ENS 52269: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by Mark Hawes)
 
(Created page by program invented by StriderTol)
 
Line 16: Line 16:
| event date = 09/28/2016 EDT
| event date = 09/28/2016 EDT
| last update date = 03/15/2017
| last update date = 03/15/2017
| title = Part 21 Report Regarding Pipe Spool Flanges For Vogtle Unit 3
| title = Part 21 Report Regarding Pipe Spool Flanges for Vogtle Unit 3
| event text = The following was excerpted from an email received from WECTEC LLC:
| event text = The following was excerpted from an email received from WECTEC LLC:
Nature of the defect or failure to comply and the safety hazard which is created or could be created by such defect or failure to comply.
Nature of the defect or failure to comply and the safety hazard which is created or could be created by such defect or failure to comply.

Latest revision as of 20:43, 1 March 2018

ENS 52269 +/-
Where
Cb&I Laurens
Charlotte, North Carolina (NRC Region 1)
Organization: Wectec Llc
Reporting
10 CFR 21.21(d)(3)(i), Failure to Comply or Defect
Time - Person (Reporting Time:+10.95 h0.456 days <br />0.0652 weeks <br />0.015 months <br />)
Opened: Curtis Castell
14:57 Sep 28, 2016
NRC Officer: Vince Klco
Last Updated: Mar 15, 2017
52269 - NRC Website