ML070460007

From kanterella
Revision as of 14:47, 10 February 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search

Request No. ISI-2006-1 to Use Later Edition and Addenda of the ASME Boiler & Pressure Vessel Code, Section Xi for Repair And/Or Replacement Activities - Third 10-year ISI Interval (TAC Nos. MD2702 and MD2703)
ML070460007
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 03/08/2007
From: Terao D
NRC/NRR/ADRO/DORL/LPLIV
To: Mitchell T G
Entergy Operations
Saba F E, NRR/DORL/LPL4, 301-415-1447
References
TAC MD2702, TAC MD2703
Download: ML070460007 (4)


Text

March 8, 2007 Mr. Timothy G. Mitchell Vice President, Operations

Arkansas Nuclear One

Entergy Operations, Inc.

1448 SR 333

Russellville, AR 72802

SUBJECT:

ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 - REQUEST NO. ISI-2006-1 TO USE LATER EDITION AND ADDENDA OF THE AMERICAN SOCIETY OF

MECHANICAL ENGINEERS BOILER AND PRESSURE VESSEL CODE, SECTION XI, FOR REPAIR AND/OR REPLACEMENT ACTIVITIES (TAC

NOS. MD2702 AND MD2703)

Dear Mr. Mitchell:

By letter dated August 2, 2006, Entergy Operations, Inc., requested to use SubarticleIWA-4461.4 of Section XI of the 1995 Edition, 1997 Addenda of the American Society of Mechanical Engineers Boiler and Pressure Vessel (ASME) Code at Arkansas Nuclear One, Units 1 and 2 (ANO-1 and ANO-2). Subarticle IWA-4461.4 provides requirements for qualification of thermal removal processes as an alternative to mechanical processing of thermally cut surfaces. The licensee submitted Request ISI-2006-1 in accordance with the Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2004-16, "Use of Later Editions and Addenda to ASME Code,Section XI, for Repair/Replacement Activities," dated October 19, 2004.

On the basis of information submitted, the NRC staff concludes that the proposed request is acceptable and approves the use of the 1995 Edition, 1997 Addenda of the ASME Code,Section XI, for the repair/replacement activities for the remainder of the third 10-year inservice

inspection (ISI) interval at ANO-1 and ANO-2, in accordance with paragraph 50.55a(g)(4)(iv) of

Title 10 of the Code of Federal Regulations. The start date of the next 10-year ISI interval for ANO-1 and ANO-2 is June 1, 2007, and March 26, 2010, respectively.

The NRC staff's safety evaluation is enclosed. This completes the NRC staff's review under TAC Nos. MD2702 and MD2703. If you have any questions concerning this matter, please call

Farideh Saba of my staff at 301-415-1447.

Sincerely,/RA/David Terao, Chief Plant Licensing Branch IV

Division of Operating Reactor Licensing

Office of Nuclear Reactor Regulation Docket Nos. 50-313 and 50-368

Enclosure:

Safety Evaluation cc w/encl: See next page March 8, 2007 Mr. Timothy G. Mitchell

Vice President, Operations

Arkansas Nuclear One

Entergy Operations, Inc.

1448 SR 333

Russellville, AR 72802

SUBJECT:

ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 - REQUEST NO. ISI-2006-1 TO USE LATER EDITION AND ADDENDA OF THE AMERICAN SOCIETY OF

MECHANICAL ENGINEERS BOILER AND PRESSURE VESSEL CODE, SECTION XI, FOR REPAIR AND/OR REPLACEMENT ACTIVITIES (TAC

NOS. MD2702 AND MD2703)

Dear Mr. Mitchell:

By letter dated August 2, 2006, Entergy Operations, Inc., requested to use SubarticleIWA-4461.4 of Section XI of the 1995 Edition, 1997 Addenda of the American Society of Mechanical Engineers Boiler and Pressure Vessel (ASME) Code at Arkansas Nuclear One, Units 1 and 2 (ANO-1 and ANO-2). Subarticle IWA-4461.4 provides requirements for qualification of thermal removal processes as an alternative to mechanical processing of thermally cut surfaces. The licensee submitted Request ISI-2006-1 in accordance with the Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2004-16, "Use of Later Editions and Addenda to ASME Code,Section XI, for Repair/Replacement Activities," dated October 19, 2004.

