ML090080046: Difference between revisions

From kanterella
Jump to navigation Jump to search
Created page by program invented by StriderTol
Created page by program invented by StriderTol
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:January 9, 2009 Mr. Peter P. Sena III Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB-1 P.O. Box 4, Route 168 Shippingport, PA 15077  
{{#Wiki_filter:January 9, 2009 Mr. Peter P. Sena III Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB-1 P.O. Box 4, Route 168 Shippingport, PA 15077


==SUBJECT:==
==SUBJECT:==
SAFETY EVALUATION REPORT WITH OPEN ITEM RELATED TO THE LICENSE RENEWAL OF BEAVER VALLEY POWER STATION, UNITS 1 AND 2  
SAFETY EVALUATION REPORT WITH OPEN ITEM RELATED TO THE LICENSE RENEWAL OF BEAVER VALLEY POWER STATION, UNITS 1 AND 2


==Dear Mr. Sena:==
==Dear Mr. Sena:==


By letter dated August 27, 2007, FirstEnergy Nuclear Operating Company submitted, for U.S. Nuclear Regulatory Commission (NRC) review, an application to renew the Beaver Valley Power Station, Units 1 and 2, operating licenses for up to an additional 20 years. The license renewal application (LRA) was submitted pursuant to Title 10 of the Code of Federal Regulations Part 54 (10 CFR 54), "Requirements for Renewal of Operating Licenses for Nuclear Power Plants.The staff determined that the LRA was complete and acceptable for docketing on October 26, 2007.
By letter dated August 27, 2007, FirstEnergy Nuclear Operating Company submitted, for U.S.
The staff has reviewed the Beaver Valley Power Station LRA and has developed the enclosed "Safety Evaluation Report With Open Item related to the License Renewal of the Beaver Valley Power Station, Units 1 and 2," hereinafter referred to as the Safety Evaluation Report (SER). This SER reflects the status of the staff's review of the LRA, requests for additional information (RAIs), the applicant's responses to the staff's RAIs and other questions related to the LRA through December 19, 2008, unless otherwise noted. Issuance of the enclosed SER is an important milestone for both the applicant and the staff.  
Nuclear Regulatory Commission (NRC) review, an application to renew the Beaver Valley Power Station, Units 1 and 2, operating licenses for up to an additional 20 years. The license renewal application (LRA) was submitted pursuant to Title 10 of the Code of Federal Regulations Part 54 (10 CFR 54), Requirements for Renewal of Operating Licenses for Nuclear Power Plants. The staff determined that the LRA was complete and acceptable for docketing on October 26, 2007.
The staff has reviewed the Beaver Valley Power Station LRA and has developed the enclosed Safety Evaluation Report With Open Item related to the License Renewal of the Beaver Valley Power Station, Units 1 and 2, hereinafter referred to as the Safety Evaluation Report (SER).
This SER reflects the status of the staffs review of the LRA, requests for additional information (RAIs), the applicants responses to the staffs RAIs and other questions related to the LRA through December 19, 2008, unless otherwise noted. Issuance of the enclosed SER is an important milestone for both the applicant and the staff.
The staff has identified an open item in its review that must be resolved before it can make a final determination on the application. The open item is summarized in SER Section 1.5, along with an explanation of the information required to satisfactorily resolve the issue.
In accordance with the schedule for completing the review of the LRA, the applicant is requested to review the enclosed SER, verify its accuracy, and provide comments and response to the open item by March 10, 2009. The staff plans to review the current content and format of the SER for further improvement while incorporating the applicants comments. A revised SER will then be issued by May 29, 2009.


The staff has identified an open item in its review that must be resolved before it can make a final determination on the application. The open item is summarized in SER Section 1.5, along with an explanation of the information required to satisfactorily resolve the issue. 
In accordance with the schedule for completing the review of the LRA, the applicant is requested to review the enclosed SER, verify its accuracy, and provide comments and response to the open item by March 10, 2009. The staff plans to review the current content and format of the SER for further improvement while incorporating the applicant's comments. A revised SER will then be issued by May 29, 2009.
The staff is committed to completing the review of the Beaver Valley Power Station SER in a timely manner. If you have any questions regarding this matter, please contact the license renewal project manager, Kent Howard, at 301-415-2989 or e-mail kent.howard@nrc.gov.
The staff is committed to completing the review of the Beaver Valley Power Station SER in a timely manner. If you have any questions regarding this matter, please contact the license renewal project manager, Kent Howard, at 301-415-2989 or e-mail kent.howard@nrc.gov.
Sincerely,       /RA SLee for
Sincerely,
/
                                            /RA SLee for/
Brian Holian, Director       Division of License Renewal       Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412  
Brian Holian, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412


