{{#Wiki_filter:[7590- 01-P]
{{#Wiki_filter:[7590-01-P]
 
NUCLEAR REGULATORY COMMISSION
NUCLEAR REGULATORY COMMISSION
 
[Docket No. 50-7513; NRC-2021-0193]
[Docket No. 5 0-7513; NRC-2021- 0193]
Kairos Power, LLC; Hermes Test Reactor AGENCY: Nuclear Regulatory Commission.
 
ACTION: Environmental impact statement; issuance.  
Kairos Power, LLC;
 
Hermes Test Reactor
 
AGENCY: Nuclear Regulatory Commission.
 
ACTION: Environmental impact statement; issuance.


==SUMMARY==
==SUMMARY==
: The U.S. Nuclear Regulatory Commission (NRC) is issuing a final
: The U.S. Nuclear Regulatory Commission (NRC) is issuing a final Environmental Impact Statement (EIS), NUREG-2263, Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor: Final Report. The NRC staff is issuing a final EIS as part of the review of the application submitted by Kairos Power, LLC (Kairos) for a construction permit (CP). The Hermes test reactor is proposed to be built in the City of Oak Ridge, Tennessee.
 
DATES: The final EIS is available as of [INSERT DATE OF PUBLICATION IN THE FEDERAL REGISTER].
Environmental Impact Statement (EIS), NUREG-2263, Environmental Impact Statement
ADDRESSES: Please refer to Docket ID NRC-2021-0193 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods:
 
Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2021-0193. Address questions about Docket IDs in Regulations.gov to Stacy Schumann; telephone: 301-415-0624; email: Stacy.Schumann@nrc.gov. For technical questions, contact the individual listed in the For Further Information Contact section of this document.
for the Construction Permit for the Kairos Hermes Test Reactor: Final Report. The NRC
NRCs Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public  
 
staff is issuing a final EIS as part of the review of the application submitted by Kairos
 
Power, LLC (Kairos) for a construction permit (CP). The Hermes test reactor is proposed
 
to be built in the City of Oak Ridge, Tennessee.
 
DATES: The final EIS is available as of [INSERT DATE OF PUBLICATION IN THE
 
FEDERAL REGISTER].
 
ADDRESSES: Please refer to Docket ID NRC-2021- 0193 when contacting the NRC
 
about the availability of information regarding this document. You may obtain publicly
 
available information related to this document using any of the following methods:
* Federal Rulemaking Webs ite: Go to http://www.regulations.gov and search
 
for Docket ID NRC-2021 -0193. Address questions about Docket IDs in Regulations.gov
 
to Stacy Schumann; telephone: 301-415- 0624; email: Stacy.Schumann@nrc.gov. For
 
technical questions, contact the individual listed in the For Further Information Contact
 
section of this document.
* NRCs Agencywide Documents Access and Management System
 
(ADAMS): You may obtain publicly available documents online in the ADAMS Public Documents collection at http://www.nrc.gov/r eading-rm/adams.html. To begin the
 
search, select Begin Web-based ADAMS Search. For problems with ADAMS, please
 
contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209, at
 
301-415-4737, or by email to PDR.Resource@nrc.gov. The final EIS is available in
 
ADAMS under Accession No. ML23214A269. The ADAMS accession number for
 
additional documents referenced in this document (if it is available in ADAMS) is
 
provided the first time that it is mentioned as follows.
* NRCs PDR: The PDR, where you may examine and order copies of publicly
 
available documents, is open by appointment. To make an appointment to visit the PDR,
 
please send an email to PDR.Resource@nrc.gov or call 1-800-397-4209 or 301-415-
 
4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except
 
Federal holidays.
* Project webs ite: The final EIS can be accessed online at the Her mes -
 
Kairos project specific web page at https://www.nrc.gov/reactors/non -power/hermes-
 
kairos.html.
* FOR FURTHER INFORMATION CONTACT: Tamsen Dozier, Office of
 
Nuclear Materials Safety and Safeguards, U.S. Nuclear Regulatory Commission,
 
Washington, DC 20555-0001; telephone: 301-415-2272, e mail:


