CNL-15-257, Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load - Revised Mode of Applicability for 2-PTI-043-04: Difference between revisions

From kanterella
Jump to navigation Jump to search
Created page by program invented by StriderTol
StriderTol Bot change
 
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-15-257 December 11, 2015 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 Facility Operating License No. NPF-96 NRC Docket No. 50-391
{{#Wiki_filter:Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-15-257 December 11, 2015 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 Facility Operating License No. NPF-96 NRC Docket No. 50-391  


==Subject:==
==Subject:==
Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load - Revised Mode of Applicability for 2-PTI-043-04
Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load - Revised Mode of Applicability for 2-PTI-043-04  


==Reference:==
==Reference:==
TVA Letter to NRC, Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load," dated November 25, 2015 On November 25, 2015, Tennessee Valley Authority (TVA) provided a list of Watts Bar Nuclear Plant (WBN), Unit 2 Preoperational Test Instructions (PTIs) to the Nuclear Regulatory Commission (NRC) that were to be completed after fuel load (Reference letter). The list enclosed in the Reference letter included the technical justification and schedule, including the power level for completion of delayed testing, and was provided as required by WBN, Unit 2 Final Safety Analysis Report (FSAR), Section 14.2, "Test Program."
TVA Letter to NRC, Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load," dated November 25, 2015 On November 25, 2015, Tennessee Valley Authority (TVA) provided a list of Watts Bar Nuclear Plant (WBN), Unit 2 Preoperational Test Instructions (PTIs) to the Nuclear Regulatory Commission (NRC) that were to be completed after fuel load (Reference letter). The list enclosed in the Reference letter included the technical justification and schedule, including the power level for completion of delayed testing, and was provided as required by WBN, Unit 2 Final Safety Analysis Report (FSAR), Section 14.2, "Test Program."
The power level for completion of 2-PTI-043-04, Primary Sampling System Gas Analyzer, was stated in the Reference letter as Prior to entering mode 5. This PTI verifies the operability and performance of the active components of the system and demonstrates the operability of the Primary Sampling System Gas Analyzer as a whole under conditions as close to design as possible. It was determined the plant conditions required to be tested and verified for this PTI would be established during Mode 5.
The power level for completion of 2-PTI-043-04, Primary Sampling System Gas Analyzer, was stated in the Reference letter as Prior to entering mode 5. This PTI verifies the operability and performance of the active components of the system and demonstrates the operability of the Primary Sampling System Gas Analyzer as a whole under conditions as close to design as possible. It was determined the plant conditions required to be tested and verified for this PTI would be established during Mode 5.
The purpose of this letter is to revise mode of applicability for completion of 2-PTI-043-04 from prior to entering mode 5 to prior to entering mode 4. The technical justification and schedule, including the power level for completion of delayed testing are provided in the Enclosure to this letter. The Joint Test Group and Test Review Group have reviewed the technical justification for delaying test completion during mode 5 and the justification has been approved by the Plant Manager. This revision does not impact the commitment that TVA will complete the delayed preoperational test instructions listed in the reference letter prior to WBN Unit 2 initial criticality.
The purpose of this letter is to revise mode of applicability for completion of 2-PTI-043-04 from prior to entering mode 5 to prior to entering mode 4. The technical justification and schedule, including the power level for completion of delayed testing are provided in the Enclosure to this letter. The Joint Test Group and Test Review Group have reviewed the technical justification for delaying test completion during mode 5 and the justification has been approved by the Plant Manager. This revision does not impact the commitment that TVA will complete the delayed preoperational test instructions listed in the reference letter prior to WBN Unit 2 initial criticality.  


U.S. Nuclear Regulatory Commission CNL-15-257 Page2 December 11, 2015 There are no new regulatory commitments contained in this submittal. Please contact Gordon Arent at (423) 365-2004 if there are questions regarding this submittal.
U.S. Nuclear Regulatory Commission CNL-15-257 Page2 December 11, 2015 There are no new regulatory commitments contained in this submittal. Please contact Gordon Arent at (423) 365-2004 if there are questions regarding this submittal.  


