{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 26, 2013 Vice President, Operations Entergy Nuclear Operations, Inc.
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 26, 2013 Vice President, Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 SUB..IECT:     INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1,2 AND 3 - REQUEST FOR ADDITIONAL INFORMATION RE: "PHYSICAL SECURITY, TRAINING AND QUALIFICATION, SAFEGUARDS CONTINGENCY PLAN, AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION SECURITY PROGRAM," REVISION 16
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 SUB..IECT:
INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1,2 AND 3 - REQUEST FOR ADDITIONAL INFORMATION RE: "PHYSICAL SECURITY, TRAINING AND QUALIFICATION, SAFEGUARDS CONTINGENCY PLAN, AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION SECURITY PROGRAM," REVISION 16  


==Dear Sir or Madam:==
==Dear Sir or Madam:==
 
By {{letter dated|date=May 29, 2013|text=letter dated May 29,2013}}, Entergy Operations, Inc., the licensee, submitted Revision 16 to the Indian Point Energy Center "Physical Security, Training and Qualification, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program." The Nuclear Regulatory Commission (NRC) staff is currently reviewing the changes to ensure that the licensee has complied with applicable regulatory requirements of Title 10 of the Code of Federal Regulations (10 CFR) 73, "Physical Protection of Plants and Material," and the provisions of 10 CFR 50.54(p)(2), which allows licensees to make changes without prior NRC approval.
By letter dated May 29,2013, Entergy Operations, Inc., the licensee, submitted Revision 16 to the Indian Point Energy Center "Physical Security, Training and Qualification, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program." The Nuclear Regulatory Commission (NRC) staff is currently reviewing the changes to ensure that the licensee has complied with applicable regulatory requirements of Title 10 of the Code of Federal Regulations (10 CFR) 73, "Physical Protection of Plants and Material," and the provisions of 10 CFR 50.54(p)(2), which allows licensees to make changes without prior NRC approval.
The NRC staff is reviewing the submittal and has determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). Based on our discussions we understand that a response to the RAI will be provided within 30 days of the date of this letter.
The NRC staff is reviewing the submittal and has determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). Based on our discussions we understand that a response to the RAI will be provided within 30 days of the date of this letter.
Please contact me at (301) 415-1364 if you have any questions on this issue.
Please contact me at (301) 415-1364 if you have any questions on this issue.
Sincerely,
Sincerely,  
                                            ~v~~
~v~~
Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-003, 50-247, and 50-286
Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-003, 50-247, and 50-286  


==Enclosure:==
==Enclosure:==
Request for Additional Information cc w/encl: Distribution via Listserv


Request for Additional Information cc w/encl: Distribution via Listserv
REQUEST FOR ADDITIONAL INFORMATION OFFICE OF NUCLEAR SECURITY AND INCIDENT RESPONSE 10 CFR SO.S4(p)(2) CHANGES TO SECURITY PLAN ENTERGY NUCLEAR OPERATIONS, INC INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1,2, AND 3 DOCKET NOS: SO-03, SO-247, and SO-286 By {{letter dated|date=May 29, 2013|text=letter dated May 29, 2013}} (Agencywide Documents Access and Management System Accession No. ML 131S6A006), Entergy Nuclear Operations, Inc. submitted the Indian Point Energy Center Physical Security Plan (PSP), Training and Qualification Plan (T&QP), and Safeguards Contingency Plan, Revision 16. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure. The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations (10 CFR), Section SO.S4(p)(2). The NRC staff has determined that the additional information requested below is needed to complete its review.
 