==Enclosure:==
==Enclosure:==


Safety Evaluation Report with   Open Item cc w/encls: See next page  
Safety Evaluation Report with Open Item cc w/encls: See next page


ML090080046OFFICE LA:DLR PM:DLR:RPB2 BC:DLR:RPB2 BC:DLR:RER1
ML090080046 OFFICE  LA:DLR               PM:DLR:RPB2         BC:DLR:RPB2       BC:DLR:RER1
* BC:DLR:RER2 NAME SFigueroa KHoward DWrona JDozier RAuluck DATE 1/9/09 1/9/09 1/9/09 1/8/09 1/9/09 OFFICE BC:DE:EMCB
* BC:DLR:RER2 NAME     SFigueroa             KHoward             DWrona             JDozier           RAuluck DATE     1/9/09               1/9/09             1/9/09             1/8/09             1/9/09 OFFICE   BC:DE:EMCB
* BC:DE:EEEB
* BC:DE:EEEB
* BC:DSS:SBPB
* BC:DSS:SBPB
* BC:DSS:SRXB
* BC:DSS:SRXB
* BC:DSS:SCVB
* BC:DSS:SCVB
* NAME KManoly GWilson DHarrison GCranston RDennig DATE 12/19/08 12/17/08 12/23/08 12/11/08 12/19/08 OFFICE BC:DCI:CVIB
* NAME     KManoly               GWilson             DHarrison         GCranston         RDennig DATE     12/19/08             12/17/08           12/23/08           12/11/08           12/19/08 OFFICE   BC:DCI:CVIB
* BC:DCI:CPNB
* BC:DCI:CPNB
* BC:DCI:CSGB
* BC:DCI:CSGB
* BC:DRA:AFPB* OGC (NLO) NAME MMitchell TChan AHiser AKlein LSubin DATE 12/17/08 12/18/08 01/06/09 01/05/09 1/9/09 OFFICE D:DE
* BC:DRA:AFPB*       OGC (NLO)
NAME     MMitchell             TChan               AHiser             AKlein             LSubin DATE     12/17/08             12/18/08           01/06/09           01/05/09           1/9/09 OFFICE   D:DE
* D:DSS
* D:DSS
* D:DCI
* D:DCI
* D:DRA D:DLR NAME PHiland WRuland (SBahadur for) MEvans MCunningham BHolian /SLee for/ DATE 1/7/09 1/8/09 1/8/09 1/9/09 1/09/09 Letter to P. Sena III from B. Holian, dated January 9, 2009 DISTRIBUTION
* D:DRA             D:DLR NAME     PHiland               WRuland             MEvans            MCunningham        BHolian (SBahadur for)                                           /SLee for/
:
DATE     1/7/09               1/8/09             1/8/09             1/9/09             1/09/09
 
Letter to P. Sena III from B. Holian, dated January 9, 2009 DISTRIBUTION:


==SUBJECT:==
==SUBJECT:==
SAFETY EVALUATION REPORT WITH OPEN ITEM RELATED TO THE LICENSE RENEWAL OF BEAVER VALLEY POWER STATION, UNITS 1 AND 2  
SAFETY EVALUATION REPORT WITH OPEN ITEM RELATED TO THE LICENSE RENEWAL OF BEAVER VALLEY POWER STATION, UNITS 1 AND 2 HARD COPY:
 
DLR RF E-MAIL:
HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSbwb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter -------------
PUBLIC RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSbwb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter
KHoward ESayoc NMorgan MModes, RI PCataldo, RI DWerkheiser, RI Beaver Valley Power Station, Units 1 and 2 cc:  Joseph J. Hagan President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH  44308
-------------
 
KHoward ESayoc NMorgan MModes, RI PCataldo, RI DWerkheiser, RI
James H. Lash Senior Vice President of Operations  and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH  44308
 
Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH  44308 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH  44308
 
