Letter Sequence Request |
---|
EPID:L-2017-LRM-0066, Slides - January 11, 2018, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit 1 Application of Leak Before Break on U1 RCS Auxiliary Lines (Open) |
|
MONTHYEARML18018B1392018-01-11011 January 2018 Slides - January 11, 2018, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit 1 Application of Leak Before Break on U1 RCS Auxiliary Lines Project stage: Request ML18018B1382018-01-22022 January 2018 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 Project stage: Meeting 2018-01-11
[Table View] |
Similar Documents at Cook |
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML23208A2922023-07-31031 July 2023 Pre-Application 7/31/2023 Meeting Slides ML22343A1752022-12-14014 December 2022 Pre-Application Public Meeting for Proposed License Amendment to Revise the CNP Emergency Plan - December 14, 2022 (Slides) ML22307A0042022-11-0707 November 2022 Slides - Pre-Application November 7, 2022 Meeting Slides ML22158A0642022-06-0707 June 2022 2021 Dresden and Quad Cities Nuclear Power Stations End of Cycle Meeting Presentation ML22006A3482022-01-0606 January 2022 Pre-Application Meeting January 11, 2022, Slides Regarding GSI-191 ML21196A4592021-07-15015 July 2021 2020 Donald C. Cook Nuclear Plant End-of-Cycle Meeting Presentation ML21196A0042021-07-14014 July 2021 Slides - Cook - Pre-Application EP 7/20/2021 Meeting Slides ML21077A0102021-03-16016 March 2021 Handout for Pre-Submittal Meeting with NRC and DC Cook Plant in March 19, 2021 ML19099A3272019-04-0202 April 2019 DC Cook ISI 10 Year Interval Layout ML18018B1392018-01-11011 January 2018 Slides - January 11, 2018, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit 1 Application of Leak Before Break on U1 RCS Auxiliary Lines ML17265A4922017-10-0404 October 2017 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 2 ML14189A5622014-07-0909 July 2014 July 9 NRC Slides for Public Meeting with Indiana/Michigan Power Co. (D.C. Cook) - NTTF 2.1 - Seismic Reevaluation - GMRS ML14190A1852014-07-0909 July 2014 July 9 Public Meeting Slides Indiana/Michigan Power Co (D.C. Cook) - NTTF 2.1 - Seismic Reevaluation - GMRS ML14197A6102014-07-0808 July 2014 July 8, 2014 NRC Slides - Donald C. Cook Nuclear Power Plant Annual Assessment Meeting ML13176A1332013-06-25025 June 2013 June 26, 2013 Public Meeting Slides Concerning D.C. Cook Unit 1 LAR to Return to Normal Operating Pressure and Temperature ML13189A2222013-04-12012 April 2013 D.C Cook Unit 1: April 12, 2013, Telecon Slides ML1116402632011-06-16016 June 2011 EOC NRC Slides for Meeting ML1112903222011-05-0606 May 2011 Slides for the 5/10/11 Meeting to Discuss Pre-application Issues Concerning Use of NFPA-805 (Fire Protection) ML1108207372011-03-21021 March 2011 Summary of Meeting Between NRC and D. C. Cook Emergency Preparedness and Regulatory Affairs to Discuss the Upcoming March 2011 Emergency Preparedness Exercise ML0734800872007-12-12012 December 2007 D.C. Cook Meeting Handout on Ice Condenser Ice Fusion ML0725306142007-09-21021 September 2007 Public Meeting Summary on the Reactor Oversight Process ML0724000232007-08-23023 August 2007 Afpb Staff Response to NFPA 805 Transition Pilot Plant FAQ 06-0011, Revision 1 ML0619507072006-07-14014 July 2006 Summary of Public Meeting at DC Cook to Discuss the End-of-Cycle Performance Assessment ML0613100372006-05-10010 May 2006 D.C. Cook Meeting Handout ML0513603422005-05-10010 May 2005 Public Meeting Handouts - May 10, 2005 ML0512603912005-04-21021 April 2005 Public Meeting NRC Slides DC Cook End-of-Cycle Plant Performance Assessment ML0331400482003-11-0606 November 2003 Handouts for Public Meeting Between NRC, DC Cook, and Framatome Fuel Transition ML0310703202003-04-21021 April 2003 Summary of Public Meeting with American Electric Power Co., to Discuss D.C. Cook End of Cycle Plant Performance Assessment.. Licensee'S Slides ML0309204992003-04-21021 April 2003 Summary of Public Meeting with American Electric Power Co., to Discuss D.C. Cook End of Cycle Plant Performance Assessment. NRC Presentation Slides ML0315307162003-04-18018 April 2003 April 18, 2003 - RIC 2003 Presentation - F2 - James E. Dyer - Region III Breakout ML0315307202003-04-18018 April 2003 April 18, 2003 - RIC 2003 Presentation - F2 - Chris Bakken - Region III Breakout 2023-07-31
