ML082620687: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 2: Line 2:
| number = ML082620687
| number = ML082620687
| issue date = 09/16/2008
| issue date = 09/16/2008
| title = Exelon'S Public Meeting Slides for Byron Regulatory Conference - 9/16/2008
| title = Exelons Public Meeting Slides for Byron Regulatory Conference - 9/16/2008
| author name =  
| author name =  
| author affiliation = Exelon Nuclear
| author affiliation = Exelon Nuclear
Line 17: Line 17:
{{#Wiki_filter:Byron Station Regulatory Conference Unit 2 Inadvertent Entry Into An Elevated Risk Condition September 16, 2008
{{#Wiki_filter:Byron Station Regulatory Conference Unit 2 Inadvertent Entry Into An Elevated Risk Condition September 16, 2008


Agenda 9 Introduction                     D. Hoots 9 Finding and Root Cause Evaluation B. Adams 9 Operations Actions               S. Fruin 9 Risk Assessment                   G. Krueger 9 Conclusion                       B. Adams 2
2 Agenda 9 Introduction D. Hoots 9 Finding and Root Cause Evaluation B. Adams 9 Operations Actions S. Fruin 9 Risk Assessment G. Krueger 9 Conclusion B. Adams  


Introduction David Hoots Site Vice President
Introduction David Hoots Site Vice President


Introduction 9 Provide information regarding the event, root cause evaluation and corrective actions taken 9 Provide insights gained from risk significance determination process evaluation 9 Provide information as to our ability to carry out mitigating actions in a timely manner 9 Provide additional technical information requested by NRC August 14, 2008 letter 9 Provide information indicating that credit for Operation actions is appropriate 4
4 Introduction 9 Provide information regarding the event, root cause evaluation and corrective actions taken 9 Provide insights gained from risk significance determination process evaluation 9 Provide information as to our ability to carry out mitigating actions in a timely manner 9 Provide additional technical information requested by NRC {{letter dated|date=August 14, 2008|text=August 14, 2008 letter}} 9 Provide information indicating that credit for Operation actions is appropriate


Finding and Root Cause Evaluation Brad Adams Plant Manager
Finding and Root Cause Evaluation Brad Adams Plant Manager


Finding 9 Potentially Greater Than Green Finding
6 Finding 9 Potentially Greater Than Green Finding
* Apparent violation of 10 CFR 50.65(a)(4)
* Apparent violation of 10 CFR 50.65(a)(4)
* Failure to perform an updated risk evaluation prior to surveillance testing of the Unit 1 Train A Emergency Diesel Generator (EDG) based on existing plant conditions
* Failure to perform an updated risk evaluation prior to surveillance testing of the Unit 1 Train A Emergency Diesel Generator (EDG) based on existing plant conditions
* Resulted in inadvertently entering an elevated risk condition on Unit 2 due to degraded internal flood mitigation capability 6
* Resulted in inadvertently entering an elevated risk condition on Unit 2 due to degraded internal flood mitigation capability  


Essential Service Water (SX)
7 Essential Service Water (SX)
System Information 9 Provides cooling water to safety related components 9 Two trains per unit with mechanical draft cooling towers providing the ultimate heat sink 9 Valves 1SX033 and 1SX034 are Unit 1 train cross-tie discharge isolation valves for the 1A and 1B SX trains 9 Valves 1SX033 and 1SX034 are located on 330 elevation in the Auxiliary Building 7
System Information 9 Provides cooling water to safety related components 9 Two trains per unit with mechanical draft cooling towers providing the ultimate heat sink 9 Valves 1SX033 and 1SX034 are Unit 1 train cross-tie discharge isolation valves for the 1A and 1B SX trains 9 Valves 1SX033 and 1SX034 are located on 330 elevation in the Auxiliary Building


Event Background 9 Replacement of 1SX034 scheduled during Unit 1 spring 2008 refueling outage 9 Part of material condition improvement project to replace SX system butterfly valves 9 Two clearance orders generated for electrical and mechanical isolation of 1SX033 9 During clearance order placement, valve 1SX033 was electrically closed to support work on 1SX034 8
8 Event Background 9 Replacement of 1SX034 scheduled during Unit 1 spring 2008 refueling outage 9 Part of material condition improvement project to replace SX system butterfly valves 9 Two clearance orders generated for electrical and mechanical isolation of 1SX033 9 During clearance order placement, valve 1SX033 was electrically closed to support work on 1SX034


