ML14085A250: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:
[[Issue date::March 24, 2014]]
 
  March 24, 2014  Mr. Eric Olson  Site Vice President
Entergy Operations, Inc. 
River Bend Station
5485 US Highway 61N St. Francisville, LA  70775 
SUBJECT: RIVER BEND STATION - NOTIFICATION OF NRC COMPONENT DESIGN BASES INSPECTION (05000458/2014007) AND INITIAL REQUEST FOR INFORMATION  Dear Mr. Olson:
On July 8, 2014, the NRC will begin a triennial baseline Component Design Bases Inspection at
the River Bend Station.  A seven person team will perform this inspection using NRC Inspection
Procedure 71111.21, "Component Design Bases Inspection."  The inspection focuses on components and operator actions that have high risk and low design
margins.  The samples reviewed during this inspection will be identified during an information
gathering visit and during the subsequent in-office preparation week.  In addition, a number of
operating experience issues will also be selected for review.  The inspection will include an information gathering site visit by the team leader and a senior
reactor analyst, and three weeks of onsite inspection by the team.  The inspection team will
consist of seven members; a team leader, four NRC inspectors, and two contractors.  Five of the members will focus on engineering and one on operations.  The current inspection schedule
is as follows:  Onsite Information Gathering Visit:  July 8, 2014
Preparation Week: July 14-18, 2014
Onsite Weeks:  July 21-25, 2014; August 4-8, 2014; and August 18-22, 2014  The purpose of the information gathering visit is to meet with members of your staff to identify potential risk-significant systems, components, and operator actions.  The team leader will also request a tour of the plant with members of your operations staff and probabilistic safety
assessment staff.  During the onsite weeks, several days of time will be needed on the plant-
referenced simulator in order to facilitate the development of operator action-based scenarios. 
Additional information and documentation needed to support the inspection will be identified during the inspection, including interviews with engineering managers, engineers, and probabilistic safety assessment staff. 
    UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD. ARLINGTON, TX  76011-4511   
E. Olson - 2 - 
Our experience with these inspections has shown that they are extremely resource intensive, both for the NRC inspectors and the licensee staff.  In order to minimize the inspection impact on the site and to ensure a productive inspection, we have enclosed a request for information
needed for the inspection.  The request has been divided into three groups.  The first group lists
information necessary for the information gathering visit and for general preparation.  This
information should be available to the regional office no later than June 23, 2014.  Insofar as possible, this information should be provided electronically to the team leader.  Since the inspection will be concentrated on high risk/low margin components, calculations associated
with your list of high risk components should be available to review during the information
gathering visit to assist in our selection of components based on available design margin.  The second group of documents requested are those items that the team will need access to during the preparation week in order to finalize the samples to be inspected.  The third group
lists information necessary to aid the inspection team in tracking issues identified as a result of the inspection.  It is requested that this information be provided to the lead inspector as the
information is generated during the inspection.  Additional requests by inspectors will be made throughout all three onsite weeks for specific documents needed to complete the review of that component/selection.  It is important that all of these documents are up to date and complete in
order to minimize the number of additional documents requested during the preparation and/or
the onsite portions of the inspection.  In order to facilitate the inspection, we request that a
contact individual be assigned to each inspector to ensure information requests, questions, and
concerns are addressed in a timely manner.    The lead inspector for this inspection is Gerond A. George.  We understand that our licensing
engineer contact for this inspection is Kristi Huffstatler.  If there are any questions about the inspection or the requested materials, please contact the lead inspector by telephone at
817-200-1562 or by e-mail at Gerond.George@nrc.gov.  In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be
made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).  ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).  Sincerely,  /RA/  Thomas R. Farnholtz, Chief Engineering Branch 1
Division of Reactor Safety 
Docket:  50-548 License: NPF-47 
Enclosure: Component Design Bases Inspection Request for Information
Electronic Distribution to River Bend Station 
 