==Enclosure:==
==Enclosure:==
Preoperational Test Instructions to be Completed after WBN Unit 2 Fuel Load cc (Enclosure):
Preoperational Test Instructions to be Completed after WBN Unit 2 Fuel Load cc (Enclosure):
NRC Regional Administrator - Region II NRC Project Manager - Watts Bar Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant, Unit 1 NRC Senior Resident Inspector - Watts Bar Nuclear Plant, Unit 2
NRC Regional Administrator - Region II NRC Project Manager - Watts Bar Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant, Unit 1 NRC Senior Resident Inspector - Watts Bar Nuclear Plant, Unit 2  


U. S. Nuclear Regulatory Commission CNL-15-257 Page 3 December 11, 2015 bcc (Enclosure):
U. S. Nuclear Regulatory Commission CNL-15-257 Page 3 December 11, 2015 bcc (Enclosure):
Ben Beasley, Branch Chief, Plant Licensing Branch II-2 U.S. Nuclear Regulatory Commission MS 08G9A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Leonard Wert, Deputy Regional Administrator for Operations U.S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257
Ben Beasley, Branch Chief, Plant Licensing Branch II-2 U.S. Nuclear Regulatory Commission MS 08G9A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Leonard Wert, Deputy Regional Administrator for Operations U.S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257
 
* All testing described in this Enclosure will be completed prior to intial criticality, thus at a power level of 0%.
Preoperational             PTI Step Number(s) and Description of                   Technical Justification for Delaying Test Until After     Schedule, including Power Test Instruction                    Item(s) Being Deferred                                                  Fuel Load                        Level for Completion of Number                                                                                                                                        Delayed Testing*
Page E-1 Preoperational Test Instruction Number PTI Step Number(s) and Description of Item(s) Being Deferred Technical Justification for Delaying Test Until After Fuel Load Schedule, including Power Level for Completion of Delayed Testing*
2-PTI-043-04 R0         All:                                                     WBN Unit 2 FSAR 9.3.2.2 [5]: A gas analyzer system       Prior to entering Mode 4 Primary Sampling                                                                  sequentially monitors points in the waste disposal and System Gas Analyzer        The PTI tests the functionality of the Primary            chemical volume and control systems for oxygen Sampling System Gas Analyzer. Test completion            concentrations in either a hydrogen or a nitrogen is being deferred to after Fuel Load during Mode 5.
2-PTI-043-04 R0 Primary Sampling System Gas Analyzer All:
atmosphere. The concentrations are displayed, and recorded, and an alarm is given at the analyzer when appropriate.
The PTI tests the functionality of the Primary Sampling System Gas Analyzer. Test completion is being deferred to after Fuel Load during Mode
: 5.
WBN Unit 2 FSAR 9.3.2.2 [5]: A gas analyzer system sequentially monitors points in the waste disposal and chemical volume and control systems for oxygen concentrations in either a hydrogen or a nitrogen atmosphere. The concentrations are displayed, and recorded, and an alarm is given at the analyzer when appropriate.
Technical Specification 5.7.2.15, Explosive Gas and Storage Tank Radioactivity Monitoring Program, discusses controls for potentially explosive gas mixtures contained in the Waste Gas Holdup System.
Technical Specification 5.7.2.15, Explosive Gas and Storage Tank Radioactivity Monitoring Program, discusses controls for potentially explosive gas mixtures contained in the Waste Gas Holdup System.
The applicability of the program is anytime there is a cover gas in the tanks. This PTI addresses monitoring of the U2 Pressurizer Relief Tank (PRT) , Reactor Coolant Drain Tank (RCDT), and Volume Control Tank (VCT). The program mode applicability for these U2 tanks is discussed below.
The applicability of the program is anytime there is a cover gas in the tanks. This PTI addresses monitoring of the U2 Pressurizer Relief Tank (PRT), Reactor Coolant Drain Tank (RCDT), and Volume Control Tank (VCT). The program mode applicability for these U2 tanks is discussed below.
2-GO-7, Refueling Operations, requires one charging pump in service to provide Chemistry control during fuel load. With Chemistrys support, manual gas sampling capability for the U2 VCT has been verified to meet the Tech Spec 5.7.2.15 requirement for fuel load. Also, the gas analyzer, which is common for U1 and U2, is functional as demonstrated by its use in providing analysis of U1 samples. Subsequent chemistry sampling requirements are in 2-GO-1, Unit Startup From Cold Shutdown To Hot Standby, and 2-GO-10, Reactor Coolant System Drain and Fill Operations.
2-GO-7, Refueling Operations, requires one charging pump in service to provide Chemistry control during fuel load. With Chemistrys support, manual gas sampling capability for the U2 VCT has been verified to meet the Tech Spec 5.7.2.15 requirement for fuel load. Also, the gas analyzer, which is common for U1 and U2, is functional as demonstrated by its use in providing analysis of U1 samples. Subsequent chemistry sampling requirements are in 2-GO-1, Unit Startup From Cold Shutdown To Hot Standby, and 2-GO-10, Reactor Coolant System Drain and Fill Operations.
2-GO-1 identifies the need to establish the H2 blanket on the VCT prior to Mode 4. 2-GO-10 identifies the need to monitor gas (O2) concentration in the PRT and RCDT during restoration which corresponds with Mode
2-GO-1 identifies the need to establish the H2 blanket on the VCT prior to Mode 4. 2-GO-10 identifies the need to monitor gas (O2) concentration in the PRT and RCDT during restoration which corresponds with Mode
: 5. Therefore scheduling this PTI to complete during Mode 5 will not adversely affect fuel loading operations or cause features that have not been tested to be relied upon for safe plant operation.
: 5. Therefore scheduling this PTI to complete during Mode 5 will not adversely affect fuel loading operations or cause features that have not been tested to be relied upon for safe plant operation.
* All testing described in this Enclosure will be completed prior to intial criticality, thus at a power level of 0%.
Prior to entering Mode 4
Page E-1


Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-15-257 December 11, 2015 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 Facility Operating License No. NPF-96 NRC Docket No. 50-391
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-15-257 December 11, 2015 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 Facility Operating License No. NPF-96 NRC Docket No. 50-391  


==Subject:==
==Subject:==
Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load - Revised Mode of Applicability for 2-PTI-043-04
Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load - Revised Mode of Applicability for 2-PTI-043-04  


==Reference:==
==Reference:==
TVA Letter to NRC, Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load," dated November 25, 2015 On November 25, 2015, Tennessee Valley Authority (TVA) provided a list of Watts Bar Nuclear Plant (WBN), Unit 2 Preoperational Test Instructions (PTIs) to the Nuclear Regulatory Commission (NRC) that were to be completed after fuel load (Reference letter). The list enclosed in the Reference letter included the technical justification and schedule, including the power level for completion of delayed testing, and was provided as required by WBN, Unit 2 Final Safety Analysis Report (FSAR), Section 14.2, "Test Program."
TVA Letter to NRC, Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load," dated November 25, 2015 On November 25, 2015, Tennessee Valley Authority (TVA) provided a list of Watts Bar Nuclear Plant (WBN), Unit 2 Preoperational Test Instructions (PTIs) to the Nuclear Regulatory Commission (NRC) that were to be completed after fuel load (Reference letter). The list enclosed in the Reference letter included the technical justification and schedule, including the power level for completion of delayed testing, and was provided as required by WBN, Unit 2 Final Safety Analysis Report (FSAR), Section 14.2, "Test Program."
The power level for completion of 2-PTI-043-04, Primary Sampling System Gas Analyzer, was stated in the Reference letter as Prior to entering mode 5. This PTI verifies the operability and performance of the active components of the system and demonstrates the operability of the Primary Sampling System Gas Analyzer as a whole under conditions as close to design as possible. It was determined the plant conditions required to be tested and verified for this PTI would be established during Mode 5.
The power level for completion of 2-PTI-043-04, Primary Sampling System Gas Analyzer, was stated in the Reference letter as Prior to entering mode 5. This PTI verifies the operability and performance of the active components of the system and demonstrates the operability of the Primary Sampling System Gas Analyzer as a whole under conditions as close to design as possible. It was determined the plant conditions required to be tested and verified for this PTI would be established during Mode 5.
The purpose of this letter is to revise mode of applicability for completion of 2-PTI-043-04 from prior to entering mode 5 to prior to entering mode 4. The technical justification and schedule, including the power level for completion of delayed testing are provided in the Enclosure to this letter. The Joint Test Group and Test Review Group have reviewed the technical justification for delaying test completion during mode 5 and the justification has been approved by the Plant Manager. This revision does not impact the commitment that TVA will complete the delayed preoperational test instructions listed in the reference letter prior to WBN Unit 2 initial criticality.
The purpose of this letter is to revise mode of applicability for completion of 2-PTI-043-04 from prior to entering mode 5 to prior to entering mode 4. The technical justification and schedule, including the power level for completion of delayed testing are provided in the Enclosure to this letter. The Joint Test Group and Test Review Group have reviewed the technical justification for delaying test completion during mode 5 and the justification has been approved by the Plant Manager. This revision does not impact the commitment that TVA will complete the delayed preoperational test instructions listed in the reference letter prior to WBN Unit 2 initial criticality.  


