MONTHYEARIR 05000456/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2024005 and 05000457/2024005) ML24225A1112024-08-13013 August 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML24164A2132024-06-13013 June 2024 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Braidwood Nuclear Plant IR 05000456/20230062024-02-28028 February 2024 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2023006 and 05000457/2023006) ML23339A0452023-12-0505 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000546/2024010 IR 05000456/20230052023-08-30030 August 2023 Updated Inspection Plan for Braidwood Station Report 05000456/2023005 and 05000457/2023005 IR 05000456/20220062023-03-0101 March 2023 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2022006 and 05000457/2022006) IR 05000456/20220052022-08-22022 August 2022 Updated Inspection Plan for Braidwood Station Units 1 and 2 (Report 05000456/2022005; 05000457/2022005) ML22111A0752022-04-21021 April 2022 Information Request Letter for 2022 Problem Identification and Resolution Inspection at Braidwood Station IR 05000456/20210062022-03-0202 March 2022 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2021006 and 05000457/2021006) ML22034A9862022-02-0404 February 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000456/2022402 05000457/2022402 ML21350A4372021-12-16016 December 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team) Inspection Report 05000456/2022010 and 05000457/2022010 IR 05000456/20210052021-09-0101 September 2021 Updated Inspection Plan for Braidwood Station, Units 1 and 2 (Report 05000456/2021005 and 05000457/2021005) ML21193A0942021-07-12012 July 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21057A1022021-02-25025 February 2021 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000456/2021010; 05000457/2021010 ML21020A1292021-01-20020 January 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000456/2021002; 05000457/2021002 IR 05000456/20200052020-09-0101 September 2020 Updated Inspection Plan for Braidwood Station Units 1 and 2 (Report 05000456/2020005 and 05000457/2020005) ML20183A3912020-07-0101 July 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000456/2020012 and 05000457/2020012 IR 05000456/20190062020-03-0303 March 2020 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2019006 and 05000457/2019006) IR 05000456/20190052019-08-28028 August 2019 Updated Inspection Plan for Braidwood Station, Units 1 and 2 (Report 05000456/2019005; 05000457/2019005) ML19154A6152019-06-0303 June 2019 Ltr. 06/03/19 Braidwood Station, Unit 1 - Notification of NRC Inspection and Request for Information; Inspection Report 05000456/2019004; 05000457/2019004 (DRS-J.Bozga) ML19136A1852019-05-15015 May 2019 Byron Station, Clinton Power Station, Dresden Nuclear Power Station, LaSalle County Station, and Quad Cities Nuclear Power Station-Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency IR 05000456/20180062019-03-0404 March 2019 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000457/2018006 and 05000456/2018006) ML18305A3542018-10-31031 October 2018 Ltr. 10/31/18 Braidwood Station, Units 1 and 2 - Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000456/2019010; 05000457/2019010 (DRS-J.CorujoSandin) IR 05000456/20180052018-08-28028 August 2018 Updated Inspection Plan for Braidwood Station, Units 1 and 2 (Report 05000456/2018005 and 05000457/2018005) IR 05000456/20170062018-03-0202 March 2018 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2017006 and 05000457/2017006) IR 05000456/20170052017-08-28028 August 2017 Updated Inspection Plan for Braidwood Station, Units 1 and 2 (Report 05000456/2017005 and 05000457/2017005) IR 05000456/20160062017-03-0101 March 2017 Annual Assessment Letter for Braidwood Station Units 1 and 2 (Report 05000456/2016006 and 05000457/2016006) ML16265A5772016-09-20020 September 2016 E-Mail; Braidwood Station, Unit 1 - Baseline Inservice Inspection Onsite Information Request (Msh) IR 05000456/20160052016-08-31031 August 2016 MID-CYCLE Assessment Letter for Braidwood Station Units 1 and 2 (Report 05000456/2016005; 05000457/2016005) ML16174A0852016-06-21021 June 2016 Notification of NRC Inspection and Request for Information 05000456/2016004; 05000457/2016004 IR 05000456/20150062016-03-0202 March 2016 Annual Assessment Letter for Braidwood Station Units 1 and 2 (Inspection Report 05000456/2015006 and 05000457/2015006) ML15328A5022015-11-24024 November 2015 Request for Information for an NRC Triennial Baseline Component Design Bases Inspection; Inspection Report 05000456/2016008; 05000457/2016008 (Bxj) IR 05000456/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Braidwood, Units 1 and 2 (Report 05000456/2015005; 05000457/2015005) ML15231A1492015-08-17017 August 2015 Ltr. 08/17/15 Braidwood Station, Unit 2 - Notification of NRC Inspection and Request for Information (Txb) IR 05000456/20140012015-03-0404 March 2015 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2014001; 05000457/2014001) ML15021A2322015-01-20020 January 2015 U1 ISI Request for Information ML14245A0692014-09-0202 September 2014 Mid-Cycle