ML20308A602

From kanterella
Revision as of 14:37, 18 January 2021 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Presentation Slides for the November 4, 2020 NEI RITF Public Meeting
ML20308A602
Person / Time
Issue date: 11/04/2020
From:
Office of Nuclear Reactor Regulation
To:
Kate Lenning-NRR/DORL 301-425-3151
References
Download: ML20308A602 (53)


Text

Public Meeting with the Nuclear Energy Institute Regulatory Issues Task Force November 4, 2020 1

Time Topic Speaker 9:00 am -9:05 am Introductions/Opening remarks NRC/NEI 9:05 am - 9:30 am NRC transformational efforts NRC 9:30 am - 9:45 am Licensing action workload update NRC 9:45 am - 10:00 am Licensing review feedback NEI 10:00 am - 10:10 am Break 10:10 am - 10:25 am VLSSIR/next steps NRC/NEI 10:25 am - 10:40 am Forward fitting/back-fitting guidance development NRC 10:40 am - 10:55 am Pre-generic issues - PRE-GI-018 HEAF involving aluminum components NRC ASME NML-1-2019, Rules for the movement of loads using overhead handling equipment in nuclear 10:55 am - 11:10 am NRC facilities 11:10 am - 11:25 am 10 CFR 50.55a 2-year rule change NEI/NRC 11:25 am - 11:40 am 2021 RIC approach NRC 11:40 am - 11:45 am 10 CFR 50.59 effort NRC Members of the 11:45 am - 11:55 am Opportunity for public comment Public 11:55 am - 12:00 pm Closing remarks NRC/NEI 12:00 pm Adjourn 2

Introductions and Opening Remarks 3

NRC Transformational Efforts 4

5 Risk Informed Process for Evaluation Whats Changed?

Streamlined Review - limited 50.69 IDP or Equivalent deterministic review as needed

& TSTF-505 TSTF-425 Risk-informed review Other risk information 6

Risk Informed Process for Evaluation Whats Next?

  • Finalized NRC Temporary Staff Guidance and safety impact characterization guidance process.
  • LSSIR Recommendation 5 Memo in concurrence to NRR Executive Team.
  • Continue working on graded approach to support other levels of risk-informed integrated decision-making.
  • Continue outreach to other interested parties and the public.

7

Request for Confirmation of Information

  • An RCI is an RAI asking for the applicant to confirm information the NRC staff understand to be accurate
  • RCIs provide enhanced clarity and efficiency of communication over standard RAIs
  • Currently available for use
  • Working on incorporating RCI into staff review guidance 8

WEB-BASED RITF RELIEF Presentation REQUESTS 9

PRESENTER: JASON DRAKE November 4, 2020

DISCUSSION TOPICS Overview of Licensee Strategic Questions WRR Interface Improvements 10

OVERVIEW Web-based Web-based NRC Alternative Exemptions Portal COVID-19 PHE Requests (COVID-related) (All)

(COVID-related) 11

LOGIN SCREEN

  • Users will get a credential issued by the NRC ICAM team which will be used to access the portal (similar to EIE).

12

PROFILE PAGE

  • Each logged in user will have the ability to update their profile.

13

ADMINISTRATOR PAGE

  • A licensee can designate an administrator and they will have the ability to administer permissions for their employees on a plant by plant basis to View, Edit or Submit.
  • Administrator default is the Licensing Director 14

LIST OF SUBMISSIONS

  • Licensees will have a list of initiated/submitted alternatives that can be checked for status or for reference purposes.
  • Status information will be auto-populated from NRC internal work planning applications.

15

ALTERNATIVE REQUEST

[123456]

16

ALTERNATIVE REQUEST 17

NEW FORM FEATURES

  • Rich Text Elements 18

NEW FORM FEATURES

  • Attachments 19

NEW FORM FEATURES

  • Preview 20

KEY TAKEAWAYS

  • Full editing capability and attachment functionality for licensees within the portal
  • PDF alternative request automatically generated by the form and processed through ADAMS for profiling; attachments added to package
  • All applicable requirements under 10 CFR 50.4 are satisfied
  • OMB clearance obtained for portal data collection specific to WRR 21

WHATS NEXT Web-based Web-based Alternative NRC Portal MAP Exemptions COVID-19 PHE Requests (All)

(COVID-related)

(COVID-related) 22

VISION Empower stakeholders with a secure, flexible, and personalized self-service MISSION ANALYTICS PORTAL - EXTERNAL gateway to retrieve, submit, enter at your own reward and interact with regulatory related information and assessment tools through a standard web browser.

