{{#Wiki_filter:L44 141105 001 Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-14-209 November 5, 2014 10 CFR 50, Appendix E, Section V 10 CFR 50.4 10 CFR 50.54(q)(5) 10 CFR 72.44(f)
{{#Wiki_filter:Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-14-209 November 5, 2014 10 CFR 50, Appendix E, Section V 10 CFR 50.4 10 CFR 50.54(q)(5) 10 CFR 72.44(f)
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390  


==Subject:==
==Subject:==
Central Emergency Control Center - Emergency Plan Implementing Procedure Revision In accordance with the requirements of 10 CFR Part 50, Appendix E, Section V and 10 CFR 72.44(f), this submittal provides the revised Central Emergency Control Center (CECC)
Central Emergency Control Center - Emergency Plan Implementing Procedure Revision In accordance with the requirements of 10 CFR Part 50, Appendix E, Section V and 10 CFR 72.44(f), this submittal provides the revised Central Emergency Control Center (CECC)
Emergency Plan Implementing Procedures (EPIPs) as listed below.
Emergency Plan Implementing Procedures (EPIPs) as listed below.
EPIP                   Revision           Title                                     Effective Date CECC EPIP-2                     46               Operations Duty Specialist Procedure       10/20/2014 for Notification of Unusual Event CECC EPIP-3                     47               Operations Duty Specialist Procedure       10/20/2014 for Alert, Site Area Emergency, or General Emergency
EPIP Revision Title Effective Date CECC EPIP-2 46 Operations Duty Specialist Procedure for Notification of Unusual Event 10/20/2014 CECC EPIP-3 47 Operations Duty Specialist Procedure for Alert, Site Area Emergency, or General Emergency 10/20/2014 L44 141105 001


U. S. Nuclear Regulatory Commission Page 2 Date November 5, 2014 provides a summary of the changes and the analyses performed that concluded the changes do not constitute a reduction in effectiveness of the EPIPs. The CECC EPIP-2 and CECC EPIP-3 procedures continue to comply with the requirements of 10 CFR 50.47(b) and 10 CFR 50 Appendix E. Enclosures 2 and 3 provide a copy of the revised EPIPs.
U. S. Nuclear Regulatory Commission Page 2 Date November 5, 2014 provides a summary of the changes and the analyses performed that concluded the changes do not constitute a reduction in effectiveness of the EPIPs. The CECC EPIP-2 and CECC EPIP-3 procedures continue to comply with the requirements of 10 CFR 50.47(b) and 10 CFR 50 Appendix E. Enclosures 2 and 3 provide a copy of the revised EPIPs.
There are no new regulatory commitments in this letter. If you have any questions regarding this submittal, please contact Edward D. Schrull at (423) 751-3850.
There are no new regulatory commitments in this letter. If you have any questions regarding this submittal, please contact Edward D. Schrull at (423) 751-3850.  
\!.lice P sident, Nuclear Licensing
\\!.lice P sident, Nuclear Licensing  


==Enclosures:==
==Enclosures:==
: 1. Central Emergency Control Center- Emergency Plan Implementing Procedure Revision - Summary of Changes and Analysis
: 1. Central Emergency Control Center-Emergency Plan Implementing Procedure Revision - Summary of Changes and Analysis
: 2. CECC EPIP-2 , "Operations Duty Specialist Procedure for Notification of Unusual Event," Revision 46
: 2. CECC EPIP-2, "Operations Duty Specialist Procedure for Notification of Unusual Event," Revision 46
: 3. CECC EPIP-3, "Operations Duty Specialist Procedure for Alert, Site Area Emergency, or General Emergency," Revision 47 cc (Enclosures):
: 3. CECC EPIP-3, "Operations Duty Specialist Procedure for Alert, Site Area Emergency, or General Emergency," Revision 47 cc (Enclosures):
NRC   Regional Administrator- Region II NRC   Senior Resident Inspector- Browns Ferry Nuclear Plant NRC   Senior Resident Inspector- Sequoyah Nuclear Plant NRC   Senior Resident Inspector- Watts Bar Nuclear Plant}}
NRC Regional Administrator-Region II NRC Senior Resident Inspector-Browns Ferry Nuclear Plant NRC Senior Resident Inspector-Sequoyah Nuclear Plant NRC Senior Resident Inspector-Watts Bar Nuclear Plant}}

Latest revision as of 10:19, 10 January 2025

Submittal of Central Emergency Control Center - Emergency Plan Implementing Procedure Revisions
ML15205A171
Person / Time
Site: Browns Ferry, Watts Bar, Sequoyah  Tennessee Valley Authority icon.png
Issue date: 11/05/2014
From: James Shea
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
CNL-14-209
Download: ML15205A171 (2)


Text

Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-14-209 November 5, 2014 10 CFR 50, Appendix E, Section V 10 CFR 50.4 10 CFR 50.54(q)(5) 10 CFR 72.44(f)

ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390

Subject:

Central Emergency Control Center - Emergency Plan Implementing Procedure Revision In accordance with the requirements of 10 CFR Part 50, Appendix E, Section V and 10 CFR 72.44(f), this submittal provides the revised Central Emergency Control Center (CECC)

Emergency Plan Implementing Procedures (EPIPs) as listed below.

EPIP Revision Title Effective Date CECC EPIP-2 46 Operations Duty Specialist Procedure for Notification of Unusual Event 10/20/2014 CECC EPIP-3 47 Operations Duty Specialist Procedure for Alert, Site Area Emergency, or General Emergency 10/20/2014 L44 141105 001

U. S. Nuclear Regulatory Commission Page 2 Date November 5, 2014 provides a summary of the changes and the analyses performed that concluded the changes do not constitute a reduction in effectiveness of the EPIPs. The CECC EPIP-2 and CECC EPIP-3 procedures continue to comply with the requirements of 10 CFR 50.47(b) and 10 CFR 50 Appendix E. Enclosures 2 and 3 provide a copy of the revised EPIPs.

There are no new regulatory commitments in this letter. If you have any questions regarding this submittal, please contact Edward D. Schrull at (423) 751-3850.

\\!.lice P sident, Nuclear Licensing

Enclosures:

1. Central Emergency Control Center-Emergency Plan Implementing Procedure Revision - Summary of Changes and Analysis
2. CECC EPIP-2, "Operations Duty Specialist Procedure for Notification of Unusual Event," Revision 46
3. CECC EPIP-3, "Operations Duty Specialist Procedure for Alert, Site Area Emergency, or General Emergency," Revision 47 cc (Enclosures):

NRC Regional Administrator-Region II NRC Senior Resident Inspector-Browns Ferry Nuclear Plant NRC Senior Resident Inspector-Sequoyah Nuclear Plant NRC Senior Resident Inspector-Watts Bar Nuclear Plant