E. Olson - 3 - 
Electronic distribution by RIV: Regional Administrator (Marc.Dapas@nrc.gov) Deputy Regional Administrator (Steven.Reynolds@nrc.gov)
DRP Director (Kriss.Kennedy@nrc.gov)
DRP Deputy Director (Troy.Pruett@nrc.gov)
Acting DRS Director (Jeff.Clark@nrc.gov)
Acting DRS Deputy Director (Geoffrey.Miller@nrc.gov) Senior Resident Inspector (Grant.Larkin@nrc.gov) Resident Inspector (Andy.Barrett@nrc.gov)
RBS Administrative Assistant (Lisa.Day@nrc.gov)
Branch Chief, DRP/C (Don.Allen@nrc.gov) 
Senior Project Engineer (Ray.Azua@nrc.gov) Project Engineer (Paul.Nizov@nrc.gov) Project Engineer (Michael.Langelier@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Alan.Wang@nrc.gov) Branch Chief, DRS/TSB (Ray.Kellar@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov) RIV/ETA: OEDO (Ernesto.Quinones@nrc.gov) 
 
 
R:\_REACTORS\RBS\2014\RBS2014007-RFI-GAG.pdf ML14085A250    SUNSI Review Initials:  Non-Sensitive  Sensitive  Publicly Available  Non-Publicly Available RI:EB1 C:EB1  GGeorge TFarnholtz  /RA/ /RA/  3/14/14 3/24/14  OFFICIAL RECORD COPY  T-Telephone  E-Email  F-Fax 
  - 1 - Enclosure Initial Request for Information Component Design Bases Inspection River Bend Station  Inspection Report:  05000548/2014007 
Information Gathering Dates:  July 8, 2014
Inspection Dates: July 21-25, 2014; August 4-8, 2014; and August 18-22, 2014
Inspection Procedure: IP 71111.21, "Component Design Bases Inspection"
Lead Inspector:  Gerond A. George, Senior Reactor Inspector  I. Information Requested Prior to Information Gathering Visit (July 8, 2014)  The following information (Section I of this enclosure) should be sent to the Region IV office in hard copy or electronic format (compact disc or Certrec IMS preferred), to the attention of Gerond A. George, by June 23, 2014, to facilitate the reduction in the items
to be selected for a final list following the information gathering visit.  The inspection
team will finalize the selected list during the prep week using the additional documents
requested in Section II of this enclosure.  The specific items selected from the lists shall
be available and ready for review on the day indicated in this request.  *Please provide requested documentation electronically in "pdf" files, Excel, or other searchable formats, if possible.  The information should contain descriptive names, and be indexed and hyperlinked to facilitate ease of use.  Information in "lists" should contain enough
information to be easily understood by someone who has knowledge of boiling water
reactor technology.  If requested documents are large and only hard copy formats are available, please inform the inspector(s), and provide subject documentation during the first day of the onsite inspection.  1. An excel spreadsheet of equipment basic events (with definitions) including importance measures sorted by risk achievement worth (RAW) and Fussell-Vesely (FV) from your internal events probabilistic risk assessment (PRA).  Include basic events with RAW value of 1.3 or greater.  2. Provide a list of the top 500 cut-sets from your PRA.  3. Copies of PRA "system notebooks," and the latest PRA summary document.  4. An excel spreadsheet of PRA human action basic events or risk ranking of operator actions from your site specific PSA sorted by RAW and FV.  Provide copies of your human reliability worksheets for these items. 
5. List of procedures used to accomplish operator actions associated with the basic events in your PRA.  6. A list of all time-critical operator actions in procedures.  7. If you have an external events or fire PSA model, provide the information requested in items 1-4 for external events and fire. 
  - 2 - Enclosure  8. Any pre-existing evaluation or list of components and associated calculations with low design margins, (i.e., pumps closest to the design limit for flow or pressure, diesel generator close to design required output, heat exchangers close to rated design heat removal, etc.).
9. List of high risk maintenance rule systems/components and functions; based on engineering or expert panel judgment.
10. Structure, system, and components in the Maintenance Rule (a)(1) category.  11. Site top 10 issues list.  12. A list of operating experience evaluations for the last 3 years.  13. List of any common-cause failure evaluation of components in the last 5 years.  14. List of root cause evaluations associated with component failures or design issues initiated/completed in the last 3 years.  15. A list of permanent and temporary modifications for the previous 3 years.  16. List of current "operator work arounds/burdens."  17. A copy of any internal/external self-assessments and associated corrective action documents generated in preparation for the inspection.  18. A copy of engineering/operations related audits completed in the last 2 years.  19. Current management and engineering organizational charts.  20. List of licensee contacts for the inspection team with pager or phone numbers.  II. Information Requested to be Available on First Day of Preparation Week (July 14, 2014)  1. An electronic copy of the Design Bases Documents for the selected components.  2. An electronic copy of the System Health notebooks for the selected components.  3. List of condition reports (corrective action documents) associated with each of the selected components for the last 5 years.  4. The corrective maintenance history associated with each of the selected components for the last 5 years. 
5. Copies of calculations associated with each of the selected components (if not previously provided), excluding data files.  Please review the calculations and also provide copies of reference material (such as drawings, engineering requests, and
vendor letters).
6. Copies of operability evaluations associated with each of the selected components and plans for restoring operability, if applicable. 
  - 3 - Enclosure  7. Copies of selected operator work-around evaluations associated with each of the selected components and plans for resolution, if applicable.  8. Lists of any open temporary modifications associated with each of the selected components, if applicable.
9. Trend data on the selected electrical/mechanical components' performance for last 3 years (for example, pumps' performance including in-service testing, other vibration monitoring, oil sample results, etc., as applicable).  10. List of motor operated valves (MOVs) in the program, design margin and risk ranking.
11. List of air operated valves (AOVs) in the valve program, design and risk ranking.  12. Mechanical piping drawings for:  * Engineered safety features * Emergency core cooling systems * Emergency diesel generators  13. Electrical one-line drawings for:  * Offsite power/switchyard supplies * Normal AC power systems * Emergency AC/DC power systems including * 120VAC power, and * 125VDC/24VDC safety class systems  III. Information Requested to be provided throughout the inspection.  1. Copies of any corrective action documents generated as a result of the team's questions or queries during this inspection.
2. Copies of the list of questions submitted by the team members and the status/resolution of the information requested (provide daily during the inspection to each team member).
3. Reference materials (available electronically and as needed during all onsite weeks):  * General set of plant drawings * IPE/IPEEE/PRA report * Procurement documents for components selected * Plant procedures (normal, abnormal, emergency, surveillance, etc.) * Technical Specifications * Updated Final Safety Analysis Report * Vendor manuals   
 