U.S. Nuclear Regulatory Commission CNL-15-257 Page2 December 11, 2015 There are no new regulatory commitments contained in this submittal. Please contact Gordon Arent at (423) 365-2004 if there are questions regarding this submittal.
U.S. Nuclear Regulatory Commission CNL-15-257 Page2 December 11, 2015 There are no new regulatory commitments contained in this submittal. Please contact Gordon Arent at (423) 365-2004 if there are questions regarding this submittal.  


==Enclosure:==
==Enclosure:==
Preoperational Test Instructions to be Completed after WBN Unit 2 Fuel Load cc (Enclosure):
Preoperational Test Instructions to be Completed after WBN Unit 2 Fuel Load cc (Enclosure):
NRC Regional Administrator - Region II NRC Project Manager - Watts Bar Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant, Unit 1 NRC Senior Resident Inspector - Watts Bar Nuclear Plant, Unit 2
NRC Regional Administrator - Region II NRC Project Manager - Watts Bar Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant, Unit 1 NRC Senior Resident Inspector - Watts Bar Nuclear Plant, Unit 2  


U. S. Nuclear Regulatory Commission CNL-15-257 Page 3 December 11, 2015 bcc (Enclosure):
U. S. Nuclear Regulatory Commission CNL-15-257 Page 3 December 11, 2015 bcc (Enclosure):
Ben Beasley, Branch Chief, Plant Licensing Branch II-2 U.S. Nuclear Regulatory Commission MS 08G9A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Leonard Wert, Deputy Regional Administrator for Operations U.S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257
Ben Beasley, Branch Chief, Plant Licensing Branch II-2 U.S. Nuclear Regulatory Commission MS 08G9A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Leonard Wert, Deputy Regional Administrator for Operations U.S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257
 
