ML19064B049: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 15: | Line 15: | ||
=Text= | =Text= | ||
{{#Wiki_filter:10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power | {{#Wiki_filter:10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Mihaela Biro, Reliability and Risk Analyst Stephen Dinsmore, Senior Reliability and Risk Analyst PRA Licensing Branch A, Division of Risk Assessment, NRR NEI Lessons-Learned Workshop, January 30 - 31, 2019 | ||
-Learned Workshop, January 30 | |||
-31, 2019 Chronology | Chronology July 2005 NEI 00-04 Nov 2004 50.69 SSC Promulgate Categorization 2002 10 CFR 50.69 Guideline South Texas Project Proof of Concept 2 | ||
*Voluntary alternative risk | |||
-informed rule | Chronology (Continued) | ||
*Determine safety significance of SSCs | Dec 2014 NRC SER on August 2012 Pilot LAR Vogtle Pilot May 2006 LAR Regulatory Guide 1.201 (Rev. 1) 3 | ||
-informed categorization process | |||
*Modify special treatment requirements for safety-related SSCs of low safety significance | 10 CFR 50.69 Overview | ||
*Must be performed for entire system(s) 10 CFR 50.69 | * Voluntary alternative risk-informed rule | ||
RISC- | * Determine safety significance of SSCs based on NRC approved risk-informed categorization process | ||
Special Treatment Can | * Modify special treatment requirements for safety-related SSCs of low safety significance | ||
* Must be performed for entire system(s) 4 | |||
10 CFR 50.69 Categorization RISC-1 RISC-2 Safety-Related, Non-Safety Related, Safety Significant Safety Significant RISC-3 RISC-4 Safety-Related, Non-Safety Related, Low Safety Significant Low Safety Significant 5 | |||
)6 Robust Categorization | Special Treatment Can Be Modified for Low Safety Significant SSCs | ||
-making Panel (IDP) | * Reporting (10 CFR Part 21) | ||
*Final decisions using PRA insights and non-PRA aspects*Highly experienced plant personnel with combined expertise in: PRA, Safety Analysis, Operations,Design and System Engineering | * Quality assurance (10 CFR 50 Appendix B) | ||
*Guidance describes a well-defined, highly structured process*Cannot change certain SSC | * Environmental qualification (10 CFR 50.49) | ||
*Documentation | * Certain containment leakage testing requirements (10 CFR 50 Appendix J) | ||
-Review of peer review findings and disposition | * Seismic qualification (10 CFR 100 App A) | ||
-PRA assumptions and sources of | * Maintenance rule (10 CFR 50.65) 6 | ||
8 Setting the Stage for Effective Staff Review*Well established regulatory basis by rule*Endorsed guidance: NEI 00-04, RG 1.201*Pilot completed 3 years prior to new | |||
*LAR Template; industry pre | Robust Categorization Process Integrated Decision-making PRA / Risk Analyses Panel (IDP) Non-PRA Internal | ||
-review*NRC acceptance reviews | * Final decisions using PRA Events insights and non-PRA aspects Qualitative Fire | ||
*Early identification of deviations 9 | * Highly experienced plant Questions personnel with combined expertise in: PRA, Safety Seismic Analysis, Operations, Design Defense in Other External and System Engineering Depth Events | ||
* Guidance describes a well-Sensitivity defined, highly structured Studies process Periodic Pressure | |||
* Cannot change certain SSC Review and Boundary HSS categorization Update Failures | |||
* Documentation requirements 7 | |||
NRC Staff LAR Review Scope Technical acceptability of PRA models (e.g. internal events, fire, seismic) | |||
- Review of peer review findings and disposition | |||
- PRA assumptions and sources of uncertainty External events treatment without PRA Categorization process Categorization results and alternative treatment not reviewed during LAR review; subject to inspection. | |||
8 | |||
Setting the Stage for Effective Staff Review | |||
* Well established regulatory basis by rule | |||
* Endorsed guidance: NEI 00-04, RG 1.201 | |||
* Pilot completed 3 years prior to new applications | |||
* LAR Template; industry pre-review | |||
* NRC acceptance reviews | |||
* Early identification of deviations 9 | |||
50.69 Review Effort Commensurate with Scope of the PRA | 50.69 Review Effort Commensurate with Scope of the PRA | ||
*Review heavily impacted by PRA acceptability | * Review heavily impacted by PRA acceptability | ||
*LARs of increased PRA scope require more NRC review hours but afford increased flexibility Number of SSCs for Alternative | * LARs of increased PRA scope require more NRC review hours but afford increased flexibility Number of SSCs for Alternative NRC Treatment Review Time Licensee Operational Flexibility Internal + Fire + External Events Events Risk Assessment (PRA) Scope 1 0 | ||
*Outdated PRA peer reviews using older guidance | Level of PRA Acceptability Depends on the Application 4b, Risk-Informed Completion Times NFPA-805, Risk-Informed Fire Acceptability Protection | ||
*Complex sequence of gap assessment(s) and focused scope peer review(s) | * Greater reliance on Required scope, PRA level of detail, | ||
*Incomplete list of F&Os or associated dispositions | * More flexibility for technical 50.69 SSC Categorization licensee robustness, and | ||
*Outdated F&Os | * More complex staff plant review representation 5b, Risk-Informed Surveillance Frequencies Risk-Informed Inservice Inspection 1 | ||
*PRA upgrades not identified or not peer reviewed | 1 | ||
*F&O closure not following NRC accepted process | |||
*Ongoing PRA changes performed during the NRC review (e.g.: parallel risk | Challenges to Effective NRC Review of PRA Acceptability | ||
-informed applications for NFPA-805 and 50.69; not addressing implementation items from previously approved LARs) 1 2 NRC Acceptance Review Process LIC-109 *Goals of the acceptance review process are to:-facilitate submittal of acceptable LARs-reduce unnecessary review delays | * Outdated PRA peer reviews using older guidance | ||
-efficiently use review resources | * Complex sequence of gap assessment(s) and focused scope peer review(s) | ||
*LAR is found acceptable for review if the application | * Incomplete list of F&Os or associated dispositions | ||
-contains scope and depth of necessary technical information | * Outdated F&Os | ||
-can support NRC | * PRA upgrades not identified or not peer reviewed | ||
*Example items that resulted in non accept with opportunity to supplement determination | * F&O closure not following NRC accepted process | ||
* Ongoing PRA changes performed during the NRC review (e.g.: parallel risk-informed applications for NFPA-805 and 50.69; not addressing implementation items from previously approved LARs) 1 2 | |||