On the basis of information submitted, the NRC staff concludes that the proposed request is acceptable and approves the use of the 1995 Edition, 1997 Addenda of the ASME Code,Section XI, for the repair/replacement activities for the remainder of the third 10-year inservice

inspection (ISI) interval at ANO-1 and ANO-2, in accordance with paragraph 50.55a(g)(4)(iv) of

Title 10 of the Code of Federal Regulations. The start date of the next 10-year ISI interval for ANO-1 and ANO-2 is June 1, 2007, and March 26, 2010, respectively.

The NRC staff's safety evaluation is enclosed. This completes the NRC staff's review under TAC Nos. MD2702 and MD2703. If you have any questions concerning this matter, please call

Farideh Saba of my staff at 301-415-1447.

Sincerely,/RA/David Terao, Chief Plant Licensing Branch IV

Division of Operating Reactor Licensing

Office of Nuclear Reactor Regulation Docket Nos. 50-313 and 50-368

Enclosure:

Safety Evaluation cc w/encl: See next pageDISTRIBUTION

PUBLIC LPLIV r/f RidsAcrsAcnwMailCenter

RidsNrrDorlLpl4 RidsNrrLAJBurkhardt RidsNrrDciCvib (KGruss)

RidsNrrPMFSaba

RidsOgcRp RidsRgn4MailCenter DCullison, EDO Region IV JTsao, NRRADAMS Accession No.: ML070460007

  • See SE input.OFFICEDORL/LPL4/PMDORL/LPL4/LADCI/CVIB/BCOGC - NLODORL/LPL4/BCNAMEFSabaLFeizollahiKGruss*JRundDTerao DATE3/1/073/1/072/8/073/8/073/8/07 February 2007OFFICIAL AGENCY RECORD Arkansas Nuclear One cc: Executive Vice President

& Chief Operating Officer

Entergy Operations, Inc.

P.O. Box 31995

Jackson, MS 39286-1995 General Manager Plant Operations

Entergy Operations, Inc.

Arkansas Nuclear One

1448 SR 333

Russellville, AR 72802 Director, Nuclear Safety Assurance Entergy Operations, Inc.

Arkansas Nuclear One

1448 SR 333

Russellville, AR 72802 Manager, Licensing Entergy Operations, Inc.

Arkansas Nuclear One

1448 SR 333

Russellville, AR 72802 Director, Nuclear Safety & Licensing Entergy Operations, Inc.

1340 Echelon Parkway

Jackson, MS 39213-8298 Section Chief, Division of Health Radiation Control Section

Arkansas Department of Health and

Human Services

4815 West Markham Street, Slot 30

Little Rock, AR 72205-3867 Section Chief, Division of Health Emergency Management Section

Arkansas Department of Health and

Human Services

4815 West Markham Street, Slot 30

Little Rock, AR 72205-3867 Senior Resident Inspector U.S. Nuclear Regulatory Commission

P.O. Box 310

London, AR 72847 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission

611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 County Judge of Pope County 100 W. Main Street

Russellville, AR 72801 Vice President, Operations Support Entergy Operations, Inc.

P.O. Box 31995

Jackson, MS 39286-1995 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATIONUSE OF LATER ASME CODE, SECTION XI FOR THERMAL REMOVAL PROCESSES ENTERGY OPERATIONS, INC.

ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 DOCKET NUMBERS 50-313 AND 50-36

81.0INTRODUCTION

By letter dated August 2, 2006 (Agencywi de Documents Access and Management System (ADAMS) Accession No. ML062200491), Entergy Operations, Inc., requested to use Subarticle IWA-4461.4 of Section XI of the 1995 Edition, 1997 Addenda of the American Society of

Mechanical Engineers Boiler and Pressure Vessel (ASME) Code at Arkansas Nuclear One, Units 1 and 2 (ANO-1 and ANO-2). Subarticle IWA-4461.4 provides requirements for

qualification of thermal removal processes as an alternative to mechanical processing of

thermally cut surfaces.

