{{#Wiki_filter:December 19, 2007  
{{#Wiki_filter:December 19, 2007 Mr. Mark B. Bezilla Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2, Mail Stop A-DB-3080 Oak Harbor, OH 43449-9760
 
Mr. Mark B. Bezilla  
 
Site Vice President  
 
FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2, Mail Stop A-DB-3080  
 
Oak Harbor, OH 43449-9760  


==SUBJECT:==
==SUBJECT:==
CHANGE TO THE INSPECTION PLAN - DAVIS-BESSE NUCLEAR POWER STATION  
CHANGE TO THE INSPECTION PLAN - DAVIS-BESSE NUCLEAR POWER STATION


==Dear Mr. Bezilla:==
==Dear Mr. Bezilla:==
As part of a periodic self-assessment, the Nuclear Regulatory Commission (NRC) thoroughly reviewed its inspection procedures to ensure the continued effective application of inspection resources. The main objective of the review was to determine the appropriate inspection scope for the majority of the inspection procedures in the reactor oversight process (ROP). The result of this effort (designated ROP realignment) created changes to both inspection scope and/or inspection frequency for selected inspection procedures in the ROP. The purpose of this letter is to update the schedule of future inspection activities at your facility that was provided with the mid-cycle assessment letter in August 2007. Please note that there were no changes made to inspection procedures in the security, emergency preparedness, and health physics areas. The enclosed inspection plan details the inspections (less those related to security) scheduled for calendar year 2008. The inspection plan is provided to resolve any scheduling and/or personnel availability issues well in advance of the inspectors' arrival onsite. Routine resident inspections are not listed due to their continuous nature. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). 


Please contact me at 630-829-9629 with any questions you may have regarding this letter or the inspection plan.
As part of a periodic self-assessment, the Nuclear Regulatory Commission (NRC) thoroughly reviewed its inspection procedures to ensure the continued effective application of inspection resources. The main objective of the review was to determine the appropriate inspection scope for the majority of the inspection procedures in the reactor oversight process (ROP). The result of this effort (designated ROP realignment) created changes to both inspection scope and/or inspection frequency for selected inspection procedures in the ROP. The purpose of this letter is to update the schedule of future inspection activities at your facility that was provided with the mid-cycle assessment letter in August 2007. Please note that there were no changes made to inspection procedures in the security, emergency preparedness, and health physics areas.
Sincerely, /RA/ Bruce L. Burgess, Chief Projects Branch 6 Division of Reactor Projects Docket No. 50-346; 72-014 License No. NPF-3  
The enclosed inspection plan details the inspections (less those related to security) scheduled for calendar year 2008. The inspection plan is provided to resolve any scheduling and/or personnel availability issues well in advance of the inspectors arrival onsite. Routine resident inspections are not listed due to their continuous nature.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
 
M. Bezilla                                  Please contact me at 630-829-9629 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
                                              /RA/
Bruce L. Burgess, Chief Projects Branch 6 Division of Reactor Projects Docket No. 50-346; 72-014 License No. NPF-3


==Enclosure:==
==Enclosure:==
As Stated  
As Stated cc w/encl:     The Honorable Dennis Kucinich J. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations and Chief Operating Officer - FENOC Richard Anderson, Vice President, Nuclear Support - FENOC Manager - Site Regulatory Compliance - FENOC D. Pace, Senior Vice President of Fleet Engineering - FENOC J. Rinckel, Vice President, Fleet Oversight - FENOC D. Jenkins, Attorney, FirstEnergy Corp.
 
Director, Fleet Regulatory Affairs - FENOC Manager - Fleet Licensing - FENOC Ohio State Liaison Officer R. Owen, Administrator, Ohio Department of Health Public Utilities Commission of Ohio President, Lucas County Board of Commissioners President, Ottawa County Board of Commissioners
cc w/encl: The Honorable Dennis Kucinich J. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations and Chief Operating Officer - FENOC Richard Anderson, Vice President, Nuclear Support - FENOC Manager - Site Regulatory Compliance - FENOC  
 
D. Pace, Senior Vice President of Fleet Engineering - FENOC J. Rinckel, Vice President, Fleet Oversight - FENOC D. Jenkins, Attorney, FirstEnergy Corp. Director, Fleet Regulatory Affairs - FENOC Manager - Fleet Licensing - FENOC Ohio State Liaison Officer R. Owen, Administrator, Ohio Department of Health Public Utilities Commission of Ohio President, Lucas County Board of Commissioners President, Ottawa County Board of Commissioners  


