| #REDIRECT [[L-77-178, St. Lucie, Unit 1 - Letter Furnishing Information Concerning Refueling Surveillance Testing]] | | {{Adams |
| | | number = ML18127B254 |
| | | issue date = 06/16/1977 |
| | | title = Letter Furnishing Information Concerning Refueling Surveillance Testing |
| | | author name = Uhrig R E |
| | | author affiliation = Florida Power & Light Co |
| | | addressee name = Davis D K |
| | | addressee affiliation = NRC/NRR |
| | | docket = 05000335 |
| | | license number = DPR-067 |
| | | contact person = |
| | | case reference number = L-77-178 |
| | | document type = Letter type:L |
| | | page count = 4 |
| | }} |
| | |
| | =Text= |
| | {{#Wiki_filter:'r~.~I r DOCKET NUMBER U.S.NUCLEAR REGULATORY Co ION ,"NRC FORM'I95 I(2.76)FILE NUMBER FROM: DATE OF DOCUMENT 6-16-77 DATE RECEIVED TO: D K Davis Florida Pwr G Light Co Miami, Fla R E Uhri Cl N OTO R I Z E D SUNCLASSIFIED BETTE R ORIGINAL OCOP Y NUMBER OF COPIES RECEIVED/@~+8 INPUT FORM PROP ENCLOSU RE DESCRIPTION furnishing info concerning refueling surveillance testing............... |
| | 2p PO g(yg EZMOVR ZGKZOWLFDGED I"PLANT NAME: St Lucie IlIl 6-28-77 ehf FOR ACTION/INFORMATION ENVIRHNMENTAL ASSIGNED AD: Vi MOORE LTR BRANCH CHIEF: PROJECT MANAGER: LICENSING ASSISTANT: |
| | 4'J C ECT MANAGER EN ING ASSISTANT: |
| | Bo HARLESS INTERNAL DISTRIBUTION PLANT SYSTEMS SITE SAFETY&ENVIRON ANALYSIS gTEMS SAFETY HEINEMAN TEDESCO DENTON&MULLER BENAROYA IPPOLITO EDE ENGINEERING ENVIRO TECH ERNST BALLARD OPERATING REACTORS G BLOOD BAER GAMMILL 2 BUTLER VAK ZTACZY GRIME SITE ANALYSIS VOLLMER BUNCH CHECK AT I J~COLLINS ALTZMAN KREGER R BERG CONTROL NUMBER EXTERNAL DISTRIBUTION ngg-77iaOO11> |
| | NSIC TIC REG IV J HANCHETT 16 CYS ACRS SENT CAT GO Y NRC FORM 195 (2.79)NRC DISTRIBUTION FoR PART 50 DOCKET MATERIAL |
| | |
| | FLORIDA POWER&LIGHT COMPANY RegIIIetory Docket ge June 16, 1977 L-77-178 Office of Nuclear Reactor Regulation Attention: |
| | Mr.Don K.Davis, Acting Chief Operating Reactors Branch I2 Division of Operating Reactors U.S.Nuclear Regulatory Commission Washington, DC 20555 |
| | |
| | ==Dear Mr.Davis:== |
| | Re: St.Lucie Unit 1 Docket No.50-335 Refuelin Surveillance Testin Our continuing efforts to plan and schedule surveillance zesting in compliance with St.Lucie Unit, 1 license reauirements have led to a problem that.could seriously impact the Unit's availability. |
| | This problem concerns the scheduling of 18-month/refueling surveillance tests.At the time of initial fuel loading, we were given the interpretation that all surveillance intervals began at the time of licensing (March 1, 1976, for DPR-67), which would bring the 18-month/refueling surveillances due between Sept-ember, l977 and January, 1978.This interpretation was given by the plant's principal inspectors from the Region II Office of Inspection and Enforcement at'*about. |
| | the.time'he operating license was iss'ued, and, until recently, planning for their conduct proceeded on this basis.Approximately two weeks ago, however, a new interpretation was given by Region II.Under the new interpretation, the 18-month/refueling surveillance interval begins at the time oj pre-operational testing.Our evaluation of the impact of this has prompted us to reexamine the overall scheduling requirements for these tests, since in either case they must be performed prior to the Cycle 2 refueling outage.The underlying problem in the conduct of these surveillances is that they will require a unit shutdown and an outage of the magnitude of a normal refueling outage.Because of a lengthy (5-month)outage during 1976 for poison shim replacement we have been forced to defer the Cycle 2 refueling outage until the late summer of 1978.If the unit has to be shut down before this refueling to perform the 18-month/refueling surveillances, the total down-time, including the forced surveillance outage and the scheduled 1978 refueling outage, would be twice the normal amount.771800111 PEOPLE...SERVING PEOPLE Mr.D.K.Davis L-77-178 June 16, 1977 page 2 Therefore, for the reasons described above,'e request that the end of the first 18-month/refueling surveillance period be extended to the first scheduled refueling outage for St.Lucie Unit l.PPZ would perform subsequent l8-month/refueling surveillances during each subsequent refueling outage in order to preclude the excessive down-time associated with the existing l8-month schedule.Our future efforts are dependent upon your response to our request because many of the outstanding surveillances require outside contractors and this increases the scheduling difficulties. |