  - 4 - Enclosure Inspector Contact Information: 
Gerond A. George Senior Reactor Inspector (817)200-1562
Gerond.George@nrc.gov
Mailing Address:  U.S. NRC, Region IV
Attn:  Gerond A. George 1600 East Lamar Blvd.
Arlington, TX 76011-4511 


Mr. Eric Olson Site Vice President Entergy Operations, Inc.
River Bend Station 5485 US Highway 61N St. Francisville, LA 70775
SUBJECT: RIVER BEND STATION - NOTIFICATION OF NRC COMPONENT DESIGN BASES INSPECTION (05000458/2014007) AND INITIAL REQUEST FOR INFORMATION
==Dear Mr. Olson:==
On July 8, 2014, the NRC will begin a triennial baseline Component Design Bases Inspection at the River Bend Station. A seven person team will perform this inspection using NRC Inspection Procedure 71111.21, "Component Design Bases Inspection." The inspection focuses on components and operator actions that have high risk and low design margins. The samples reviewed during this inspection will be identified during an information gathering visit and during the subsequent in-office preparation week. In addition, a number of operating experience issues will also be selected for review. The inspection will include an information gathering site visit by the team leader and a senior reactor analyst, and three weeks of onsite inspection by the team. The inspection team will consist of seven members; a team leader, four NRC inspectors, and two contractors. Five of the members will focus on engineering and one on operations. The current inspection schedule is as follows: Onsite Information Gathering Visit: July 8, 2014 Preparation Week: July 14-18, 2014 Onsite Weeks: July 21-25, 2014; August 4-8, 2014; and August 18-22, 2014 The purpose of the information gathering visit is to meet with members of your staff to identify potential risk-significant systems, components, and operator actions. The team leader will also request a tour of the plant with members of your operations staff and probabilistic safety assessment staff. During the onsite weeks, several days of time will be needed on the plant-
referenced simulator in order to facilitate the development of operator action-based scenarios.
Additional information and documentation needed to support the inspection will be identified during the inspection, including interviews with engineering managers, engineers, and probabilistic safety assessment staff. Our experience with these inspections has shown that they are extremely resource intensive, both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on the site and to ensure a productive inspection, we have enclosed a request for information needed for the inspection. The request has been divided into three groups. The first group lists information necessary for the information gathering visit and for general preparation. This information should be available to the regional office no later than June 23, 2014. Insofar as possible, this information should be provided electronically to the team leader. Since the inspection will be concentrated on high risk/low margin components, calculations associated with your list of high risk components should be available to review during the information gathering visit to assist in our selection of components based on available design margin. The second group of documents requested are those items that the team will need access to during the preparation week in order to finalize the samples to be inspected. The third group lists information necessary to aid the inspection team in tracking issues identified as a result of the inspection. It is requested that this information be provided to the lead inspector as the information is generated during the inspection. Additional requests by inspectors will be made throughout all three onsite weeks for specific documents needed to complete the review of that component/selection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection. In order to facilitate the inspection, we request that a contact individual be assigned to each inspector to ensure information requests, questions, and concerns are addressed in a timely manner. The lead inspector for this inspection is Gerond A. George. We understand that our licensing engineer contact for this inspection is Kristi Huffstatler. If there are any questions about the inspection or the requested materials, please contact the lead inspector by telephone at 817-200-1562 or by e-mail at Gerond.George@nrc.gov. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,/RA/ Thomas R. Farnholtz, Chief Engineering Branch 1 Division of Reactor Safety
Docket: 50-548 License: NPF-47
===Enclosure:===
Component Design Bases Inspection Request for Information
Electronic Distribution to River Bend Station
}}
}}