23

Licensing Action Workload Enhancements November 4, 2020 24

Significant Activities in FY 2020

  • Prompt Actions Taken in Response to COVID-19 Public Health Emergency (PHE)
  • Improvements Achieved in the Operating Reactor Licensing Workload Management Process
  • Increased Efficiencies and Ability to Identify Trends in Large Licensing Submittals
  • Communications with Industry Effective during the PHE 25

26 Completed COVID-19 Actions COVID-19 Actions

  • Part 26 Work Hours 2 38
  • Part 50 Fire Protection
  • Part 55 Operators Licenses 19
  • Part 73 Security Training 4 5
  • Part 20 Respiratory Requirements
  • Part 50 EP Biennial Exercise 1 186 Other Requests Processed
  • License Amendments
  • Part 50.55a relief/alternative
  • Part 50 Quality Assurance Programs
  • Topical Reports - Audit Frequencies 27

28 Avg = 8.7 months Avg = 7.4 months Avg = 36 days 29

Workload Management Enhancements

  • On-Line Portal for Exemptions and Relief Requests
  • New and Modernized Licensing Tools

- Enhanced reports and tools in project management system (RPS)

- Mission Analytics Portal (MAP): Interactive Licensing Dashboard

  • Enhanced Workload Management Process

- Real-time Analytics

- Predictive Indicators and Metrics 30

31 Efficiencies Gained in FY 2020

  • Completed >1100 licensing actions and other licensing tasks

- 20% higher volume than FY 2019, highest in last 3 years

  • Average Completion Time for All Actions < 6.5 months

- 30% lower than FY2019, lowest in last 5 years

  • Met or Exceeded All Performance Goal Year Timeliness: Licensing Actions = 99%; Other Licensing Tasks = 97%

Year Timeliness = 100%

- Improved performance against estimates

  • Developed new internal goals to achieve additional efficiencies, and metrics to monitor our progress 32

Large Submittals (TSTF-582, TSTF-505, 10 CFR 50.69)

- Up to 22 expected with most expected to have 6 month completion times

- 9 submitted; All requested 6 month or less completion time

  • Requests to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times

- 2 completed; All less than estimated schedule and estimated hours

- 7 new submittals; Most estimates consistent with or below prior submittals

- 1 request to modify prior approval

  • Requests to Implement 10 CFR 50.69, Risk-informed categorization and treatment of structures, systems and components

- 6 completed; All less than estimated schedule and estimated hours

- 7 new submittals; Most estimates consistent with submittals

- 3 requests to modify prior approvals 33

Effective Communication

  • Sharing information is a key focus area during the ongoing response to the COVID-19 PHE
  • Provided NRCs PHE response information on the public website
  • Increased staff remote login capability to ensure continued access for communications and agency information
  • Routine licensing communications continued during full time telework period 34

Licensing Review Feedback NEI 35

BREAK 36

Very Low Safety Significance Issue Resolution (VLSSIR) Process - Update

  • The use of the VLSSIR process has resulted in the closure of 5 issues in 10 months. 3 of 4 Regions have used the VLSSIR process. The amount of issues in this timeframe is what was about expected when implementing the new VLSSIR process.
  • All regions reviewed their open URIs in the first quarter of this year to determine which ones could be closed to the VLSSIR process. This resulted in 2 issues closed.
  • DRO conducted a survey in April 2020 for all regional DRS and DRP branch chiefs on their experience with the VLSSIR process for the first quarter of 2020. Summary of lessons learned from this Survey:

o Some inspectors are still concerned that licensees will push an inspector to use this process when it is not applicable.

o Need to reemphasize that the VLSSIR process is also for issues that would screen to minor in IMC 0612.

  • An effectiveness review is planned to be conducted in January 2021 after one-year of run-time on the new VLSSIR process.