Please contact me at 630-829-9629 with any questions you may have regarding this letter or the inspection plan.
M. Bezilla                                                              Please contact me at 630-829-9629 with any questions you may have regarding this letter or the inspection plan.
Sincerely, /RA/ Bruce L. Burgess, Chief Projects Branch 6 Division of Reactor Projects Docket No. 50-346; 72-014 License No. NPF-3  
Sincerely,
                                                                          /RA/
Bruce L. Burgess, Chief Projects Branch 6 Division of Reactor Projects Docket No. 50-346; 72-014 License No. NPF-3


==Enclosure:==
==Enclosure:==
As Stated  
As Stated cc w/encl:                The Honorable Dennis Kucinich J. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations and Chief Operating Officer - FENOC Richard Anderson, Vice President, Nuclear Support - FENOC Manager - Site Regulatory Compliance - FENOC D. Pace, Senior Vice President of Fleet Engineering - FENOC J. Rinckel, Vice President, Fleet Oversight - FENOC D. Jenkins, Attorney, FirstEnergy Corp.
Director, Fleet Regulatory Affairs - FENOC Manager - Fleet Licensing - FENOC Ohio State Liaison Officer R. Owen, Administrator, Ohio Department of Health Public Utilities Commission of Ohio President, Lucas County Board of Commissioners President, Ottawa County Board of Commissioners DOCUMENT NAME:G:\BRANCH TSS\ALL MOC\MIDCYCLE 2006 TO 2007\ROP REALIGNMENT LETTER\DAVIS BESSE.DOC G Publicly Available                        G Non-Publicly Available                  G Sensitive              G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE              RIII                                RIII                            RIII                              RIII NAME                BBurgess:cms DATE                12/19/07 OFFICIAL RECORD COPY


cc w/encl: The Honorable Dennis Kucinich J. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations and  Chief Operating Officer - FENOC Richard Anderson, Vice President, Nuclear Support - FENOC Manager - Site Regulatory Compliance - FENOC
Letter to M. Bezilla from B. Burgess dated December 19, 2007


D. Pace, Senior Vice President of Fleet Engineering - FENOC J. Rinckel, Vice President, Fleet Oversight - FENOC D. Jenkins, Attorney, FirstEnergy Corp. Director, Fleet Regulatory Affairs - FENOC Manager - Fleet Licensing - FENOC Ohio State Liaison Officer R. Owen, Administrator, Ohio Department of Health Public Utilities Commission of Ohio President, Lucas County Board of Commissioners President, Ottawa County Board of Commissioners DOCUMENT NAME:G:\BRANCH TSS\ALL MOC\MIDCYCLE 2006 TO 2007\ROP REALIGNMENT LETTER\DAVIS BESSE.DOC G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence  box "C" = Copy without attach/encl "E" = Copy with attach/encl  "N" = No copy OFFICE  RIII    RIII    RIII    RIII    NAME  BBurgess:cms
==SUBJECT:==
 
CHANGE TO THE INSPECTION PLAN - DAVIS-BESSE NUCLEAR POWER STATION DISTRIBUTION:
DATE  12/19/07        OFFICIAL RECORD COPY
RAG1 TEB SPS1 TJW2 RidsNrrDirsIrib MAS KGO JKH3 JER7 CAA1 DRPIII DRSIII PLB1 TXN