Revision as of 07:14, 22 March 2018

River Bend Station - Notification of NRC Component Design Bases Inspection (05000458/2014007) and Initial Request for Information
ML14085A250
Person / Time
Site: River Bend Entergy icon.png
Issue date: 03/24/2014
From: Thomas Farnholtz
Region 4 Engineering Branch 1
To: Olson E
Entergy Operations
G. George
References
IR-14-007
Download: ML14085A250 (7)


See also: IR 05000458/2014007

Text

March 24, 2014 Mr. Eric Olson Site Vice President

Entergy Operations, Inc.

River Bend Station

5485 US Highway 61N St. Francisville, LA 70775

SUBJECT: RIVER BEND STATION - NOTIFICATION OF NRC COMPONENT DESIGN BASES INSPECTION (05000458/2014007) AND INITIAL REQUEST FOR INFORMATION Dear Mr. Olson:

On July 8, 2014, the NRC will begin a triennial baseline Component Design Bases Inspection at

the River Bend Station. A seven person team will perform this inspection using NRC Inspection

Procedure 71111.21, "Component Design Bases Inspection." The inspection focuses on components and operator actions that have high risk and low design

margins. The samples reviewed during this inspection will be identified during an information

gathering visit and during the subsequent in-office preparation week. In addition, a number of

operating experience issues will also be selected for review. The inspection will include an information gathering site visit by the team leader and a senior

reactor analyst, and three weeks of onsite inspection by the team. The inspection team will

consist of seven members; a team leader, four NRC inspectors, and two contractors. Five of the members will focus on engineering and one on operations. The current inspection schedule

is as follows: Onsite Information Gathering Visit: July 8, 2014

Preparation Week: July 14-18, 2014

Onsite Weeks: July 21-25, 2014; August 4-8, 2014; and August 18-22, 2014 The purpose of the information gathering visit is to meet with members of your staff to identify potential risk-significant systems, components, and operator actions. The team leader will also request a tour of the plant with members of your operations staff and probabilistic safety

assessment staff. During the onsite weeks, several days of time will be needed on the plant-

referenced simulator in order to facilitate the development of operator action-based scenarios.

Additional information and documentation needed to support the inspection will be identified during the inspection, including interviews with engineering managers, engineers, and probabilistic safety assessment staff.