* All testing described in this Enclosure will be completed prior to intial criticality, thus at a power level of 0%.
Preoperational             PTI Step Number(s) and Description of                   Technical Justification for Delaying Test Until After     Schedule, including Power Test Instruction                    Item(s) Being Deferred                                                  Fuel Load                        Level for Completion of Number                                                                                                                                        Delayed Testing*
Page E-1 Preoperational Test Instruction Number PTI Step Number(s) and Description of Item(s) Being Deferred Technical Justification for Delaying Test Until After Fuel Load Schedule, including Power Level for Completion of Delayed Testing*
2-PTI-043-04 R0         All:                                                     WBN Unit 2 FSAR 9.3.2.2 [5]: A gas analyzer system       Prior to entering Mode 4 Primary Sampling                                                                  sequentially monitors points in the waste disposal and System Gas Analyzer        The PTI tests the functionality of the Primary            chemical volume and control systems for oxygen Sampling System Gas Analyzer. Test completion            concentrations in either a hydrogen or a nitrogen is being deferred to after Fuel Load during Mode 5.
2-PTI-043-04 R0 Primary Sampling System Gas Analyzer All:
atmosphere. The concentrations are displayed, and recorded, and an alarm is given at the analyzer when appropriate.
The PTI tests the functionality of the Primary Sampling System Gas Analyzer. Test completion is being deferred to after Fuel Load during Mode
: 5.
WBN Unit 2 FSAR 9.3.2.2 [5]: A gas analyzer system sequentially monitors points in the waste disposal and chemical volume and control systems for oxygen concentrations in either a hydrogen or a nitrogen atmosphere. The concentrations are displayed, and recorded, and an alarm is given at the analyzer when appropriate.
Technical Specification 5.7.2.15, Explosive Gas and Storage Tank Radioactivity Monitoring Program, discusses controls for potentially explosive gas mixtures contained in the Waste Gas Holdup System.
Technical Specification 5.7.2.15, Explosive Gas and Storage Tank Radioactivity Monitoring Program, discusses controls for potentially explosive gas mixtures contained in the Waste Gas Holdup System.
The applicability of the program is anytime there is a cover gas in the tanks. This PTI addresses monitoring of the U2 Pressurizer Relief Tank (PRT) , Reactor Coolant Drain Tank (RCDT), and Volume Control Tank (VCT). The program mode applicability for these U2 tanks is discussed below.
The applicability of the program is anytime there is a cover gas in the tanks. This PTI addresses monitoring of the U2 Pressurizer Relief Tank (PRT), Reactor Coolant Drain Tank (RCDT), and Volume Control Tank (VCT). The program mode applicability for these U2 tanks is discussed below.
2-GO-7, Refueling Operations, requires one charging pump in service to provide Chemistry control during fuel load. With Chemistrys support, manual gas sampling capability for the U2 VCT has been verified to meet the Tech Spec 5.7.2.15 requirement for fuel load. Also, the gas analyzer, which is common for U1 and U2, is functional as demonstrated by its use in providing analysis of U1 samples. Subsequent chemistry sampling requirements are in 2-GO-1, Unit Startup From Cold Shutdown To Hot Standby, and 2-GO-10, Reactor Coolant System Drain and Fill Operations.
2-GO-7, Refueling Operations, requires one charging pump in service to provide Chemistry control during fuel load. With Chemistrys support, manual gas sampling capability for the U2 VCT has been verified to meet the Tech Spec 5.7.2.15 requirement for fuel load. Also, the gas analyzer, which is common for U1 and U2, is functional as demonstrated by its use in providing analysis of U1 samples. Subsequent chemistry sampling requirements are in 2-GO-1, Unit Startup From Cold Shutdown To Hot Standby, and 2-GO-10, Reactor Coolant System Drain and Fill Operations.
2-GO-1 identifies the need to establish the H2 blanket on the VCT prior to Mode 4. 2-GO-10 identifies the need to monitor gas (O2) concentration in the PRT and RCDT during restoration which corresponds with Mode
2-GO-1 identifies the need to establish the H2 blanket on the VCT prior to Mode 4. 2-GO-10 identifies the need to monitor gas (O2) concentration in the PRT and RCDT during restoration which corresponds with Mode
: 5. Therefore scheduling this PTI to complete during Mode 5 will not adversely affect fuel loading operations or cause features that have not been tested to be relied upon for safe plant operation.
: 5. Therefore scheduling this PTI to complete during Mode 5 will not adversely affect fuel loading operations or cause features that have not been tested to be relied upon for safe plant operation.
* All testing described in this Enclosure will be completed prior to intial criticality, thus at a power level of 0%.
Prior to entering Mode 4}}
Page E-1}}

Latest revision as of 06:07, 10 January 2025

Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load - Revised Mode of Applicability for 2-PTI-043-04
ML15345A452
Person / Time
Site: Watts Bar 
Issue date: 12/11/2015
From: James Shea
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
CNL-15-257
Download: ML15345A452 (4)


Text

Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-15-257 December 11, 2015 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 Facility Operating License No. NPF-96 NRC Docket No. 50-391

Subject:

Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load - Revised Mode of Applicability for 2-PTI-043-04

Reference:

TVA Letter to NRC, Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load," dated November 25, 2015 On November 25, 2015, Tennessee Valley Authority (TVA) provided a list of Watts Bar Nuclear Plant (WBN), Unit 2 Preoperational Test Instructions (PTIs) to the Nuclear Regulatory Commission (NRC) that were to be completed after fuel load (Reference letter). The list enclosed in the Reference letter included the technical justification and schedule, including the power level for completion of delayed testing, and was provided as required by WBN, Unit 2 Final Safety Analysis Report (FSAR), Section 14.2, "Test Program."

The power level for completion of 2-PTI-043-04, Primary Sampling System Gas Analyzer, was stated in the Reference letter as Prior to entering mode 5. This PTI verifies the operability and performance of the active components of the system and demonstrates the operability of the Primary Sampling System Gas Analyzer as a whole under conditions as close to design as possible. It was determined the plant conditions required to be tested and verified for this PTI would be established during Mode 5.