Assessment Letter for Braidwood Station, Units 1 and 2 ML14223B2132014-08-11011 August 2014 Heat Sink Request for Information IR 05000456/20130012014-03-0404 March 2014 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2013001; 05000457/2013001) IR 05000456/20130062013-09-0303 September 2013 Mid-Cycle Assessment Letter (IR 05000456-13-006 & 05000457-13-006) ML13120A5842013-04-29029 April 2013 Request for Information for an NRC Triennial Baseline Component Design Bases Inspection (CDBI) Inspection Report 05000456-13-007 05000457-13-007 IR 05000456/20120012013-03-0404 March 2013 Annual Assessment Letter - Braidwood Station, Units 1 and 2, 05000456/2012001 and 05000457/2012001 ML12248A3062012-09-0404 September 2012 Mid-Cycle Assessment Letter for Braidwood Station Units 1 and 2 IR 05000456/20110072012-03-0505 March 2012 Annual Assessment Letter for Braidwood Station, Units 1 & 2 (Report 05000456-11-007 and 05000457-11-007) IR 05000456/20110062011-09-0101 September 2011 Mid-Cycle Letter for Braidwood Station, Units 1 and 2, - 05000456/2011-006; 05000457/2011-006 ML1024401002010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Braidwood Nuclear Power Plant IR 05000456/20100012010-03-0303 March 2010 Braidwood Power Plant EOC Annual Assessment Letter (05000456-10-001; 05000457-10-001) ML0924404022009-09-0101 September 2009 Braidwood - Mid-Cycle Performance Review and Inspection Plan ML0906302842009-03-0404 March 2009 Annual Assessment Letter - Braidwood (05000456/2010-001; 05000457/2010-001) 2024-08-29
[Table view] Category:Letter
MONTHYEARRS-24-098, Units 1 and 2 - Supplement to License Amendment Request to Revise Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel Assembly Storage, 4.3.1, Fuel Storage, Criticality2024-10-23023 October 2024 Units 1 and 2 - Supplement to License Amendment Request to Revise Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel Assembly Storage, 4.3.1, Fuel Storage, Criticality ML24291A0012024-10-17017 October 2024 Submittal of Core Operating Limits Report, Cycle 25 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-095, Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals2024-10-10010 October 2024 Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24263A1272024-09-23023 September 2024 – Request for Additional Information (EPID 2023-LLA-0136) - Non-Proprietary IR 05000456/20240112024-09-12012 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000456/2024011 and 05000457/2024011 ML24164A0032024-09-10010 September 2024 Issuance of Amendment Nos. 235 and 235 Revision of Technical Specifications for the Ultimate Heat Sink ML24227A0522024-08-29029 August 2024 Audit Plan for LAR to Remove ATWS Mtc Limit IR 05000456/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2024005 and 05000457/2024005) ML24225A1112024-08-13013 August 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000456/20240022024-08-0808 August 2024 Integrated Inspection Report 05000456/2024002 and 05000457/2024002 ML24172A1252024-07-26026 July 2024 Environmental Assessment and Finding of No Significant Impact Related to a Requested Increase in Ultimate Heat Sink Temperature (EPID L-2024-LLA-0075) - Transmittal Letter ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24163A3922024-06-25025 June 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, & Opportunity for a Hearing (EPID L-2024-LLA-0075)- Letter RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24164A2132024-06-13013 June 2024 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Braidwood Nuclear Plant RS-24-057, License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink2024-06-0404 June 2024 License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink IR 05000456/20240102024-05-31031 May 2024 License Renewal Phase 1 Report 05000456/2024010 RS-24-044, License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed2024-05-28028 May 2024 License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed RS-24-043, Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications2024-05-24024 May 2024 Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24136A2452024-05-15015 May 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000457/2024004 ML24136A0132024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report ML24128A1212024-05-0707 May 2024 Response to Braidwood and Dresden FOF Dates Change Request (2025) ML24122A6522024-05-0101 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests IR 05000456/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000456/2024301; 05000457/2024301 RS-24-026, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR)2024-04-25025 April 2024 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML24116A0052024-04-25025 April 2024 Transmittal of Braidwood Station, Unit 1, Core Operating Limits Report, Braidwood Unit 1 Cycle 25 IR 05000456/20240012024-04-24024 April 2024 Integrated Inspection Report 05000456/2024001 and 05000457/2024001 ML24113A1272024-04-22022 April 2024 Audit Plan in Support of Review of LAR Revision of TS 3.7.15, 3.7.16, and 4.3.1 (EPID: L-2023-LLA-0136) (Non-Proprietary) IR 05000457/20240902024-04-19019 