The licensee submitted Request ISI-2006-1 in accordance with the Nuclear Regulatory Commission (NRC) Regulatory Issue Summary (RIS) 2004-16, "Use of Later Editions and Addenda to ASME Code,Section XI, for Repair/Replacement Activities," dated October 19, 2004. RIS 2004-16 states that licensees who wish to use provisions of subsequent editions and addenda of the ASME Code,Section XI, for activities, including repair/replacement activities, must receive prior NRC approval as required by paragraph 50.55a(g)(4)(iv) of Title 10 of the

Code of Federal Regulations (10 CFR). 2.0REGULATORY REQUIREMENTS Pursuant to 10 CFR 50.55a(g)(4), ASME Code Class 1, 2, and 3 components (including supports) shall meet the requirements, except the design and access provisions and the

pre-service examination requirements, set forth in the ASME Code,Section XI, "Rules for Inservice Inspection [ISI] of Nuclear Power Plant Components," to the extent practical within the

limitations of design, geometry, and materials of construction of the components. Paragraph

50.55a(g)(4)(ii) of 10 CFR requires that ISI examination of components and system pressure tests conducted during successive 120-month inspection intervals must comply with the requirements in the latest edition and addenda of Section XI of the ASME Code, incorporated by

reference in 10 CFR 50.55a(b), 12 months prior to the start of the 120-month interval, subject to

the limitations and modifications listed therein.

The repair, replacement, and modification of pl ant components are not explicitly mentioned in 10 CFR 50.55a(g)(4) and associated subparagraphs. However, these activities are specifically mentioned in the ASME Code,Section XI. The NRC staff maintains that these activities are not separate and distinct from, but are included under , inservice examinations. Therefore, the requirements of 10 CFR 50.55a(g)(4)(iv) are applicable to repair/replacement activities.

Paragraph 10 CFR 50.55a(g)(4)(iv) states that inservice examination of components and system pressure tests may meet the requirements set forth in subsequent editions and addenda

of the ASME Code provided that they are incorporated by reference in 10 CFR 50.55a(b),

subject to the limitations and modifications listed in 10 CFR 50.55a(b), and subject to

Commission approval. Portions of editions or addenda may be used provided that all related

requirements of the respective editions or addenda are met. Currently, paragraph 50.55a(b)(2) of 10 CFR incorporates by reference the ASME Code,Section XI, from the 1970 Edition through

the 1976 Winter Addenda, and the 1977 Edition through the 2003 Addenda.3.0LICENSEE'S REQUEST ISI-2006-13.1ASME Code Components AffectedAll Class 1, 2, and 3 vessels, piping, pumps, and valves in the Section XI pressure boundary at ANO-1 and ANO-2.3.2Applicable Code Edition and Addenda Repair/replacement activities at ANO-1 and ANO-2 are currently performed in accordance withthe 1992 Edition of ASME Code,Section XI, with portions of the 1993 Addenda for pressure

testing.The start date of the next 120-month ISI interval (the fourth interval) for ANO-1 and ANO-2 is June 1, 2007, and March 26, 2010, respectively.3.3Proposed Subsequent Code Edition and Addenda (or Portion)

The licensee currently performs repair/replacement activities in accordance with the 1992Edition of ASME Code,Section XI, with portions of the 1993 Addenda for pressure testing.

However, Subarticle IWA-4000 in the 1992 Edition does not contain rules for qualifying thermal

removal processes, such as electrodischarge machining, that can be used without mechanical

processing of thermally cut surfaces.The 1997 Addenda of the 1995 Edition of the ASME Code,Section XI, revised the rules applicable to thermal removal processes for all repair/replacement activities. The 1997

Addenda also added new rules that exempted mechanical processing of thermally cut surfaces

provided the thermal removal process was qualified in accordance with Subarticle IWA-4461.4 of the ASME Code,Section XI.

Pursuant to 10 CFR 50.55a(g)(4)(iv), the licensee requested permission to use SubarticleIWA-4461.4 in the 1995 Edition, 1997 Addenda of ASME Code,Section XI. Subarticle

IWA-4461.4 provides rules for qualifying thermal removal processes as an alternative to

mechanical processing of thermally cut surfaces of P-Numbers 3, 4, 5, 6, 7, 8, 9, 10, 11A, and

43 materials. The NRC approved the use of the 1995 Edition, 1997 Addenda as documented in 10 CFR 50.55a(b)(2) with no limitations, conditions, or modifications on Subarticle IWA-4461.4.3.4Related Requirements Subarticle IWA-4461.4 of the 1995 Edition, 1997 Addenda specifies rules for qualification of a thermal removal process as an alternative to mechanical processing of thermally cut surfaces.