REQUEST FOR ADDITIONAL INFORMATION OFFICE OF NUCLEAR SECURITY AND INCIDENT RESPONSE 10 CFR SO.S4(p)(2) CHANGES TO SECURITY PLAN ENTERGY NUCLEAR OPERATIONS, INC INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1,2, AND 3 DOCKET NOS: SO-03, SO-247, and SO-286 By letter dated May 29, 2013 (Agencywide Documents Access and Management System Accession No. ML 131S6A006), Entergy Nuclear Operations, Inc. submitted the Indian Point Energy Center Physical Security Plan (PSP), Training and Qualification Plan (T&QP), and Safeguards Contingency Plan, Revision 16. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure. The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations (10 CFR), Section SO.S4(p)(2). The NRC staff has determined that the additional information requested below is needed to complete its review.
: 1. The description of changes report and Section 2.4 "Medical Examinations and Physical Fitness Qualifications," of the T&QP (Appendix B), discuss changes to the physical fitness test for strength, endurance, and agility. Describe how these changes continue to simulate, as closely as practicable, the specific conditions under which the individual shall be required to perform assigned duties and responsibilities. Additionally, describe what is worn by security force members during each aspect of this physical fitness test.
: 1. The description of changes report and Section 2.4 "Medical Examinations and Physical Fitness Qualifications," of the T&QP (Appendix B), discuss changes to the physical fitness test for strength, endurance, and agility. Describe how these changes continue to simulate, as closely as practicable, the specific conditions under which the individual shall be required to perform assigned duties and responsibilities. Additionally, describe what is worn by security force members during each aspect of this physical fitness test.
Lastly, confirm that appropriate changes will be made during the next revision of the site's security plans to clearly describe the physical fitness test.
Lastly, confirm that appropriate changes will be made during the next revision of the site's security plans to clearly describe the physical fitness test.
Line 40: Line 39:
Consistent with 10 CFR 73.SS(c)(4), "the licensee shall establish, maintain, implement, and follow a Training and Qualification Plan that describes how the criteria set forth in Appendix B to this part, 'General Criteria for Security Personnel' will be implemented."
Consistent with 10 CFR 73.SS(c)(4), "the licensee shall establish, maintain, implement, and follow a Training and Qualification Plan that describes how the criteria set forth in Appendix B to this part, 'General Criteria for Security Personnel' will be implemented."
Consistent with 10 CFR Part 73, Appendix B, VI. (A.)(S), "the licensee shall ensure that the training and qualification program simulates, as closely as practicable, the specific conditions under which the individual shall be required to perform assigned duties and responsibilities."
Consistent with 10 CFR Part 73, Appendix B, VI. (A.)(S), "the licensee shall ensure that the training and qualification program simulates, as closely as practicable, the specific conditions under which the individual shall be required to perform assigned duties and responsibilities."
Enclosure
Enclosure  


                                                - 2 Consistent with 10 CFR Part 73, Appendix B, VI. (B.)(4)(b)(3), "the physical fitness test must include physical attributes and performance objectives which demonstrate the strength, endurance, and agility, consistent with assigned duties in the Commission-approved security plans, licensee protective strategy, and implementing procedures during normal and emergency conditions."
- 2 Consistent with 10 CFR Part 73, Appendix B, VI. (B.)(4)(b)(3), "the physical fitness test must include physical attributes and performance objectives which demonstrate the strength, endurance, and agility, consistent with assigned duties in the Commission-approved security plans, licensee protective strategy, and implementing procedures during normal and emergency conditions."
: 2. The description of changes report and Section 9 "Security Personnel Equipment" of the PSP include a change to the personnel equipment list and associated annual requalification training on that equipment. The description of changes did not adequately describe the rationale for this change. Further describe the rationale for this change in issued equipment and associated annual requalification training, to include any supporting site-specific analyses. Describe whether or not it applies to all members of the security organization or particular positions within the security organization.
: 2. The description of changes report and Section 9 "Security Personnel Equipment" of the PSP include a change to the personnel equipment list and associated annual requalification training on that equipment. The description of changes did not adequately describe the rationale for this change. Further describe the rationale for this change in issued equipment and associated annual requalification training, to include any supporting site-specific analyses. Describe whether or not it applies to all members of the security organization or particular positions within the security organization.
Additionally, describe impacts, if any, to the site's use of force continuum.
Additionally, describe impacts, if any, to the site's use of force continuum.
Line 49: Line 48:
Consistent with 10 CFR 73.55(c)(4), "the licensee shall establish, maintain, and implement, and follow a Training and Qualification Plan that describes how the criteria set forth in Appendix B to this part, 'General Criteria for Security Personnel.' will be implemented."
Consistent with 10 CFR 73.55(c)(4), "the licensee shall establish, maintain, and implement, and follow a Training and Qualification Plan that describes how the criteria set forth in Appendix B to this part, 'General Criteria for Security Personnel.' will be implemented."
Consistent with 10 CFR Part 73, Appendix B, VI. (D.)(2.)(a), "armed and unarmed individuals shall be requalified at least annually in accordance with the requirements of this appendix and the Commission-approved training and qualification plan."
Consistent with 10 CFR Part 73, Appendix B, VI. (D.)(2.)(a), "armed and unarmed individuals shall be requalified at least annually in accordance with the requirements of this appendix and the Commission-approved training and qualification plan."
Consistent with 10 CFR Part 73, Appendix B, VI. (G.)(2.)(c)(3), "based on the licensee protective strategy and the specific duties and responsibilities assigned to each individual, the licensee should provide, as appropriate. but is not limited to, the following: (1) Flashlights and batteries; (2) Baton or other non-lethal weapons; (3) Handcuffs; (4) Binoculars; (5) Night vision aids (e.g. goggles, weapons sights); (6) Hand-fired illumination flares or equivalent; (7) Duress alarms."
Consistent with 10 CFR Part 73, Appendix B, VI. (G.)(2.)(c)(3), "based on the licensee protective strategy and the specific duties and responsibilities assigned to each individual, the licensee should provide, as appropriate. but is not limited to, the following: (1) Flashlights and batteries; (2) Baton or other non-lethal weapons; (3) Handcuffs; (4) Binoculars; (5) Night vision aids (e.g. goggles, weapons sights); (6) Hand-fired illumination flares or equivalent; (7) Duress alarms."  