April 2024 Final Significance Determination for 2b Auxiliary Feedwater Pump Diesel Engine Fuel Oil Dilution Issue - NRC Inspection Report 05000457/2024090 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-24-034, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-04-10010 April 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors ML24094A2692024-04-0303 April 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Report, WCAP-17451-P, Revision 2, Reactor Internals Guide Tube Wear Westinghouse Domestic Fleet Operational Projections RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24057A0372024-03-26026 March 2024 Proposed Alternative from Certain Requirements Contained in the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI RS-24-024, Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2024-03-22022 March 2024 Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML24067A3252024-03-0707 March 2024 U.S. Department of Energy, Office of Legacy Management, 2023 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites ML24066A0122024-03-0606 March 2024 Operator Licensing Examination Approval Braidwood Station, Units 1 and 2, March 2024 IR 05000456/20244012024-03-0505 March 2024 Cyber Security Inspection Report 05000456/2024401 and 05000457/2024401 (Public) IR 05000456/20230062024-02-28028 February 2024 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2023006 and 05000457/2023006) ML24057A3022024-02-26026 February 2024 Regulatory Conference Supplemental Information ML24047A2382024-02-20020 February 2024 Regulatory Conference to Discuss Risk Associated with 2b Auxiliary Feedwater Pump Diesel Engine Fuel Oil Leak RS-24-013, Response to Request for Additional Information Regarding Proposed Alternative to Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators2024-02-13013 February 2024 Response to Request for Additional Information Regarding Proposed Alternative to Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators IR 05000456/20230042024-02-0202 February 2024 Integrated Inspection Report 05000456/2023004 and 05000457/2023004 2024-09-23
[Table view] |
Text
August 31, 2007 Mr. Christopher M. Crane President and Chief Nuclear Officer
Exelon Nuclear
Exelon Generation Company, LLC
4300 Winfield Road
Warrenville, IL 60555
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
BRAIDWOOD STATION
Dear Mr. Crane:
On August 14, 2007, the NRC staff completed its performance review of the Braidwood Station for the first half of the calendar year (CY) 2007 assessment cycle. Our technical
staff reviewed performance indicators (PIs) for the most recent quarter and inspection
results over the previous 12 months. The purpos e of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at
your facility.
This performance review and enclosed inspection plan do not include security information.
A separate letter designated and marked as "Official Use Only - Security-Related Information"
will include the security cornerstone review and resultant inspection plan.
Plant performance for the most recent quarter at the Braidwood Nuclear Generating Plant Units 1 and 2 was within the Licensee Response column of the NRC's Action
Matrix, based on all inspection findings being classified as having very low safety
significance (Green) and all PIs indicating performance at a level requiring no additional
NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP)
baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to security, scheduled through December 31, 2008. Significant inspections planned include a Biennial Problem
Identification and Resolution inspection in October 2008, and an Evaluation of Changes, Tests, or Experiments and Permanent Plant Modifications inspection in November 2008. The
inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel
availability issues well in advance of inspector arrival onsite. Routine resident inspections are
not listed due to their ongoing and continuous nature. The inspections in the last nine months
of the inspection plan are tentative and may be revised at the end-of-cycle review.
C. Crane In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Reco rds (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
The NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the
inspection plan, we will contact you to discuss the change as soon as possible. Please contact
Richard A. Skokowski at (630) 829-9620 with any questions you may have regarding this letter
or the inspection plan.
Sincerely,/RA by A. H. Hsia for/
Cynthia D. Pederson, Director Division of Reactor Projects Docket Nos. 50-456; 50-457 License Nos. NPF-72; NPF-77
Enclosure:
Braidwood Station Inspection/Activity Plan DISTRIBUTION:
See next page C. Crane In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Reco rds (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
The NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the
inspection plan, we will contact you to discuss the change as soon as possible. Please contact
Richard A. Skokowski at (630) 829-9620 with any questions you may have regarding this letter
or the inspection plan.
