PNO-II-97-006A, on 970129,plant Shutdown Due to Primary Pressure Boundary Leakage Update.Licensee Continuing to Cold Shutdown Conditions to Perform Addl Corrective Maint Activities.Resident Inspectors Monitoring Repair Actions: Difference between revisions

From kanterella
Jump to navigation Jump to search
StriderTol Bot change
StriderTol Bot change
 
(One intermediate revision by the same user not shown)
Line 1: Line 1:
#REDIRECT [[PNO-II-97-006, on 970129,Unit 1 Declared Notice of Unusual Event for Reactor Coolant Pressure Boundary Leakage,As Defined in TS 3.4.4.Resident Inspectors on Site Monitoring Licensee Actions.State of Ga Notified]]
{{Adams
| number = ML20134B631
| issue date = 01/30/1997
| title = PNO-II-97-006A:on 970129,plant Shutdown Due to Primary Pressure Boundary Leakage Update.Licensee Continuing to Cold Shutdown Conditions to Perform Addl Corrective Maint Activities.Resident Inspectors Monitoring Repair Actions
| author name = Carrion R
| author affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
| addressee name =
| addressee affiliation =
| docket = 05000321
| license number =
| contact person =
| document report number = PNO-II-97-006A, PNO-II-97-6A, NUDOCS 9701300248
| document type = PRELIMINARY NOTIFICATION OF EVENT OR OCCURRENCE (PNO,, TEXT-INSPECTION & AUDIT & I&E CIRCULARS
| page count = 1
}}
{{#Wiki_filter:-
v January 30, 1997 PRELmm_Y NOTIFICATION OF avasu OR unuw=1 OCCUMmCE PNO-II 0 0 6A l Thic preliminary notification constitutes EARLY notice of events of POSSIBLE l cofoty or public interest significance. The information is as initially l rocsived without verification or evaluation, and is basically all that is known by Region II staff in Atlanta, Georgia on this date.
Facility Licensee Emeraency Classification l Giorgia Power Co.
Notification of Unusual Event
! Hntch 1 Alert l Bcxlcy, Georgia Site Area Emergency l Docksts: 50-321 General Emergency X Not Applicable Subjsct:
PLANT SHUTDOWN DUE TO PRIMARY PRESSURE BOUNDARY LEAKAGE - UPDATE 1
This is an update to the PN issued on January 29, 1997, which reported j
the plant shutdown due to primary system pressure boundary leakage.
The licensee has completed weld repairs to the three-quarter inch vent line cnd the line has been returned to service.
The licensee terminated the Notification of Unusual Event at 7:25 a.m. on January 30.
The licensee is continuing to cold shutdown conditions to perform additional corrsetive maintenance activities.
They are scheduled to return to power operations approximately 12:00 noon on February 1, 1997.
The licensee reported that a local radio station expressed interest but tha licensee still does not plan to issue a press release.
1 The resident inspectors have been monitoring the licensee's repair actions and plant status control during the repair and root cause annlysis.
Tha State of Georgia has been notified.
This information is current as of 1:00 p.m. on January 30, 1997.
 
==Contact:==
R. CARRION (404)331-0345 l
I 9701300248 970130 PDR I&E PNO-II-97-006A PDR
\\
\\\\
D\\
. - _ _ _}}
 
{{PNO-Nav|region=II}}

Latest revision as of 06:48, 12 December 2024

PNO-II-97-006A:on 970129,plant Shutdown Due to Primary Pressure Boundary Leakage Update.Licensee Continuing to Cold Shutdown Conditions to Perform Addl Corrective Maint Activities.Resident Inspectors Monitoring Repair Actions
ML20134B631
Person / Time
Site: Hatch 
Issue date: 01/30/1997
From: Robert Carrion
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
References
PNO-II-97-006A, PNO-II-97-6A, NUDOCS 9701300248
Download: ML20134B631 (1)


-

v January 30, 1997 PRELmm_Y NOTIFICATION OF avasu OR unuw=1 OCCUMmCE PNO-II 0 0 6A l Thic preliminary notification constitutes EARLY notice of events of POSSIBLE l cofoty or public interest significance. The information is as initially l rocsived without verification or evaluation, and is basically all that is known by Region II staff in Atlanta, Georgia on this date.

Facility Licensee Emeraency Classification l Giorgia Power Co.

Notification of Unusual Event

! Hntch 1 Alert l Bcxlcy, Georgia Site Area Emergency l Docksts: 50-321 General Emergency X Not Applicable Subjsct:

PLANT SHUTDOWN DUE TO PRIMARY PRESSURE BOUNDARY LEAKAGE - UPDATE 1

This is an update to the PN issued on January 29, 1997, which reported j

the plant shutdown due to primary system pressure boundary leakage.

The licensee has completed weld repairs to the three-quarter inch vent line cnd the line has been returned to service.

The licensee terminated the Notification of Unusual Event at 7:25 a.m. on January 30.

The licensee is continuing to cold shutdown conditions to perform additional corrsetive maintenance activities.

They are scheduled to return to power operations approximately 12:00 noon on February 1, 1997.

The licensee reported that a local radio station expressed interest but tha licensee still does not plan to issue a press release.

1 The resident inspectors have been monitoring the licensee's repair actions and plant status control during the repair and root cause annlysis.

Tha State of Georgia has been notified.

This information is current as of 1:00 p.m. on January 30, 1997.

Contact:

R. CARRION (404)331-0345 l

I 9701300248 970130 PDR I&E PNO-II-97-006A PDR

\\

\\\\

D\\

. - _ _ _