ML12248A082: Difference between revisions

From kanterella
Jump to navigation Jump to search
Created page by program invented by StriderTol
Created page by program invented by StriderTol
Line 3: Line 3:
| issue date = 09/13/2012
| issue date = 09/13/2012
| title = License Condition 3.K.1, Extended Power Uprate Modifications, Regarding Spent Fuel Pool Supplemental Heat Exchangers
| title = License Condition 3.K.1, Extended Power Uprate Modifications, Regarding Spent Fuel Pool Supplemental Heat Exchangers
| author name = Saba F E
| author name = Saba F
| author affiliation = NRC/NRR/DORL/LPLII-2
| author affiliation = NRC/NRR/DORL/LPLII-2
| addressee name = Nazar M
| addressee name = Nazar M
Line 9: Line 9:
| docket = 05000251
| docket = 05000251
| license number = DPR-041
| license number = DPR-041
| contact person = Saba F E
| contact person = Saba F
| case reference number = TAC ME9248
| case reference number = TAC ME9248
| document type = Letter
| document type = Letter
Line 29: Line 29:
This concludes the NRC staff reviews associated with License Condition 3.K.1 for TPN Unit No.4. Therefore, TAC No. ME9246 will be closed. If you have any questions, please contact me at 301-415-1447 or via e-mail at Farideh.Saba@nrc.gov. Sincerely, Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket No. 50-251 cc: Distribution via Listserv M. Nazar -2 The NRC staff reviewed the summary information and finds it acceptable because the piping stresses, pipe supports, heat exchanger nozzle loads, supplemental spent fuel pool heat exchanger supports, and valve accelerations meet the respective acceptance limits. The licensee has satisfactorily demonstrated that the design and structural integrity evaluations associated with the modifications related to the spent fuel pool supplemental heat exchangers are complete and that the results demonstrate compliance with the appropriate UFSAR and code req uirements.
This concludes the NRC staff reviews associated with License Condition 3.K.1 for TPN Unit No.4. Therefore, TAC No. ME9246 will be closed. If you have any questions, please contact me at 301-415-1447 or via e-mail at Farideh.Saba@nrc.gov. Sincerely, Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket No. 50-251 cc: Distribution via Listserv M. Nazar -2 The NRC staff reviewed the summary information and finds it acceptable because the piping stresses, pipe supports, heat exchanger nozzle loads, supplemental spent fuel pool heat exchanger supports, and valve accelerations meet the respective acceptance limits. The licensee has satisfactorily demonstrated that the design and structural integrity evaluations associated with the modifications related to the spent fuel pool supplemental heat exchangers are complete and that the results demonstrate compliance with the appropriate UFSAR and code req uirements.
This concludes the NRC staff reviews associated with License Condition 3.K.1 forTPN Unit NO.4. Therefore, TAC No. ME9246 will be closed. If you have any questions, please contact me at 301-415-1447 or via e-mail at Farideh.Saba@nrc.gov. Docket No. 50-251 cc: Distribution via Listserv DISTRIBUTION:
This concludes the NRC staff reviews associated with License Condition 3.K.1 forTPN Unit NO.4. Therefore, TAC No. ME9246 will be closed. If you have any questions, please contact me at 301-415-1447 or via e-mail at Farideh.Saba@nrc.gov. Docket No. 50-251 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrDorlLpl2-2 Resource RidsNrrPMTurkeyPoint Resource RidsRgn2MailCenter Resource RidsNrrDeEmcb ADAMS Accession No. ML 12248A082 Sincerely, IRA! Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsAcrsAcnw_MailCTR Resource RidsNrrLABClayton Resource RidsOgcRp Resource CBasavaraju, NRR NAME I DATE DORULPL2-2/PM FSaba 09/05/12 DORU ILPL2-2/LA BClayton 09/04/12 DE/EMCB/BC MMurphy 09/10/12 DORULPL2-2/BC(A)
PUBLIC RidsNrrDorlLpl2-2 Resource RidsNrrPMTurkeyPoint Resource RidsRgn2MailCenter Resource RidsNrrDeEmcb ADAMS Accession No. ML12248A082 Sincerely, IRA! Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsAcrsAcnw_MailCTR Resource RidsNrrLABClayton Resource RidsOgcRp Resource CBasavaraju, NRR NAME I DATE DORULPL2-2/PM FSaba 09/05/12 DORU ILPL2-2/LA BClayton 09/04/12 DE/EMCB/BC MMurphy 09/10/12 DORULPL2-2/BC(A)
DORULPL2-2/PM JQuichocho (TOrt for) FSaba 09/12/12 09/13/12 OFFICIAL RECORD}}
DORULPL2-2/PM JQuichocho (TOrt for) FSaba 09/12/12 09/13/12 OFFICIAL RECORD}}

