ML20078M039

From kanterella
Revision as of 00:24, 15 December 2024 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Notifies of Resolution of NUREG-0737,TMI Action Plan Item II.K.2.17, Potential for Voiding in RCS During Transients. Results of Analysis Presented in CEN-199 Applicable to Facilities W/Stated Exception
ML20078M039
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 10/19/1983
From: Lundvall A
BALTIMORE GAS & ELECTRIC CO.
To: John Miller
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.K.2.17, TASK-TM NUDOCS 8310240162
Download: ML20078M039 (1)


Text

BA LTIMO RE GAS AND ELECTRIC CHARLES CENTER *P.O. BOX 1475 BALTIMORE, MARYLAND 21203 October 19,1983 Af4THun L LUNovALL. JR.

v.cc m. a.a SuppLv Director of Nuclear Reactor Regulation Attention: Mr. 3. R. Miller, Chief Operating Reactors Branch #3 Division of 1.icensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Subject:

Calvert Cliffs Nuclear Power Plant Units Nos.1 & 2; Dockets Nos. 50-317 and 50-318 Natural Circulation Cooldown Gentlemen:

NUREG-0737 Action Plan Item II.K.2.17, " Potential for Voiding in the Reactor Coolant System During Transients," requires licensees to analyze the potential for voiding in the reactor coolant system (RCS) during anticipated transients.

An analysis has been completed by the Combustion Engineering. Owners Group which demonstrates that natural circulation cooldown of the RCS can be accomplished for these transients while maintaining conformance to NRC acceptance criteria. The results of this analysis are presented in CE Owners Group Report CEN-199, dated March 1982, and are applicable to the Calvert Cliffs Nuclear Power Plant, with one exception.

For operating plants, section 2.3 of CEN-199 makes reference to a 20-hour cooldown period or RCS " soak time" prior to depressurization for entry into shutdown cooling. The upgraded emergency operating procedures (EOPs) for Calvert Cliffs will utilize the specific guidance contained in CE Owners Group Report CEN-154, dated October 1981, with regard to the appropriate duration of RCS cooldown. For example, the specified cooldown period beginning with entry into natural circulation and ending with RCS depreswrization for entry into shutdown cooling would be 17.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. This period consists of a 5.5-hour period for cooldown to an RCS bulk temperature of 330 F followed by a 12.0-hour RCS " soak time".

Noting the above exception, we reference the results of CEN-199 for the resolution of NRC Action Plan Item II.K.2.17.

If you should have any quest!ons, please do not hesitate to contact us.

Sincerely -

f,;rn

~.

h

,1

'AEL/BSM/vf cc: 3. A. Biddison,3r., Esq.

- G. F. Trowbridge, Esq.

g Mr. D. H. Jaffe, NRC Mr. R. E. Architzel. NRC B310240162 831019 PDR ADOCK 05000317 P