{{#Wiki_filter: | {{#Wiki_filter: (4) EOI, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (5) EOI, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; (6) EOI, pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility. | ||
(3) Safety Analysis Report The licensee's SAR supplement submitted pursuant to 10 CFR 54.21(d), as revised on March 14, 2001, describes certain future inspection activities to be completed before the period of extended operation. | : c. This renewed license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations in 10 CFR Chapter I: Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Sections 50.54 and 50.59 of Part 50, and Section 70.32 of Part 70; is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below: | ||
The licensee shall complete these activities no later than May 20, 2014.(4) Physical Protection EOI shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, Renewed License No. DPR-51 Amendment No. 229 ECP 3.7.8 3.7 PLANT SYSTEMS 3.7.8 Emergency Cooling Pond (ECP)LCO 3.7.8 | (1) Maximum Power Level EOI is authorized to operate the facility at steady state reactor core power levels not in excess of 2568 megawatts thermal. | ||
The ECP shall be OPERABLE.MODES 1, 2, 3, and 4.ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Degradation of the ECP A.1 Determine ECP remains 7 days noted pursuant to acceptable for continued SR 3.7.8.4 below or by operation. | (2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 229, are hereby incorporated in the renewed license. | ||
EOI shall operate the facility in accordance with the Technical Specifications. | |||
(3) Safety Analysis Report The licensee's SAR supplement submitted pursuant to 10 CFR 54.21(d), | |||
as revised on March 14, 2001, describes certain future inspection activities to be completed before the period of extended operation. The licensee shall complete these activities no later than May 20, 2014. | |||
(4) Physical Protection EOI shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, Renewed License No. DPR-51 Amendment No. 229 | |||
ECP 3.7.8 3.7 PLANT SYSTEMS 3.7.8 Emergency Cooling Pond (ECP) | |||
LCO 3.7.8 The ECP shall be OPERABLE. | |||
APPLICABILITY: MODES 1, 2, 3, and 4. | |||
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Degradation of the ECP A.1 Determine ECP remains 7 days noted pursuant to acceptable for continued SR 3.7.8.4 below or by operation. | |||
other inspection. | other inspection. | ||
B. Required Action and B.1 Be in MODE 3. 6 hours associated Completion Time of Condition A not AND met.B.2 Be in MODE 5. 36 hours OR LCO not met for reasons other than Condition A.SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.7.8.1 Verify that the indicated water level of the ECP is 24 hours greater than or equal to that required for an ECP volume of 70 acre-ft.SR 3.7.8.2 ------------------- | B. Required Action and B.1 Be in MODE 3. 6 hours associated Completion Time of Condition A not AND met. | ||
NOTE ---------------- | B.2 Be in MODE 5. 36 hours OR LCO not met for reasons other than Condition A. | ||
Only required to be performed from June 1 through September 30.Verify average water temperature is _< 100 0 F. 24 hours ANO-1 3.7.8-1 Amendment No. 2-1-5, 229 ECP 3.7.8 SURVEILLANCE FREQUENCY SR 3.7.8.3 Perform soundings of the ECP to verify: 12 months 1. A contained water volume of ECP _> 70 acre-feet, and 2. The minimum indicated water level needed to ensure a volume of 70 acre-feet is maintained. | SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.7.8.1 Verify that the indicated water level of the ECP is 24 hours greater than or equal to that required for an ECP volume of 70 acre-ft. | ||
SR 3.7.8.4 Perform visual inspection of the ECP to verify 12 months conformance with design requirements. | SR 3.7.8.2 ------------------- NOTE ---------------- | ||
ANO-1 3.7.8-2 Amendment No. 21-5, 229 3 facility at the designated location in Pope County, Arkansas in accordance with the procedures and limitations set forth in this renewed license;(3) EOI, pursuant to the Act and 10 CFR Part 70, to receive, possess and use at any time at the facility site and as designated solely for the facility, special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Final Safety Analysis Report, as supplemented and amended;(4) EOI, pursuant to the Act and 10 CFR Parts 30, 40 and 70 to receive, possess and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required;(5) EOI, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (6) EOI, pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.C. This renewed license shall be deemed to contain and is subject to conditions specified in the following Commission regulations in 10 CFR Chapter 1; Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Sections 50.54 and 50.59 of Part 50, and Section 70.32 of Part 70; and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below: (1) Maximum Power Level EOI is authorized to operate the facility at steady state reactor core power levels not in excess of 3026 megawatts thermal. Prior to attaining this power level EOI shall comply with the conditions in Paragraph 2.C.(3).(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 271 are hereby incorporated in the renewed Renewed License No. NPF-6 Amendment No. 271 PLANT SYSTEMS 3/4.7.4 EMERGENCY COOLING POND LIMITING CONDITION FOR OPERATION 3.7.4.1 The emergency cooling pond (ECP) shall be OPERABLE with: a. A minimum contained water volume of 70 acre-feet. | Only required to be performed from June 1 through September 30. | ||
