Line 23: Line 23:
GGNS is currently in Mode 3. Reactor level is being maintained with the `A' reactor feedwater pump and pressure is being maintained with the turbine bypass valves.
GGNS is currently in Mode 3. Reactor level is being maintained with the `A' reactor feedwater pump and pressure is being maintained with the turbine bypass valves.
The NRC Resident Inspector was notified.
The NRC Resident Inspector was notified.
| URL = https://www.nrc.gov/reading-rm/doc-collections/event-status/event/2022/20221221en.html#en56282
| URL = https://www.nrc.gov/reading-rm/doc-collections/event-status/event/2022/20221222en.html#en56282
}}{{unit info
}}{{unit info
| Unit = 1
| Unit = 1

Revision as of 08:30, 22 December 2022

ENS 56282 +/-
Where
Grand Gulf Entergy icon.png
Mississippi (NRC Region 4)
Reporting
10 CFR 50.72(b)(2)(iv)(B), RPS Actuation
Time - Person (Reporting Time:+-2.62 h-0.109 days <br />-0.0156 weeks <br />-0.00359 months <br />)
Opened: Jason Overcash
00:24 Dec 20, 2022
NRC Officer: Lloyd Desotell
Last Updated: Dec 20, 2022
56282 - NRC Website