| | Your prompt response in this matter will bc apprec'at-d. |
| | We are reviewing our surveillance program in light, of the new interpretation from Region II and the revised refueling schedule in an effort to satisfy technical specification requirements without affecting unit availability. |
| | We will be available to discuss this issue with you in order that we may reach a mutually acceptable solution.Very truly yours, Robert E.Uhrig Vice President REU.:RLH:MAS:dm cc: Norman.C.Moseley, Region II Robert Lowenstein, Esquire}} |
|
---|
Category:Letter type:L
MONTHYEARL-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) L-2024-004, Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years2024-01-18018 January 2024 Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years L-2024-002, Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump2024-01-0808 January 2024 Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-179, Unusual or Important Environmental Event - Turtle Mortality2023-12-14014 December 2023 Unusual or Important Environmental Event - Turtle Mortality L-2023-168, License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 52023-12-12012 December 2023 License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 5 L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-162, Response to 50.69 2nd Round of Rals2023-11-21021 November 2023 Response to 50.69 2nd Round of Rals L-2023-131, Subsequent License Renewal Application - Second Annual Update2023-09-28028 September 2023 Subsequent License Renewal Application - Second Annual Update L-2023-136, Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-26026 September 2023 Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-2023-122, Corrections to the 2022 Annual Radiological Environmental Operating Report2023-09-20020 September 2023 Corrections to the 2022 Annual Radiological Environmental Operating Report L-2023-127, Correction to the 2022 Annual Radioactive Effluent Release Report2023-09-18018 September 2023 Correction to the 2022 Annual Radioactive Effluent Release Report L-2023-113, Correction to the 2020 Annual Radiological Environmental Operating Report2023-09-14014 September 2023 Correction to the 2020 Annual Radiological Environmental Operating Report L-2023-118, Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-11011 September 2023 Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-2023-108, Report of 10 CFR 50.59 Plant Changes2023-09-11011 September 2023 Report of 10 CFR 50.59 Plant Changes L-2023-112, Corrections to the 2021 Annual Radioactive Effluent Release Report2023-09-0606 September 2023 Corrections to the 2021 Annual Radioactive Effluent Release Report L-2023-107, Technical Specification Bases Control Program Periodic Report of Bases Changes TS 6.8.4.j.42023-09-0606 September 2023 Technical Specification Bases Control Program Periodic Report of Bases Changes TS 6.8.4.j.4 L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 L-2023-105, Preparation and Scheduling of Operator Licensing Examinations2023-08-0303 August 2023 Preparation and Scheduling of Operator Licensing Examinations L-2023-099, Pump Relief Request 10 (PR-10), One-Time Request for an Alternative to the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump2023-07-26026 July 2023 Pump Relief Request 10 (PR-10), One-Time Request for an Alternative to the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump L-2023-102, Relief Request PSL2-15-RR-01, Proposed Alternative to ASME Section XI Code Examination Requirements for Reactor Vessel Bottom Area and Piping in Covered Trenches2023-07-26026 July 2023 Relief Request PSL2-15-RR-01, Proposed Alternative to ASME Section XI Code Examination Requirements for Reactor Vessel Bottom Area and Piping in Covered Trenches L-2023-097, Subsequent License Renewal Application Revision 1 - Supplement 62023-07-13013 July 2023 Subsequent License Renewal Application Revision 1 - Supplement 6 L-2023-076, In-Service Inspection Program Owner'S Activity Report (OAR-1)2023-07-11011 July 2023 In-Service Inspection Program Owner'S Activity Report (OAR-1) L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) L-2023-082, Subsequent License Renewal Application Revision 1, Supplement 52023-06-14014 June 2023 Subsequent License Renewal Application Revision 1, Supplement 5 L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal L-2023-059, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response2023-04-21021 April 2023 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response L-2023-055, 2022 Annual Environmental Operating Report2023-04-12012 April 2023 2022 Annual Environmental Operating Report L-2023-041, Annual Radiological Environmental Operating Report for Calendar Year 20222023-04-0404 April 2023 Annual Radiological Environmental Operating Report for Calendar Year 2022 L-2023-051, Report of 10 CFR 50.59 Plant Changes2023-04-0404 April 2023 Report of 10 CFR 50.59 Plant Changes L-2023-021, Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-03-28028 March 2023 Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2023-042, Periodic Update of Population Data within 10 and 50 Miles of the Plant2023-03-27027 March 2023 Periodic Update of Population Data within 10 and 50 Miles of the Plant L-2023-026, Subsequent License Renewal Application - Aging Management Requests for Additional Information Set 42023-03-27027 March 2023 Subsequent License Renewal Application - Aging Management Requests for Additional Information Set 4 L-2023-028, and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2023-03-27027 March 2023 and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications L-2023-025, Fleet Relief Request (Frr) 23-01, Proposed Alternative to ASME Section XI Authorizing Implementation of ASME Code Case N-752-12023-03-15015 March 2023 Fleet Relief Request (Frr) 23-01, Proposed Alternative to ASME Section XI Authorizing Implementation of ASME Code Case N-752-1 L-2023-029, and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3)2023-03-10010 March 2023 and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3) L-2023-039, Cycle 27 Core Operating Limits Report2023-03-0707 March 2023 Cycle 27 Core Operating Limits Report L-2023-032, 2022 Annual Radioactive Effluent Release Report2023-02-28028 February 2023 2022 Annual Radioactive Effluent Release Report L-2023-038, 2022 Annual Operating Report2023-02-28028 February 2023 2022 Annual Operating Report L-2023-016, Radiological Emergency Plan - Revision 74 Report of Changes to Emergency Plan2023-02-15015 February 2023 Radiological Emergency Plan - Revision 74 Report of Changes to Emergency Plan L-2023-019, Annual Summary of Commitment Changes Implemented Without Prior NRC Notification for Calendar Year 20222023-02-15015 February 2023 Annual Summary of Commitment Changes Implemented Without Prior NRC Notification for Calendar Year 2022 L-2023-009, Owner'S Activity Report2023-01-31031 January 2023 Owner'S Activity Report L-2022-188, Unusual or Important Environmental Event - Turtle Mortality2022-12-19019 December 2022 Unusual or Important Environmental Event - Turtle Mortality L-2022-185, Turkey Points, Units 3 & 4; Seabrook Station; and Point Beach, Units 1 and 2 - Supplement to License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22022-12-0909 December 2022 Turkey Points, Units 3 & 4; Seabrook Station; and Point Beach, Units 1 and 2 - Supplement to License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 L-2022-175, Application to Adopt 10 CPR 50.69, 'Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2022-12-0202 December 2022 Application to Adopt 10 CPR 50.69, 'Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-2022-180, CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2022-11-0909 November 2022 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums L-2022-165, Subsequent License Renewal Application - Aging Management Request for Additional Information (RAI) 4.3.1-1a(second Round) - Class 1 Fatigue Response2022-10-26026 October 2022 Subsequent License Renewal Application - Aging Management Request for Additional Information (RAI) 4.3.1-1a(second Round) - Class 1 Fatigue Response L-2022-160, Station,, Point Beach Units 1 and 2, License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22022-10-0404 October 2022 Station,, Point Beach Units 1 and 2, License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 2024-01-08
[Table view] |
Text
'r~.~I r DOCKET NUMBER U.S.NUCLEAR REGULATORY Co ION ,"NRC FORM'I95 I(2.76)FILE NUMBER FROM: DATE OF DOCUMENT 6-16-77 DATE RECEIVED TO: D K Davis Florida Pwr G Light Co Miami, Fla R E Uhri Cl N OTO R I Z E D SUNCLASSIFIED BETTE R ORIGINAL OCOP Y NUMBER OF COPIES RECEIVED/@~+8 INPUT FORM PROP ENCLOSU RE DESCRIPTION furnishing info concerning refueling surveillance testing...............
