ML24178A393: Difference between revisions
StriderTol (talk | contribs) (StriderTol Bot change) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 19: | Line 19: | ||
=Text= | =Text= | ||
{{#Wiki_filter:Getachew Tesfaye | {{#Wiki_filter:1 Getachew Tesfaye From: | ||
Getachew Tesfaye Sent: | |||
From: Getachew Tesfaye Sent: Thursday, June 27, 2024 8:02 PM To: Regulatory Affairs Cc: Griffith, Thomas; Sfowler@nuscalepower.com; Lynn, Kevin; Dennis Galvin; Mahmoud -MJ-Jardaneh; Stacy Joseph | Thursday, June 27, 2024 8:02 PM To: | ||
Regulatory Affairs Cc: | |||
Griffith, Thomas; Sfowler@nuscalepower.com; Lynn, Kevin; Dennis Galvin; Mahmoud -MJ-Jardaneh; Stacy Joseph | |||
==Subject:== | ==Subject:== | ||
DWO LTR Revised Completeness Determination - NRC Form 898 Attachments: DWO NRC 898 for Updated Resource Estimate and RAI Schedule Final.pdf | DWO LTR Revised Completeness Determination - NRC Form 898 Attachments: | ||
DWO NRC 898 for Updated Resource Estimate and RAI Schedule Final.pdf Attached please find the revised completed NRC Form 898 for the U.S. Nuclear Regulatory Commission staff Licensing Topical Report (LTR) Completeness Determination for NuScale Power, LLC Topical Report TR-131981, Methodology for the Determination of the Onset of Density Wave Oscillations (DWO), Revision 1. | |||
Attached please find the revised completed NRC Form 898 for the U.S. Nuclear Regulatory Commission staff Licensing Topical Report (LTR) Completeness Determination for NuScale Power, LLC Topical Report TR-131981, Methodology for the Determination of the Onset of Density Wave Oscillations (DWO), Revision 1. | The LTR was submitted by {{letter dated|date=July 17, 2023|text=letter dated July 17, 2023}} (Agencywide Documents Access and Management System [ADAMS] Accession Nos. ML23198A244 [proprietary] and ML23198A245 [nonproprietary]). | ||
The LTR was submitted by {{letter dated|date=July 17, 2023|text=letter dated July 17, 2023}} (Agencywide Documents Access and Management System [ADAMS] Accession Nos. ML23198A244 [ | |||
The revised schedule for issuing request for additional information and the revised resource estimate was discussed with your staff, Thomas Griffith, on June 26, 2024. | The revised schedule for issuing request for additional information and the revised resource estimate was discussed with your staff, Thomas Griffith, on June 26, 2024. | ||
Thank you, Getachew Tesfaye (He/Him) | Thank you, Getachew Tesfaye (He/Him) | ||
Senior Project Manager NRC/NRR/DNRL/NRLB 301-415-8013 | Senior Project Manager NRC/NRR/DNRL/NRLB 301-415-8013}} | ||
Latest revision as of 17:46, 24 November 2024
| ML24178A393 | |
| Person / Time | |
|---|---|
| Site: | 05200050 |
| Issue date: | 06/27/2024 |
| From: | Getachew Tesfaye NRC/NRR/DNRL/NRLB |
| To: | NuScale |
| Tesfaye, G., NRR/DNRL, 301-415-8013 | |
| Shared Package | |
| ML24178A391 | List: |
| References | |
| EPID L-2022-TOP-0019 | |
| Download: ML24178A393 (1) | |
Text
1 Getachew Tesfaye From:
Getachew Tesfaye Sent:
Thursday, June 27, 2024 8:02 PM To:
Regulatory Affairs Cc:
Griffith, Thomas; Sfowler@nuscalepower.com; Lynn, Kevin; Dennis Galvin; Mahmoud -MJ-Jardaneh; Stacy Joseph
Subject:
DWO LTR Revised Completeness Determination - NRC Form 898 Attachments:
DWO NRC 898 for Updated Resource Estimate and RAI Schedule Final.pdf Attached please find the revised completed NRC Form 898 for the U.S. Nuclear Regulatory Commission staff Licensing Topical Report (LTR) Completeness Determination for NuScale Power, LLC Topical Report TR-131981, Methodology for the Determination of the Onset of Density Wave Oscillations (DWO), Revision 1.
The LTR was submitted by letter dated July 17, 2023 (Agencywide Documents Access and Management System [ADAMS] Accession Nos. ML23198A244 [proprietary] and ML23198A245 [nonproprietary]).
The revised schedule for issuing request for additional information and the revised resource estimate was discussed with your staff, Thomas Griffith, on June 26, 2024.
Thank you, Getachew Tesfaye (He/Him)
Senior Project Manager NRC/NRR/DNRL/NRLB 301-415-8013