2 Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select Begin Web-based ADAMS Search. For problems with ADAMS, please contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email to PDR.Resource@nrc.gov. The final EIS is available in ADAMS under Accession No. ML23214A269. The ADAMS accession number for additional documents referenced in this document (if it is available in ADAMS) is provided the first time that it is mentioned as follows.
NRCs PDR: The PDR, where you may examine and order copies of publicly available documents, is open by appointment. To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1-800-397-4209 or 301-415-4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays.
Project website: The final EIS can be accessed online at the Hermes -
Kairos project specific web page at https://www.nrc.gov/reactors/non-power/hermes-kairos.html.
FOR FURTHER INFORMATION CONTACT: Tamsen Dozier, Office of Nuclear Materials Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-2272, email:
Tamsen.Dozier@nrc.gov.
Tamsen.Dozier@nrc.gov.
SUPPLEMENTARY INFORMATION:
SUPPLEMENTARY INFORMATION:
I. Background By letter to the NRC dated September 29, 2021 (ADAMS Package Accession Number No. ML21272A375), Kairos Power LLC (Kairos) submitted an application for a construction permit for the Hermes non-power test reactor, pursuant to part 50 of title 10 of the Code of Federal Regulations (10 CFR), Domestic Licensing of Production and


I. Background
3 Utilization Facilities, and Section 104c of the Atomic Energy Act of 1954, as amended.
 
Additionally, by {{letter dated|date=October 31, 2021|text=letter dated October 31, 2021}} (ADAMS Package Accession No. ML21306A131), Kairos submitted an Environmental Report (ER) in support of its Hermes construction permit application. The test reactor is proposed to be built in Oak Ridge, Tennessee.
By letter to the NRC dated September 29, 2021 (ADAMS Package Accession
By {{letter dated|date=November 29, 2021|text=letter dated November 29, 2021}} (ADAMS Accession No. ML21319A354), the NRC staff informed Kairos of its determination that the Kairos application for a construction permit for the Hermes test reactor was acceptable for docketing under Docket No. 50-7513.
 
A notice of acceptance for docketing of the application was published in the Federal Register on December 1, 2021 (86 FR 68290) and a notice of opportunity for hearing was published on February 9, 2022 (87 FR 7503). A notice of intent to prepare an EIS and to conduct scoping process was published in the Federal Register on February 18, 2022 (87 FR 9394). A notice of availability of the draft EIS was published by the NRC in the Federal Register on September 29, 2022 (87 FR 59124). The public comment period for the draft EIS closed on December 6, 2022. Public comments are addressed in Appendix G in the final EIS (ADAMS Accession No. ML23214A269). This notice is being published in accordance with the National Environmental Policy Act of 1969, as amended and the NRCs regulations in 10 CFR part 51.
Number No. ML21272A375), Kairos Power LLC (Kairos) submitted an application for a
In addition, as outlined in 36 CFR 800.8(c), Coordination with the National Environmental Policy Act, the NRC staff used the process and documentation for the preparation of the EIS to comply with Section 106 of the National Historic Preservation Act (NHPA) in lieu of the procedures set forth on 36 CFR 800.3 through 800.6.
 
II. Discussion As discussed in the final EIS, the NRC staffs recommendation related to the  
construction permit for the Hermes non-power test reactor, pursuant to part 50 of t itle
 
10 of the Code of Federal Regulations (10 CFR), Domestic Licensing of Production and
 
2 Utilization Facilities, and Section 104c of the Atomic Energy Act of 1954, as amended.
 
Additionally, by {{letter dated|date=October 31, 2021|text=letter dated October 31, 2021}} (ADAMS Package Accession No.
 
ML21306A131), Kairos submitted an Environmental Report (ER) in support of its
 
Hermes construction permit application. The test reactor is proposed to be built in Oak
 
Ridge, Tennessee.
 
