{{#Wiki_filter:TSTF-557, Rev. 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program Original      Change    Change      Change                Reason Schedule      5/3/18    9/7/18    11/1/18 3/18/18 Submitted            12/19/17 RAIs                  4/17/18  No RAIs Draft SE              9/28/18            10/26/18    11/8/18              OGC then DORL delays Final SE              12/19/18 RAI Response to Final SE: 10 Months TSTF-563, Rev. 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program Original    Change Change Change        Change  Change Change                    Reason Schedule      7/3/17 2/15/18 7/3/18        8/2/18  9/20/18 10/12/18 7/3/17 Submitted              5/10/17 RAIs                    9/7/17 10/5/17 2/15/18                                            Draft RAIs from EICB and APLA.
Second round APLA RAI on 2/15/18.
TSTF                                    4/17/18                                              TSTF to respond to draft to save Response                                                                                                                time.
Draft SE                3/3/18                    8/31/18 10/31/18 9/20/18                                Actual on 9/20/18 Final SE              5/17/18                                                12/20/18 RAI Response to Final SE: 8 Months Page 1                                EXCEL Services Corporation
 
TSTF-564, Rev. 1, Safety Limit MCPR - High priority, plant startup related Original    Change Change      Change    Change  Change    Change                  Reason Schedule    4/12/18 6/8/18      7/3/18    9/7/18 10/4/18  10/24/18 11/18/17 Submitted            8/28/17 RAIs                  3/16/18 4/12/18                                                                        Draft RAI 3/20/18 TSTF                          5/29/18                                                          TSTF provided draft on 5/3/18.
Response                                                                                      Revised draft response based on NRC comments Draft SE              5/30/18            6/29/18    8/31/18  9/30/18 10/4/18                                    Actual 10/4/18 Final SE              7/31/18                                                  11/26/18 RAI Response to Final SE: 6 Months TSTF-566, Rev. 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems Original    Change      Change      Change                Reason Schedule      4/5/18    10/29/18 3/26/18 Submitted            1/18/18 RAIs                  5/4/18        --                              Determined no RAI needed Draft SE            10/16/18              11/8/18                      On schedule as of 9/7/18 Final SE              1/18/19                              ??
RAI Response to Final SE: 9 Months Page 2                                EXCEL Services Corporation}}

Revision as of 10:57, 20 October 2019

Handout from 11/08/2018 TSTF Meeting for Agenda Item Ii.B.C November 2018 Traveler Review Schedule Changes
ML18312A367
Person / Time
Site: Technical Specifications Task Force
Issue date: 11/08/2018
From:
Technical Specifications Task Force
To:
Office of Nuclear Reactor Regulation
Honcharik M
Shared Package
ML18312A362 List:
References
Download: ML18312A367 (2)


Text

TSTF-557, Rev. 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program Original Change Change Change Reason Schedule 5/3/18 9/7/18 11/1/18 3/18/18 Submitted 12/19/17 RAIs 4/17/18 No RAIs Draft SE 9/28/18 10/26/18 11/8/18 OGC then DORL delays Final SE 12/19/18 RAI Response to Final SE: 10 Months TSTF-563, Rev. 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program Original Change Change Change Change Change Change Reason Schedule 7/3/17 2/15/18 7/3/18 8/2/18 9/20/18 10/12/18 7/3/17 Submitted 5/10/17 RAIs 9/7/17 10/5/17 2/15/18 Draft RAIs from EICB and APLA.

Second round APLA RAI on 2/15/18.

TSTF 4/17/18 TSTF to respond to draft to save Response time.

Draft SE 3/3/18 8/31/18 10/31/18 9/20/18 Actual on 9/20/18 Final SE 5/17/18 12/20/18 RAI Response to Final SE: 8 Months Page 1 EXCEL Services Corporation

TSTF-564, Rev. 1, Safety Limit MCPR - High priority, plant startup related Original Change Change Change Change Change Change Reason Schedule 4/12/18 6/8/18 7/3/18 9/7/18 10/4/18 10/24/18 11/18/17 Submitted 8/28/17 RAIs 3/16/18 4/12/18 Draft RAI 3/20/18 TSTF 5/29/18 TSTF provided draft on 5/3/18.

Response Revised draft response based on NRC comments Draft SE 5/30/18 6/29/18 8/31/18 9/30/18 10/4/18 Actual 10/4/18 Final SE 7/31/18 11/26/18 RAI Response to Final SE: 6 Months TSTF-566, Rev. 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems Original Change Change Change Reason Schedule 4/5/18 10/29/18 3/26/18 Submitted 1/18/18 RAIs 5/4/18 -- Determined no RAI needed Draft SE 10/16/18 11/8/18 On schedule as of 9/7/18 Final SE 1/18/19  ??

RAI Response to Final SE: 9 Months Page 2 EXCEL Services Corporation