Event Timeline 9 March 28, 2008
9 Event Timeline 9 March 28, 2008
* Risk configuration assessment conducted to support work on 1SX034
* Risk configuration assessment conducted to support work on 1SX034
* Leak-by noted and an attempt to manually close 1SX033 to reduce leak-by performed
* Leak-by noted and an attempt to manually close 1SX033 to reduce leak-by performed
* During manual operation of 1SX033, an abnormal noise heard from the valve actuator, which prompted the decision to conduct troubleshooting on the actuator 9
* During manual operation of 1SX033, an abnormal noise heard from the valve actuator, which prompted the decision to conduct troubleshooting on the actuator


Event Timeline (cont.)
10 Event Timeline (cont.)
9 April 1, 2008
9 April 1, 2008
* Revision to the risk assessment performed to cover the 1SX033 troubleshooting and potential repair 9 April 2, 2008
* Revision to the risk assessment performed to cover the 1SX033 troubleshooting and potential repair 9 April 2, 2008
* 1SX033 and 1SX034 were left in the closed position and electrically de-energized to support the troubleshooting on 1SX033 9 April 4, 2008
* 1SX033 and 1SX034 were left in the closed position and electrically de-energized to support the troubleshooting on 1SX033 9 April 4, 2008
* The outage schedule contained a task to perform a clearance order to electrically open 1SX033 and manually open 1SX034 to support (1A EDG) testing
* The outage schedule contained a task to perform a clearance order to electrically open 1SX033 and manually open 1SX034 to support (1A EDG) testing
* However, the scheduled task could not be executed as written because, both valves were maintained in the closed position, electrically de-energized and incapable of opening from the main control room 10
* However, the scheduled task could not be executed as written because, both valves were maintained in the closed position, electrically de-energized and incapable of opening from the main control room


Event Timeline (cont.)
11 Event Timeline (cont.)
9 April 5, 2008, at 02:19
9 April 5, 2008, at 02:19
* Equipment Status Tags (ESTs) were hung on valves 1SX033 and 1SX034 9 April 5, 2008, at 03:04
* Equipment Status Tags (ESTs) were hung on valves 1SX033 and 1SX034 9 April 5, 2008, at 03:04
* To support EDG testing, both 1SX033 and 1SX034 valves were opened manually
* To support EDG testing, both 1SX033 and 1SX034 valves were opened manually
* This configuration change was not evaluated for Unit 2 on-line risk impact 9 April 6, 2008
* This configuration change was not evaluated for Unit 2 on-line risk impact 9 April 6, 2008
* During Work Control Cycle Manager review of risk configurations for the next week, the configuration change was recognized as a potential risk impact and the Station Risk Engineer was consulted 11
* During Work Control Cycle Manager review of risk configurations for the next week, the configuration change was recognized as a potential risk impact and the Station Risk Engineer was consulted


Event Timeline (cont.)
12 Event Timeline (cont.)
9 April 6, 2008
9 April 6, 2008
* At 16:52, based on input from the Station Risk Engineer and Work Control Cycle Manager, Operations declared Unit 2 on-line risk to be Orange due to 1SX033 and 1SX034 being unable to close from the main control room
* At 16:52, based on input from the Station Risk Engineer and Work Control Cycle Manager, Operations declared Unit 2 on-line risk to be Orange due to 1SX033 and 1SX034 being unable to close from the main control room
* At 17:12, operator stationed at valve 1SX033 and Unit 2 on-line risk was evaluated as being Green (38 hours)
* At 17:12, operator stationed at valve 1SX033 and Unit 2 on-line risk was evaluated as being Green (38 hours)
* At 21:24, 1SX034 was manually closed (42.3 hours) 12
* At 21:24, 1SX034 was manually closed (42.3 hours)