When applying Subarticle IWA-4461.4, the following related requirement also applies:

Subarticle IWA-4461.4 states that "[m]echanical processing of thermally cut surfaces for materials identified in IWA-4461.2 and IWA-4461.3 is not required

when using a thermal removal process qualified as follows-" Because

[Subarticle] IWA-4461.4 is an alternative to mechanical processing of thermally

cut surfaces for the materials identified in [Subarticles] IWA-4461.2 and

IWA-4461.3, it is only applicable to P-Number[s] 3, 4, 5, 6, 7, 8, 9, 10, 11A, and

43 materials; it cannot be applied to P-Number 1 materials of [Subarticle]

IWA-4461.1.

Therefore, when invoking Subarticle IWA-4461.4 in the 1995 Edition, 1997 Addenda, the licensee will also apply this related requirement.

The NRC prohibition on "evaluation of thermally cut surfaces" in 10 CFR 50.55a(b)(2)(xxiii) does not apply to the qualification alternative of IWA-4461.4. Rather, this NRC prohibition applies to

Subarticle IWA-4461.4.2, "Evaluation of Thermally Cut Surfaces," which was not included into the ASME Code,Section XI, until the 2001 Edition.3.5Duration of Proposed Request ANO-1 and ANO-2 are currently under the third ISI interval. The duration of Request ISI-2006-1 will be effective from the date of the NRC approval to June 1, 2007, for ANO-1 and March 26, 2010, for ANO-2. These are the dates for the start of the next (fourth) ISI interval. Therefore, the duration of the proposed request is for the remainder of the third ISI interval at ANO-1 and

ANO-2.4.0STAFF EVALUATION The NRC staff evaluated the licensee's request ISI-2006-1 pursuant to 10 CFR 50.55a(g)(4)(iv), which states that inservice examination of co mponents and system pressure tests may meet the requirements set forth in subsequent editions and addenda of the ASME Code provided certain

criteria are satisfied.The first criterion is that the edition and addenda of the ASME Code,Section XI, that will be used in the proposed request is incorporated by reference in 10 CFR 50.55a(b). Currently, paragraph 50.55a(b)(2) incorporates by reference the ASME Code,Section XI, from the

1970 Edition through the 1976 Winter Addenda, and the 1977 Edition (Division 1) through the

2003 Addenda (Division 1), which includes the 1995 Edition, 1997 Addenda of the ASME Code,Section XI, which was proposed by the licensee. Therefore, the NRC staff finds that the first

criterion has been satisfied. The second criterion is that the limitations and modifications listed in 10 CFR 50.55a(b) are satisfied for the specific use of the proposed subsequent edition and addenda of the ASME Code,Section XI. Paragraph 50.55a(b) of 10 CFR sets no limitations and modifications on Subarticle IWA-4461.4 of the 1995 Edition, 1997 Addenda of the ASME Code,Section XI.

Therefore, the NRC staff finds that the second criterion has been satisfied.

The third criterion is that if portions of subsequent editions or addenda of the ASME Code,Section XI, are used, all related requirements of the respective editions or addenda must be

met. The NRC staff is satisfied that the licensee has listed all related requirements in Subarticle IWA-4461.4 of the 1995 Edition, 1997 Addenda of the ASME Code,Section XI, that are relevant

to the stated repair/replacement activities. Therefore, the NRC staff finds that the third criterion

has been satisfied.

Based on the above, the NRC staff finds that the criteria of 10 CFR 50.55a(g)(4)(iv) are satisfied and that the licensee's request to use the 1995 Edition, 1997 Addenda of the ASME Code,Section XI, for repair/replacement activities is acceptable.

5.0CONCLUSION

On the basis of evaluating the information submitted, the NRC staff concludes that the proposed request ISI-2006-1 is acceptable and approves the use of Subarticle IWA-4461.4 of the 1995 Edition, 1997 Addenda of the ASME Code,Section XI, for the specified repair/replacement

activities for the remainder of the third 10-year ISI intervals at ANO-1 and ANO-2. All other requirements of the ASME Code, Sections III and XI, for which relief has not been specifically requested and approved remain applic able, including third-party review by the Authorized Nuclear Inservice Inspector.

Principal Contributor: John Tsao

Date: March 8, 2007