Letter to M. Bezilla from B. Burgess dated December 19, 2007
Davis-Besse Inspection / Activity Plan 01/01/2008 - 12/31/2008 No. of Staff    Planned Dates          Inspection Inspection Activity                                                Title                                          on Site        Start    End              Type BI RP        - RADIATION PROTECTION BASELINE INSPECTION                                                                2 IP 7112101          Access Control to Radiologically Significant Areas                                                    01/07/2008 01/11/2008 Baseline Inspections IP 7112102          ALARA Planning and Controls                                                                            01/07/2008 01/11/2008 Baseline Inspections BI ENG        - ENGINEERING INSERVICE INSPECTION/150/172                                                                2 IP 2515/150          Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC ORDER EA                    01/02/2008 02/01/2008 Safety Issues IP 2515/172          Reactor Coolant System Dissimiliar Metal Butt Welds                                                    01/02/2008 02/01/2008 Generic Safety Inspec IP 7111108P          Inservice Inspection Activities - PWR                                                                  01/02/2008 02/01/2008 Baseline Inspections ORDER        - CONF ORDER FOLLOW UP AKRON, OHIO                                                                        1 IP 95003            Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple              01/01/2008 01/30/2008 Supplemental Program OL EXAM      - DAVIS-BESSE INIT PREP 08/2007                                                                            3 W90159            OL - INITIAL EXAM - DAVIS BESSE - AUG/SEP 2007                                                        01/21/2008 01/25/2008 Not Applicable BI EP        - EP ROUTINE INSPECTION / PI VERIFICATION                                                                  1 IP 7111402          Alert and Notification System Testing                                                                  02/25/2008 03/01/2008 EP Baseline Inspectio IP 7111403          Emergency Response Organization Augmentation Testing                                                  02/25/2008 03/01/2008 EP Baseline Inspectio IP 7111405          Correction of Emergency Preparedness Weaknesses and Deficiencies                                      02/25/2008 03/01/2008 EP Baseline Inspectio IP 71151-EP01        Drill/Exercise Performance                                                                            02/25/2008 03/01/2008 Baseline Inspections IP 71151-EP02        ERO Drill Participation                                                                                02/25/2008 03/01/2008 Baseline Inspections IP 71151-EP03        Alert & Notification System                                                                            02/25/2008 03/01/2008 Baseline Inspections OL EXAM      - DAVIS-BESSE INIT EXAM 09/2007                                                                            3 W90159            OL - INITIAL EXAM - DAVIS BESSE - AUG/SEP 2007                                                        02/18/2008 02/29/2008 Not Applicable BI RP        - RADIATION PROTECTION BASELINE INSPECTION                                                                1 IP 7112103          Radiation Monitoring Instrumentation and Protective Equipment                                          03/03/2008 03/07/2008 Baseline Inspections SC/SCWE      - '07 SC/SCWE REPORT REVIEW                                                                                1 IP 95003            Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple              03/01/2008 04/30/2008 Supplemental Program 2515/166      - TI 2515/166 PWR SUMP INSPECTION                                                                          1 IP 2515/166          Pressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02]                      03/31/2008 04/04/2008 Safety Issues 95003        - INDEP OPS ASSESSMENT F/U                                                                                2 IP 95003            Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple              04/01/2008 09/30/2008 Supplemental Program 95003        - INDP ENGR ASSESS. F/U                                                                                    1 IP 95003            Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple              04/01/2008 09/30/2008 Supplemental Program BI RP        - RADIATION PROTECTION BASELINE INSPECTION                                                                1 IP 7112203          Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P                05/19/2008 05/23/2008 Baseline Inspections IP 71151-PR01        RETS/ODCM Radiological Effluent                                                                        05/19/2008 05/23/2008 Baseline Inspections BI ENG        - ENGINEERING MODIFICATIONS / 50.59 INSP.                                                                 3 IP 7111102          Evaluation of Changes, Tests, or Experiments                                                          06/23/2008 07/11/2008 Baseline Inspections