-Unclear scope of peer reviews | |||
-Unclear scope of PRA | NRC Acceptance Review Process LIC-109 | ||
-F&O closure conducted prior to the May 3, 2017 NRC acceptance | * Goals of the acceptance review process are to: | ||
-Incomplete or no dispositions for multiple F&Os or uncertainties | - facilitate submittal of acceptable LARs | ||
-No description of key assumptions and sources of uncertainties | - reduce unnecessary review delays | ||
-Lack of sufficient safety justification for deviations from guidance or approved precedent | - efficiently use review resources | ||
*Lack of detail slowed down review | * LAR is found acceptable for review if the application | ||
-First few LARs after pilot did not describe process, stated that guidance in NEI 00-04 will be followed | - contains scope and depth of necessary technical information | ||
-Process was first reviewed for the pilot Vogtle application | - can support NRC staffs completion of detailed technical review in appropriate time frame 1 | ||
-Staff found certain aspects of the guidance could be open to interpretations | 3 | ||
*Initial audits reviewed categorization process, sampled categorization results and observed a mock IDP*RAI requested a summary of the process | |||
-Describe order of process, what categorization can be changed by IDP, how the IDP will use qualitative | NRC Acceptance Review Process Increases Review Efficiency | ||
*Example: categorization of pressure | * Example items that resulted in non accept with opportunity to supplement determination: | ||
-retaining items | - Incomplete or outdated peer reviews | ||
-Many LARs requested applying passive component methodology to Class 1 pressure retaining items | - Unclear scope of peer reviews | ||
-Pilot approved it for Class 2 and 3 | - Unclear scope of PRA | ||
-Staff requested additional justification because | - F&O closure conducted prior to the May 3, 2017 NRC acceptance | ||
*Class 1 SSCs constitute principal fission product barrier*Consequence of pressure boundary failure for Class 1 SSCs may be different than for Class 2 and Class 3-Had the potential to slow down all 50.69 | - Incomplete or no dispositions for multiple F&Os or uncertainties | ||
*NEI 00-04 has specific guidance of treatment of other external hazards, Figure 5 | - No description of key assumptions and sources of uncertainties | ||
-6 1 7 Treatment of Other External Hazards | - Lack of sufficient safety justification for deviations 1 | ||
*LARs generally silent on addressing NEI 00 | from guidance or approved precedent 4 | ||
-04, Figure 5-6 guidance; state that other external hazards (e.g. high winds, external flooding, etc.) were screened from applicability; LARs provide summary of screening results | |||
*RAIs requested licensee to: | Categorization Process Review | ||
-Justify screening for each hazard; LAR summary sometimes was unclear | * Lack of detail slowed down review | ||
-Identify and justify any SSCs credited for screening | - First few LARs after pilot did not describe process, stated that guidance in NEI 00-04 will be followed | ||
-Confirm NEI 00 | - Process was first reviewed for the pilot Vogtle application | ||
-04 Figure 5 | - Staff found certain aspects of the guidance could be open to interpretations | ||
-6 will be applied | * Initial audits reviewed categorization process, sampled categorization results and observed a mock IDP | ||
*i.e. SSCs would be HSS, if screened scenario(s) would become | * RAI requested a summary of the process | ||
*PRA credit for Westinghouse RCP Shutdown Seals consistent with NRC safety evaluation for PWROG-14001-P, Revision 1 (ML17200A116 | - Describe order of process, what categorization can be changed by IDP, how the IDP will use qualitative questions RAI response incorporated into later LAR template; facilitates expedited review 1 5 | ||
-1855*Other external hazards treatment consistent with NEI 00-04 guidance | LAR Deviations Lead to Inefficient Review | ||
* | * Deviations from guidance or approved precedent slow down reviews | ||
-04 guidance and approved precedents 1 9 Audits Improve Review Efficiency | * Example: categorization of pressure-retaining items | ||
*Audits support improved staff understanding, more effective RAIs and safety evaluations | - Many LARs requested applying passive component methodology to Class 1 pressure retaining items | ||
*On site, or virtual with electronic portal and teleconference | - Pilot approved it for Class 2 and 3 | ||
*50.69 Audits:-Early audits verified categorization process | - Staff requested additional justification because | ||
-Observed mock IDP | * Class 1 SSCs constitute principal fission product barrier | ||
-Electronic audits of F&O Closure reports-Virtual audits for later reviews 2 0 PRA Acceptability to Support Effective Staff Review | * Consequence of pressure boundary failure for Class 1 SSCs may be different than for Class 2 and Class 3 | ||
*PRA readiness heavily impacts review schedule*Stable PRA at time of submittal improves efficiency | - Had the potential to slow down all 50.69 reviews Request withdrawn by industry which facilitated timely completion of many LARs 1 6 | ||
-Current peer reviews following accepted peer review guidance-Use of Independent Assessment F&O closure consistent with NRC accepted process | |||
*Complete dispositions of open F&Os and key sources of uncertainty | Treatment of Other External Hazards | ||
-Justify why there is no impact on the categorization, or | * NEI 00-04 has specific guidance of treatment of other external hazards, Figure 5-6 1 | ||
-Commit to fix the PRA, or | 7 | ||
-Describe and justify sensitivity studies to be performed during categorization (NEI 00 | |||
-04, Section 5) 2 1 Key Assumptions and Sources of Uncertainty Guidance | Treatment of Other External Hazards | ||
*RG 1.200, Determining PRA Technical Adequacy | * LARs generally silent on addressing NEI 00-04, Figure 5-6 guidance; state that other external hazards (e.g. | ||
-Staff review focused on key assumptions and F&Os-NUREG-1855 provides guidance on identifying and evaluating key assumptions | high winds, external flooding, etc.) were screened from applicability; LARs provide summary of screening results | ||
*NEI 00-04, 10 CFR 50.69 SSC Categorization Guidelines | * RAIs requested licensee to: | ||
-SSCs categorized though a series of steps, ending with an aggregate risk increase assessment | - Justify screening for each hazard; LAR summary sometimes was unclear | ||