August 26,2013 Vice President, Operations Entergy Nuclear Operations, Inc.
August 26,2013 Vice President, Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249  


==SUBJECT:==
==SUBJECT:==
INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1,2 AND 3 - REQUEST FOR ADDITIONAL INFORMATION RE: "PHYSICAL SECURITY, TRAINING AND QUALIFICATION, SAFEGUARDS CONTINGENCY PLAN, AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION SECURITY PROGRAM," REVISION 16
INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1,2 AND 3 - REQUEST FOR ADDITIONAL INFORMATION RE: "PHYSICAL SECURITY, TRAINING AND QUALIFICATION, SAFEGUARDS CONTINGENCY PLAN, AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION SECURITY PROGRAM," REVISION 16  


==Dear Sir or Madam:==
==Dear Sir or Madam:==
 
By {{letter dated|date=May 29, 2013|text=letter dated May 29,2013}}, Entergy Operations, Inc., the licensee, submitted Revision 16 to the Indian Point Energy Center "Physical Security, Training and Qualification, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program." The Nuclear Regulatory Commission (NRC) staff is currently reviewing the changes to ensure that the licensee has complied with applicable regulatory requirements of Title 10 of the Code of Federal Regulations (10 CFR) 73, "Physical Protection of Plants and Materia'," and the provisions of 10 CFR 50.54(p)(2), which allows licensees to make changes without prior NRC approval.
By letter dated May 29,2013, Entergy Operations, Inc., the licensee, submitted Revision 16 to the Indian Point Energy Center "Physical Security, Training and Qualification, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program." The Nuclear Regulatory Commission (NRC) staff is currently reviewing the changes to ensure that the licensee has complied with applicable regulatory requirements of Title 10 of the Code of Federal Regulations (10 CFR) 73, "Physical Protection of Plants and Materia'," and the provisions of 10 CFR 50.54(p)(2), which allows licensees to make changes without prior NRC approval.
The NRC staff is reviewing the submittal and has determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). Based on our discussions we understand that a response to the RAI will be provided within 30 days of the date of this letter.
The NRC staff is reviewing the submittal and has determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). Based on our discussions we understand that a response to the RAI will be provided within 30 days of the date of this letter.
Please contact me at (301) 415-1364 if you have any questions on this issue.
Please contact me at (301) 415-1364 if you have any questions on this issue.
Sincerely, IRA!
Sincerely, IRA!
Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor licenSing Office of Nuclear Reactor Regulation Docket Nos. 50-003, 50-247, and 50-286
Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor licenSing Office of Nuclear Reactor Regulation Docket Nos. 50-003, 50-247, and 50-286  