Revision as of 16:36, 22 June 2019

License Condition 3.K.1, Extended Power Uprate Modifications, Regarding Spent Fuel Pool Supplemental Heat Exchangers
ML12248A082
Person / Time
Site: Turkey Point 
Issue date: 09/13/2012
From: Farideh Saba
Plant Licensing Branch II
To: Nazar M
Florida Power & Light Co
Saba F
References
TAC ME9248
Download: ML12248A082 (3)


Text

UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555*0001 September 13, 2012 Mr. Mano Executive Vice President Chief Nuclear Florida Power and Light P.O. Box Juno Beach, Florida TURKEY POINT NUCLEAR GENERATING UNIT NO.4 -CONDITION 3.K.1,"EXTENDED POWER UPRATE REGARDING SPENT FUEL POOL SUPPLEMENTAL HEAT (TAC NO.

Dear Mr. Nazar:

On June 15, 2012, the U. S. Nuclear Regulatory Commission (NRC) issued Extended Power Uprate (EPU) Amendments 249 and 245 for Renewed Facility Operating Licenses DPR-31 and DPR-41 for Turkey Point Nuclear Generating (TPN) Unit Nos. 3 and 4, respectively.

The amendments included license conditions 3.J.1 for Unit 3 and 3.K.1 for Unit 4, "Extended Power Uprate Modifications." These license conditions state: Prior to completion of the Cycle 26 [27] refueling outage for Unit 3 [4], the licensee shall provide confirmation to the NRC staff that the design and structural integrity evaluations associated with the modifications related to the spent fuel pool supplemental heat exchangers are complete, and that the results demonstrate compliance with appropriate UFSAR and code requirements.

As part of the confirmation, the licensee shall provide a summary of the structural qualification results of the piping, pipe supports, supplemental heat exchanger supports, and the inter-tie connection with the existing heat exchanger for the appropriate load combinations along with the margins. By letter dated August 10, 2012, Florida Power &Light (the licensee) provided confirmation that the design and structural integrity evaluations associated with the modifications related to the spent fuel pool supplemental heat exchange for TPN, Unit NO.4 have been completed.

In accordance with license condition

3. K.1, the licensee submitted a summary of the structural qualification results of the piping, the pipe supports, major valves, and supplemental heat exchanger inlet and outlet nozzles and supports for appropriate load combinations along with the associated design margins. Due to the extent of the piping that is being added or modified as a result of the addition (inter-tie) of the supplemental heat exchanger, the entire main process piping and associated supports have been re-analyzed by the licensee to ensure compliance with the appropriate Updated Final Safety Analysis Report (UFSAR) and code requirements.

M. Nazar -The NRC staff reviewed the summary information and finds it acceptable because the piping stresses, pipe supports, heat exchanger nozzle loads, supplemental spent fuel pool heat exchanger supports, and valve accelerations meet the respective acceptance limits. The licensee has satisfactorily demonstrated that the design and structural integrity evaluations associated with the modifications related to the spent fuel pool supplemental heat exchangers are complete and that the results demonstrate compliance with the appropriate UFSAR and code requirements.

This concludes the NRC staff reviews associated with License Condition 3.K.1 for TPN Unit No.4. Therefore, TAC No. ME9246 will be closed. If you have any questions, please contact me at 301-415-1447 or via e-mail at Farideh.Saba@nrc.gov. Sincerely, Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket No. 50-251 cc: Distribution via Listserv M. Nazar -2 The NRC staff reviewed the summary information and finds it acceptable because the piping stresses, pipe supports, heat exchanger nozzle loads, supplemental spent fuel pool heat exchanger supports, and valve accelerations meet the respective acceptance limits. The licensee has satisfactorily demonstrated that the design and structural integrity evaluations associated with the modifications related to the spent fuel pool supplemental heat exchangers are complete and that the results demonstrate compliance with the appropriate UFSAR and code req uirements.

This concludes the NRC staff reviews associated with License Condition 3.K.1 forTPN Unit NO.4. Therefore, TAC No. ME9246 will be closed. If you have any questions, please contact me at 301-415-1447 or via e-mail at Farideh.Saba@nrc.gov. Docket No. 50-251 cc: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsNrrDorlLpl2-2 Resource RidsNrrPMTurkeyPoint Resource RidsRgn2MailCenter Resource RidsNrrDeEmcb ADAMS Accession No. ML12248A082 Sincerely, IRA! Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsAcrsAcnw_MailCTR Resource RidsNrrLABClayton Resource RidsOgcRp Resource CBasavaraju, NRR NAME I DATE DORULPL2-2/PM FSaba 09/05/12 DORU ILPL2-2/LA BClayton 09/04/12 DE/EMCB/BC MMurphy 09/10/12 DORULPL2-2/BC(A)

DORULPL2-2/PM JQuichocho (TOrt for) FSaba 09/12/12 09/13/12 OFFICIAL RECORD