-Includes | - Identify and justify any SSCs credited for screening | ||
-Address the impact of key assumptions on the categorization through the | - Confirm NEI 00-04 Figure 5-6 will be applied | ||
-1855*List of generic assumptions | * i.e. SSCs would be HSS, if screened scenario(s) would become unscreened Addressing issues upfront in LAR expedites review 1 8 | ||
-EPRI TR-1016737 (internal events) | |||
-EPRI TR-1026511 (fire, external events) | Addressing Known Common Issues Upfront Expedites Staff Review Examples: | ||
*Each assumption evaluated to determine if a different reasonable alternative assumption would produce different results (i.e., Key assumption) | * PRA credit for FLEX address May 30, 2017 memo (ML17031A269) | ||
*Three options after impact of key assumption known | * PRA credit for Westinghouse RCP Shutdown Seals consistent with NRC safety evaluation for PWROG-14001-P, Revision 1 (ML17200A116) | ||
-redefine the application, or | * Process for reviewing key assumptions and sources of uncertainty consistent with NUREG-1855 | ||
-refine the Probabilistic Risk Assessment, or | * Other external hazards treatment consistent with NEI 00-04 guidance | ||
-use compensatory measures or performance monitoring requirements | * Categorization process consistent with NEI 00-04 guidance and approved precedents 1 9 | ||
-1855 Need to | Audits Improve Review Efficiency | ||
-Learned Workshop, January 30 | * Audits support improved staff understanding, more effective RAIs and safety evaluations | ||
-31, 2019 Discussion Topics | * On site, or virtual with electronic portal and teleconference | ||
*Technical acceptability of external hazards PRAs | * 50.69 Audits: | ||
-Addressing staff comments on NEI 12 Addressing internal events F&Os | - Early audits verified categorization process | ||
-Differences between Addenda A and B of ASME/ANS PRA Standard for SPRAs | - Observed mock IDP | ||
*Use of external hazards PRAs for categorization | - Electronic audits of F&O Closure reports | ||
-Calculations of importance measures- | - Virtual audits for later reviews 2 | ||
-Key assumptions and sources of uncertainty | 0 | ||
-Performance monitoring | |||
*Proposed alternative seismic approach 1 | PRA Acceptability to Support Effective Staff Review | ||
Addressing Staff Comments on NEI 12-13*Staff accepted NEI 12 | * PRA readiness heavily impacts review schedule | ||
-13 (ADAMS ML18025C025) with clarifications and exceptions including | * Stable PRA at time of submittal improves efficiency | ||
-Identification of review of | - Current peer reviews following accepted peer review guidance | ||
-Qualifications of the peer review team | - Use of Independent Assessment F&O closure consistent with NRC accepted process | ||
-Use of UAMs-Use of expert judgement | * Complete dispositions of open F&Os and key sources of uncertainty | ||
-Review of any supporting requirement against CC I-Performing "in | - Justify why there is no impact on the categorization, or | ||
-process" peer review (i.e., separate peer review for each external hazard technical element | - Commit to fix the PRA, or | ||
- Describe and justify sensitivity studies to be performed during categorization (NEI 00-04, Section 5) 2 1 | |||
-review 2 Addressing Internal Events PRA F&Os | |||
*External hazards PRAs are usually built using the IEPRA as the base | Key Assumptions and Sources of Uncertainty Guidance | ||
*Important to ensure acceptability of IEPRA used as the base for external hazards PRAs | * RG 1.200, Determining PRA Technical Adequacy | ||
-Finding may not impact certain applications of IEPRA model, but may impact external hazards | - Staff review focused on key assumptions and F&Os | ||
-Resolutions may not have been propagated to external hazards PRAs-Resolution of finding in IEPRA may be different from what was propagated to other PRAs at time of development | - NUREG-1855 provides guidance on identifying and evaluating key assumptions | ||
*Beneficial to have explicit consideration of IEPRA acceptability in self-assessment as well as peer review for external hazards PRAs 3 | * NEI 00-04, 10 CFR 50.69 SSC Categorization Guidelines | ||
- SSCs categorized though a series of steps, ending with an aggregate risk increase assessment | |||
- Includes applicable sensitivity studies for each PRA, as needed | |||
* RG 1.201 endorses NEI 00-04 | |||
- Key assumptions identified via peer reviews or self assessment | |||
- Address the impact of key assumptions on the categorization through the applicable sensitivity studies 2 2 | |||
Key Assumptions and Sources of Uncertainty Guidance NUREG-1855 | |||
* List of generic assumptions | |||
- EPRI TR-1016737 (internal events) | |||
- EPRI TR-1026511 (fire, external events) | |||
* Each assumption evaluated to determine if a different reasonable alternative assumption would produce different results (i.e., Key assumption) | |||
* Three options after impact of key assumption known | |||
- redefine the application, or | |||
- refine the Probabilistic Risk Assessment, or | |||
- use compensatory measures or performance monitoring requirements. | |||
* Challenges encountered with these evaluations 2 | |||
3 | |||
All Stages of NUREG-1855 Need to Be Addressed 2 | |||
4 | |||
Observations on Consideration of External Hazards Risk in 50.69 Mehdi Reisi-Fard, Team Leader Shilp Vasavada, Reliability and Risk Analyst Risk Informed Licensing Initiatives Team, DRA, NRR NEI Lessons-Learned Workshop, January 30 - 31, 2019 | |||
Discussion Topics | |||
* Technical acceptability of external hazards PRAs | |||
- Addressing staff comments on NEI 12-13 | |||
- Addressing internal events F&Os | |||
- Differences between Addenda A and B of ASME/ANS PRA Standard for SPRAs | |||
* Use of external hazards PRAs for categorization | |||
- Calculations of importance measures | |||
- Mapping of components in external hazard PRAs | |||
- Key assumptions and sources of uncertainty | |||
- Performance monitoring | |||
* Proposed alternative seismic approach 1 | |||
Addressing Staff Comments on NEI 12-13 | |||
* Staff accepted NEI 12-13 (ADAMS ML18025C025) with clarifications and exceptions including | |||
- Identification of review of newly developed methods | |||
- Qualifications of the peer review team | |||
- Use of UAMs | |||
- Use of expert judgement | |||
- Review of any supporting requirement against CC I | |||
- Performing "in-process" peer review (i.e., separate peer review for each external hazard technical element) | |||