==SUBJECT:==
Davis-Besse Inspection / Activity Plan 01/01/2008 - 12/31/2008 No. of Staff   Planned Dates        Inspection Inspection Activity                                                Title                                          on Site       Start     End            Type BI ENG       - ENGINEERING MODIFICATIONS / 50.59 INSP.                                                                  3 IP 7111117B          Permanent Plant Modifications                                                                          06/23/2008 07/11/2008 Baseline Inspections ORDER         - CONFIRMATORY ORDER FOLLOW UP AKRON, OHIO                                                                 1 IP 95003             Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple              07/01/2008 07/30/2008 Supplemental Program 95003         - INDEP CAP ASSESS. F/U                                                                                   1 IP 95003             Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple              07/01/2008 12/31/2008 Supplemental Program 95003         - INDP SC/SCWE ASSESS. F/U                                                                                 1 IP 95003             Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple              07/01/2008 12/31/2008 Supplemental Program BI ENG       - TRIENNIAL HEAT SINK INSPECTION                                                                           1 IP 7111107B          Heat Sink Performance                                                                                  08/25/2008 08/29/2008 Baseline Inspections BI RP         - RADIATION PROTECTION BASELINE INSPECTION                                                                 1 IP 7112101           Access Control to Radiologically Significant Areas                                                     08/25/2008 08/29/2008 Baseline Inspections IP 7112102           ALARA Planning and Controls                                                                           08/25/2008 08/29/2008 Baseline Inspections IP 71151-BI01       Reactor Coolant System Activity                                                                       08/25/2008 08/29/2008 Baseline Inspections IP 71151-OR01       Occupational Exposure Control Effectiveness                                                           08/25/2008 08/29/2008 Baseline Inspections 2515/172     - TI 2515/172 RCS WELD INSPECTION                                                                         1 IP 2515/172         Reactor Coolant System Dissimiliar Metal Butt Welds                                                   09/08/2008 09/12/2008 Generic Safety Inspec BI PI&R       - BIENNIAL PI&R INSPECTION                                                                                 3 IP 71152B            Identification and Resolution of Problems                                                              09/08/2008 09/19/2008 Baseline Inspections SC/SCWE       - '08 INDEP. SC/SCWE OBSERVATION                                                                           1 IP 95003             Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple              10/01/2008 10/30/2008 Supplemental Program BI OL         - BIENNIAL REQUAL. PROGRAM INSPECTION                                                                     2 IP 7111111B          Licensed Operator Requalification Program                                                              11/10/2008 11/14/2008 Baseline Inspections BI RP         - RADIATION PROTECTION BASELINE INSPECTION                                                                 1 IP 7112201           Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems                               11/17/2008 11/21/2008 Baseline Inspections}}
CHANGE TO THE INSPECTION PLAN - DAVIS-BESSE NUCLEAR POWER STATION DISTRIBUTION:
RAG1 TEB SPS1 TJW2 RidsNrrDirsIrib MAS KGO JKH3 JER7 CAA1 DRPIII DRSIII PLB1 TXN Davis-Besse Inspection / Activity Plan 01/01/2008
-12/31/2008 Inspection Type Inspection Activity Planned Dates Start          End No. of Staff on Site Title Unit Number Page 1 of 2 12/19/2007 Report 22 2 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 01/07/2008 01/11/2008 1     7112101 IP A ccess Control to Radiologically Significant Areas Baseline Inspections 01/07/2008 01/11/2008 1    7112102 IP A LARA Planning and Controls 2 BI ENG-ENGINEERING INSERVICE INSPECTION/150/172 Safety Issues 01/02/2008 02/01/2008 1    2515/150 IP Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC ORDER EA Generic Safety Inspe c 01/02/2008 02/01/2008 1    2515/172 IP Reactor Coolant System Dissimiliar Metal Butt Welds Baseline Inspections 01/02/2008 02/01/2008 1    7111108P IP Inservice Inspection Activities - PWR 1 ORDER-CONF ORDER FOLLOW UP AKRON, OHIO Supplemental Progra m 01/01/2008 01/30/2008 1     95003 IP Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multipl e 3 OL EXAM-DAVIS-BESSE INIT PREP 08/2007 Not Applicable 01/21/2008 01/25/2008 1    W90159 OL - INITIAL EXAM - DAVIS BESSE - AUG/SEP  2007 1 BI EP-EP ROUTINE INSPECTION / PI VERIFICATION EP Baseline Inspecti o 02/25/2008 03/01/2008 1    7111402 IP A lert and Notification System Testing EP Baseline Inspecti o 02/25/2008 03/01/2008 1    7111403 IP Emergency Response Organization Augmentation Testing EP Baseline Inspecti o 02/25/2008 03/01/2008 1    7111405 IP Correction of Emergency Preparedness Weaknesses and Deficiencies Baseline Inspections 02/25/2008 03/01/2008 1    71151-EP01 IP Drill/Exercise Performance Baseline Inspections 02/25/2008 03/01/2008 1    71151-EP02 IP ERO Drill Participation Baseline Inspections 02/25/2008 03/01/2008 1    71151-EP03 IP A lert & Notification System 3 OL EXAM-DAVIS-BESSE INIT EXAM 09/2007 Not Applicable 02/18/2008 02/29/2008 1    W90159 OL - INITIAL EXAM - DAVIS BESSE - AUG/SEP  2007 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 03/03/2008 03/07/2008 1    7112103 IP Radiation Monitoring Instrumentation and Protective Equipment 1 SC/SCWE-'07 SC/SCWE REPORT REVIEW Supplemental Progra m 03/01/2008 04/30/2008 1    95003 IP Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multipl e 1 2515/166-TI 2515/166 PWR SUMP INSPECTION Safety Issues 03/31/2008 04/04/2008 1    2515/166 IP Pressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02
]2 95003-INDEP OPS ASSESSMENT F/U Supplemental Progra m 04/01/2008 09/30/2008 1    95003 IP Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multipl e 1 95003-INDP ENGR ASSESS. F/U Supplemental Progra m 04/01/2008 09/30/2008 1     95003 IP Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multipl e 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 05/19/2008 05/23/2008 1    7112203 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P Baseline Inspections 05/19/2008 05/23/2008 1    71151-PR01 IP RETS/ODCM Radiological Effluent 3 BI ENG-ENGINEERING MODIFICATIONS / 50.59 INSP.
Baseline Inspections 06/23/2008 07/11/2008 1    7111102 IP Evaluation of Changes, Tests, or Experiments This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Davis-Besse Inspection / Activity Plan 01/01/2008
-12/31/2008 Inspection Type Inspection Activity Planned Dates Start          End No. of Staff on Site Title Unit Number Page 2 of 2 12/19/2007 Report 22 3 BI ENG-ENGINEERING MODIFICATIONS / 50.59 INSP.
Baseline Inspections 06/23/2008 07/11/2008 1    7111117B IP Permanent Plant Modifications 1 ORDER-CONFIRMATORY ORDER FOLLOW UP AKRON, OHIO Supplemental Progra m 07/01/2008 07/30/2008 1    95003 IP Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multipl e 1 95003-INDEP CAP ASSESS. F/U Supplemental Progra m 07/01/2008 12/31/2008 1     95003 IP Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multipl e 1 95003-INDP SC/SCWE ASSESS. F/U Supplemental Progra m 07/01/2008 12/31/2008 1    95003 IP Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multipl e 1 BI ENG-TRIENNIAL HEAT SINK INSPECTION Baseline Inspections 08/25/2008 08/29/2008 1    7111107B IP Heat Sink Performance 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 08/25/2008 08/29/2008 1     7112101 IP A ccess Control to Radiologically Significant Areas Baseline Inspections 08/25/2008 08/29/2008 1    7112102 IP A LARA Planning and Controls Baseline Inspections 08/25/2008 08/29/2008 1    71151-BI01 IP Reactor Coolant System Activity Baseline Inspections 08/25/2008 08/29/2008 1    71151-OR01 IP Occupational Exposure Control Effectiveness 1 2515/172-TI 2515/172 RCS WELD INSPECTION Generic Safety Inspe c 09/08/2008 09/12/2008 1     2515/172 IP Reactor Coolant System Dissimiliar Metal Butt Welds 3 BI PI&R-BIENNIAL PI&R INSPECTION Baseline Inspections 09/08/2008 09/19/2008 1    71152B IP Identification and Resolution of Problems 1 SC/SCWE-'08 INDEP. SC/SCWE OBSERVATION Supplemental Progra m 10/01/2008 10/30/2008 1     95003 IP Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multipl e 2 BI OL-BIENNIAL REQUAL. PROGRAM INSPECTION Baseline Inspections 11/10/2008 11/14/2008 1    7111111B IP Licensed Operator Requalification Program 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 11/17/2008 11/21/2008 1     7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.}}

