MONTHYEARML13182A3502013-06-26026 June 2013 License Amendment Request 271 - Transition to 10 CFR 50.48(c) - NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition. Part 2 of 3 Project stage: Other ML13256A1972013-09-0909 September 2013 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 Acceptance Review Regarding the NFPA 805 License Amendment Request - Opportunity to Supplement Project stage: Acceptance Review NRC 2013-0092, License Amendment Request 271 Supplement 1 Transition to 10 CFR 50.48(c)- NFPA 8052013-09-16016 September 2013 License Amendment Request 271 Supplement 1 Transition to 10 CFR 50.48(c)- NFPA 805 Project stage: Supplement ML13267A0372013-09-25025 September 2013 Acceptance Review of Licensing Action License Amendment Request to Transition to NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Acceptance Review ML14127A2942014-05-0909 May 2014 Regulatory Audit in Support of License Amendment Request to Implement NFPA 805, as Incorporated Into 10 CFR 50.48(c) Project stage: Other ML14153A3902014-05-27027 May 2014 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 Final Requests for Additional Information License Amendment Request Associated with NFPA 805 (TAC Nos. MF2372 and MF2373) Project stage: RAI ML14189A3652014-07-0808 July 2014 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 Final (Revised) Requests for Additional Information License Amendment Request Associated with NFPA 805 Project stage: RAI NRC-2014-0043, Response (60 Day) to Request for Additional Information License Amendment Request Associated with NFPA 8052014-07-29029 July 2014 Response (60 Day) to Request for Additional Information License Amendment Request Associated with NFPA 805 Project stage: Request NRC 2014-0054, Response (90 Day) to Request for Additional Information License Amendment Request Associated with NFPA 8052014-08-28028 August 2014 Response (90 Day) to Request for Additional Information License Amendment Request Associated with NFPA 805 Project stage: Request NRC 2014-0056, Response (120 Day) to Request for Additional Information and Revision to 60 Day Response License Amendment Request 271 Associated with NFPA 8052014-09-25025 September 2014 Response (120 Day) to Request for Additional Information and Revision to 60 Day Response License Amendment Request 271 Associated with NFPA 805 Project stage: Request ML14325A5412014-11-14014 November 2014 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Follow-up Requests for Additional Information (Afpb) NFPA 805 License Amendment Request Review Project stage: RAI NRC 2014-0073, Response to Request for Additional Information (Radiation Release) License Amendment Request 271 Associated with NFPA 8052014-11-14014 November 2014 Response to Request for Additional Information (Radiation Release) License Amendment Request 271 Associated with NFPA 805 Project stage: Response to RAI ML14325A5402014-11-19019 November 2014 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Follow-up Requests for Additional Information (Afpb) NFPA 805 License Amendment Request Review Project stage: RAI ML15091A5172015-04-0606 April 2015 4/6/2015, Meeting Slide for Public Teleconference on Point Beach MCR Abandonment Analysis for Loss of Control Scenarios Project stage: Request ML15106A5932015-04-14014 April 2015 NRR E-mail Capture - Request for Additional Information - Point Beach Nuclear Plant, Unit 1 and 2 - MF2372 and MF2373 Project stage: RAI ML15106A7122015-04-23023 April 2015 Summary of April 6, 2015, Meeting with NextEra Energy Point Beach, LLC, to Discuss License Amendment Request to Transition to NFPA 805 Project stage: Meeting ML15121A0572015-05-15015 May 2015 June 9 - 12, 2014 Summary of Audit at Point Beach Nuclear Plant, Unit Nos. 1 and 2, Associated with License Amendment Request to Transition to National Fire Protection Association Standard 805 Project stage: Other NRC 2016-0012, Response to Request for Additional Information, License Amendment Request 271 Associated with NFPA 8052016-04-0707 April 2016 Response to Request for Additional Information, License Amendment Request 271 Associated with NFPA 805 Project stage: Response to RAI 2014-07-29
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24248A0152024-09-0505 September 2024 Summary of August 28, 2024, Public Pre-Application Meeting with NextEra Energy Point Beach, LLC Regarding Assessing Seismic Risk ML24227A5082024-08-15015 August 2024 Summary of the July 15, 2024, Public Outreach to Discuss the NRC 2023 End-Of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML23199A0262023-07-18018 July 2023 Summary of Public Outreach to Discuss the NRC 2022 End of Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML23118A1762023-05-0404 May 2023 – Audit Summary for License Amendment Request Regarding Risk-Informed Approach for Closure of Generic Safety Issue 191 ML22144A0022022-09-14014 September 2022 Summary of February 16, and May 18, 2022, Meetings with