* Beneficial to include explicit discussion of consideration of staff comments during performance of the peer-review 2 | |||
Addressing Internal Events PRA F&Os | |||
* External hazards PRAs are usually built using the IEPRA as the base | |||
* Important to ensure acceptability of IEPRA used as the base for external hazards PRAs | |||
- Finding may not impact certain applications of IEPRA model, but may impact external hazards | |||
- Resolutions may not have been propagated to external hazards PRAs | |||
- Resolution of finding in IEPRA may be different from what was propagated to other PRAs at time of development | |||
* Beneficial to have explicit consideration of IEPRA acceptability in self-assessment as well as peer review for external hazards PRAs 3 | |||
Use of Addendum B in Licensing Applications | Use of Addendum B in Licensing Applications | ||
*Staff endorsed EPRI report 1025287, known as SPID, for use in developing SPRAs to respond to the 10 CFR 50.54(f) letter | * Staff endorsed EPRI report 1025287, known as SPID, for use in developing SPRAs to respond to the 10 CFR 50.54(f) letter | ||
*SPID cites Part 5 of 2013 version of ASME/ANS PRA Standard (Addendum B) | * SPID cites Part 5 of 2013 version of ASME/ANS PRA Standard (Addendum B) | ||
-Peer reviews of seismic PRAs performed against Addendum B | - Peer reviews of seismic PRAs performed against Addendum B | ||
-Addendum B has not been endorsed for use in licensing activities | - Addendum B has not been endorsed for use in licensing activities | ||
* | * Gap assessment of differences between SPRA SRs in Addenda A and B needed (example: ADAMS ML17192A245) | ||
*Staff accepted Code Case to Part 5 of Addendum B with comments (ADAMS ML18017A964) 4 Calculation of Importance Measures | * Staff accepted Code Case to Part 5 of Addendum B with comments (ADAMS ML18017A964) 4 | ||
*Calculation of importance measures from external hazard PRAs is not as straightforward as that for internal events: | |||
-Discretize the hazard curve into | Calculation of Importance Measures | ||
-specific failure modes for components in addition to random failures | * Calculation of importance measures from external hazard PRAs is not as straightforward as that for internal events: | ||
*Staff approved approaches submitted in recent LARs to calculate F | - Discretize the hazard curve into bins for quantification purposes | ||
-V and RAW from external hazard PRAs (example: ADAMS ML18180A062 | - Include hazard-specific failure modes for components in addition to random failures | ||
* Staff approved approaches submitted in recent LARs to calculate F-V and RAW from external hazard PRAs 5 | |||
*External hazard PRAs include SSCs and failure modes that may not be modeled in other PRA models | (example: ADAMS ML18180A062) | ||
*SSCs or failure modes can be mapped to components that are modeled (e.g. considered as part of the | |||
-component | Mapping of Components | ||
*If SSCs are determined to be HSS from the external hazard PRAs and mapping cannot be performed | * External hazard PRAs include SSCs and failure modes that may not be modeled in other PRA models | ||
-Integrated importance measure may be determined, or | * SSCs or failure modes can be mapped to components that are modeled (e.g. considered as part of the super-component boundary) | ||
-SSC can conservatively assumed to be HSS and presented as such to the IDP for categorization. | * If SSCs are determined to be HSS from the external hazard PRAs and mapping cannot be performed | ||
6 Key Assumptions and Sources of Uncertainty | - Integrated importance measure may be determined, or | ||
*RG 1.200: | - SSC can conservatively assumed to be HSS and presented as such to the IDP for categorization. | ||
*An effective approach for identification and disposition of key assumptions and sources of uncertainty includes | 6 | ||
-Compilation all assumptions used across technical elements (i.e., hazard, fragility, and plant response) | |||
-Use of RG 1.200 definition and NUREG | Key Assumptions and Sources of Uncertainty | ||
-1855 guidance to identify key assumptions and sources of uncertainty | * RG 1.200: the applicant identifies the key assumptions [] | ||
-Disposition of the identified key assumptions using qualitative or quantitative (i.e., sensitivity studies) means on an application | relevant to that application. This will be used to identify sensitivity studies | ||
-specific basis 7 | * An effective approach for identification and disposition of key assumptions and sources of uncertainty includes | ||
- Compilation all assumptions used across technical elements (i.e., | |||
hazard, fragility, and plant response) | |||
- Use of RG 1.200 definition and NUREG-1855 guidance to identify key assumptions and sources of uncertainty | |||
- Disposition of the identified key assumptions using qualitative or quantitative (i.e., sensitivity studies) means on an application-specific basis 7 | |||
Performance Monitoring | Performance Monitoring | ||
*10 CFR 50.69(e) requires performance monitoring and | * 10 CFR 50.69(e) requires performance monitoring and feedback loop | ||
* | * Risk Sensitivity Study in NEI 00-04 guidance used to evaluate the risk implications of changes in special treatment | ||
-04 guidance used to evaluate the risk implications of changes in special treatment*Consideration of external hazard (e.g., seismically | * Consideration of external hazard (e.g., seismically-induced) failure modes not explicitly addressed in guidance | ||
-induced) failure modes not explicitly addressed in guidance*Factor of 3 to 5 increase in unreliability due to change in special treatment is not considered applicable to such failure modes based on existing information 8 | * Factor of 3 to 5 increase in unreliability due to change in special treatment is not considered applicable to such failure modes based on existing information 8 | ||
Performance Monitoring ( | |||
*Existing or enhanced programs and processes along with PRA configuration control should demonstrate the | Performance Monitoring (Contd) | ||
*Programs and processes unaffected by categorization | * Existing or enhanced programs and processes along with PRA configuration control should demonstrate the feedback loop | ||
*Design change control process with enhancement for seismic impact assessment, aging management, and degradation monitoring | * Programs and processes unaffected by categorization | ||