Revision as of 23:49, 22 November 2019

Inspection Plan 1/1/08 - 12/31/08
ML073532235
Person / Time
Site: Davis Besse  Cleveland Electric icon.png
Issue date: 12/19/2007
From: Burgess B
Reactor Projects Region 2 Branch 6
To: Bezilla M
FirstEnergy Nuclear Operating Co
References
Download: ML073532235 (6)


Text

December 19, 2007 Mr. Mark B. Bezilla Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2, Mail Stop A-DB-3080 Oak Harbor, OH 43449-9760

SUBJECT:

CHANGE TO THE INSPECTION PLAN - DAVIS-BESSE NUCLEAR POWER STATION

Dear Mr. Bezilla:

As part of a periodic self-assessment, the Nuclear Regulatory Commission (NRC) thoroughly reviewed its inspection procedures to ensure the continued effective application of inspection resources. The main objective of the review was to determine the appropriate inspection scope for the majority of the inspection procedures in the reactor oversight process (ROP). The result of this effort (designated ROP realignment) created changes to both inspection scope and/or inspection frequency for selected inspection procedures in the ROP. The purpose of this letter is to update the schedule of future inspection activities at your facility that was provided with the mid-cycle assessment letter in August 2007. Please note that there were no changes made to inspection procedures in the security, emergency preparedness, and health physics areas.