2p PO g(yg EZMOVR ZGKZOWLFDGED I"PLANT NAME: St Lucie IlIl 6-28-77 ehf FOR ACTION/INFORMATION ENVIRHNMENTAL ASSIGNED AD: Vi MOORE LTR BRANCH CHIEF: PROJECT MANAGER: LICENSING ASSISTANT:
4'J C ECT MANAGER EN ING ASSISTANT:
Bo HARLESS INTERNAL DISTRIBUTION PLANT SYSTEMS SITE SAFETY&ENVIRON ANALYSIS gTEMS SAFETY HEINEMAN TEDESCO DENTON&MULLER BENAROYA IPPOLITO EDE ENGINEERING ENVIRO TECH ERNST BALLARD OPERATING REACTORS G BLOOD BAER GAMMILL 2 BUTLER VAK ZTACZY GRIME SITE ANALYSIS VOLLMER BUNCH CHECK AT I J~COLLINS ALTZMAN KREGER R BERG CONTROL NUMBER EXTERNAL DISTRIBUTION ngg-77iaOO11>
NSIC TIC REG IV J HANCHETT 16 CYS ACRS SENT CAT GO Y NRC FORM 195 (2.79)NRC DISTRIBUTION FoR PART 50 DOCKET MATERIAL
FLORIDA POWER&LIGHT COMPANY RegIIIetory Docket ge June 16, 1977 L-77-178 Office of Nuclear Reactor Regulation Attention:
Mr.Don K.Davis, Acting Chief Operating Reactors Branch I2 Division of Operating Reactors U.S.Nuclear Regulatory Commission Washington, DC 20555
Dear Mr.Davis:
Re: St.Lucie Unit 1 Docket No.50-335 Refuelin Surveillance Testin Our continuing efforts to plan and schedule surveillance zesting in compliance with St.Lucie Unit, 1 license reauirements have led to a problem that.could seriously impact the Unit's availability.
This problem concerns the scheduling of 18-month/refueling surveillance tests.At the time of initial fuel loading, we were given the interpretation that all surveillance intervals began at the time of licensing (March 1, 1976, for DPR-67), which would bring the 18-month/refueling surveillances due between Sept-ember, l977 and January, 1978.This interpretation was given by the plant's principal inspectors from the Region II Office of Inspection and Enforcement at'*about.
the.time'he operating license was iss'ued, and, until recently, planning for their conduct proceeded on this basis.Approximately two weeks ago, however, a new interpretation was given by Region II.Under the new interpretation, the 18-month/refueling surveillance interval begins at the time oj pre-operational testing.Our evaluation of the impact of this has prompted us to reexamine the overall scheduling requirements for these tests, since in either case they must be performed prior to the Cycle 2 refueling outage.The underlying problem in the conduct of these surveillances is that they will require a unit shutdown and an outage of the magnitude of a normal refueling outage.Because of a lengthy (5-month)outage during 1976 for poison shim replacement we have been forced to defer the Cycle 2 refueling outage until the late summer of 1978.If the unit has to be shut down before this refueling to perform the 18-month/refueling surveillances, the total down-time, including the forced surveillance outage and the scheduled 1978 refueling outage, would be twice the normal amount.771800111 PEOPLE...SERVING PEOPLE Mr.D.K.Davis L-77-178 June 16, 1977 page 2 Therefore, for the reasons described above,'e request that the end of the first 18-month/refueling surveillance period be extended to the first scheduled refueling outage for St.Lucie Unit l.PPZ would perform subsequent l8-month/refueling surveillances during each subsequent refueling outage in order to preclude the excessive down-time associated with the existing l8-month schedule.Our future efforts are dependent upon your response to our request because many of the outstanding surveillances require outside contractors and this increases the scheduling difficulties.
Your prompt response in this matter will bc apprec'at-d.
We are reviewing our surveillance program in light, of the new interpretation from Region II and the revised refueling schedule in an effort to satisfy technical specification requirements without affecting unit availability.
We will be available to discuss this issue with you in order that we may reach a mutually acceptable solution.Very truly yours, Robert E.Uhrig Vice President REU.:RLH:MAS:dm cc: Norman.C.Moseley, Region II Robert Lowenstein, Esquire