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD. ARLINGTON, TX 76011-4511

E. Olson - 2 -

Our experience with these inspections has shown that they are extremely resource intensive, both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on the site and to ensure a productive inspection, we have enclosed a request for information

needed for the inspection. The request has been divided into three groups. The first group lists

information necessary for the information gathering visit and for general preparation. This

information should be available to the regional office no later than June 23, 2014. Insofar as possible, this information should be provided electronically to the team leader. Since the inspection will be concentrated on high risk/low margin components, calculations associated

with your list of high risk components should be available to review during the information

gathering visit to assist in our selection of components based on available design margin. The second group of documents requested are those items that the team will need access to during the preparation week in order to finalize the samples to be inspected. The third group

lists information necessary to aid the inspection team in tracking issues identified as a result of the inspection. It is requested that this information be provided to the lead inspector as the

information is generated during the inspection. Additional requests by inspectors will be made throughout all three onsite weeks for specific documents needed to complete the review of that component/selection. It is important that all of these documents are up to date and complete in

order to minimize the number of additional documents requested during the preparation and/or

the onsite portions of the inspection. In order to facilitate the inspection, we request that a

contact individual be assigned to each inspector to ensure information requests, questions, and

concerns are addressed in a timely manner. The lead inspector for this inspection is Gerond A. George. We understand that our licensing

engineer contact for this inspection is Kristi Huffstatler. If there are any questions about the inspection or the requested materials, please contact the lead inspector by telephone at

817-200-1562 or by e-mail at Gerond.George@nrc.gov. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be

made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Sincerely, /RA/ Thomas R. Farnholtz, Chief Engineering Branch 1

Division of Reactor Safety

Docket: 50-548 License: NPF-47

Enclosure: Component Design Bases Inspection Request for Information

Electronic Distribution to River Bend Station

E. Olson - 3 -

Electronic distribution by RIV: Regional Administrator (Marc.Dapas@nrc.gov) Deputy Regional Administrator (Steven.Reynolds@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov)

DRP Deputy Director (Troy.Pruett@nrc.gov)

Acting DRS Director (Jeff.Clark@nrc.gov)

Acting DRS Deputy Director (Geoffrey.Miller@nrc.gov) Senior Resident Inspector (Grant.Larkin@nrc.gov) Resident Inspector (Andy.Barrett@nrc.gov)

RBS Administrative Assistant (Lisa.Day@nrc.gov)

Branch Chief, DRP/C (Don.Allen@nrc.gov)

Senior Project Engineer (Ray.Azua@nrc.gov) Project Engineer (Paul.Nizov@nrc.gov) Project Engineer (Michael.Langelier@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Alan.Wang@nrc.gov) Branch Chief, DRS/TSB (Ray.Kellar@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov) RIV/ETA: OEDO (Ernesto.Quinones@nrc.gov)

R:\_REACTORS\RBS\2014\RBS2014007-RFI-GAG.pdf ML14085A250 SUNSI Review Initials: Non-Sensitive Sensitive Publicly Available Non-Publicly Available RI:EB1 C:EB1 GGeorge TFarnholtz /RA/ /RA/ 3/14/14 3/24/14 OFFICIAL RECORD COPY T-Telephone E-Email F-Fax

- 1 - Enclosure Initial Request for Information Component Design Bases Inspection River Bend Station Inspection Report: 05000548/2014007

Information Gathering Dates: July 8, 2014

Inspection Dates: July 21-25, 2014; August 4-8, 2014; and August 18-22, 2014

Inspection Procedure: IP 71111.21, "Component Design Bases Inspection"

Lead Inspector: Gerond A. George, Senior Reactor Inspector I. Information Requested Prior to Information Gathering Visit (July 8, 2014) The following information (Section I of this enclosure) should be sent to the Region IV office in hard copy or electronic format (compact disc or Certrec IMS preferred), to the attention of Gerond A. George, by June 23, 2014, to facilitate the reduction in the items

to be selected for a final list following the information gathering visit. The inspection

team will finalize the selected list during the prep week using the additional documents

requested in Section II of this enclosure. The specific items selected from the lists shall

be available and ready for review on the day indicated in this request. *Please provide requested documentation electronically in "pdf" files, Excel, or other searchable formats, if possible. The information should contain descriptive names, and be indexed and hyperlinked to facilitate ease of use. Information in "lists" should contain enough

information to be easily understood by someone who has knowledge of boiling water

