PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, NJ 08038-0236 NOV 30 2015 PSEG Nuclear LLC LR-N15-0246 NEI 99-04 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Salem Generating Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-70 and DPR-75 NRC Docket Nos. 50-272 and 50-311
Subject:
2014 Summary of Revised Regulatory Commitments- Salem In accordance with the Nuclear Energy Institute (NEI) process for managing Nuclear Regulatory Commission (NRC) commitments and associated NRC notifications, PSEG Nuclear LLC (PSEG) submits this correspondence to notify the commission that there were no changes to commitments evaluated in 2014 that were not reported by other means.
There are no new commitments in this letter.
If there are any questions, please contact Thomas Cachaza at 856-339-5038.
Sincerely, r
Site Vice Preside !,!- Salem
LR-N15-0246 Page 2 cc: Mr. D. Dorman, Administrator - Region 1, NRC Mr. T. Wengert, Licensing Project Manager (acting) - Salem, NRC Mr. P. Finney, USNRC Senior Resident Inspector - Salem (X24)
Mr. P. Mulligan, Manager, IV, Bureau of Nuclear Engineering Mr. T. Cachaza, Salem Commitment Coordinator Mr. L. Marabella, Corporate Commitment Coordinator
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, NJ 08038-0236 NOV 30 2015 PSEG Nuclear LLC LR-N15-0246 NEI 99-04 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Salem Generating Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-70 and DPR-75 NRC Docket Nos. 50-272 and 50-311
Subject:
2014 Summary of Revised Regulatory Commitments- Salem In accordance with the Nuclear Energy Institute (NEI) process for managing Nuclear Regulatory Commission (NRC) commitments and associated NRC notifications, PSEG Nuclear LLC (PSEG) submits this correspondence to notify the commission that there were no changes to commitments evaluated in 2014 that were not reported by other means.
There are no new commitments in this letter.
If there are any questions, please contact Thomas Cachaza at 856-339-5038.
Sincerely, r
Site Vice Preside !,!- Salem
LR-N15-0246 Page 2 cc: Mr. D. Dorman, Administrator - Region 1, NRC Mr. T. Wengert, Licensing Project Manager (acting) - Salem, NRC Mr. P. Finney, USNRC Senior Resident Inspector - Salem (X24)
Mr. P. Mulligan, Manager, IV, Bureau of Nuclear Engineering Mr. T. Cachaza, Salem Commitment Coordinator Mr. L. Marabella, Corporate Commitment Coordinator