Please let me know if you have any questions or concerns.  
Please let me know if you have any questions or concerns.  


Sincerely,  Terry A. Beltz, Senior Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-3049 Terry.Beltz@nrc.gov Hearing Identifier:  NRR_PMDA  Email Number:  664  Mail Envelope Properties  (87B1F1BDFE5A554CA9DC5EAA75EB6D0DD4D4F89912)
Sincerely,  Terry A. Beltz, Senior Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-3049 Terry.Beltz@nrc.gov Hearing Identifier:  NRR_PMDA  Email Number:  664  Mail Envelope Properties  (87B1F1BDFE5A554CA9DC5EAA75EB6D0DD4D4F89912)  
Subject:   Monticello Nuclear Generating Plant - Request for Additional Information re:  License Amendment Request to Revise EAL RA1.2 (TAC No. MF0461)  Sent Date:  4/11/2013 2:25:47 PM  Received Date:  4/11/2013 2:25:00 PM  From:    Beltz, Terry  Created By:  Terry.Beltz@nrc.gov  Recipients:    "'Eckholt, Gene F.'" <Eugene.Eckholt@xenuclear.com>  Tracking Status: None "Carlson, Robert" <Robert.Carlson@nrc.gov>  Tracking Status: None  "Wasem, Michael" <Michael.Wasem@nrc.gov>
 
==Subject:==
Monticello Nuclear Generating Plant - Request for Additional Information re:  License Amendment Request to Revise EAL RA1.2 (TAC No. MF0461)  Sent Date:  4/11/2013 2:25:47 PM  Received Date:  4/11/2013 2:25:00 PM  From:    Beltz, Terry  Created By:  Terry.Beltz@nrc.gov  Recipients:    "'Eckholt, Gene F.'" <Eugene.Eckholt@xenuclear.com>  Tracking Status: None "Carlson, Robert" <Robert.Carlson@nrc.gov>  Tracking Status: None  "Wasem, Michael" <Michael.Wasem@nrc.gov>
Tracking Status: None  "Johnson, Don" <Don.Johnson@nrc.gov>  Tracking Status: None   
Tracking Status: None  "Johnson, Don" <Don.Johnson@nrc.gov>  Tracking Status: None   
"'Loeffler, Richard A.'" <Richard.Loeffler@xenuclear.com>  Tracking Status: None Post Office:  HQCLSTR01.nrc.gov  Files    Size      Date & Time  MESSAGE    1445      4/11/2013 2:25:00 PM image001.gif    3939  Monticello Nuclear Generating Plant - Draft RAIs to Support LAR EAL RA1.2  (TAC No. MF0461).docx    18963  Options  Priority:    Standard  Return Notification:    No  Reply Requested:    No  Sensitivity:    Normal  Expiration Date:      Recipients Received:
"'Loeffler, Richard A.'" <Richard.Loeffler@xenuclear.com>  Tracking Status: None Post Office:  HQCLSTR01.nrc.gov  Files    Size      Date & Time  MESSAGE    1445      4/11/2013 2:25:00 PM image001.gif    3939  Monticello Nuclear Generating Plant - Draft RAIs to Support LAR EAL RA1.2  (TAC No. MF0461).docx    18963  Options  Priority:    Standard  Return Notification:    No  Reply Requested:    No  Sensitivity:    Normal  Expiration Date:      Recipients Received:

Revision as of 07:41, 27 March 2018

2013/04/11 NRR E-mail Capture - Monticello Nuclear Generating Plant - Request for Additional Information License Amendment Request to Revise EAL RA1.2 (TAC No. MF0461)
ML13102A194
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 04/11/2013
From: Beltz T A
Plant Licensing Branch III
To: Loeffler R A
Northern States Power Co
References
TAC MF0461
Download: ML13102A194 (3)


Text

1NRR-PMDAPEm ResourceFrom:Beltz, TerrySent:Thursday, April 11, 2013 2:26 PMTo:'Loeffler, Richard A.'Cc:'Eckholt, Gene F.'; Carlson, Robert; Wasem, Michael; Johnson, DonSubject:Monticello Nuclear Generating Plant - Request for Additional Information re: License Amendment Request to Revise EAL RA1.2 (TAC No. MF0461)Attachments:Monticello Nuclear Generating Plant - Draft RAIs to Support LAR EAL RA1.2 (TAC No. MF0461).docxDear Mr. Loeffler:

By letter dated December 12, 2012 (Agencywide Documents Access and Management System Accession No. ML12356A473), Northern States Power Company - Minnesota, doing business as Xcel Energy, Inc., submitted a license amendment request to revise the emergency action level (EAL) RA1.2 to a value that is within the indication range of the Turbine Building Normal Waste Sump (radiation) monitor.