The purpose of this letter is to revise mode of applicability for completion of 2-PTI-043-04 from prior to entering mode 5 to prior to entering mode 4. The technical justification and schedule, including the power level for completion of delayed testing are provided in the Enclosure to this letter. The Joint Test Group and Test Review Group have reviewed the technical justification for delaying test completion during mode 5 and the justification has been approved by the Plant Manager. This revision does not impact the commitment that TVA will complete the delayed preoperational test instructions listed in the reference letter prior to WBN Unit 2 initial criticality.

U.S. Nuclear Regulatory Commission CNL-15-257 Page2 December 11, 2015 There are no new regulatory commitments contained in this submittal. Please contact Gordon Arent at (423) 365-2004 if there are questions regarding this submittal.

Enclosure:

Preoperational Test Instructions to be Completed after WBN Unit 2 Fuel Load cc (Enclosure):

NRC Regional Administrator - Region II NRC Project Manager - Watts Bar Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant, Unit 1 NRC Senior Resident Inspector - Watts Bar Nuclear Plant, Unit 2

U. S. Nuclear Regulatory Commission CNL-15-257 Page 3 December 11, 2015 bcc (Enclosure):

Ben Beasley, Branch Chief, Plant Licensing Branch II-2 U.S. Nuclear Regulatory Commission MS 08G9A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Leonard Wert, Deputy Regional Administrator for Operations U.S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257

  • All testing described in this Enclosure will be completed prior to intial criticality, thus at a power level of 0%.

Page E-1 Preoperational Test Instruction Number PTI Step Number(s) and Description of Item(s) Being Deferred Technical Justification for Delaying Test Until After Fuel Load Schedule, including Power Level for Completion of Delayed Testing*

2-PTI-043-04 R0 Primary Sampling System Gas Analyzer All:

The PTI tests the functionality of the Primary Sampling System Gas Analyzer. Test completion is being deferred to after Fuel Load during Mode

5.

WBN Unit 2 FSAR 9.3.2.2 [5]: A gas analyzer system sequentially monitors points in the waste disposal and chemical volume and control systems for oxygen concentrations in either a hydrogen or a nitrogen atmosphere. The concentrations are displayed, and recorded, and an alarm is given at the analyzer when appropriate.

Technical Specification 5.7.2.15, Explosive Gas and Storage Tank Radioactivity Monitoring Program, discusses controls for potentially explosive gas mixtures contained in the Waste Gas Holdup System.

The applicability of the program is anytime there is a cover gas in the tanks. This PTI addresses monitoring of the U2 Pressurizer Relief Tank (PRT), Reactor Coolant Drain Tank (RCDT), and Volume Control Tank (VCT). The program mode applicability for these U2 tanks is discussed below.

2-GO-7, Refueling Operations, requires one charging pump in service to provide Chemistry control during fuel load. With Chemistrys support, manual gas sampling capability for the U2 VCT has been verified to meet the Tech Spec 5.7.2.15 requirement for fuel load. Also, the gas analyzer, which is common for U1 and U2, is functional as demonstrated by its use in providing analysis of U1 samples. Subsequent chemistry sampling requirements are in 2-GO-1, Unit Startup From Cold Shutdown To Hot Standby, and 2-GO-10, Reactor Coolant System Drain and Fill Operations.

2-GO-1 identifies the need to establish the H2 blanket on the VCT prior to Mode 4. 2-GO-10 identifies the need to monitor gas (O2) concentration in the PRT and RCDT during restoration which corresponds with Mode

5. Therefore scheduling this PTI to complete during Mode 5 will not adversely affect fuel loading operations or cause features that have not been tested to be relied upon for safe plant operation.

Prior to entering Mode 4

Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-15-257 December 11, 2015 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 Facility Operating License No. NPF-96 NRC Docket No. 50-391

Subject:

Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load - Revised Mode of Applicability for 2-PTI-043-04

Reference:

TVA Letter to NRC, Exceptions to Completion of Preoperational Test Instructions Prior to Fuel Load," dated November 25, 2015 On November 25, 2015, Tennessee Valley Authority (TVA) provided a list of Watts Bar Nuclear Plant (WBN), Unit 2 Preoperational Test Instructions (PTIs) to the Nuclear Regulatory Commission (NRC) that were to be completed after fuel load (Reference letter). The list enclosed in the Reference letter included the technical justification and schedule, including the power level for completion of delayed testing, and was provided as required by WBN, Unit 2 Final Safety Analysis Report (FSAR), Section 14.2, "Test Program."

