150A6142019-05-28028 May 2019 Letter to R. Boyle Request for Additional Information for Review of the Revalidation of the Model No. TNF-XI Package (Docket No. 71-3092) (EPID: L-2018-LLA-0170) (W/Enclosure) Project stage: RAI ML19219A0362019-08-12012 August 2019 Letter to R. W. Boyle Revalidation Recommendation for the French Certificate of Approval No. F/381/AF-96, Revision Dk, Model No. TNF-XI Package (Docket No. 71-3092)(w/Enclosure 1) Project stage: Other ML19232A1572019-08-12012 August 2019 Enclosuapplicant SER Comments (08/12/2019, E-Mail from P. Vescovi/Tn Americas to N. Garcia-Santos/NRC Need Clarification on Redactions - TNX-XI--Due Today) Project stage: Other 2019-03-29
[Table View] |
|
---|
Category:Letter
MONTHYEARML22305A6612022-11-0909 November 2022 Letter to R. Boyle re- Revalidation Recommendation for the French Certificate of Approval No. F/381/AF-96, Revision En for the Model No. TNF-XI Package, Docket No. 71-3092 ML22307A1552022-07-11011 July 2022 Letter from R. Boyle Revalidation Request for the Model No. TNF-XI Package, USA/0653/AF-96, Revision En, Docket No. 71-3092 ML22153A0892022-06-10010 June 2022 Cover Letter 71-3092 ML22118A3412022-03-24024 March 2022 Cover Letter - RAI Response Letter to NRC Signed 042822 ML22118A3422022-03-21021 March 2022 RAI Response - E-60638 TNF-XI RAI Response Package ML22061A2082022-03-15015 March 2022 Request for Additional Information - Request for Revalidation of French Certificate of Approval USA/0653/AF-96 for Validation of French Competent Authority Certificate F/381/AF-96 for the Model No. TNF-XI; Docket Number 71-3092 ML22061A1632021-07-12012 July 2021 Application for Revision to Competent Authority Certification, USA/0653/AF-96 for Validation of French Competent Authority Certificate F/381/AF-96 for the Model No. TNF-XI ML19219A0362019-08-12012 August 2019 Letter to R. W. Boyle Revalidation Recommendation for the French Certificate of Approval No. F/381/AF-96, Revision Dk, Model No. TNF-XI Package (Docket No. 71-3092)(w/Enclosure 1) ML19232A1572019-08-12012 August 2019 Enclosuapplicant SER Comments (08/12/2019, E-Mail from P. Vescovi/Tn Americas to N. Garcia-Santos/NRC Need Clarification on Redactions - TNX-XI--Due Today) ML19150A6142019-05-28028 May 2019 Letter to R. Boyle Request for Additional Information for Review of the Revalidation of the Model No. TNF-XI Package (Docket No. 71-3092) (EPID: L-2018-LLA-0170) (W/Enclosure) ML19091A0552019-03-29029 March 2019 Letter to R. Boyle Application for Revising the Model No. TNF-XI Transport Package - Accepted for Review ML18222A1742018-08-0909 August 2018 NRC Certificate 9301 Rev 9 and SER (08/09/2018, E-Mail from M. Conroy/Dot to N. Garcia Santos/Nrc TNF-XI CAC Rev. 11) ML18212A0442018-07-30030 July 2018 Letter to R. Boyle Application for the Model No. TNF-XI Transport Package Supplemental Information Needed (W/Enclosure) 2022-07-11
[Table view] |
Text
March 29, 2019 Mr. Richard W. Boyle, Chief Sciences Branch Division of Engineering and Research Office of Hazardous Materials Safety U.S. Department of Transportation 1200 New Jersey Ave., S.E.
Washington, D.C. 20590
SUBJECT:
APPLICATION FOR REVISING THE MODEL NO. TNF-XI TRANSPORT PACKAGE - ACCEPTED FOR REVIEW (EPID: L-2018-LLA-0170)
Dear Mr. Boyle:
By letter dated June 7, 2018 [Agencywide Documents Access and Management System (ADAMS) Accession No. ML18192B131], the United States (U.S.) Department of Transportation requested that the U.S. Nuclear Regulatory Commission (NRC) staff performs a review of the Competent Authority Certification (CAC) USA/0653/AF-96, French Approval Certificate Number F/381/AF-96, Revision Di, Model No. TNF-XI transport package, and make a recommendation concerning the revalidation of the package for import and export use.
The NRC staff performed an acceptance review of your application to determine whether the application contains sufficient technical information in scope and depth to allow the NRC staff to complete a detailed technical review per the International Atomic Energy Agency Specific Safety Requirements No. 6, Regulations for the Safe Transport of Radioactive Material, 2012 Edition.
With the information supplied by letters dated August 21, 2018 (ADAMS Accession No.
ML18250A061), October 24, 2018 (ADAMS Accession No. ML18313A064), and February 26, 2019 (ADAMS Accession No. ML19071A145), the application appears to contain the information needed for our technical review.
We have established a schedule for the review and estimated that the staff may need approximately 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> to complete its review. The schedule allows for the staff to issue the first request for additional information (RAI) in May 2019 and, if a second RAI is not needed, a revalidation recommendation in August 2019, based on you responding to the first RAI in June 2019. In general, no additional changes to the application should be submitted except for changes resulting from your response to an RAI.
R. Boyle Please reference Docket No. 71-3092 in future correspondence related to this action. The staff is available to meet and discuss your proposed responses. If you have any questions regarding this matter, please contact me at (301) 415-6999.
Sincerely,
/RA/
Norma García Santos, Project Manager Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 71-3092 EPID L-2018-LLA-0170
ML19091A055 OFFICE: DSFM DSFM DSFM NAME: NGarcía Santos SFigueroa IBerrios by email DATE: 3/28/19 3/29/19 3/29/19