*PRA configuration control expected to capture potential degradations during life of the program | * Design change control process with enhancement for seismic impact assessment, aging management, and degradation monitoring | ||
*Above examples of performance monitoring are applicable after categorization 34 | * PRA configuration control expected to capture potential degradations during life of the program | ||
*Industry proposed an alternative approach | * Above examples of performance monitoring are applicable after categorization 9 34 | ||
-Three-tiered approach for plants with low, medium and high seismic hazard/margin | |||
-Seismic insights from four sensitivity studies used to claim that most seismic risk significant SSCs are identified by internal events and/or fire PRAs*NRC has discussed technical issues in public meetings | Proposed Alternative Seismic Approach | ||
*A lead plant has recently submitted Tier 1 of the approach; Second lead plant expected to submit Tier 2 of the approach* | * Subset of plants do not have SPRA or SMA | ||
-31, 2019 Effective and Efficient Reviews | * Industry proposed an alternative approach | ||
*Reviewing a process not a product | - Three-tiered approach for plants with low, medium and high seismic hazard/margin | ||
-Technical staff observation of IDP | - Seismic insights from four sensitivity studies used to claim that most seismic risk significant SSCs are identified by internal events and/or fire PRAs | ||
*Work with NEI to provide comments on model LAR | * NRC has discussed technical issues in public meetings | ||
*LAR pre-flight screening by NEI | * A lead plant has recently submitted Tier 1 of the approach; Second lead plant expected to submit Tier 2 of the approach 1 | ||
*Interface with NEI to resolve common issues and provide NRC staff feedback during the development of new approaches | 35 | ||
*Staggering LARs with deviations from guidance or proposing new approaches | * Staffs review is ongoing 0 | ||
*Allowing pilot reviews to complete before submitting other LARs 1 | |||
Observations on Consideration of External Hazards Risk in 50.69 Ed Miller, Project Manager Special Projects & Processes Branch, Division of Operating Reactor Licensing, NRR NEI Lessons-Learned Workshop, January 30 - 31, 2019 | |||
Effective and Efficient Reviews | |||
* Reviewing a process not a product | |||
- Technical staff observation of IDP | |||
* Work with NEI to provide comments on model LAR | |||
* LAR pre-flight screening by NEI | |||
* Interface with NEI to resolve common issues and provide NRC staff feedback during the development of new approaches | |||
* Staggering LARs with deviations from guidance or proposing new approaches | |||
* Allowing pilot reviews to complete before submitting other LARs 1 | |||
LAR Preparation | LAR Preparation | ||
*LAR template facilitates consistency | * LAR template facilitates consistency | ||
-Recognition that one size | - Recognition that one size cant fit all | ||
*Open communication | * Open communication | ||
-Pre-application meetings | - Pre-application meetings | ||
-Address deviations from, or exceptions to, model LAR*Industry review prior to submittal | - Address deviations from, or exceptions to, model LAR | ||
-Avoiding repeat RAIs | * Industry review prior to submittal | ||
*Submit mature LARs | - Avoiding repeat RAIs | ||
-License conditions to resolve issues following approval of the LAR add to review complexity | * Submit mature LARs | ||
*Stagger non | - License conditions to resolve issues following approval of the LAR add to review complexity | ||
-standard LARs 2 | * Stagger non-standard LARs 2 | ||
LAR Review | LAR Review | ||
*Acceptance review discipline | * Acceptance review discipline | ||
*Existing tools can be heavily leveraged | * Existing tools can be heavily leveraged | ||
-Information portals | - Information portals | ||
-Audits-Public meetings | - Audits | ||
*Coordination of reviewers | - Public meetings | ||
-A goal, but not always possible | * Coordination of reviewers | ||
*Integrated review teams 3 | - A goal, but not always possible | ||
* Integrated review teams 3 | |||
10 CFR 50.69 Review Status | 10 CFR 50.69 Review Status | ||
*20 applications for 50.69 received* | * 20 applications for 50.69 received Risk Informed Licensing Actions | ||
* 8 completed (includes 2 for Vogtle) 100 87 | |||
-805 review | * 9 under review; 3 withdrawn 90 80 79 70 TMRE 60 NTTF R2.1 50 41 50.69 40 Misc 30 20 AOT 10 TSTF-0 505, 4B FY16 FY17 FY18 1 High Winds, External Flooding PRA 2 Tied to NFPA-805 review 4 3 Lead plant for new seismic approach | ||
Conclusions | Conclusions | ||
*NRC and stakeholders have established an effective LAR application and review process*Ongoing coordination and communication with industry is critical to maintaining efficiency | * NRC and stakeholders have established an effective LAR application and review process | ||
*Minimizing deviations and providing high quality LARs supports review efficiency Acronyms*ADAMS -Agencywide Documents Access and Management System | * Ongoing coordination and communication with industry is critical to maintaining efficiency | ||
*ANS -American Nuclear Society | * Minimizing deviations and providing high quality LARs supports review efficiency | ||
*ASME -American Society of Mechanical Engineers | |||
*CC -Capability Category | Acronyms | ||
*F&Os -Facts and Observations (PRA)*F-V -Fussell-Vesely*HSS -High Safety Significant | * ADAMS - Agencywide Documents | ||
*IDP -Integrated Decision | * NFPA-805 Access and Management System | ||
-making Panel*IEPRA -Internal Events PRA*LAR -License Amendment Request | * PRA - Probabilistic Risk Assessment | ||
*LIC-109 -NRC Licensing Procedure | * ANS - American Nuclear Society | ||
* RAI - Request for Additional | |||
* ASME - American Society of Information Mechanical Engineers | |||
* RAW - Risk Achievement Worth | |||
* CC - Capability Category | |||
* RCP - Reactor Coolant Pump | |||
* F&Os - Facts and Observations | |||
* RG - Regulatory Guide (PRA) | |||
* RISC - Risk-informed Safety Class | |||
* F-V - Fussell-Vesely | |||
* SER - Safety Evaluation Report | |||
*UAM - | * HSS - High Safety Significant | ||
* SSCs - Structures, Systems and | |||
* IDP - Integrated Decision-making Components Panel | |||
* SPID - Screening, Prioritization and | |||
* IEPRA - Internal Events PRA Implementation Details, EPRI Report | |||
* LAR - License Amendment Request 1025287 | |||
* LIC-109 - NRC Licensing Procedure | |||
* SR - Supporting Requirement for Acceptance Review | |||
* UAM - Unreviewed Analysis Method | |||
