Notice of Violation from Insp on 850520-24
ML20133F608
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 07/25/1985
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20133F585 List:
References
50-368-85-16, NUDOCS 8508080359
Download: ML20133F608 (1)


Text

F 1

1 APPENDIX A NOTICE OF VIOLATION Arkansas Power and Light Company Docket:

50-368 Arkansas Nuclear One, Unit 2 License:

NPF-6 l

l During an NRC inspection conducted on May 20-24, 1985, a violation of NRC requirements was identified.

The violation involved failure to maintain procedures current.

In accordance with the " General Statement of Policy and Procedure for NRC Enforceeent Actions," 10 CFR Part 2, Appendix C (1985), the violation is listed below:

i i

Failure to Maintain Procedures Arkansas Nuc1 car One, Unit 2, Technical Specifications paragraph 6.8.1 states:

" Written procedures shall be established, implemented, and maintained covering the activities referenced below:

. f. Fire protection program implementation...."

Contrary to the above, Procedure 2203.09, " Fire Protection System Annunciator Corrective Action," Revision 0, dated June 26, 1981, Attachment A, 1-5-5, " Corridor by Emergency Control Room Chillers Zone Module " had not been revised to reflect deactivation of remote actuation by closing supply valve for deluge system automatic valve as a result of the granting of an exemption request to deactivate the automatic capability of this deluge valve.

This is a Severity Level V Violation.

(Supplement I) (50-368/85-16)

Pursuant to the provlsions of 10 CFR 2.201, Arkansas Power & Light Company is hereby required to submit to this office, within 30 days of the date of the letter transmittin0 this Notice, a written statement or explanation in reply, includin0:

(1) the reason for the violation if admitted, (2) the corrective steps which have been taken and the results achieved; (3) corrective steps which will be taken to avoid further violations; and (4) the date when full compliance will be achieved. Where good cause is shown, consideration will be Diven to extending the response time.

Dated at Arlington, Texas d

this Ji day of July,1985 0500000359 050705 i

PDN ADOCK 050003f3 0

PDH

.