The power level for completion of 2-PTI-043-04, Primary Sampling System Gas Analyzer, was stated in the Reference letter as Prior to entering mode 5. This PTI verifies the operability and performance of the active components of the system and demonstrates the operability of the Primary Sampling System Gas Analyzer as a whole under conditions as close to design as possible. It was determined the plant conditions required to be tested and verified for this PTI would be established during Mode 5.

The purpose of this letter is to revise mode of applicability for completion of 2-PTI-043-04 from prior to entering mode 5 to prior to entering mode 4. The technical justification and schedule, including the power level for completion of delayed testing are provided in the Enclosure to this letter. The Joint Test Group and Test Review Group have reviewed the technical justification for delaying test completion during mode 5 and the justification has been approved by the Plant Manager. This revision does not impact the commitment that TVA will complete the delayed preoperational test instructions listed in the reference letter prior to WBN Unit 2 initial criticality.

U.S. Nuclear Regulatory Commission CNL-15-257 Page2 December 11, 2015 There are no new regulatory commitments contained in this submittal. Please contact Gordon Arent at (423) 365-2004 if there are questions regarding this submittal.

Enclosure:

Preoperational Test Instructions to be Completed after WBN Unit 2 Fuel Load cc (Enclosure):

NRC Regional Administrator - Region II NRC Project Manager - Watts Bar Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant, Unit 1 NRC Senior Resident Inspector - Watts Bar Nuclear Plant, Unit 2

U. S. Nuclear Regulatory Commission CNL-15-257 Page 3 December 11, 2015 bcc (Enclosure):

Ben Beasley, Branch Chief, Plant Licensing Branch II-2 U.S. Nuclear Regulatory Commission MS 08G9A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Leonard Wert, Deputy Regional Administrator for Operations U.S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257

  • All testing described in this Enclosure will be completed prior to intial criticality, thus at a power level of 0%.

Page E-1 Preoperational Test Instruction Number PTI Step Number(s) and Description of Item(s) Being Deferred Technical Justification for Delaying Test Until After Fuel Load Schedule, including Power Level for Completion of Delayed Testing*

2-PTI-043-04 R0 Primary Sampling System Gas Analyzer All:

The PTI tests the functionality of the Primary Sampling System Gas Analyzer. Test completion is being deferred to after Fuel Load during Mode

5.

WBN Unit 2 FSAR 9.3.2.2 [5]: A gas analyzer system sequentially monitors points in the waste disposal and chemical volume and control systems for oxygen concentrations in either a hydrogen or a nitrogen atmosphere. The concentrations are displayed, and recorded, and an alarm is given at the analyzer when appropriate.

Technical Specification 5.7.2.15, Explosive Gas and Storage Tank Radioactivity Monitoring Program, discusses controls for potentially explosive gas mixtures contained in the Waste Gas Holdup System.

The applicability of the program is anytime there is a cover gas in the tanks. This PTI addresses monitoring of the U2 Pressurizer Relief Tank (PRT), Reactor Coolant Drain Tank (RCDT), and Volume Control Tank (VCT). The program mode applicability for these U2 tanks is discussed below.

2-GO-7, Refueling Operations, requires one charging pump in service to provide Chemistry control during fuel load. With Chemistrys support, manual gas sampling capability for the U2 VCT has been verified to meet the Tech Spec 5.7.2.15 requirement for fuel load. Also, the gas analyzer, which is common for U1 and U2, is functional as demonstrated by its use in providing analysis of U1 samples. Subsequent chemistry sampling requirements are in 2-GO-1, Unit Startup From Cold Shutdown To Hot Standby, and 2-GO-10, Reactor Coolant System Drain and Fill Operations.

2-GO-1 identifies the need to establish the H2 blanket on the VCT prior to Mode 4. 2-GO-10 identifies the need to monitor gas (O2) concentration in the PRT and RCDT during restoration which corresponds with Mode

5. Therefore scheduling this PTI to complete during Mode 5 will not adversely affect fuel loading operations or cause features that have not been tested to be relied upon for safe plant operation.

Prior to entering Mode 4