* NEI - Nuclear Energy Institute}} |
Revision as of 23:32, 19 October 2019
ML19064B049 | |
Person / Time | |
---|---|
Issue date: | 01/30/2019 |
From: | Mihaela Biro, Stephen Dinsmore NRC/NRR/DRA/APLA |
To: | |
References | |
Download: ML19064B049 (42) | |
Text
10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Mihaela Biro, Reliability and Risk Analyst Stephen Dinsmore, Senior Reliability and Risk Analyst PRA Licensing Branch A, Division of Risk Assessment, NRR NEI Lessons-Learned Workshop, January 30 - 31, 2019
Chronology July 2005 NEI 00-04 Nov 2004 50.69 SSC Promulgate Categorization 2002 10 CFR 50.69 Guideline South Texas Project Proof of Concept 2
Chronology (Continued)
Dec 2014 NRC SER on August 2012 Pilot LAR Vogtle Pilot May 2006 LAR Regulatory Guide 1.201 (Rev. 1) 3
10 CFR 50.69 Overview
- Voluntary alternative risk-informed rule
- Determine safety significance of SSCs based on NRC approved risk-informed categorization process
- Modify special treatment requirements for safety-related SSCs of low safety significance
- Must be performed for entire system(s) 4
10 CFR 50.69 Categorization RISC-1 RISC-2 Safety-Related, Non-Safety Related, Safety Significant Safety Significant RISC-3 RISC-4 Safety-Related, Non-Safety Related, Low Safety Significant Low Safety Significant 5
Special Treatment Can Be Modified for Low Safety Significant SSCs
- Reporting (10 CFR Part 21)
- Quality assurance (10 CFR 50 Appendix B)
- Environmental qualification (10 CFR 50.49)
- Certain containment leakage testing requirements (10 CFR 50 Appendix J)
- Seismic qualification (10 CFR 100 App A)
- Maintenance rule (10 CFR 50.65) 6
Robust Categorization Process Integrated Decision-making PRA / Risk Analyses Panel (IDP) Non-PRA Internal
- Final decisions using PRA Events insights and non-PRA aspects Qualitative Fire
- Highly experienced plant Questions personnel with combined expertise in: PRA, Safety Seismic Analysis, Operations, Design Defense in Other External and System Engineering Depth Events
- Guidance describes a well-Sensitivity defined, highly structured Studies process Periodic Pressure
- Documentation requirements 7
NRC Staff LAR Review Scope Technical acceptability of PRA models (e.g. internal events, fire, seismic)
- Review of peer review findings and disposition
- PRA assumptions and sources of uncertainty External events treatment without PRA Categorization process Categorization results and alternative treatment not reviewed during LAR review; subject to inspection.
8
Setting the Stage for Effective Staff Review
- Well established regulatory basis by rule
- Pilot completed 3 years prior to new applications
- LAR Template; industry pre-review
- Early identification of deviations 9
50.69 Review Effort Commensurate with Scope of the PRA
- Review heavily impacted by PRA acceptability
- LARs of increased PRA scope require more NRC review hours but afford increased flexibility Number of SSCs for Alternative NRC Treatment Review Time Licensee Operational Flexibility Internal + Fire + External Events Events Risk Assessment (PRA) Scope 1 0
Level of PRA Acceptability Depends on the Application 4b, Risk-Informed Completion Times NFPA-805, Risk-Informed Fire Acceptability Protection
- Greater reliance on Required scope, PRA level of detail,
- More flexibility for technical 50.69 SSC Categorization licensee robustness, and
- More complex staff plant review representation 5b, Risk-Informed Surveillance Frequencies Risk-Informed Inservice Inspection 1
1
Challenges to Effective NRC Review of PRA Acceptability
- Outdated PRA peer reviews using older guidance
- Complex sequence of gap assessment(s) and focused scope peer review(s)
- Incomplete list of F&Os or associated dispositions
- Outdated F&Os
- PRA upgrades not identified or not peer reviewed
- F&O closure not following NRC accepted process
- Ongoing PRA changes performed during the NRC review (e.g.: parallel risk-informed applications for NFPA-805 and 50.69; not addressing implementation items from previously approved LARs) 1 2
NRC Acceptance Review Process LIC-109
- Goals of the acceptance review process are to:
- facilitate submittal of acceptable LARs
- reduce unnecessary review delays
- efficiently use review resources
- LAR is found acceptable for review if the application
- contains scope and depth of necessary technical information
- can support NRC staffs completion of detailed technical review in appropriate time frame 1
3
NRC Acceptance Review Process Increases Review Efficiency
- Example items that resulted in non accept with opportunity to supplement determination:
- Incomplete or outdated peer reviews
- Unclear scope of peer reviews
- Unclear scope of PRA
- F&O closure conducted prior to the May 3, 2017 NRC acceptance
- Incomplete or no dispositions for multiple F&Os or uncertainties
- No description of key assumptions and sources of uncertainties
- Lack of sufficient safety justification for deviations 1
from guidance or approved precedent 4
Categorization Process Review
- Lack of detail slowed down review
- First few LARs after pilot did not describe process, stated that guidance in NEI 00-04 will be followed
- Process was first reviewed for the pilot Vogtle application
- Staff found certain aspects of the guidance could be open to interpretations
- Initial audits reviewed categorization process, sampled categorization results and observed a mock IDP
- RAI requested a summary of the process
- Describe order of process, what categorization can be changed by IDP, how the IDP will use qualitative questions RAI response incorporated into later LAR template; facilitates expedited review 1 5
LAR Deviations Lead to Inefficient Review
- Deviations from guidance or approved precedent slow down reviews
- Example: categorization of pressure-retaining items
- Many LARs requested applying passive component methodology to Class 1 pressure retaining items
- Pilot approved it for Class 2 and 3
- Staff requested additional justification because
- Class 1 SSCs constitute principal fission product barrier
- Consequence of pressure boundary failure for Class 1 SSCs may be different than for Class 2 and Class 3
- Had the potential to slow down all 50.69 reviews Request withdrawn by industry which facilitated timely completion of many LARs 1 6
Treatment of Other External Hazards
- NEI 00-04 has specific guidance of treatment of other external hazards, Figure 5-6 1
7
Treatment of Other External Hazards
- LARs generally silent on addressing NEI 00-04, Figure 5-6 guidance; state that other external hazards (e.g.
