ENS 45833: Difference between revisions
Jump to navigation
Jump to search
StriderTol (talk | contribs) (Created page by program invented by Mark Hawes) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 16: | Line 16: | ||
| event date = 04/12/2010 07:21 CDT | | event date = 04/12/2010 07:21 CDT | ||
| last update date = 04/12/2010 | | last update date = 04/12/2010 | ||
| title = Actuation | | title = Actuation of Blackout Sequencers Due to Loss of One Offsite Power Source | ||
| event text = At 0721 [CDT] on 4/12/10 the Comanche Peak Nuclear Power Plant experienced a loss of 138 KV transformer XST1 due to a failed transmission line insulator. Unit 1 is currently defueled per 1RF14 refueling outage schedule. Unit 2 was subjected to actuation of both blackout sequencers causing an automatic start of both motor driven Aux Feedwater (AFW) pumps as well as the turbine driven AFW pump. | | event text = At 0721 [CDT] on 4/12/10 the Comanche Peak Nuclear Power Plant experienced a loss of 138 KV transformer XST1 due to a failed transmission line insulator. Unit 1 is currently defueled per 1RF14 refueling outage schedule. Unit 2 was subjected to actuation of both blackout sequencers causing an automatic start of both motor driven Aux Feedwater (AFW) pumps as well as the turbine driven AFW pump. | ||
No emergency diesel generator started as per design. | No emergency diesel generator started as per design. |
Latest revision as of 22:09, 1 March 2018
Where | |
---|---|
Comanche Peak ![]() Texas (NRC Region 4) | |
Reporting | |
10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
Time - Person (Reporting Time:+-2.35 h-0.0979 days <br />-0.014 weeks <br />-0.00322 months <br />) | |
Opened: | Pat Minahan 10:00 Apr 12, 2010 |
NRC Officer: | Bill Huffman |
Last Updated: | Apr 12, 2010 |
45833 - NRC Website
| |