The enclosed inspection plan details the inspections (less those related to security) scheduled for calendar year 2008. The inspection plan is provided to resolve any scheduling and/or personnel availability issues well in advance of the inspectors arrival onsite. Routine resident inspections are not listed due to their continuous nature.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

M. Bezilla Please contact me at 630-829-9629 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Bruce L. Burgess, Chief Projects Branch 6 Division of Reactor Projects Docket No. 50-346;72-014 License No. NPF-3

Enclosure:

As Stated cc w/encl: The Honorable Dennis Kucinich J. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations and Chief Operating Officer - FENOC Richard Anderson, Vice President, Nuclear Support - FENOC Manager - Site Regulatory Compliance - FENOC D. Pace, Senior Vice President of Fleet Engineering - FENOC J. Rinckel, Vice President, Fleet Oversight - FENOC D. Jenkins, Attorney, FirstEnergy Corp.

Director, Fleet Regulatory Affairs - FENOC Manager - Fleet Licensing - FENOC Ohio State Liaison Officer R. Owen, Administrator, Ohio Department of Health Public Utilities Commission of Ohio President, Lucas County Board of Commissioners President, Ottawa County Board of Commissioners

M. Bezilla Please contact me at 630-829-9629 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Bruce L. Burgess, Chief Projects Branch 6 Division of Reactor Projects Docket No. 50-346;72-014 License No. NPF-3

Enclosure:

As Stated cc w/encl: The Honorable Dennis Kucinich J. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations and Chief Operating Officer - FENOC Richard Anderson, Vice President, Nuclear Support - FENOC Manager - Site Regulatory Compliance - FENOC D. Pace, Senior Vice President of Fleet Engineering - FENOC J. Rinckel, Vice President, Fleet Oversight - FENOC D. Jenkins, Attorney, FirstEnergy Corp.

Director, Fleet Regulatory Affairs - FENOC Manager - Fleet Licensing - FENOC Ohio State Liaison Officer R. Owen, Administrator, Ohio Department of Health Public Utilities Commission of Ohio President, Lucas County Board of Commissioners President, Ottawa County Board of Commissioners DOCUMENT NAME:G:\BRANCH TSS\ALL MOC\MIDCYCLE 2006 TO 2007\ROP REALIGNMENT LETTER\DAVIS BESSE.DOC G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME BBurgess:cms DATE 12/19/07 OFFICIAL RECORD COPY

Letter to M. Bezilla from B. Burgess dated December 19, 2007

SUBJECT:

CHANGE TO THE INSPECTION PLAN - DAVIS-BESSE NUCLEAR POWER STATION DISTRIBUTION:

