{{#Wiki_filter:ENCLOSURE 3Current Synchronous Condenser Project Schedule Task NameIDuration iStart Date finish DateTue MonSynchronous Condenser Proiect (DRAFT) 453 days 11125114 1123117Tue ThuRadiological Characterization Work 212 days 11125114 11/26115Phase 1 & 2: Develop and approve survey package(s) for 40 days Tue Thucore bores 11/25/14 1/29/15Phase 1 & 2: Geotechnical Exploration & Collection of Mon Thu 2/5/15Radiological Samples from Core Bores 1/19/15Phase 3: Develop and approve survey package(s) for 2 weeks Mon 7/6/15 Thuprepared areas 7/16/15Phase 3: Conduct excavation radiological surveys Mon Thu(opportunity for Oak Ridge Associated Universities (ORAU) 2 weeks Mon Thuin-process surveys)Phase 3: Conduct excavation radiological near surface soil 2 weeks Mon Thusamples (opportunity for ORAU split samples) 8/10/15 8/20/15Phase 4: Sample backfill to be used for finalized pad 7 weeks Mon Thu(opportunity for ORAU split samples) 8/24/15 10/8/15As needed Phase: Conduct finalized pad radiological Mon Thusurveys (placeholder) (possible opportunity for ORAU 2 weeks Mon Thuin-process surveys) 1As needed Phase: Conduct finalized pad radiological nearsurface soil samples (placeholder) (possible opportunity for 2 weeks Mon ThuORAU split samples)Radiological Characterization Data Evaluation, Pkg 5 weeks Mon ThuClosure, & Report Prep 10/26/15 11/26/15Tue MonInstallation Work 408 days 2110115 1123117TueEngineering 104 days 2/10/15 Fri 7/3/15Site Development -Excavation 20 days Mon 7/6/15 Thu 8/6/15Mon ThuSite Development -Finalize Pad 28 days 8/24/15 10/8/15Tue MonConstruction 245 days 11/10/15 10/17/16MonCommissioning 99 days Wed 8/3/16 12/1 1/23/17Page E3-1}} | {{#Wiki_filter:ENCLOSURE 3Current Synchronous Condenser Project Schedule Task NameIDuration iStart Date finish DateTue MonSynchronous Condenser Proiect (DRAFT) 453 days 11125114 1123117Tue ThuRadiological Characterization Work 212 days 11125114 11/26115Phase 1 & 2: Develop and approve survey package(s) for 40 days Tue Thucore bores 11/25/14 1/29/15Phase 1 & 2: Geotechnical Exploration | ||
& Collection of Mon Thu 2/5/15Radiological Samples from Core Bores 1/19/15Phase 3: Develop and approve survey package(s) for 2 weeks Mon 7/6/15 Thuprepared areas 7/16/15Phase 3: Conduct excavation radiological surveys Mon Thu(opportunity for Oak Ridge Associated Universities (ORAU) 2 weeks Mon Thuin-process surveys)Phase 3: Conduct excavation radiological near surface soil 2 weeks Mon Thusamples (opportunity for ORAU split samples) 8/10/15 8/20/15Phase 4: Sample backfill to be used for finalized pad 7 weeks Mon Thu(opportunity for ORAU split samples) 8/24/15 10/8/15As needed Phase: Conduct finalized pad radiological Mon Thusurveys (placeholder) | |||
(possible opportunity for ORAU 2 weeks Mon Thuin-process surveys) 1As needed Phase: Conduct finalized pad radiological nearsurface soil samples (placeholder) | |||
(possible opportunity for 2 weeks Mon ThuORAU split samples)Radiological Characterization Data Evaluation, Pkg 5 weeks Mon ThuClosure, | |||
& Report Prep 10/26/15 11/26/15Tue MonInstallation Work 408 days 2110115 1123117TueEngineering 104 days 2/10/15 Fri 7/3/15Site Development | |||
-Excavation 20 days Mon 7/6/15 Thu 8/6/15Mon ThuSite Development | |||
-Finalize Pad 28 days 8/24/15 10/8/15Tue MonConstruction 245 days 11/10/15 10/17/16MonCommissioning 99 days Wed 8/3/16 12/1 1/23/17Page E3-1}} |
Revision as of 03:12, 1 July 2018
ML15071A021 | |
Person / Time | |
---|---|
Site: | San Onofre |
Issue date: | 03/03/2015 |
From: | Brabec R C Southern California Edison Co |
To: | Office of Nuclear Reactor Regulation |
References | |
Download: ML15071A021 (2) | |
Text
ENCLOSURE 3Current Synchronous Condenser Project Schedule Task NameIDuration iStart Date finish DateTue MonSynchronous Condenser Proiect (DRAFT) 453 days 11125114 1123117Tue ThuRadiological Characterization Work 212 days 11125114 11/26115Phase 1 & 2: Develop and approve survey package(s) for 40 days Tue Thucore bores 11/25/14 1/29/15Phase 1 & 2: Geotechnical Exploration
& Collection of Mon Thu 2/5/15Radiological Samples from Core Bores 1/19/15Phase 3: Develop and approve survey package(s) for 2 weeks Mon 7/6/15 Thuprepared areas 7/16/15Phase 3: Conduct excavation radiological surveys Mon Thu(opportunity for Oak Ridge Associated Universities (ORAU) 2 weeks Mon Thuin-process surveys)Phase 3: Conduct excavation radiological near surface soil 2 weeks Mon Thusamples (opportunity for ORAU split samples) 8/10/15 8/20/15Phase 4: Sample backfill to be used for finalized pad 7 weeks Mon Thu(opportunity for ORAU split samples) 8/24/15 10/8/15As needed Phase: Conduct finalized pad radiological Mon Thusurveys (placeholder)
(possible opportunity for ORAU 2 weeks Mon Thuin-process surveys) 1As needed Phase: Conduct finalized pad radiological nearsurface soil samples (placeholder)
(possible opportunity for 2 weeks Mon ThuORAU split samples)Radiological Characterization Data Evaluation, Pkg 5 weeks Mon ThuClosure,
& Report Prep 10/26/15 11/26/15Tue MonInstallation Work 408 days 2110115 1123117TueEngineering 104 days 2/10/15 Fri 7/3/15Site Development
-Excavation 20 days Mon 7/6/15 Thu 8/6/15Mon ThuSite Development
-Finalize Pad 28 days 8/24/15 10/8/15Tue MonConstruction 245 days 11/10/15 10/17/16MonCommissioning 99 days Wed 8/3/16 12/1 1/23/17Page E3-1