ML18331A091
ML18331A091 | |
Person / Time | |
---|---|
Site: | PROJ0712, 99901376 |
Issue date: | 12/06/2018 |
From: | Dennis Morey NRC/NRR/DLP/PLPB |
To: | Michelle Catts GE-Hitachi Nuclear Energy Americas |
Gilla J | |
References | |
EPID L-2018-TOP-40, NEDE-24011-P-A-26 | |
Download: ML18331A091 (4) | |
Text
December 6, 2018 Ms. Michelle Catts Senior Vice President, Regulatory Affairs GE-Hitachi Nuclear Energy Americas, LLC P.O. Box 780, M/C A-10 Wilmington, NC 28401-0780
SUBJECT:
ACCEPTANCE FOR REVIEW OF GLOBAL NUCLEAR FUEL PROPOSED ADMINISTRATIVE AMENDMENT 48 TO NEDE-24011-P-A-26, GENERAL ELECTRIC STANDARD APPLICATION FOR REACTOR FUEL (EPID L-2018-TOP-40)
Dear Ms. Catts:
By letter dated June 6, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18157A181), Global Nuclear Fuel - Americas (GNF), submitted for U.S. Nuclear Regulatory Commission (NRC) staff review Proposed Administrative Amendment 48 to NEDE-24011-P-A-26, General Electric Standard Application for Reactor Fuel.
Also by letter dated September 26, 2018 (ADAMS Accession No. ML18269A023), GNF submitted Additional Modification to the Proposed Administrative Amendment 48 for staff review. The NRC staff has performed an acceptance review of these submittals. We have found that the material presented is sufficient to begin our review. We expect to issue our request for additional information by April 3, 2019, and issue our draft safety evaluation by June 19, 2019.
This schedule information takes into consideration the NRCs current review priorities and available technical resources and may be subject to change. If modifications to these dates are deemed necessary, we will provide appropriate updates to this information. The NRC staff estimates that the review will require approximately 120 staff hours including project management. The review schedule milestones and estimated review costs were discussed and agreed upon in an email exchange between Ms. Lisa Schichlein and the NRC staff on November 27, 2018.
Section 170.21 of Title 10 of the Code of Federal Regulations requires that topical reports are subject to fees based on the full cost of the review. You did not request a fee waiver; therefore, NRC staff hours will be billed accordingly.
M. Catts Please contact Joseph A. Golla at (301) 415-1002, if you have any questions on this subject.
Sincerely,
/RA/
Dennis C. Morey, Chief Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation Docket No. 99901376 Project No. 712 cc: See next page
ML18331A091 *concurrence via e-mail NRR-106 OFFICE NRR/DLP/PLPB/PM NRR/DLP/PLPB/LA* NRR/DSS/SNPB/BC NRR/DLP/PLPB/BC NAME JGolla DHarrison RLukes DMorey DATE 12/6/2018 12/4/2018 12/6/2018 12/6/2018 GE-Hitachi Nuclear Energy Americas Docket No. 99901376 cc:
Ms. Michelle P. Catts Senior Vice President, Regulatory Affairs GE-Hitachi Nuclear Energy Americas, LLC P.O. Box 780 M/C A-10 Wilmington, NC 28401 Michelle.Catts@ge.com Mr. Kent E. Halac Senior Project Manager, Regulatory Affairs GE-Hitachi Nuclear Energy Americas, LLC P.O. Box 780, M/C A-70 Wilmington, NC 28401-0780 Kent.Halac@ge.com Dr. Brian R. Moore General Manager, Core & Fuel Engineering Global Nuclear Fuel-Americas, LLC P.O. Box 780, M/C A-75 Wilmington, NC 28401-0780 Brian.Moore@ge.com Ms. Lisa K. Schichlein Senior Project Manager, Regulatory Affairs GE-Hitachi Nuclear Energy Americas, LLC P.O. Box 780, M/C A-70 Wilmington, NC 28401-0780 Lisa.Schichlein@ge.com