Nextera Energy/Florida Power & Light Company Regarding Planned Submittal of License Amendment Request for a Common Fleet Emergency Plan ML22181B1182022-06-30030 June 2022 Summary of the June 23, 2022, Public Outreach to Discuss the NRC 2021 End-of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML22019A2792022-01-20020 January 2022 Summary of Public Webinar with NextEra Energy Point Beach, LLC Regarding Future License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant ML22004A0772022-01-0606 January 2022 Summaries of December 8, 2021 Draft Supplemental Environmental Impact Statement for Subsequent License Renewal Application Public Meetings ML21295A2532021-10-26026 October 2021 Summary of Public Webinar with NextEra Energy Point Beach,Llc Regarding Proposed Future LAR to Adopt TSTF-505, Rev.2, Provide Risk Informed Extended Completion Times-RITSTF Initiative 4B, at Point Beach Plant, Units 1&2 (L-2021-LRM-0086) ML21288A1222021-10-20020 October 2021 SLRA Summary of August 5, 2021, Public Meeting on Proposed Aging Management Activities of Irradiated Concrete and Steel Reactor Vessel Supports ML21214A1512021-08-27027 August 2021 SLRA June 3, 2021, Public Meeting - Proposed Aging Management Activities of Irradiated Concrete and Steel Reactor Vessel Supports ML21214A1652021-08-27027 August 2021 SLRA June 30, 2021, Public Meeting - Proposed Aging Management of Reactor Vessel Internals ML21161A2992021-06-17017 June 2021 Summary of May 18, 2021 Public Webinar with Nextera Energy Point Beach, LLC Regarding Path Forward for Generic Letter 2004-02 Closure ML21166A2192021-06-15015 June 2021 Summary of June 10, 2021, Public Webinar to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of the Point Beach Nuclear Plant ML21148A1162021-06-0101 June 2021 SLRA Public Meeting Discussion Questions 6-3-21 ML21075A3422021-03-17017 March 2021 Meeting Summary: Public Scoping Meeting for the Environmental Review of the Subsequent License Renewal Application for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (EPID No.: L-2020-SLE-0002) - Memo ML21075A3432021-02-17017 February 2021 Meeting Summary: Public Scoping Meeting for the Environmental Review of the Subsequent License Renewal Application for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (EPID No.: L-2020-SLE-0002) - Summary ML20253A1382020-09-11011 September 2020 8/13/2020 Summary of Public Meeting with NextEra Energy Point Beach, LLC Regarding Proposed License Amendment Request for Point Beach Nuclear Plant, Unit 1, Containment Building Truss License Condition Change Due to COVID-19 ML20233A7902020-08-20020 August 2020 Summary of the July 30, 2020, Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of the Duane Arnold Energy Center and the Point Beach Nuclear Plant ML19344A0162019-12-12012 December 2019 Summary of Pre-Application Public Teleconference with Nextera Energy Point Beach, LLC, for Point Beach Nuclear Plant, Units 1 and 2 ML19246A6242019-09-10010 September 2019 Summary of August 14, 2019, Pre-Application Public Teleconference with NextEra Energy Point Beach, LLC, for Point Beach Nuclear Plant, Unit 2 ML19179A0662019-07-17017 July 2019 Summary of Closed Meeting with Nextera Energy, LLC, to Discuss Security-Related Information for Point Beach Nuclear Plant, Unit 1 and 2, and Duane Arnold Energy Center ML19095B7772019-04-0505 April 2019 Summary of Public Outreach/Open House to Discuss the NRC 2018 End-of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML18220B0192018-08-13013 August 2018 7/12/2018 Summary of Meeting with NextEra Energy Point Beach, Llc. to Discuss Supplemental Response to the RAI for Containment Dome Truss License Amendment Request for Point Beach Nuclear Plant, Unit 1 and 2 (CAC Nos. MF9532 & MF9533; ... ML18179A4032018-06-29029 June 2018 Public Meeting Discussion Points ML18136A9052018-05-31031 May 2018 Summary of April 25, 2017, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of Exemption Requests to Support Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML18141A8452018-05-29029 May 2018 Summary of May 1, 2018 Meeting with NextEra Energy Point Beach, LLC, to Discuss License Amendment Request for High Winds Probabilistic Risk Assessment for Point Beach Nuclear Plant, Unit Nos. 1 and 2 ML18121A3142018-05-0101 May 2018 Summary of the April 10, 2018 Public Outreach/Open House for the NRC to Discuss the 2017 End-of-Cycle Plant Performance Assessment of Point Beach Plant, Units 1 and 2 ML17346A9122017-12-22022 December 2017 Summary of November 14, 2017 Public Teleconference with NextEra Energy Point Beach, LLC, to Discuss Containment Dome Truss License Amendment Request for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (CAC Nos. MF9532 and MF9533; EPID L-2017-L ML17310B2062017-11-20020 November 2017 Summary of September 20, 2017, Meeting with Florida Power & Light Company and NextEra Energy Regarding Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML17216A1732017-09-0707 