Sincerely,/RA by A. H. Hsia for/
Cynthia D. Pederson, Director Division of Reactor Projects Docket Nos. 50-456; 50-457 License Nos. NPF-72; NPF-77
Enclosure:
Braidwood Station Inspection/Activity Plan DISTRIBUTION:
See next page DOCUMENT NAME: G:\Branch TSS\ALL MOC\midcycle 2006 to 2007\Braidwood\Braidwood MOC Letter 2007.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-SensitiveTo receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copyOFFICERIIIRIIINAMERSkokowski:dtpCPederson*AHH forDATE08/24/0708/30/07 OFFICIAL RECORD COPY Letter to C. Crane from C. Pederson dated August 31, 2007
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
BRAIDWOOD STATION cc w/encl:Site Vice President - Braidwood Station Plant Manager - Braidwood Station
Regulatory Assurance Manager - Braidwood Station
Chief Operating Officer
Senior Vice President - Nuclear Services
Vice President - Operations Support
Vice President - Licensing and Regulatory Affairs
Director Licensing
Manager Licensing - Braidwood and Byron
Senior Counsel, Nuclear, Mid-West Regional
Operating Group
Document Control Desk - Licensing
Assistant Attorney General
Illinois Emergency Management Agency
State Liaison Officer
Chairman, Illinois Commerce Commission
Will County Executive
Will County Sheriff
Director, Will County Emergency Management
Agency Mayor of Joliet
City Manager of Joliet
Kendall County Board Chairman
Kendall County Sheriff
Grundy County Board Chairman
Grundy County Sheriff
Grundy County Emergency Management Agency
Mayor of Morris
Minooka Village President
Mayor of Coal City
Mayor of Carbon Hill
Mayor of Diamond
Mayor of Braidwood
Mayor of Wilmington
Channahon Village President
Channahon Village Administrator
Mayor of Shorewood
Shorewood Village Administrator
Mayor of Elwood
Mayor of Braceville
Mayor of Kankakee
INPO Letter to C. Crane from C. Pederson dated August 31, 2007
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
BRAIDWOOD STATION DISTRIBUTION
- RAG1 TEB RFK RidsNrrDirslpab
JLC1 MAS KGO JKH3 RML2 SAM9 SRI Braidwood
DRPIII DRSIII PLB1 TXN Braidwood Inspection / Activity Plan 09/01/2007
-12/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 1 08/28/2007 Report 22 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 10/08/2007 10/19/2007 1 7112102 IP A LARA Planning and Controls 1 BI ENG-ENGINEERING INSERVICE INSPECTION Baseline Inspections 10/08/2007 10/26/2007 1 7111108P IP Inservice Inspection Activities - PWR 3 OL EXAM-EXAM PREPARATION 11/2007 Not Applicable 10/22/2007 10/26/2007 1 W90172 OL - INITIAL EXAM - BRAIDWOOD - NOV/DEC 2007 3 OL EXAM-INITIAL LICENSING EXAM 12/2007 Not Applicable 12/03/2007 12/14/2007 1 W90172 OL - INITIAL EXAM - BRAIDWOOD - NOV/DEC 2007 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 03/10/2008 03/14/2008 1 7112103 IP Radiation Monitoring Instrumentation and Protective Equipment 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 04/28/2008 05/02/2008 1 7112101 IP A ccess Control to Radiologically Significant Areas Baseline Inspections 04/28/2008 05/02/2008 1 7112102 IP A LARA Planning and Controls 1 BI ENG-ENGINEERING INSERVICE INSPECTION Baseline Inspections 04/21/2008 05/16/2008 2 7111108P IP Inservice Inspection Activities - PWR 1 BI ENG-BIENNIAL MAINTENANCE EFFECTIVENESS INSP.
Baseline Inspections 07/21/2008 07/25/2008 1 7111112B IP Maintenance Effectiveness 1 BI ENG-BIENNIAL HEAT SINK INSPECTION Baseline Inspections 08/04/2008 08/08/2008 1 7111107B IP Heat Sink Performance 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 09/22/2008 09/26/2008 1 7112202 IP Radioactive Material Processing and Transportation Baseline Inspections 09/22/2008 09/26/2008 1 71151-BI01 IP Reactor Coolant System Activity Baseline Inspections 09/22/2008 09/26/2008 1 71151-OR01 IP Occupational Exposure Control Effectiveness Baseline Inspections 09/22/2008 09/26/2008 1 71151-PR01 IP RETS/ODCM Radiological Effluent 3 BI PI&R-BIENNIAL PI&R INSPECTION Baseline Inspections 10/06/2008 10/24/2008 1 71152B IP Identification and Resolution of Problems 2 BI ENG-ENGINEERING MODIFICATIONS / 50.59 INSP.
Baseline Inspections 11/03/2008 11/21/2008 1 7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 11/03/2008 11/21/2008 1 7111117B IP Permanent Plant Modifications 3 BI EP-EP EXERCISE INSPECTION / PI VERIFICATION Baseline Inspections 11/17/2008 11/21/2008 1 7111401 IP Exercise Evaluation Baseline Inspections 11/17/2008 11/21/2008 1 71151-EP01 IP Drill/Exercise Performance Baseline Inspections 11/17/2008 11/21/2008 1 71151-EP02 IP ERO Drill Participation Baseline Inspections 11/17/2008 11/21/2008 1 71151-EP03 IP A lert & Notification System This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.