RAG1 TEB SPS1 TJW2 RidsNrrDirsIrib MAS KGO JKH3 JER7 CAA1 DRPIII DRSIII PLB1 TXN

Davis-Besse Inspection / Activity Plan 01/01/2008 - 12/31/2008 No. of Staff Planned Dates Inspection Inspection Activity Title on Site Start End Type BI RP - RADIATION PROTECTION BASELINE INSPECTION 2 IP 7112101 Access Control to Radiologically Significant Areas 01/07/2008 01/11/2008 Baseline Inspections IP 7112102 ALARA Planning and Controls 01/07/2008 01/11/2008 Baseline Inspections BI ENG - ENGINEERING INSERVICE INSPECTION/150/172 2 IP 2515/150 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC ORDER EA 01/02/2008 02/01/2008 Safety Issues IP 2515/172 Reactor Coolant System Dissimiliar Metal Butt Welds 01/02/2008 02/01/2008 Generic Safety Inspec IP 7111108P Inservice Inspection Activities - PWR 01/02/2008 02/01/2008 Baseline Inspections ORDER - CONF ORDER FOLLOW UP AKRON, OHIO 1 IP 95003 Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple 01/01/2008 01/30/2008 Supplemental Program OL EXAM - DAVIS-BESSE INIT PREP 08/2007 3 W90159 OL - INITIAL EXAM - DAVIS BESSE - AUG/SEP 2007 01/21/2008 01/25/2008 Not Applicable BI EP - EP ROUTINE INSPECTION / PI VERIFICATION 1 IP 7111402 Alert and Notification System Testing 02/25/2008 03/01/2008 EP Baseline Inspectio IP 7111403 Emergency Response Organization Augmentation Testing 02/25/2008 03/01/2008 EP Baseline Inspectio IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 02/25/2008 03/01/2008 EP Baseline Inspectio IP 71151-EP01 Drill/Exercise Performance 02/25/2008 03/01/2008 Baseline Inspections IP 71151-EP02 ERO Drill Participation 02/25/2008 03/01/2008 Baseline Inspections IP 71151-EP03 Alert & Notification System 02/25/2008 03/01/2008 Baseline Inspections OL EXAM - DAVIS-BESSE INIT EXAM 09/2007 3 W90159 OL - INITIAL EXAM - DAVIS BESSE - AUG/SEP 2007 02/18/2008 02/29/2008 Not Applicable BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 03/03/2008 03/07/2008 Baseline Inspections SC/SCWE - '07 SC/SCWE REPORT REVIEW 1 IP 95003 Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple 03/01/2008 04/30/2008 Supplemental Program 2515/166 - TI 2515/166 PWR SUMP INSPECTION 1 IP 2515/166 Pressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02] 03/31/2008 04/04/2008 Safety Issues 95003 - INDEP OPS ASSESSMENT F/U 2 IP 95003 Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple 04/01/2008 09/30/2008 Supplemental Program 95003 - INDP ENGR ASSESS. F/U 1 IP 95003 Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple 04/01/2008 09/30/2008 Supplemental Program BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P 05/19/2008 05/23/2008 Baseline Inspections IP 71151-PR01 RETS/ODCM Radiological Effluent 05/19/2008 05/23/2008 Baseline Inspections BI ENG - ENGINEERING MODIFICATIONS / 50.59 INSP. 3 IP 7111102 Evaluation of Changes, Tests, or Experiments 06/23/2008 07/11/2008 Baseline Inspections

Davis-Besse Inspection / Activity Plan 01/01/2008 - 12/31/2008 No. of Staff Planned Dates Inspection Inspection Activity Title on Site Start End Type BI ENG - ENGINEERING MODIFICATIONS / 50.59 INSP. 3 IP 7111117B Permanent Plant Modifications 06/23/2008 07/11/2008 Baseline Inspections ORDER - CONFIRMATORY ORDER FOLLOW UP AKRON, OHIO 1 IP 95003 Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple 07/01/2008 07/30/2008 Supplemental Program 95003 - INDEP CAP ASSESS. F/U 1 IP 95003 Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple 07/01/2008 12/31/2008 Supplemental Program 95003 - INDP SC/SCWE ASSESS. F/U 1 IP 95003 Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple 07/01/2008 12/31/2008 Supplemental Program BI ENG - TRIENNIAL HEAT SINK INSPECTION 1 IP 7111107B Heat Sink Performance 08/25/2008 08/29/2008 Baseline Inspections BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112101 Access Control to Radiologically Significant Areas 08/25/2008 08/29/2008 Baseline Inspections IP 7112102 ALARA Planning and Controls 08/25/2008 08/29/2008 Baseline Inspections IP 71151-BI01 Reactor Coolant System Activity 08/25/2008 08/29/2008 Baseline Inspections IP 71151-OR01 Occupational Exposure Control Effectiveness 08/25/2008 08/29/2008 Baseline Inspections 2515/172 - TI 2515/172 RCS WELD INSPECTION 1 IP 2515/172 Reactor Coolant System Dissimiliar Metal Butt Welds 09/08/2008 09/12/2008 Generic Safety Inspec BI PI&R - BIENNIAL PI&R INSPECTION 3 IP 71152B Identification and Resolution of Problems 09/08/2008 09/19/2008 Baseline Inspections SC/SCWE - '08 INDEP. SC/SCWE OBSERVATION 1 IP 95003 Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple 10/01/2008 10/30/2008 Supplemental Program BI OL - BIENNIAL REQUAL. PROGRAM INSPECTION 2 IP 7111111B Licensed Operator Requalification Program 11/10/2008 11/14/2008 Baseline Inspections BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 11/17/2008 11/21/2008 Baseline Inspections