NL-08-147, Notification of Delay of Submittal of Program for Maintenance of Irradiated Fuel and Preliminary Decommissioning Cost Analysis in Accordance with 10 CFR 50.54 (Bb) and 10 CFR 50.75 (f)(3): Difference between revisions

From kanterella
Jump to navigation Jump to search
Created page by program invented by StriderTol
Created page by program invented by StriderTol
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 nI12r Buchanan, N.Y. 10511-0249 Tel (914) 734-6700 J. E. Pollock Site Vice President September 29, 2008 Re: Indian Point Units 1 & 2 Docket Nos. 50-3 & 50-247 License Nos. DPR-5 & DPR-26 NL-08-147 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001
{{#Wiki_filter:Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 nI12r                                                               Buchanan, N.Y. 10511-0249 Tel (914) 734-6700 J. E. Pollock Site Vice President September 29, 2008 Re:   Indian Point Units 1 & 2 Docket Nos. 50-3 & 50-247 License Nos. DPR-5 & DPR-26 NL-08-147 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001


==SUBJECT:==
==SUBJECT:==
Line 22: Line 22:


==Dear Sir or Madam:==
==Dear Sir or Madam:==
The purpose of this letter is to advise the NRC that the 10 CFR 50.54(bb) and 10 CFR 50.75(f)(3) submittals for Indian Point Unit Nos. 1 and 2 will be delayed until October 27, 2008. This delay is needed to allow Entergy Nuclear Operations Inc. (Entergy)additional time to successfully address comments Entergy received from the NRC on our Pilgrim submittal.
 
The successful resolution of these comments on the Pilgrim submittal will impact the final product produced for the Indian Point Unit Nos. 1 and 2.There are no commitments in this submittal.
The purpose of this letter is to advise the NRC that the 10 CFR 50.54(bb) and 10 CFR 50.75(f)(3) submittals for Indian Point Unit Nos. 1 and 2 will be delayed until October 27, 2008. This delay is needed to allow Entergy Nuclear Operations Inc. (Entergy) additional time to successfully address comments Entergy received from the NRC on our Pilgrim submittal. The successful resolution of these comments on the Pilgrim submittal will impact the final product produced for the Indian Point Unit Nos. 1 and 2.
There are no commitments in this submittal.
Should you have any questions concerning this submittal, please contact Mr. Robert Walpole at 914-734-6710.
Should you have any questions concerning this submittal, please contact Mr. Robert Walpole at 914-734-6710.
Sincerely, J. E. Pollock Site Vice President Indian Point Energy Center Vj-j:, C)4 Docket Nos. 50-3 & 50-247 NL-08-147 Page 2 of 2 cc: Mr. Samuel J. Collins, Regional Administrator, NRC Region 1 Mr. John P. Boska, Senior Project Manager, NRC NRR DORL NRC Resident Inspectors Office, Indian Point 2 & 3 Mr. Paul Eddy, NYS Department of Public Service}}
Sincerely, J. E. Pollock Site Vice President Indian Point Energy Center Vj-j:, C)4
 
Docket Nos. 50-3 & 50-247 NL-08-147 Page 2 of 2 cc:
Mr. Samuel J. Collins, Regional Administrator, NRC Region 1 Mr. John P. Boska, Senior Project Manager, NRC NRR DORL NRC Resident Inspectors Office, Indian Point 2 & 3 Mr. Paul Eddy, NYS Department of Public Service}}

Revision as of 13:11, 14 November 2019

Notification of Delay of Submittal of Program for Maintenance of Irradiated Fuel and Preliminary Decommissioning Cost Analysis in Accordance with 10 CFR 50.54 (Bb) and 10 CFR 50.75 (f)(3)
ML082840583
Person / Time
Site: Indian Point  
(DPR-005, DPR-026)
Issue date: 09/29/2008
From: Joseph E Pollock
Entergy Nuclear Operations
To:
Document Control Desk, NRC/FSME
References
FOIA/PA-2009-0026, NL-08-147
Download: ML082840583 (2)


Text

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 nI12r Buchanan, N.Y. 10511-0249 Tel (914) 734-6700 J. E. Pollock Site Vice President September 29, 2008 Re: Indian Point Units 1 & 2 Docket Nos. 50-3 & 50-247 License Nos. DPR-5 & DPR-26 NL-08-147 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001

SUBJECT:

Notification of Delay of Submittal for Unit 1 & 2 Program for Maintenance of Irradiated Fuel and Preliminary Decommissioning Cost Analysis in accordance with 10 CFR 50.54 (bb) and 10 CFR 50.75(f)(3)

Dear Sir or Madam:

The purpose of this letter is to advise the NRC that the 10 CFR 50.54(bb) and 10 CFR 50.75(f)(3) submittals for Indian Point Unit Nos. 1 and 2 will be delayed until October 27, 2008. This delay is needed to allow Entergy Nuclear Operations Inc. (Entergy) additional time to successfully address comments Entergy received from the NRC on our Pilgrim submittal. The successful resolution of these comments on the Pilgrim submittal will impact the final product produced for the Indian Point Unit Nos. 1 and 2.

There are no commitments in this submittal.

Should you have any questions concerning this submittal, please contact Mr. Robert Walpole at 914-734-6710.

Sincerely, J. E. Pollock Site Vice President Indian Point Energy Center Vj-j:, C)4

Docket Nos. 50-3 & 50-247 NL-08-147 Page 2 of 2 cc:

Mr. Samuel J. Collins, Regional Administrator, NRC Region 1 Mr. John P. Boska, Senior Project Manager, NRC NRR DORL NRC Resident Inspectors Office, Indian Point 2 & 3 Mr. Paul Eddy, NYS Department of Public Service