By {{letter dated|date=November 29, 2021|text=letter dated November 29, 2021}} (ADAMS Accession No. ML21319A354), the
 
NRC staff informed Kairos of its determination that the Kairos application for a
 
construction permit for the Hermes test reactor was acceptable for docketing under
 
Docket No. 50-7513.
 
A notice of acceptance for docketing of the application was published in the
 
Federal Register on December 1, 2021 (86 FR 68290) and a notice of opportunity for
 
hearing was published on February 9, 2022 (87 FR 7503). A notice of intent to prepare
 
an EIS and to conduct scoping process was published in the Federal Register on
 
February 18, 2022 (87 FR 9394). A notice of availability of the draft EIS was published
 
by the NRC in the Federal Register on September 29, 2022 (87 FR 59124). The public
 
comment period for the draft EIS closed on December 6, 2022. Public comments are
 
addressed in Appendix G in the final EIS (ADAMS Accession No. ML23214A269). This
 
notice is being published in accordance with the National Environmental Policy Act of
 
1969, as amended and the NRCs regulations in 10 CFR part 51.
 
In addition, as outlined in 36 CFR 800.8(c), Coordination with the National
 
Environmental Policy Act, the NRC staff used the process and documentation for the
 
preparation of the EIS to comply with Section 106 of the National Historic Preservation
 
Act (NHPA) in lieu of the procedures set forth on 36 CFR 800.3 through 800.6.
 
II.Discussion
 
As discussed in the final EIS, the NRC staffs recommendation related to the
 
3 environmental aspects of the proposed action is that the CP should be issued once the
 
NHPA Section 106 process is complete. This recommendation is based on: 1) the ER
 
submitted by Kairos, as revised; 2) consultation with Federal, State, Tribal and local
 
agencies; 3) the NRC staffs consideration of comments received during the
 
environmen tal review; and 4 ) the staffs independent review and asses sment
 
summarized in the final EIS, including the potential mitigation measures identified in the
 
ER and in the final EIS.
 
In addition, in making its recommendation, the NRC staff has concluded that
 
there are no environmentally preferable or obviously superior sites in the region of
 
interest.


4 environmental aspects of the proposed action is that the CP should be issued once the NHPA Section 106 process is complete. This recommendation is based on: 1) the ER submitted by Kairos, as revised; 2) consultation with Federal, State, Tribal and local agencies; 3) the NRC staffs consideration of comments received during the environmental review; and 4) the staffs independent review and assessment summarized in the final EIS, including the potential mitigation measures identified in the ER and in the final EIS.
In addition, in making its recommendation, the NRC staff has concluded that there are no environmentally preferable or obviously superior sites in the region of interest.
Dated: August 17, 2023.
Dated: August 17, 2023.
 
For the Nuclear Regulatory Commission.  
For the Nuclear Regulatory Commission.
/RA/
 
Christopher M. Regan, Director, Division of Rulemaking, Environmental, and Financial Support, Office of Nuclear Material Safety and Safeguards.}}
/RA/
 
Christopher M. Regan, Director, Division of Rulemaking, Environmental, and Financial Support, Office of Nuclear Material Safety and Safeguards.
 
4}}

Latest revision as of 02:54, 27 November 2024

Kairos Construction Permit Notice of Issuance
ML23178A191
Person / Time
Site: Hermes File:Kairos Power icon.png
Issue date: 08/17/2023
From: Christopher Regan
Office of Nuclear Material Safety and Safeguards
To:
References
NRC-2021-0193
Download: ML23178A191 (1)


Text

[7590-01-P]

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-7513; NRC-2021-0193]

Kairos Power, LLC; Hermes Test Reactor AGENCY: Nuclear Regulatory Commission.

ACTION: Environmental impact statement; issuance.

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) is issuing a final Environmental Impact Statement (EIS), NUREG-2263, Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor: Final Report. The NRC staff is issuing a final EIS as part of the review of the application submitted by Kairos Power, LLC (Kairos) for a construction permit (CP). The Hermes test reactor is proposed to be built in the City of Oak Ridge, Tennessee.