high winds, external flooding, etc.) were screened from applicability; LARs provide summary of screening results
- RAIs requested licensee to:
- Justify screening for each hazard; LAR summary sometimes was unclear
- Identify and justify any SSCs credited for screening
- Confirm NEI 00-04 Figure 5-6 will be applied
- i.e. SSCs would be HSS, if screened scenario(s) would become unscreened Addressing issues upfront in LAR expedites review 1 8
Addressing Known Common Issues Upfront Expedites Staff Review Examples:
- PRA credit for FLEX address May 30, 2017 memo (ML17031A269)
- PRA credit for Westinghouse RCP Shutdown Seals consistent with NRC safety evaluation for PWROG-14001-P, Revision 1 (ML17200A116)
- Process for reviewing key assumptions and sources of uncertainty consistent with NUREG-1855
- Other external hazards treatment consistent with NEI 00-04 guidance
- Categorization process consistent with NEI 00-04 guidance and approved precedents 1 9
Audits Improve Review Efficiency
- Audits support improved staff understanding, more effective RAIs and safety evaluations
- On site, or virtual with electronic portal and teleconference
- 50.69 Audits:
- Early audits verified categorization process
- Observed mock IDP
- Electronic audits of F&O Closure reports
- Virtual audits for later reviews 2
0
PRA Acceptability to Support Effective Staff Review
- PRA readiness heavily impacts review schedule
- Stable PRA at time of submittal improves efficiency
- Current peer reviews following accepted peer review guidance
- Use of Independent Assessment F&O closure consistent with NRC accepted process
- Complete dispositions of open F&Os and key sources of uncertainty
- Justify why there is no impact on the categorization, or
- Commit to fix the PRA, or
- Describe and justify sensitivity studies to be performed during categorization (NEI 00-04, Section 5) 2 1
Key Assumptions and Sources of Uncertainty Guidance
- Staff review focused on key assumptions and F&Os
- NUREG-1855 provides guidance on identifying and evaluating key assumptions
- NEI 00-04, 10 CFR 50.69 SSC Categorization Guidelines
- SSCs categorized though a series of steps, ending with an aggregate risk increase assessment
- Includes applicable sensitivity studies for each PRA, as needed
- Key assumptions identified via peer reviews or self assessment
- Address the impact of key assumptions on the categorization through the applicable sensitivity studies 2 2
Key Assumptions and Sources of Uncertainty Guidance NUREG-1855
- List of generic assumptions
- EPRI TR-1016737 (internal events)
- EPRI TR-1026511 (fire, external events)
- Each assumption evaluated to determine if a different reasonable alternative assumption would produce different results (i.e., Key assumption)
- Three options after impact of key assumption known
- redefine the application, or
- refine the Probabilistic Risk Assessment, or
- use compensatory measures or performance monitoring requirements.
- Challenges encountered with these evaluations 2
3
All Stages of NUREG-1855 Need to Be Addressed 2
4
Observations on Consideration of External Hazards Risk in 50.69 Mehdi Reisi-Fard, Team Leader Shilp Vasavada, Reliability and Risk Analyst Risk Informed Licensing Initiatives Team, DRA, NRR NEI Lessons-Learned Workshop, January 30 - 31, 2019
Discussion Topics
- Technical acceptability of external hazards PRAs
- Addressing staff comments on NEI 12-13
- Addressing internal events F&Os
- Differences between Addenda A and B of ASME/ANS PRA Standard for SPRAs
- Use of external hazards PRAs for categorization
- Calculations of importance measures
- Mapping of components in external hazard PRAs
- Key assumptions and sources of uncertainty
- Performance monitoring
- Proposed alternative seismic approach 1
Addressing Staff Comments on NEI 12-13
- Staff accepted NEI 12-13 (ADAMS ML18025C025) with clarifications and exceptions including
- Identification of review of newly developed methods
- Qualifications of the peer review team
- Use of UAMs
- Use of expert judgement
- Review of any supporting requirement against CC I
- Performing "in-process" peer review (i.e., separate peer review for each external hazard technical element)
- Beneficial to include explicit discussion of consideration of staff comments during performance of the peer-review 2
Addressing Internal Events PRA F&Os
- External hazards PRAs are usually built using the IEPRA as the base
- Important to ensure acceptability of IEPRA used as the base for external hazards PRAs
- Finding may not impact certain applications of IEPRA model, but may impact external hazards
- Resolutions may not have been propagated to external hazards PRAs
- Resolution of finding in IEPRA may be different from what was propagated to other PRAs at time of development
- Beneficial to have explicit consideration of IEPRA acceptability in self-assessment as well as peer review for external hazards PRAs 3
Use of Addendum B in Licensing Applications
- Staff endorsed EPRI report 1025287, known as SPID, for use in developing SPRAs to respond to the 10 CFR 50.54(f) letter
- Peer reviews of seismic PRAs performed against Addendum B
- Addendum B has not been endorsed for use in licensing activities
- Gap assessment of differences between SPRA SRs in Addenda A and B needed (example: ADAMS ML17192A245)
- Staff accepted Code Case to Part 5 of Addendum B with comments (ADAMS ML18017A964) 4
Calculation of Importance Measures
- Calculation of importance measures from external hazard PRAs is not as straightforward as that for internal events:
- Discretize the hazard curve into bins for quantification purposes
- Include hazard-specific failure modes for components in addition to random failures
- Staff approved approaches submitted in recent LARs to calculate F-V and RAW from external hazard PRAs 5
(example: ADAMS ML18180A062)
Mapping of Components
- SSCs or failure modes can be mapped to components that are modeled (e.g. considered as part of the super-component boundary)
- Integrated importance measure may be determined, or
- SSC can conservatively assumed to be HSS and presented as such to the IDP for categorization.
