ML13182A350 | 26 June 2013 | Point Beach | License Amendment Request 271 - Transition to 10 CFR 50.48(c) - NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition. Part 2 of 3 | Other |
ML13256A197 | 9 September 2013 | Beltz T Plant Licensing Branch III | NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 Acceptance Review Regarding the NFPA 805 License Amendment Request - Opportunity to Supplement | Acceptance Review |
ML13267A037 | 25 September 2013 | Beltz T Plant Licensing Branch III | Acceptance Review of Licensing Action License Amendment Request to Transition to NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants | Acceptance Review |
ML14127A294 | 9 May 2014 | Beltz T Plant Licensing Branch III | Regulatory Audit in Support of License Amendment Request to Implement NFPA 805, as Incorporated Into 10 CFR 50.48(c) | Other |
ML14153A390 | 27 May 2014 | Beltz T Plant Licensing Branch III | NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 Final Requests for Additional Information License Amendment Request Associated with NFPA 805 (TAC Nos. MF2372 and MF2373) | RAI |
ML14189A365 | 8 July 2014 | Beltz T Plant Licensing Branch III | NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 Final (Revised) Requests for Additional Information License Amendment Request Associated with NFPA 805 | RAI |
ML14325A540 | 19 November 2014 | Beltz T Plant Licensing Branch III | NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Follow-up Requests for Additional Information (Afpb) NFPA 805 License Amendment Request Review | RAI |
ML14325A541 | 14 November 2014 | Beltz T Plant Licensing Branch III | NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Follow-up Requests for Additional Information (Afpb) NFPA 805 License Amendment Request Review | RAI |
ML15091A517 | 6 April 2015 | Point Beach Cross W | 4/6/2015, Meeting Slide for Public Teleconference on Point Beach MCR Abandonment Analysis for Loss of Control Scenarios | Request |
ML15106A593 | 14 April 2015 | Mahesh Chawla Plant Licensing Branch III | NRR E-mail Capture - Request for Additional Information - Point Beach Nuclear Plant, Unit 1 and 2 - MF2372 and MF2373 | RAI |
ML15106A712 | 23 April 2015 | Mahesh Chawla Plant Licensing Branch III | Summary of April 6, 2015, Meeting with NextEra Energy Point Beach, LLC, to Discuss License Amendment Request to Transition to NFPA 805 | Meeting |
ML15121A057 | 15 May 2015 | Mahesh Chawla Plant Licensing Branch III | June 9 - 12, 2014 Summary of Audit at Point Beach Nuclear Plant, Unit Nos. 1 and 2, Associated with License Amendment Request to Transition to National Fire Protection Association Standard 805 | Other |
NRC 2013-0092, License Amendment Request 271 Supplement 1 Transition to 10 CFR 50.48(c)- NFPA 805 | 16 September 2013 | Point Beach Meyer L | License Amendment Request 271 Supplement 1 Transition to 10 CFR 50.48(c)- NFPA 805 | Supplement |
NRC 2014-0054, Response (90 Day) to Request for Additional Information License Amendment Request Associated with NFPA 805 | 28 August 2014 | Point Beach Mccartney E | Response (90 Day) to Request for Additional Information License Amendment Request Associated with NFPA 805 | Request |
NRC 2014-0056, Response (120 Day) to Request for Additional Information and Revision to 60 Day Response License Amendment Request 271 Associated with NFPA 805 | 25 September 2014 | Point Beach Mccartney E | Response (120 Day) to Request for Additional Information and Revision to 60 Day Response License Amendment Request 271 Associated with NFPA 805 | Request |
NRC 2014-0073, Response to Request for Additional Information (Radiation Release) License Amendment Request 271 Associated with NFPA 805 | 14 November 2014 | Point Beach Mccartney E | Response to Request for Additional Information (Radiation Release) License Amendment Request 271 Associated with NFPA 805 | Response to RAI |
NRC 2016-0012, Response to Request for Additional Information, License Amendment Request 271 Associated with NFPA 805 | 7 April 2016 | Point Beach Mccartney E | Response to Request for Additional Information, License Amendment Request 271 Associated with NFPA 805 | Response to RAI |
NRC-2014-0043, Response (60 Day) to Request for Additional Information License Amendment Request Associated with NFPA 805 | 29 July 2014 | Point Beach Mccartney E | Response (60 Day) to Request for Additional Information License Amendment Request Associated with NFPA 805 | Request |