Paul A. Harden Vice President, Nuclear Support FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH  44308 David W. Jenkins, Attorney FirstEnergy Corporation Mail Stop A-GO-15 76 South Main Street Akron, OH  44308
 
Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH  44308 Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH  44308 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-A P.O. Box 4, Route 168 Shippingport, PA  15077
 
Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA  19406
 
Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA  15077
 
Cliff Custer FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA  15077
 
Steve Dort FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA  15077


Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA   15077}}
Beaver Valley Power Station, Units 1 and 2 cc:
Joseph J. Hagan                            Manager, Fleet Licensing President and Chief Nuclear Officer        FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company      Mail Stop A-GO-2 Mail Stop A-GO-19                          76 South Main Street 76 South Main Street                      Akron, OH 44308 Akron, OH 44308 Director, Fleet Regulatory Affairs James H. Lash                              FirstEnergy Nuclear Operating Company Senior Vice President of Operations        Mail Stop A-GO-2 and Chief Operating Officer              76 South Main Street FirstEnergy Nuclear Operating Company      Akron, OH 44308 Mail Stop A-GO-14 76 South Main Street                      Manager, Site Regulatory Compliance Akron, OH 44308                            FirstEnergy Nuclear Operating Company Beaver Valley Power Station Danny L. Pace                              Mail Stop A-BV-A Senior Vice President, Fleet Engineering  P.O. Box 4, Route 168 FirstEnergy Nuclear Operating Company      Shippingport, PA 15077 Mail Stop A-GO-14 76 South Main Street                      Regional Administrator, Region I Akron, OH 44308                            U.S. Nuclear Regulatory Commission 475 Allendale Road Jeannie M. Rinckel                        King of Prussia, PA 19406 Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company      Resident Inspector Mail Stop A-GO-14                          U.S. Nuclear Regulatory Commission 76 South Main Street                      P.O. Box 298 Akron, OH 44308                            Shippingport, PA 15077 Paul A. Harden                            Cliff Custer Vice President, Nuclear Support            FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company      Beaver Valley Power Station Mail Stop A-GO-14                          P.O. Box 4, Route 168 76 South Main Street                      Shippingport, PA 15077 Akron, OH 44308 Steve Dort David W. Jenkins, Attorney                FirstEnergy Nuclear Operating Company FirstEnergy Corporation                    Beaver Valley Power Station Mail Stop A-GO-15                          P.O. Box 4, Route 168 76 South Main Street                      Shippingport, PA 15077 Akron, OH 44308 Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077}}

Revision as of 11:02, 14 November 2019

Safety Evaluation Report with Open Item Related to the License Renewal of Beaver Valley Power Station, Units 1 and 2
ML090080046
Person / Time
Site: Beaver Valley
(DPR-066, NPF-073)
Issue date: 01/09/2009
From: Brian Holian
Division of License Renewal
To: Sena P
FirstEnergy Nuclear Operating Co
Howard K, NRR/DLR/RLRB, 415-2989
Shared Package
ML090120354 List:
References
Download: ML090080046 (5)


Text

January 9, 2009 Mr. Peter P. Sena III Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB-1 P.O. Box 4, Route 168 Shippingport, PA 15077

SUBJECT:

SAFETY EVALUATION REPORT WITH OPEN ITEM RELATED TO THE LICENSE RENEWAL OF BEAVER VALLEY POWER STATION, UNITS 1 AND 2

Dear Mr. Sena:

By letter dated August 27, 2007, FirstEnergy Nuclear Operating Company submitted, for U.S.

Nuclear Regulatory Commission (NRC) review, an application to renew the Beaver Valley Power Station, Units 1 and 2, operating licenses for up to an additional 20 years. The license renewal application (LRA) was submitted pursuant to Title 10 of the Code of Federal Regulations Part 54 (10 CFR 54), Requirements for Renewal of Operating Licenses for Nuclear Power Plants. The staff determined that the LRA was complete and acceptable for docketing on October 26, 2007.

The staff has reviewed the Beaver Valley Power Station LRA and has developed the enclosed Safety Evaluation Report With Open Item related to the License Renewal of the Beaver Valley Power Station, Units 1 and 2, hereinafter referred to as the Safety Evaluation Report (SER).

This SER reflects the status of the staffs review of the LRA, requests for additional information (RAIs), the applicants responses to the staffs RAIs and other questions related to the LRA through December 19, 2008, unless otherwise noted. Issuance of the enclosed SER is an important milestone for both the applicant and the staff.