reactor technology. If requested documents are large and only hard copy formats are available, please inform the inspector(s), and provide subject documentation during the first day of the onsite inspection. 1. An excel spreadsheet of equipment basic events (with definitions) including importance measures sorted by risk achievement worth (RAW) and Fussell-Vesely (FV) from your internal events probabilistic risk assessment (PRA). Include basic events with RAW value of 1.3 or greater. 2. Provide a list of the top 500 cut-sets from your PRA. 3. Copies of PRA "system notebooks," and the latest PRA summary document. 4. An excel spreadsheet of PRA human action basic events or risk ranking of operator actions from your site specific PSA sorted by RAW and FV. Provide copies of your human reliability worksheets for these items.

5. List of procedures used to accomplish operator actions associated with the basic events in your PRA. 6. A list of all time-critical operator actions in procedures. 7. If you have an external events or fire PSA model, provide the information requested in items 1-4 for external events and fire.

- 2 - Enclosure 8. Any pre-existing evaluation or list of components and associated calculations with low design margins, (i.e., pumps closest to the design limit for flow or pressure, diesel generator close to design required output, heat exchangers close to rated design heat removal, etc.).

9. List of high risk maintenance rule systems/components and functions; based on engineering or expert panel judgment.

10. Structure, system, and components in the Maintenance Rule (a)(1) category. 11. Site top 10 issues list. 12. A list of operating experience evaluations for the last 3 years. 13. List of any common-cause failure evaluation of components in the last 5 years. 14. List of root cause evaluations associated with component failures or design issues initiated/completed in the last 3 years. 15. A list of permanent and temporary modifications for the previous 3 years. 16. List of current "operator work arounds/burdens." 17. A copy of any internal/external self-assessments and associated corrective action documents generated in preparation for the inspection. 18. A copy of engineering/operations related audits completed in the last 2 years. 19. Current management and engineering organizational charts. 20. List of licensee contacts for the inspection team with pager or phone numbers. II. Information Requested to be Available on First Day of Preparation Week (July 14, 2014) 1. An electronic copy of the Design Bases Documents for the selected components. 2. An electronic copy of the System Health notebooks for the selected components. 3. List of condition reports (corrective action documents) associated with each of the selected components for the last 5 years. 4. The corrective maintenance history associated with each of the selected components for the last 5 years.

5. Copies of calculations associated with each of the selected components (if not previously provided), excluding data files. Please review the calculations and also provide copies of reference material (such as drawings, engineering requests, and

vendor letters).

6. Copies of operability evaluations associated with each of the selected components and plans for restoring operability, if applicable.

- 3 - Enclosure 7. Copies of selected operator work-around evaluations associated with each of the selected components and plans for resolution, if applicable. 8. Lists of any open temporary modifications associated with each of the selected components, if applicable.

9. Trend data on the selected electrical/mechanical components' performance for last 3 years (for example, pumps' performance including in-service testing, other vibration monitoring, oil sample results, etc., as applicable). 10. List of motor operated valves (MOVs) in the program, design margin and risk ranking.

11. List of air operated valves (AOVs) in the valve program, design and risk ranking. 12. Mechanical piping drawings for: * Engineered safety features * Emergency core cooling systems * Emergency diesel generators 13. Electrical one-line drawings for: * Offsite power/switchyard supplies * Normal AC power systems * Emergency AC/DC power systems including * 120VAC power, and * 125VDC/24VDC safety class systems III. Information Requested to be provided throughout the inspection. 1. Copies of any corrective action documents generated as a result of the team's questions or queries during this inspection.

2. Copies of the list of questions submitted by the team members and the status/resolution of the information requested (provide daily during the inspection to each team member).

3. Reference materials (available electronically and as needed during all onsite weeks): * General set of plant drawings * IPE/IPEEE/PRA report * Procurement documents for components selected * Plant procedures (normal, abnormal, emergency, surveillance, etc.) * Technical Specifications * Updated Final Safety Analysis Report * Vendor manuals

- 4 - Enclosure Inspector Contact Information:

Gerond A. George Senior Reactor Inspector (817)200-1562

Gerond.George@nrc.gov

Mailing Address: U.S. NRC, Region IV

Attn: Gerond A. George 1600 East Lamar Blvd.

Arlington, TX 76011-4511