[Table view] |
Text
D.C. Cook Application of Leak Before Break on U1 RCS Auxiliary LinesJanuary 11, 2018 Leak Before Break (LBB) Background
- All SSCs important to Safety require protection from accidents, including pipe break. *Historically, the method of pipe break protection has been to assume an instantaneous formation of an arbitrary break and separation across the pipe diameter. This methodology is non
-mechanistic and provides the most severe condition requiring a complex protection system to counteract the dynamic forces created by the pipe break.
- In reality, a pipe break occurs through the formation of a tiny crack in the line that, if unstable, develops into a full size crack over time. A second method to protect from a pipe break accident is to evaluate the potential for the pipe to crack and, in the event of formation, evaluate whether sufficient warning will be available to safely shut down the plant.
- This methodology has been termed "Leak Before Break" (LBB) and the application for this methodology has been provided for in modified GDC 4 of Appendix A of 10 CFR Part 50. Guidance for the application of LBB methodology is provided in NUREG-1061, Volume 3 and in the Standard Review Plan (NUREG
-0800) Section 3.6.3.
D.C. Cook Unit 1 LBB LAR
- LBB methodology has previously been approved by the NRC for Unit 1 and applied to the Main Reactor Coolant Loop piping. (NRC SE ML8402010410, dated 2/1/84)
- LBB methodology has previously been approved by the NRC for Unit 1 and applied to the Pressurizer Surge Line. (NRC SE ML003767675, dated 11/8/2000)
- In this License Amendment Request (LAR), NRC approval is requested for implementation of LBB methodology for Unit 1 RCS Auxiliary Lines, which includes:
-8" and 14" RHR lines
-10" Accumulator lines
-6", 8" and 10" SI lines
- This LAR will not include changes to our Technical Specifications. Previous NRC approval for LBB for Unit 1 Pressurizer Surge Line modified the Technical Specification for Leakage Detection. The existing Leakage Detection capability for Unit 1 is sufficient for the requirements of the LBB analysis for Unit 1 RCS Auxiliary Lines Why and when?
- Purpose of LBB methodology on RCS Auxiliary Lines for Cook Unit 1:
-The primary purpose is for risk mitigation for the reactor vessel internals upflowconversion modification being implemented on Unit 1 in the Spring 2019 refueling outage.
- Analysis to support the modification is scheduled to be completed October 2018.
- Although a low risk, the analysis for upflowconversion could potentially be unacceptable without the added margin provided by application of LBB methodology on RCS Auxiliary Lines.
-Baffle bolt replacement activities scheduled for Spring 2019 refueling outage may be able to be reduced in scope given the margin provided by approval of this LBB analysis, resulting in a shorter outage duration.
-Significantly reduces dynamic loading on equipment and supports
-Increases available design margins and results in overall reduction of loads on piping and supports
-Can be used to eliminate the need for existing pipe whip restraints
- The proposed timeline for this LAR is as follows:
-LAR to be submitted to NRC in February 2018
-NRC approval requested by December 2018 Questions?