September 2017 Notice of Meeting with Florida Power & Light Company and NextEra Energy to Discuss Closing Out Generic Safety Issue-191 and Generic Letter 2004-02 ML17202U7272017-07-19019 July 2017 Summary of July 11, 2017, Open House to Discuss the 2016 End-Of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML16305A3882016-11-0808 November 2016 Summary of October 18, 2016 Meeting with Nextera Energy Point Beach, Llc, to Discuss Containment Dome Truss License Amendment Request for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (TAC Nos. MF8403 and MF8404) ML16160A1742016-06-0707 June 2016 Summary of Public Meeting with Nextera Energy Point Beach, LLC to Discuss the 2015 End-of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant Units 1 and 2 ML15341A0182015-12-16016 December 2015 Summary of Closed Pre-Application Teleconference with Nextera Energy Point Beach Regarding Steam Generators H* License Amendment Request ML15217A3312015-08-26026 August 2015 July 28, 2015, Summary of Ublic Meeting with NextEra Energy Point Beach, LLC, to Discuss a Proposed Licensing Basis Change for the Turbine-Driven Auxiliary Feedwater Pumps at the Point Beach Nuclear Plant, Units 1 and 2 ML15215A0502015-08-0505 August 2015 Summary of Public Meeting with NextEra Energy Point Beach, LLC, to Discuss Proposed Changes to Containment Dome Truss Design Bases Code for Point Beach Nuclear Plant, Units 1 and 2 ML15121A0572015-05-15015 May 2015 June 9 - 12, 2014 Summary of Audit at Point Beach Nuclear Plant, Unit Nos. 1 and 2, Associated with License Amendment Request to Transition to National Fire Protection Association Standard 805 ML15113B3862015-04-23023 April 2015 April 20, 2015 Summary of Public Outreach/Open House to Discuss the NRC 2014 End-Of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant ML15106A7122015-04-23023 April 2015 Summary of April 6, 2015, Meeting with NextEra Energy Point Beach, LLC, to Discuss License Amendment Request to Transition to NFPA 805 ML14114A1002014-04-23023 April 2014 Summary of Public Meeting to Discuss 2013 Annual Assessment Results for Point Beach Nuclear Plant ML13192A1432013-07-10010 July 2013 6/26/2013 - Summary of Open House to Discuss the 2012 Point Beach Nuclear Plant End-Of-Cycle Performance Assessment ML1212805092012-06-18018 June 2012 May 1, 2012 - Summary of Teleconference with Performance Contracting, Inc., Regarding Large Flume Testing for Point Beach Nuclear Plant ML11173A2332011-06-22022 June 2011 Summary of Public Meeting with NextEra Energy Point Beach, LLC to Discuss the Point Beach Nuclear Plant End-of-Cycle Performance Assessment for 2010 ML1108208272011-04-21021 April 2011 Summary of Pre-application Meeting with NextEra Energy, Inc., and Florida Power & Light Company, on Turkey Point, Units 3 and 4, St. Lucie, Units 1 & 2, Point Beach, Units 1 & 2, Duane Arnold Transition to NFPA-805 ML1014000432010-05-20020 May 2010 Summary of Public Meeting with FPL Energy Point Beach, LLC to Discuss Progress on the Nuclear Excellence Model and Updates on Operational Excellence, Generation Reliability, and Organizational Effectiveness at Point Beach ML1012502352010-05-0505 May 2010 Summary of the April 22, 2010, Public Meeting to Discuss the 2009 Point Beach End-of-Cycle Performance Assessment ML0924305212009-08-31031 August 2009 July 29, 2009,Summary of Public Meeting to Discuss the Progress on Actions Taken in Response to Substantive Cross Cutting Issues and the Results of an Independent Assessment of Corrective Actions for Recent Nuclear Safety Culture Surveys ML0914001932009-05-20020 May 2009 Summary of Public Meeting to Discuss the Progress on Actions Taken in Response to a Nuclear Safety Culture Survey in 2008 - Point Beach Nuclear Plant ML0832308202008-11-20020 November 2008 Teleconference Summary Regarding the 2008 Steam Generator Tube Inspection Results 2024-09-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 23, 2015 LICENSEE: NextEra Energy Point Beach, LLC FACILITY: Point Beach Nuclear Plant, Units 1 and 2
SUBJECT:
SUMMARY
OF APRIL 6, 2015, MEETING WITH NEXTERA ENERGY POINT BEACH, LLC, TO DISCUSS THE LICENSE AMENDMENT REQUEST FOR TRANSITION TO NATIONAL FIRE PROTECTION ASSOCIATION STANDARD (NFPA) 805 FOR THE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 (TAC NOS. MF2372 AND MF2373)
On April 6, 2015, a Category 1 public conference call was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of NextEra Energy Point Beach, LLC (NextEra, the licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the conference call was to discuss NextEra's proposed method for estimating the change in risk associated with fires that might result in main control room abandonment on loss of control at the Point Beach Nuclear Plant, Units 1 and 2 (Point Beach). The meeting notice and agenda, dated March 23, 2015, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML15091A736. A list of the meeting attendees is enclosed.