DATES: The final EIS is available as of [INSERT DATE OF PUBLICATION IN THE FEDERAL REGISTER].

ADDRESSES: Please refer to Docket ID NRC-2021-0193 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods:

Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2021-0193. Address questions about Docket IDs in Regulations.gov to Stacy Schumann; telephone: 301-415-0624; email: Stacy.Schumann@nrc.gov. For technical questions, contact the individual listed in the For Further Information Contact section of this document.

NRCs Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public

2 Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select Begin Web-based ADAMS Search. For problems with ADAMS, please contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email to PDR.Resource@nrc.gov. The final EIS is available in ADAMS under Accession No. ML23214A269. The ADAMS accession number for additional documents referenced in this document (if it is available in ADAMS) is provided the first time that it is mentioned as follows.

NRCs PDR: The PDR, where you may examine and order copies of publicly available documents, is open by appointment. To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1-800-397-4209 or 301-415-4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays.

Project website: The final EIS can be accessed online at the Hermes -

Kairos project specific web page at https://www.nrc.gov/reactors/non-power/hermes-kairos.html.

FOR FURTHER INFORMATION CONTACT: Tamsen Dozier, Office of Nuclear Materials Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-2272, email:

Tamsen.Dozier@nrc.gov.

SUPPLEMENTARY INFORMATION:

I. Background By letter to the NRC dated September 29, 2021 (ADAMS Package Accession Number No. ML21272A375), Kairos Power LLC (Kairos) submitted an application for a construction permit for the Hermes non-power test reactor, pursuant to part 50 of title 10 of the Code of Federal Regulations (10 CFR), Domestic Licensing of Production and

3 Utilization Facilities, and Section 104c of the Atomic Energy Act of 1954, as amended.

Additionally, by letter dated October 31, 2021 (ADAMS Package Accession No. ML21306A131), Kairos submitted an Environmental Report (ER) in support of its Hermes construction permit application. The test reactor is proposed to be built in Oak Ridge, Tennessee.

By letter dated November 29, 2021 (ADAMS Accession No. ML21319A354), the NRC staff informed Kairos of its determination that the Kairos application for a construction permit for the Hermes test reactor was acceptable for docketing under Docket No. 50-7513.

A notice of acceptance for docketing of the application was published in the Federal Register on December 1, 2021 (86 FR 68290) and a notice of opportunity for hearing was published on February 9, 2022 (87 FR 7503). A notice of intent to prepare an EIS and to conduct scoping process was published in the Federal Register on February 18, 2022 (87 FR 9394). A notice of availability of the draft EIS was published by the NRC in the Federal Register on September 29, 2022 (87 FR 59124). The public comment period for the draft EIS closed on December 6, 2022. Public comments are addressed in Appendix G in the final EIS (ADAMS Accession No. ML23214A269). This notice is being published in accordance with the National Environmental Policy Act of 1969, as amended and the NRCs regulations in 10 CFR part 51.

In addition, as outlined in 36 CFR 800.8(c), Coordination with the National Environmental Policy Act, the NRC staff used the process and documentation for the preparation of the EIS to comply with Section 106 of the National Historic Preservation Act (NHPA) in lieu of the procedures set forth on 36 CFR 800.3 through 800.6.

II. Discussion As discussed in the final EIS, the NRC staffs recommendation related to the

4 environmental aspects of the proposed action is that the CP should be issued once the NHPA Section 106 process is complete. This recommendation is based on: 1) the ER submitted by Kairos, as revised; 2) consultation with Federal, State, Tribal and local agencies; 3) the NRC staffs consideration of comments received during the environmental review; and 4) the staffs independent review and assessment summarized in the final EIS, including the potential mitigation measures identified in the ER and in the final EIS.

In addition, in making its recommendation, the NRC staff has concluded that there are no environmentally preferable or obviously superior sites in the region of interest.

Dated: August 17, 2023.

For the Nuclear Regulatory Commission.

/RA/

Christopher M. Regan, Director, Division of Rulemaking, Environmental, and Financial Support, Office of Nuclear Material Safety and Safeguards.