6
Key Assumptions and Sources of Uncertainty
- RG 1.200: the applicant identifies the key assumptions []
relevant to that application. This will be used to identify sensitivity studies
- An effective approach for identification and disposition of key assumptions and sources of uncertainty includes
- Compilation all assumptions used across technical elements (i.e.,
hazard, fragility, and plant response)
- Use of RG 1.200 definition and NUREG-1855 guidance to identify key assumptions and sources of uncertainty
- Disposition of the identified key assumptions using qualitative or quantitative (i.e., sensitivity studies) means on an application-specific basis 7
Performance Monitoring
- 10 CFR 50.69(e) requires performance monitoring and feedback loop
- Risk Sensitivity Study in NEI 00-04 guidance used to evaluate the risk implications of changes in special treatment
- Consideration of external hazard (e.g., seismically-induced) failure modes not explicitly addressed in guidance
- Factor of 3 to 5 increase in unreliability due to change in special treatment is not considered applicable to such failure modes based on existing information 8
Performance Monitoring (Contd)
- Existing or enhanced programs and processes along with PRA configuration control should demonstrate the feedback loop
- Programs and processes unaffected by categorization
- Design change control process with enhancement for seismic impact assessment, aging management, and degradation monitoring
- PRA configuration control expected to capture potential degradations during life of the program
- Above examples of performance monitoring are applicable after categorization 9 34
Proposed Alternative Seismic Approach
- Industry proposed an alternative approach
- Three-tiered approach for plants with low, medium and high seismic hazard/margin
- Seismic insights from four sensitivity studies used to claim that most seismic risk significant SSCs are identified by internal events and/or fire PRAs
- NRC has discussed technical issues in public meetings
- A lead plant has recently submitted Tier 1 of the approach; Second lead plant expected to submit Tier 2 of the approach 1
35
- Staffs review is ongoing 0
Observations on Consideration of External Hazards Risk in 50.69 Ed Miller, Project Manager Special Projects & Processes Branch, Division of Operating Reactor Licensing, NRR NEI Lessons-Learned Workshop, January 30 - 31, 2019
Effective and Efficient Reviews
- Reviewing a process not a product
- Technical staff observation of IDP
- Work with NEI to provide comments on model LAR
- LAR pre-flight screening by NEI
- Interface with NEI to resolve common issues and provide NRC staff feedback during the development of new approaches
- Staggering LARs with deviations from guidance or proposing new approaches
- Allowing pilot reviews to complete before submitting other LARs 1
LAR Preparation
- LAR template facilitates consistency
- Recognition that one size cant fit all
- Open communication
- Pre-application meetings
- Address deviations from, or exceptions to, model LAR
- Industry review prior to submittal
- Avoiding repeat RAIs
- Submit mature LARs
- License conditions to resolve issues following approval of the LAR add to review complexity
- Stagger non-standard LARs 2
LAR Review
- Acceptance review discipline
- Existing tools can be heavily leveraged
- Information portals
- Audits
- Public meetings
- Coordination of reviewers
- A goal, but not always possible
- Integrated review teams 3
10 CFR 50.69 Review Status
- 20 applications for 50.69 received Risk Informed Licensing Actions
- 8 completed (includes 2 for Vogtle) 100 87
- 9 under review; 3 withdrawn 90 80 79 70 TMRE 60 NTTF R2.1 50 41 50.69 40 Misc 30 20 AOT 10 TSTF-0 505, 4B FY16 FY17 FY18 1 High Winds, External Flooding PRA 2 Tied to NFPA-805 review 4 3 Lead plant for new seismic approach
Conclusions
- NRC and stakeholders have established an effective LAR application and review process
- Ongoing coordination and communication with industry is critical to maintaining efficiency
- Minimizing deviations and providing high quality LARs supports review efficiency
- ADAMS - Agencywide Documents
- NFPA-805 Access and Management System
- ANS - American Nuclear Society
- RAI - Request for Additional
- ASME - American Society of Information Mechanical Engineers
- RAW - Risk Achievement Worth
- CC - Capability Category
- RCP - Reactor Coolant Pump
- F&Os - Facts and Observations
- RISC - Risk-informed Safety Class
- F-V - Fussell-Vesely
- SER - Safety Evaluation Report
- HSS - High Safety Significant
- SSCs - Structures, Systems and
- IDP - Integrated Decision-making Components Panel
- SPID - Screening, Prioritization and
- LAR - License Amendment Request 1025287
- LIC-109 - NRC Licensing Procedure
- SR - Supporting Requirement for Acceptance Review
- UAM - Unreviewed Analysis Method
- NEI - Nuclear Energy Institute