==Enclosure:==
==Enclosure:==
Request for Additional Information cc w/encl: Distribution via Listserv DISTRIBUTION:
Request for Additional Information cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC                               RidsNrrDorlLpl1-1               RidsNrrPMlndianPoint LPL1-1 Reading File                   RFelts, NSIR                     RidsNrrLAKGoldstein RidsAcrsAcnw_ MailCTR                 RidsNrrDorlDpr                   RidsRgn1 MailCenter ABurritt, R1                         DGordon, NSIR                   JCrockett, NSIR RCaldwell, NSIR ADAMS ACCESSION NO.: ML13221A043 PL1-1/PM           LPL 1-1/LA         RSLB/NSIR/BC                   LPL 1-1/BC(A)
PUBLIC RidsNrrDorlLpl1-1 RidsNrrPMlndianPoint LPL1-1 Reading File RFelts, NSIR RidsNrrLAKGoldstein RidsAcrsAcnw _ MailCTR RidsNrrDorlDpr RidsRgn1 MailCenter ABurritt, R1 DGordon, NSIR JCrockett, NSIR RCaldwell, NSIR ADAMS ACCESSION NO.: ML13221A043 PL1-1/PM LPL1-1/LA RSLB/NSIR/BC LPL 1-1/BC(A)
NAME       DPickett             KGoldstein         RCaldwell by memo dated       RBeali
NAME DPickett KGoldstein RCaldwell by memo dated RBeali  
. DATE       08/26/13             08/12/13           08/06/13                       08/26/13 OFFICIAL RECORD COpy}}
. DATE 08/26/13 08/12/13 08/06/13 08/26/13 OFFICIAL RECORD COpy}}

Latest revision as of 06:12, 11 January 2025

Request for Additional Information Physical Security, Training and Qualification, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program, Revision 16 - Indian Point Nuclear Generating Unit Nos. 1, 2 an
ML13221A043
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 08/26/2013
From: Pickett D
Plant Licensing Branch 1
To:
Entergy Nuclear Operations
Pickett D
References
Download: ML13221A043 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 26, 2013 Vice President, Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 SUB..IECT:

INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1,2 AND 3 - REQUEST FOR ADDITIONAL INFORMATION RE: "PHYSICAL SECURITY, TRAINING AND QUALIFICATION, SAFEGUARDS CONTINGENCY PLAN, AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION SECURITY PROGRAM," REVISION 16

Dear Sir or Madam:

By letter dated May 29,2013, Entergy Operations, Inc., the licensee, submitted Revision 16 to the Indian Point Energy Center "Physical Security, Training and Qualification, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program." The Nuclear Regulatory Commission (NRC) staff is currently reviewing the changes to ensure that the licensee has complied with applicable regulatory requirements of Title 10 of the Code of Federal Regulations (10 CFR) 73, "Physical Protection of Plants and Material," and the provisions of 10 CFR 50.54(p)(2), which allows licensees to make changes without prior NRC approval.

The NRC staff is reviewing the submittal and has determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). Based on our discussions we understand that a response to the RAI will be provided within 30 days of the date of this letter.

Please contact me at (301) 415-1364 if you have any questions on this issue.

Sincerely,

~v~~

Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.50-003, 50-247, and 50-286

Enclosure:

Request for Additional Information cc w/encl: Distribution via Listserv

REQUEST FOR ADDITIONAL INFORMATION OFFICE OF NUCLEAR SECURITY AND INCIDENT RESPONSE 10 CFR SO.S4(p)(2) CHANGES TO SECURITY PLAN ENTERGY NUCLEAR OPERATIONS, INC INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1,2, AND 3 DOCKET NOS: SO-03, SO-247, and SO-286 By letter dated May 29, 2013 (Agencywide Documents Access and Management System Accession No. ML 131S6A006), Entergy Nuclear Operations, Inc. submitted the Indian Point Energy Center Physical Security Plan (PSP), Training and Qualification Plan (T&QP), and Safeguards Contingency Plan, Revision 16. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure. The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations (10 CFR), Section SO.S4(p)(2). The NRC staff has determined that the additional information requested below is needed to complete its review.

1. The description of changes report and Section 2.4 "Medical Examinations and Physical Fitness Qualifications," of the T&QP (Appendix B), discuss changes to the physical fitness test for strength, endurance, and agility. Describe how these changes continue to simulate, as closely as practicable, the specific conditions under which the individual shall be required to perform assigned duties and responsibilities. Additionally, describe what is worn by security force members during each aspect of this physical fitness test.

Lastly, confirm that appropriate changes will be made during the next revision of the site's security plans to clearly describe the physical fitness test.

Regulatory Basis:

Consistent with 10 CFR 73.SS(c)(1 )(i), "licensee security plans must describe how the licensee will implement requirements of this section through the establishment and maintenance of a security organization, the use of security equipment and technology, the training and qualification of security personnel, the implementation of predetermined response plans and strategies, and the protection of digital computer and communication systems and networks."

Consistent with 10 CFR 73.SS(c)(4), "the licensee shall establish, maintain, implement, and follow a Training and Qualification Plan that describes how the criteria set forth in Appendix B to this part, 'General Criteria for Security Personnel' will be implemented."

