| event date = 03/23/2017 00:14 EDT | | event date = 03/23/2017 00:14 EDT | ||
| last update date = 03/23/2017 | | last update date = 03/23/2017 | ||
| title = Automatic Start | | title = Automatic Start of Auxiliary Feed Water | ||
| event text = On March 23, 2017, at 0014 EDT, Watts Bar Nuclear Plant Unit 2 (WBN2) experienced an unplanned trip of both Turbine Driven Main Feed Pumps (TDMFP) following a loss of Main Condenser Vacuum. The trip of both TDMFPs caused an automatic start of both Motor Driven Auxiliary Feed Water Pumps and the Turbine Driven Auxiliary Feed Water Pump. [The] cause of the loss of Main Condenser Vacuum is currently under investigation. | | event text = On March 23, 2017, at 0014 EDT, Watts Bar Nuclear Plant Unit 2 (WBN2) experienced an unplanned trip of both Turbine Driven Main Feed Pumps (TDMFP) following a loss of Main Condenser Vacuum. The trip of both TDMFPs caused an automatic start of both Motor Driven Auxiliary Feed Water Pumps and the Turbine Driven Auxiliary Feed Water Pump. [The] cause of the loss of Main Condenser Vacuum is currently under investigation. | ||
The plant was performing a normal startup, and had just synced the main generator to the grid. Subsequent to the event, the plant was transitioned to Mode 3. All rods are fully inserted. Decay heat is being removed via the atmospheric relief valves. | The plant was performing a normal startup, and had just synced the main generator to the grid. Subsequent to the event, the plant was transitioned to Mode 3. All rods are fully inserted. Decay heat is being removed via the atmospheric relief valves. |
Latest revision as of 21:43, 1 March 2018
Where | |
---|---|
Watts Bar Tennessee (NRC Region 2) | |
Reporting | |
10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
Time - Person (Reporting Time:+-1.43 h-0.0596 days <br />-0.00851 weeks <br />-0.00196 months <br />) | |
Opened: | Damon Fegley 02:48 Mar 23, 2017 |
NRC Officer: | Karl Diederich |
Last Updated: | Mar 23, 2017 |
52630 - NRC Website
| |