The staff has identified an open item in its review that must be resolved before it can make a final determination on the application. The open item is summarized in SER Section 1.5, along with an explanation of the information required to satisfactorily resolve the issue.

In accordance with the schedule for completing the review of the LRA, the applicant is requested to review the enclosed SER, verify its accuracy, and provide comments and response to the open item by March 10, 2009. The staff plans to review the current content and format of the SER for further improvement while incorporating the applicants comments. A revised SER will then be issued by May 29, 2009.

The staff is committed to completing the review of the Beaver Valley Power Station SER in a timely manner. If you have any questions regarding this matter, please contact the license renewal project manager, Kent Howard, at 301-415-2989 or e-mail kent.howard@nrc.gov.

Sincerely,

/RA SLee for/

Brian Holian, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412

Enclosure:

Safety Evaluation Report with Open Item cc w/encls: See next page

ML090080046 OFFICE LA:DLR PM:DLR:RPB2 BC:DLR:RPB2 BC:DLR:RER1

  • BC:DLR:RER2 NAME SFigueroa KHoward DWrona JDozier RAuluck DATE 1/9/09 1/9/09 1/9/09 1/8/09 1/9/09 OFFICE BC:DE:EMCB
  • BC:DE:EEEB
  • BC:DSS:SBPB
  • BC:DSS:SRXB
  • BC:DSS:SCVB
  • NAME KManoly GWilson DHarrison GCranston RDennig DATE 12/19/08 12/17/08 12/23/08 12/11/08 12/19/08 OFFICE BC:DCI:CVIB
  • BC:DCI:CPNB
  • BC:DCI:CSGB

NAME MMitchell TChan AHiser AKlein LSubin DATE 12/17/08 12/18/08 01/06/09 01/05/09 1/9/09 OFFICE D:DE

  • D:DSS
  • D:DCI
  • D:DRA D:DLR NAME PHiland WRuland MEvans MCunningham BHolian (SBahadur for) /SLee for/

DATE 1/7/09 1/8/09 1/8/09 1/9/09 1/09/09

Letter to P. Sena III from B. Holian, dated January 9, 2009 DISTRIBUTION:

SUBJECT:

SAFETY EVALUATION REPORT WITH OPEN ITEM RELATED TO THE LICENSE RENEWAL OF BEAVER VALLEY POWER STATION, UNITS 1 AND 2 HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSbwb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter


KHoward ESayoc NMorgan MModes, RI PCataldo, RI DWerkheiser, RI

Beaver Valley Power Station, Units 1 and 2 cc:

Joseph J. Hagan Manager, Fleet Licensing President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 Mail Stop A-GO-19 76 South Main Street 76 South Main Street Akron, OH 44308 Akron, OH 44308 Director, Fleet Regulatory Affairs James H. Lash FirstEnergy Nuclear Operating Company Senior Vice President of Operations Mail Stop A-GO-2 and Chief Operating Officer 76 South Main Street FirstEnergy Nuclear Operating Company Akron, OH 44308 Mail Stop A-GO-14 76 South Main Street Manager, Site Regulatory Compliance Akron, OH 44308 FirstEnergy Nuclear Operating Company Beaver Valley Power Station Danny L. Pace Mail Stop A-BV-A Senior Vice President, Fleet Engineering P.O. Box 4, Route 168 FirstEnergy Nuclear Operating Company Shippingport, PA 15077 Mail Stop A-GO-14 76 South Main Street Regional Administrator, Region I Akron, OH 44308 U.S. Nuclear Regulatory Commission 475 Allendale Road Jeannie M. Rinckel King of Prussia, PA 19406 Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Resident Inspector Mail Stop A-GO-14 U.S. Nuclear Regulatory Commission 76 South Main Street P.O. Box 298 Akron, OH 44308 Shippingport, PA 15077 Paul A. Harden Cliff Custer Vice President, Nuclear Support FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-GO-14 P.O. Box 4, Route 168 76 South Main Street Shippingport, PA 15077 Akron, OH 44308 Steve Dort David W. Jenkins, Attorney FirstEnergy Nuclear Operating Company FirstEnergy Corporation Beaver Valley Power Station Mail Stop A-GO-15 P.O. Box 4, Route 168 76 South Main Street Shippingport, PA 15077 Akron, OH 44308 Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077