The U.S. Nuclear Regulatory Commission (NRC) staff in the Operating Reactor Licensing and Outreach Branch (ORLOB) of the Office of Nuclear Security and Incident Response is currently reviewing your submittal. The ORLOB staff has determined that additional information is required to complete its review. The draft requests for additional information (RAI) are attached.

You may accept this draft RAI as a formal Request for Additional Information and respond to the questions by May 17, 2013. The NRC staff suggests that the contents of the draft RAIs may want to be discussed in a conference call. Please coordinate any conference call, if desired, directly through me.

Please let me know if you have any questions or concerns.

Sincerely, Terry A. Beltz, Senior Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-3049 Terry.Beltz@nrc.gov Hearing Identifier: NRR_PMDA Email Number: 664 Mail Envelope Properties (87B1F1BDFE5A554CA9DC5EAA75EB6D0DD4D4F89912)

Subject:

Monticello Nuclear Generating Plant - Request for Additional Information re: License Amendment Request to Revise EAL RA1.2 (TAC No. MF0461) Sent Date: 4/11/2013 2:25:47 PM Received Date: 4/11/2013 2:25:00 PM From: Beltz, Terry Created By: Terry.Beltz@nrc.gov Recipients: "'Eckholt, Gene F.'" <Eugene.Eckholt@xenuclear.com> Tracking Status: None "Carlson, Robert" <Robert.Carlson@nrc.gov> Tracking Status: None "Wasem, Michael" <Michael.Wasem@nrc.gov>

Tracking Status: None "Johnson, Don" <Don.Johnson@nrc.gov> Tracking Status: None

"'Loeffler, Richard A.'" <Richard.Loeffler@xenuclear.com> Tracking Status: None Post Office: HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 1445 4/11/2013 2:25:00 PM image001.gif 3939 Monticello Nuclear Generating Plant - Draft RAIs to Support LAR EAL RA1.2 (TAC No. MF0461).docx 18963 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received:

DRAFT REQUEST FOR ADDITIONAL INFORMATION REGARDING MONTICELLO NUCLEAR GENERATING PLANT LICENSE AMENDMENT REQUEST TO REVISE EMERGENCY PLAN EMERGENCY ACTION LEVEL RA1.2 NORTHERN STATES POWER COMPANY - MINNESOTA DOCKET NO. 50-263 (TAC NO. MF0461) By letter dated December 21, 2012, Northern States Power Company - Minnesota, doing business as Xcel Energy, submitted a license amendment request for the Monticello Nuclear Generating Plant (Agencywide Documents Access and Management System Accession No. ML12356A473). The proposed amendment would revise emergency action level (EAL) RA1.2 to a value that is within the indicating range of Turbine Building Normal Waste Sump (radiation) monitor.

The U.S. Nuclear Regulatory Commission staff in the Operating Reactor Licensing and Outreach Branch (ORLOB) of the Office of Nuclear Security and Incident Response requires additional information to facilitate its technical review. Timely and accurate response to these draft RAIs is requested.

The draft RAIs from the NRC staff are provided below.

1. Please discuss the mechanism to alert the EAL decision maker that a setpoint on the table associated with RA1.2 has been exceeded and to ensure that timely classification of the event is made?

2. The application indicates that the insufficient range of indication was documented in the corrective action program. Please discuss whether an extent of condition evaluation was performed on the other radiation monitoring systems to determine if this condition exists elsewhere?
3. If an alarm setpoint has been exceeded, but the release path has been isolated, will the EAL be declared?
4. NRC Staff Comment - an enhancement to the effluent EALs would be to include the following information from the basis as a note to the EAL, "The Emergency Director should not wait until 15 minutes has elapsed, but should declare the event as soon as it is determined that the release duration has or will likely exceed 15 minutes."