: b. An average water temperature of _< | Verify average water temperature is _<100 0 F. 24 hours ANO-1 3.7.8-1 Amendment No. 2-1-5, 229 | ||
MODES 1, 2, 3 and 4.ACTION: a. With the volume and/or temperature requirements of the above specification not satisfied or, with the requirements of Action b not met, be in at least HOT STANDBY within 6 hours and in COLD SHUTDOWN within the following 30 hours.b. If degradation is noted pursuant to 4.7.4.1 .d below or by other inspection, perform an evaluation to determine that the ECP remains acceptable for continued operation within 7 days.SURVEILLANCE REQUIREMENTS 4.7.4.1 The ECP shall be determined OPERABLE: a. At least once per 24 hours by verifying that the indicated water level of the ECP is greater than or equal to that required for an ECP volume of 70 acre-feet. | |||
: b. At least once per 24 hours during the period of June 1 through September 30 by verifying that the pond's average water temperature at the point of discharge from the pond is within its limit.c. At least once per 12 months by making soundings of the pond and verifying: | ECP 3.7.8 SURVEILLANCE FREQUENCY SR 3.7.8.3 Perform soundings of the ECP to verify: 12 months | ||
: 1. A contained water volume of ECP | : 1. A contained water volume of ECP _>70 acre-feet, and | ||
: 2. The minimum indicated water level needed to ensure a volume of 70 acre-feet is maintained. | |||
SR 3.7.8.4 Perform visual inspection of the ECP to verify 12 months conformance with design requirements. | |||
ANO-1 3.7.8-2 Amendment No. 21-5, 229 | |||
3 facility at the designated location in Pope County, Arkansas in accordance with the procedures and limitations set forth in this renewed license; (3) EOI, pursuant to the Act and 10 CFR Part 70, to receive, possess and use at any time at the facility site and as designated solely for the facility, special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Final Safety Analysis Report, as supplemented and amended; (4) EOI, pursuant to the Act and 10 CFR Parts 30, 40 and 70 to receive, possess and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (5) EOI, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (6) EOI, pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility. | |||
C. This renewed license shall be deemed to contain and is subject to conditions specified in the following Commission regulations in 10 CFR Chapter 1; Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Sections 50.54 and 50.59 of Part 50, and Section 70.32 of Part 70; and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below: | |||
(1) Maximum Power Level EOI is authorized to operate the facility at steady state reactor core power levels not in excess of 3026 megawatts thermal. Prior to attaining this power level EOI shall comply with the conditions in Paragraph 2.C.(3). | |||
(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 271 are hereby incorporated in the renewed Renewed License No. NPF-6 Amendment No. 271 | |||
PLANT SYSTEMS 3/4.7.4 EMERGENCY COOLING POND LIMITING CONDITION FOR OPERATION 3.7.4.1 The emergency cooling pond (ECP) shall be OPERABLE with: | |||
: a. A minimum contained water volume of 70 acre-feet. | |||
: b. An average water temperature of _<100°F. | |||
APPLICABILITY: MODES 1, 2, 3 and 4. | |||
ACTION: | |||
: a. With the volume and/or temperature requirements of the above specification not satisfied or, with the requirements of Action b not met, be in at least HOT STANDBY within 6 hours and in COLD SHUTDOWN within the following 30 hours. | |||
: b. If degradation is noted pursuant to 4.7.4.1 .d below or by other inspection, perform an evaluation to determine that the ECP remains acceptable for continued operation within 7 days. | |||
SURVEILLANCE REQUIREMENTS 4.7.4.1 The ECP shall be determined OPERABLE: | |||
: a. At least once per 24 hours by verifying that the indicated water level of the ECP is greater than or equal to that required for an ECP volume of 70 acre-feet. | |||
: b. At least once per 24 hours during the period of June 1 through September 30 by verifying that the pond's average water temperature at the point of discharge from the pond is within its limit. | |||
: c. At least once per 12 months by making soundings of the pond and verifying: | |||
: 1. A contained water volume of ECP Ž_70 acre-feet, and | |||
: 2. The minimum indicated water level needed to ensure a volume of 70 acre-feet is maintained. | |||
: d. At least once per 12 months by performance of a visual inspection of the ECP to verify conformance with design requirements. | : d. At least once per 12 months by performance of a visual inspection of the ECP to verify conformance with design requirements. | ||
ARKANSAS -UNIT 2 3/4 7-16 Amendment No. 41-, 271}} | ARKANSAS - UNIT 2 3/4 7-16 Amendment No. 41-, 271}} |
Revision as of 08:39, 23 November 2019
ML070680249 | |
Person / Time | |
---|---|
Site: | Arkansas Nuclear |
Issue date: | 03/09/2007 |
From: | Farideh Saba NRC/NRR/ADRO/DORL/LPLIV |
To: | |
Saba F, NRR/DORL/LPL4, 301-415-1447 | |
Shared Package | |
ML062910326 | List: |
References | |
TAC MC8768, TAC MC8769 | |
Download: ML070680249 (5) | |
Text
(4) EOI, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (5) EOI, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; (6) EOI, pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.
