ENCLOSURE 3 Current Synchronous Condenser Project Schedule Task Name IDuration iStart Date finish Date Tue Mon Synchronous Condenser Proiect (DRAFT) 453 days 11125114 1123117 Tue Thu Radiological Characterization Work 212 days 11125114 11/26115 Phase 1 & 2: Develop and approve survey package(s) for 40 days Tue Thu core bores 11/25/14 1/29/15 Phase 1 & 2: Geotechnical Exploration
& Collection of Mon Thu 2/5/15 Radiological Samples from Core Bores 1/19/15 Phase 3: Develop and approve survey package(s) for 2 weeks Mon 7/6/15 Thu prepared areas 7/16/15 Phase 3: Conduct excavation radiological surveys Mon Thu (opportunity for Oak Ridge Associated Universities (ORAU) 2 weeks Mon Thu in-process surveys)Phase 3: Conduct excavation radiological near surface soil 2 weeks Mon Thu samples (opportunity for ORAU split samples) 8/10/15 8/20/15 Phase 4: Sample backfill to be used for finalized pad 7 weeks Mon Thu (opportunity for ORAU split samples) 8/24/15 10/8/15 As needed Phase: Conduct finalized pad radiological Mon Thu surveys (placeholder) (possible opportunity for ORAU 2 weeks Mon Thu in-process surveys) 1 As needed Phase: Conduct finalized pad radiological near surface soil samples (placeholder) (possible opportunity for 2 weeks Mon Thu ORAU split samples)Radiological Characterization Data Evaluation, Pkg 5 weeks Mon Thu Closure, & Report Prep 10/26/15 11/26/15 Tue Mon Installation Work 408 days 2110115 1123117 Tue Engineering 104 days 2/10/15 Fri 7/3/15 Site Development
-Excavation 20 days Mon 7/6/15 Thu 8/6/15 Mon Thu Site Development
-Finalize Pad 28 days 8/24/15 10/8/15 Tue Mon Construction 245 days 11/10/15 10/17/16 Mon Commissioning 99 days Wed 8/3/16 12/1 1/23/17 Page E3-1