RITF Public Briefing, November 2020 NRR/DRO Program

Contact:

Phil McKenna 37

Technical Assistance Request (TAR)

Process- Status

  • Revitalized process, TAR (COM-106, Rev. 6)1 took effect August 24, 2020
  • Rollout training for NRR and Region staff planned in fall/winter 2020 Restructured as a fact-gathering exercise to inform decisionmaking in other processes, TAR will offer a graded, risk-informed approach to screen, scope and evaluate potential issues early TAR Scope: Operating reactors, and reactors and non-power utilization facilities in construction TAR has nexus to VLSSIR and Backfitting - Connected by the transformative thread of holistic problem-solving 0 TARs in Process RITF Public Briefing, November 2020 NRR/DORL Program

Contact:

Booma Venkataraman 1 ADAMS Accession No. ML19176A098 38

NUREG-1409 Revision Status RITF Meeting November 4, 2020 39

Draft NUREG-1409, Rev. 1

  • Complete rewrite of 1990 version
  • Guidance on how to implement Commissions direction in MD 8.4
  • Made available for comment in March 2020
  • Comment period extended because of COVID-19
  • Comments made available to NRC staff in August 40

Comments

  • ~ 250 comments from 13 submissions
  • Significant comment topics:

- Backfitting steps

- Forward fitting process

- Appeal process and timing

- Organization of Chapter 5

- Inspection and enforcement

- Public involvement 41

Status

  • Revision is at working group level
  • NUREG due to Commission in March 2021
  • Commission has a 10-day review period
  • Issue final NUREG in 2021
  • Publish Federal Register notice of issuance
  • Update NRC implementing procedures 42

High Energy Arcing Faults Involving Aluminum Components RITF Meeting November 4, 2020 45

Proposed Path to Resolution of Pre GI-0018 on HEAF

  • NRC staff developing approach to resolve the pre generic issue on HEAF involving aluminum without additional NRC sponsored testing
  • Approach will build off NRC/EPRI Working Group project plan, including the EPRI survey, to determine the extent of aluminum in plants and plant-specific electrical configurations
  • Initial steps will include filling in gaps identified in the survey
  • The NRC/EPRI Working group is developing specific Zones of Influence (ZOI) and PRA methods to address the hazard posed by aluminum HEAFs
  • Anticipate public meeting no later than the next quarter of FY21 46

American Society of Mechanical Engineers NML-1-2019, Rules for the Movement of Loads Using Overhead Handling Equipment in Nuclear Facilities Endorsement Status REGULATORY ISSUES TASK FORCE NOVEMBER 4, 2020 PUBLIC MEETING 45

  • Regulatory Guide (RG) endorsement expected to enhance handling system use flexibility and reduce special lift device nondestructive examination and testing frequency consistent with risk insights
  • Draft RG internal reviews commencing mid-November
  • RG issuance for stakeholder comments 2nd Quarter FY21; final RG in 4th Quarter FY21 46

10 CFR 50.55(a) 2-year Rule Change 47

2021 Virtual Regulatory Information Conference (RIC)

Nathan Sanfilippo 48

- 100% virtual: Monday, March 8 - Thursday, March 11, 2021; 10 AM - 2:45 PM Eastern Time

- 8 plenary sessions and ~28 technical sessions

- All sessions will be delivered on the virtual platform, which will also include digital exhibits and other engaging content

- Conference program currently being finalized 49

Enhancing the Use of Risk Information in 50.59 Evaluations Nathan Sanfilippo 50

Use of Risk in 50.59 Evaluations

- Staff is engaging with NEI and industry to evaluate the potential to increase the use of risk information in the application of 10 CFR 50.59

- NEI stated that NEI 96-07, Rev. 1 may include self-imposed limitations on the ability to fully utilize the change provisions allowed by 10 CFR 50.59

- Several public meetings have been held (6/4, 8/5, and 10/15) for staff and industry to exchange views and questions

- Discussion involves the extent to which the 50.59 Statements of Consideration preclude quantitative risk techniques such as the use of CDF and LERF

- Staff is developing a new Inspection Manual Chapter (IMC) to enhance the knowledge of and guidance to inspectors on 50.59 51

Opportunity for Public Comment 52

NEI and NRC Management Closing Remarks 53