- c. This renewed license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations in 10 CFR Chapter I: Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Sections 50.54 and 50.59 of Part 50, and Section 70.32 of Part 70; is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1) Maximum Power Level EOI is authorized to operate the facility at steady state reactor core power levels not in excess of 2568 megawatts thermal.
(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 229, are hereby incorporated in the renewed license.
EOI shall operate the facility in accordance with the Technical Specifications.
(3) Safety Analysis Report The licensee's SAR supplement submitted pursuant to 10 CFR 54.21(d),
as revised on March 14, 2001, describes certain future inspection activities to be completed before the period of extended operation. The licensee shall complete these activities no later than May 20, 2014.
(4) Physical Protection EOI shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, Renewed License No. DPR-51 Amendment No. 229
ECP 3.7.8 3.7 PLANT SYSTEMS 3.7.8 Emergency Cooling Pond (ECP)
LCO 3.7.8 The ECP shall be OPERABLE.
APPLICABILITY: MODES 1, 2, 3, and 4.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Degradation of the ECP A.1 Determine ECP remains 7 days noted pursuant to acceptable for continued SR 3.7.8.4 below or by operation.
other inspection.
B. Required Action and B.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time of Condition A not AND met.
B.2 Be in MODE 5. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> OR LCO not met for reasons other than Condition A.
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.7.8.1 Verify that the indicated water level of the ECP is 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> greater than or equal to that required for an ECP volume of 70 acre-ft.
SR 3.7.8.2 ------------------- NOTE ----------------
Only required to be performed from June 1 through September 30.
Verify average water temperature is _<100 0 F. 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> ANO-1 3.7.8-1 Amendment No. 2-1-5, 229
ECP 3.7.8 SURVEILLANCE FREQUENCY SR 3.7.8.3 Perform soundings of the ECP to verify: 12 months
- 1. A contained water volume of ECP _>70 acre-feet, and
- 2. The minimum indicated water level needed to ensure a volume of 70 acre-feet is maintained.
SR 3.7.8.4 Perform visual inspection of the ECP to verify 12 months conformance with design requirements.
ANO-1 3.7.8-2 Amendment No. 21-5, 229
3 facility at the designated location in Pope County, Arkansas in accordance with the procedures and limitations set forth in this renewed license; (3) EOI, pursuant to the Act and 10 CFR Part 70, to receive, possess and use at any time at the facility site and as designated solely for the facility, special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Final Safety Analysis Report, as supplemented and amended; (4) EOI, pursuant to the Act and 10 CFR Parts 30, 40 and 70 to receive, possess and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (5) EOI, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (6) EOI, pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.
C. This renewed license shall be deemed to contain and is subject to conditions specified in the following Commission regulations in 10 CFR Chapter 1; Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Sections 50.54 and 50.59 of Part 50, and Section 70.32 of Part 70; and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1) Maximum Power Level EOI is authorized to operate the facility at steady state reactor core power levels not in excess of 3026 megawatts thermal. Prior to attaining this power level EOI shall comply with the conditions in Paragraph 2.C.(3).
(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 271 are hereby incorporated in the renewed Renewed License No. NPF-6 Amendment No. 271
PLANT SYSTEMS 3/4.7.4 EMERGENCY COOLING POND LIMITING CONDITION FOR OPERATION 3.7.4.1 The emergency cooling pond (ECP) shall be OPERABLE with:
- a. A minimum contained water volume of 70 acre-feet.
- b. An average water temperature of _<100°F.
APPLICABILITY: MODES 1, 2, 3 and 4.
ACTION:
- a. With the volume and/or temperature requirements of the above specification not satisfied or, with the requirements of Action b not met, be in at least HOT STANDBY within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
- b. If degradation is noted pursuant to 4.7.4.1 .d below or by other inspection, perform an evaluation to determine that the ECP remains acceptable for continued operation within 7 days.
SURVEILLANCE REQUIREMENTS 4.7.4.1 The ECP shall be determined OPERABLE:
- a. At least once per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> by verifying that the indicated water level of the ECP is greater than or equal to that required for an ECP volume of 70 acre-feet.
- b. At least once per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> during the period of June 1 through September 30 by verifying that the pond's average water temperature at the point of discharge from the pond is within its limit.
- c. At least once per 12 months by making soundings of the pond and verifying:
- 1. A contained water volume of ECP Ž_70 acre-feet, and
- 2. The minimum indicated water level needed to ensure a volume of 70 acre-feet is maintained.
- d. At least once per 12 months by performance of a visual inspection of the ECP to verify conformance with design requirements.
ARKANSAS - UNIT 2 3/4 7-16 Amendment No. 41-, 271