| event date = 06/30/2009 15:13 PDT | | event date = 06/30/2009 15:13 PDT | ||
| last update date = 06/30/2009 | | last update date = 06/30/2009 | ||
| title = Potential Media Interest Due | | title = Potential Media Interest Due to Forced Outage | ||
| event text = On June 30, 2009, at 1513 PDT, Unit 2 commenced a ramp[-down] in accordance with the annunciator response guidance to enter Operating Procedure (OP) Abnormal Procedure AP-25 due to loss of forced cooling to main transformer bank (MTB) C-Phase transformer. At 1538, Unit 2 was separated from the grid in accordance with plant OP AP-25 initiation of a main generator unit trip. At 1554 PDT, the Reactor Trip Breakers (RTBs) were manually opened per OP AP-25 Step 24.j. [Reactor] power was being held in Mode 2 at about 3% reactor power per the procedure when the RTBs were opened. | | event text = On June 30, 2009, at 1513 PDT, Unit 2 commenced a ramp[-down] in accordance with the annunciator response guidance to enter Operating Procedure (OP) Abnormal Procedure AP-25 due to loss of forced cooling to main transformer bank (MTB) C-Phase transformer. At 1538, Unit 2 was separated from the grid in accordance with plant OP AP-25 initiation of a main generator unit trip. At 1554 PDT, the Reactor Trip Breakers (RTBs) were manually opened per OP AP-25 Step 24.j. [Reactor] power was being held in Mode 2 at about 3% reactor power per the procedure when the RTBs were opened. | ||
The investigation into the cause is continuing. | The investigation into the cause is continuing. |
Latest revision as of 22:11, 1 March 2018
Where | |
---|---|
Diablo Canyon California (NRC Region 4) | |
Reporting | |
10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release | |
Time - Person (Reporting Time:+-0.4 h-0.0167 days <br />-0.00238 weeks <br />-5.4792e-4 months <br />) | |
Opened: | Anthony Chitwood 21:49 Jun 30, 2009 |
NRC Officer: | Vince Klco |
Last Updated: | Jun 30, 2009 |