Consistent with 10 CFR Part 73, Appendix B, VI. (A.)(S), "the licensee shall ensure that the training and qualification program simulates, as closely as practicable, the specific conditions under which the individual shall be required to perform assigned duties and responsibilities."

Enclosure

- 2 Consistent with 10 CFR Part 73, Appendix B, VI. (B.)(4)(b)(3), "the physical fitness test must include physical attributes and performance objectives which demonstrate the strength, endurance, and agility, consistent with assigned duties in the Commission-approved security plans, licensee protective strategy, and implementing procedures during normal and emergency conditions."

2. The description of changes report and Section 9 "Security Personnel Equipment" of the PSP include a change to the personnel equipment list and associated annual requalification training on that equipment. The description of changes did not adequately describe the rationale for this change. Further describe the rationale for this change in issued equipment and associated annual requalification training, to include any supporting site-specific analyses. Describe whether or not it applies to all members of the security organization or particular positions within the security organization.

Additionally, describe impacts, if any, to the site's use of force continuum.

Regulatory Basis:

Consistent with 10 CFR 73.55( c)(1 )(i), "licensee security plans must describe how the licensee will implement requirements of this section through the establishment and maintenance of a security organization, the use of security equipment and technology, the training and qualification of security personnel, the implementation of predetermined response plans and strategies, and the protection of digital computer and communication systems and networks."

Consistent with 10 CFR 73.55(c)(4), "the licensee shall establish, maintain, and implement, and follow a Training and Qualification Plan that describes how the criteria set forth in Appendix B to this part, 'General Criteria for Security Personnel.' will be implemented."

Consistent with 10 CFR Part 73, Appendix B, VI. (D.)(2.)(a), "armed and unarmed individuals shall be requalified at least annually in accordance with the requirements of this appendix and the Commission-approved training and qualification plan."

Consistent with 10 CFR Part 73, Appendix B, VI. (G.)(2.)(c)(3), "based on the licensee protective strategy and the specific duties and responsibilities assigned to each individual, the licensee should provide, as appropriate. but is not limited to, the following: (1) Flashlights and batteries; (2) Baton or other non-lethal weapons; (3) Handcuffs; (4) Binoculars; (5) Night vision aids (e.g. goggles, weapons sights); (6) Hand-fired illumination flares or equivalent; (7) Duress alarms."

August 26,2013 Vice President, Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249

SUBJECT:

INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1,2 AND 3 - REQUEST FOR ADDITIONAL INFORMATION RE: "PHYSICAL SECURITY, TRAINING AND QUALIFICATION, SAFEGUARDS CONTINGENCY PLAN, AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION SECURITY PROGRAM," REVISION 16

Dear Sir or Madam:

By letter dated May 29,2013, Entergy Operations, Inc., the licensee, submitted Revision 16 to the Indian Point Energy Center "Physical Security, Training and Qualification, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program." The Nuclear Regulatory Commission (NRC) staff is currently reviewing the changes to ensure that the licensee has complied with applicable regulatory requirements of Title 10 of the Code of Federal Regulations (10 CFR) 73, "Physical Protection of Plants and Materia'," and the provisions of 10 CFR 50.54(p)(2), which allows licensees to make changes without prior NRC approval.

The NRC staff is reviewing the submittal and has determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). Based on our discussions we understand that a response to the RAI will be provided within 30 days of the date of this letter.

Please contact me at (301) 415-1364 if you have any questions on this issue.

Sincerely, IRA!

Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor licenSing Office of Nuclear Reactor Regulation Docket Nos.50-003, 50-247, and 50-286

Enclosure:

Request for Additional Information cc w/encl: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsNrrDorlLpl1-1 RidsNrrPMlndianPoint LPL1-1 Reading File RFelts, NSIR RidsNrrLAKGoldstein RidsAcrsAcnw _ MailCTR RidsNrrDorlDpr RidsRgn1 MailCenter ABurritt, R1 DGordon, NSIR JCrockett, NSIR RCaldwell, NSIR ADAMS ACCESSION NO.: ML13221A043 PL1-1/PM LPL1-1/LA RSLB/NSIR/BC LPL 1-1/BC(A)

NAME DPickett KGoldstein RCaldwell by memo dated RBeali

. DATE 08/26/13 08/12/13 08/06/13 08/26/13 OFFICIAL RECORD COpy