Category:Press Release
MONTHYEARPress Release-16-005, NRC to Issue South Texas Project New Reactor Licenses, Following Conclusion of Mandatory Hearing2016-02-0909 February 2016 Press Release-16-005: NRC to Issue South Texas Project New Reactor Licenses, Following Conclusion of Mandatory Hearing Press Release-15-071, NRC to Hold Mandatory Hearing on South Texas Project New Reactor Application Nov. 19 in Rockville, Md2015-11-0404 November 2015 Press Release-15-071: NRC to Hold Mandatory Hearing on South Texas Project New Reactor Application Nov. 19 in Rockville, Md Press Release-15-061, NRC Completes Safety Review of Proposed New Reactors at South Texas Project2015-10-0101 October 2015 Press Release-15-061: NRC Completes Safety Review of Proposed New Reactors at South Texas Project Press Release-13-103, NRC Issues Final Environmental Impact Statement for South Texas Project Nuclear Power Plant License Renewal2013-12-13013 December 2013 Press Release-13-103: NRC Issues Final Environmental Impact Statement for South Texas Project Nuclear Power Plant License Renewal Press Release-13-084, Atomic Safety and Licensing Board Postpones Hearing on Proposed New South Texas Project Reactors2013-10-0808 October 2013 Press Release-13-084: Atomic Safety and Licensing Board Postpones Hearing on Proposed New South Texas Project Reactors Press Release-13-079, Atomic Safety and Licensing Board to Hold Hearing Oct. 16 in Houston on Proposed New South Texas Project Reactors2013-09-16016 September 2013 Press Release-13-079: Atomic Safety and Licensing Board to Hold Hearing Oct. 16 in Houston on Proposed New South Texas Project Reactors Press Release-11-144, Licensing Board to Conduct Hearing Aug. 17 in Austin, Texas, on South Texas Project New Nuclear Reactor Application2011-08-0202 August 2011 Press Release-11-144: Licensing Board to Conduct Hearing Aug. 17 in Austin, Texas, on South Texas Project New Nuclear Reactor Application Press Release-11-033, NRC Issues Final Environmental Impact Statement for South Texas Project New Reactors Application2011-03-0202 March 2011 Press Release-11-033: NRC Issues Final Environmental Impact Statement for South Texas Project New Reactors Application Press Release-10-178, Licensing Board to Hear Oral Argument Oct. 21 in Bay City, Texas, on South Texas Project New Nuclear Reactor Application2010-10-0606 October 2010 Press Release-10-178: Licensing Board to Hear Oral Argument Oct. 21 in Bay City, Texas, on South Texas Project New Nuclear Reactor Application Press Release-10-054, Licensing Board to Hear Oral Argument April 7 in Bay City, Texas, on South Texas Project New Nuclear Reactor Application2010-03-26026 March 2010 Press Release-10-054: Licensing Board to Hear Oral Argument April 7 in Bay City, Texas, on South Texas Project New Nuclear Reactor Application Press Release-10-050, NRC Seeks Public Input on Draft Environmental Impact Statement for So. Tx. Project New Reactor; Meeting Scheduled2010-03-19019 March 2010 Press Release-10-050: NRC Seeks Public Input on Draft Environmental Impact Statement for So. Tx. Project New Reactor; Meeting Scheduled Press Release-09-107, Licensing Board to Hear Oral Argument June 23-24 in Bay City, Texas, on South Texas Project New Nuclear Reactor Application2009-06-0909 June 2009 Press Release-09-107: Licensing Board to Hear Oral Argument June 23-24 in Bay City, Texas, on South Texas Project New Nuclear Reactor Application Press Release-09-036, NRC Announces Opportunity to Participate in Hearing on New Nuclear Reactor Application for South Texas Project Site2009-02-20020 February 2009 Press Release-09-036: NRC Announces Opportunity to Participate in Hearing on New Nuclear Reactor Application for South Texas Project Site Press Release-08-110, NRC Accepts Partial Application for New Reactor at Calvert Cliffs2008-06-0404 June 2008 Press Release-08-110: NRC Accepts Partial Application for New Reactor at Calvert Cliffs Press Release-08-002, NRC to Hold Public Meetings Feb. 5 on Environmental Scoping for South Texas Project New Reactor Application2008-01-0707 January 2008 Press Release-08-002: NRC to Hold Public Meetings Feb. 5 on Environmental Scoping for South Texas Project New Reactor Application Press Release-07-160, NRC Accepts South Texas Project'S New Reactor Application; Review Schedule Awaits More Information2007-11-29029 November 2007 Press Release-07-160: NRC Accepts South Texas Project'S New Reactor Application; Review Schedule Awaits More Information 2016-02-09
[Table view] |
Text
No: 13-103 December 13, 2013 CONTACT: David McIntyre, 301
-415-8200 NRC Issues Final Environmental Impact Statement for South Texas Project Nuclear Power Plant License Renewal The Nuclear Regulatory Commission has issued its final supplemental environmental impact statement (SEIS) for the proposed renewal of the operating licenses for the South Texas Project nuclear power plant, Units 1 and 2. The report concludes there are no environmental impacts that would preclude renewing the plant's licenses.
The South Texas Project is two pressurized water reactors located in Bay City, about 90 miles southwest of Houston. The current licenses expire on Aug. 20, 2027, for Unit 1 and Dec. 15, 2028, for Unit 2. The licensee, STP Nuclear Operating Co., filed its renewal application on Oct. 25, 2010 , seeking to extend the operating licenses for an additional 20 years, to 2047 for Unit 1 and 2048 for Unit
- 2. The license renewal review process proceeds along two tracks
- one for review of safety issues and another for environmental issues. As part of its environmental review of the application, the NRC held public meetings near the plant to discuss the review process and the draft version of the environmental impact statement. Comments were received and considered from members of the public, local officials, and representatives of state and federal agencies.
The NRC published a safety evaluation report with open items in February. However, the safety review has been paused until 2014 at the applicant's request.
The final supplemental environmental impact statement for the South Texas Project license renewal (NUREG-1437, Supplement 48
), as well as the license renewal application and other information on the review, can be found on the NRC website.