The licensee provided slides for the presentation (ADAMS Accession No. ML15091A517),
which were attached to the meeting notice prior to the meeting. During the conference call, the licensee discussed each of the presentation slides. The NRC staff asked some clarification questions during the presentation. After the presentation, the staff indicated that the information presented during the meeting appeared to be in accordance with the guidance established for the NFPA 805 projects. However, an additional request for information may be needed to obtain further clarification on the information previously submitted on the docket. The NRC staff stated that it would review the provided information and, if needed, provide a request for additional information and establish the next steps to support completion of the license amendment request.
There were members of the public who attended the teleconference. However, public meeting feedback forms were not requested by anyone.
Please direct any inquiries to me at 301-415-8371, or by e-mail to Mahesh.Chawla@nrc.gov.
Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Enclosure:
List of Attendees cc w/enclosure: Distribution via Listserv
LIST OF ATTENDEES APRIL 6. 2015. PUBLIC TELECONFERENCE WITH NEXTERA ENERGY POINT BEACH. LLC TO DISCUSS THE LICENSE AMENDMENT REQUEST FOR TRANSITIONING TO NFPA 805 AT THE POINT BEACH NUCLEAR PLANT. UNITS 1 AND 2 U.S. Nuclear Regulatory Commission, Office of Nuclear Reactor Regulation Division Name Title Division of Operating Mahesh Chawla Project Manager (PM)
Reactor Licensing (DORL)
Branch Chief, Probabilistic Risk Hossein Hamzehee Assessment (PRA) Licensing Branch Alex Klein Branch Chief, Fire Protection Branch Division of Risk Assessment Stephen Dinsmore Senior Reliability and Risk Analyst (ORA)
Harold Barrett Senior Fire Protection Engineer J.S.Hyslop Senior Reliability and Risk Enqineer P. Lee NextEra Point Beach, LLC **
William A Cross Fleet Requlatory Proqrams Manaqer Stan Guokas Site PRA Ron Fish Site PM Point Beach Nuclear Plant Liz Abbot Director Regulatory Projects Anil Julka Fleet PRA Manaqer Rob Regan Fleet 805 PM Rick Mrozinsky Safe Shutdown and Licensing Engineer Members of Public/Contractors **
Ratchford Diversified Andy Ratchford Consultant Services Enercon Services, Inc Mark R. Winsor, PE Principal Engineer Jensen Hughes Vinny Rubano Director, Fire Protection Programs Scott Brinkman, Technical Manager (Risk Services Division)
Engineering Planning and Andrew Bittleman Staff Enqineer II (Risk Services)
Management (EPM), Inc. Senior Technical Manager (Fire James Blum Protection group)
Senior Technical Manager (Risk Leroy Kreider Services)
Diablo Canyon Power Senior Consulting Engineer - PRA Plant/Pacific Gas and John Pyo Group Electric
- Participated via phone Enclosure
There were members of the public who attended the teleconference. However, public meeting feedback forms were not requested by anyone.
Please direct any inquiries to me at 301-415-8371, or by e-mail to Mahesh.Chawla@nrc.gov.
IRA/
Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Enclosure:
List of Attendees cc w/enclosure: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL3-1 r/f RidsNrrDorl Resource TWertz, NRR SDinsmore, NRR RidsNrrPMPointBeach Resource RidsRgn3MailCenter Resource Plee, NRR KButler, EDO RidsNrrLAHenderson Resource RidsNrrDorllpl3-1 Resource KGreen, NRR JCameron, R3 RidsNrrDraApla Resource HBarrett, NRR JS Hyslop, NRR DOliver, R3 RidsNrrDraAfpb Resource RidsAcrsAcnw_MailCTR Resource ADAMS Accession Numbers:
Package: ML15106A719 Meeting Notice: ML15091A736 Meeting Summary: ML15106A712 Licensee Slide Presentation* ML15091A517
- Concurrence via e-mail OFFICE LPL3-1/PM LPL3-1/LA DRA/APLA/BC DRA/AFPB/BC LPL3-1/BC LPL3-1/PM NAME TBeltz MHenderson HHamzehee* AKlein* DPelton MChawla DATE 04/16/2015 04/20/2015 04/15/2015 04/15/2015 04/23/2015 04/23/2015 OFFICIAL RECORD COPY