Root Cause Evaluation 9 Root Cause
13 Root Cause Evaluation 9 Root Cause
* Less than adequate Operations ownership of on-line risk process when plant configuration changed 9 Contributing Causes
* Less than adequate Operations ownership of on-line risk process when plant configuration changed 9 Contributing Causes
* Less than adequate training provided for work groups which led to a lack of knowledge of configuration risk management
* Less than adequate training provided for work groups which led to a lack of knowledge of configuration risk management
* Work Management procedural guidance associated with configuration risk management lacked specificity
* Work Management procedural guidance associated with configuration risk management lacked specificity
* Equipment difficulty associated with emergent work on 1SX033                                                 13
* Equipment difficulty associated with emergent work on 1SX033


Root Cause Evaluation (cont.)
14 Root Cause Evaluation (cont.)
9 Organizational and Programmatic Issues
9 Organizational and Programmatic Issues
* Less than adequate site awareness of Auxiliary Building internal flooding with respect to processes and procedures
* Less than adequate site awareness of Auxiliary Building internal flooding with respect to processes and procedures
* Limited management oversight of configuration risk management process 14
* Limited management oversight of configuration risk management process


Immediate Corrective Actions 9 Performance management performed for personnel involved in event 9 Increased awareness provided for risk management reviews
15 Immediate Corrective Actions 9 Performance management performed for personnel involved in event 9 Increased awareness provided for risk management reviews
* Formal Standing Order issued to the Operations Shift
* Formal Standing Order issued to the Operations Shift
* Clear expectations for ownership communicated to all Operations Shift Managers by the Shift Operations Superintendent 15
* Clear expectations for ownership communicated to all Operations Shift Managers by the Shift Operations Superintendent


Interim Corrective Action to Prevent Recurrence (CAPR) 9 Developed and implemented Byron-specific revisions to Exelon CAP and Online Work Control Process procedures to include expectations and clear guidance for Operations Shift Management roles and responsibilities regarding risk management
16 Interim Corrective Action to Prevent Recurrence (CAPR) 9 Developed and implemented Byron-specific revisions to Exelon CAP and Online Work Control Process procedures to include expectations and clear guidance for Operations Shift Management roles and responsibilities regarding risk management
* Specific guidance on the use of Paragon risk program
* Specific guidance on the use of Paragon risk program
* Specific guidance for review of the Risk Summary Sheet that Work Management generates
* Specific guidance for review of the Risk Summary Sheet that Work Management generates
* Specific guidance for communications
* Specific guidance for communications
* The change management process is being utilized to incorporate this interim action prior to the upcoming refueling outage 16
* The change management process is being utilized to incorporate this interim action prior to the upcoming refueling outage  


Corrective Actions 9 CAPR - Revise the corporate procedures (CAP and Online Work Control Process) to include
17 Corrective Actions 9 CAPR - Revise the corporate procedures (CAP and Online Work Control Process) to include
* Specific guidance on the use of Paragon risk program
* Specific guidance on the use of Paragon risk program
* Specific guidance for review of the Risk Summary Sheet that Work Management generates
* Specific guidance for review of the Risk Summary Sheet that Work Management generates
* Specific guidance for communications
* Specific guidance for communications
* Responsible - Operations           Due 11/19/08 17
* Responsible - Operations Due 11/19/08


Additional Corrective Actions 9 Perform and document observations, including targeted observations during the refueling outage
18 Additional Corrective Actions 9 Perform and document observations, including targeted observations during the refueling outage
* Perform periodic roll-ups of the observations 9 Used the Systematic Approach to Training (SAT) process to include enhanced training in the 1st quarter, 2009 licensed operator requalification training 18
* Perform periodic roll-ups of the observations 9 Used the Systematic Approach to Training (SAT) process to include enhanced training in the 1st quarter, 2009 licensed operator requalification training  


Summary 9 Lessons Learned
19 Summary 9 Lessons Learned
* Did not maintain proper Operations focus for evaluating risk when conditions changed Primarily focused on Technical Specifications applicability
* Did not maintain proper Operations focus for evaluating risk when conditions changed Primarily focused on Technical Specifications applicability
* Improvements needed in teamwork between site groups to assure focus includes evaluating risk
* Improvements needed in teamwork between site groups to assure focus includes evaluating risk
* Going forward Performance management has been applied Procedures have been improved Training program is being strengthened Progress is being monitored 19
* Going forward Performance management has been applied Procedures have been improved Training program is being strengthened Progress is being monitored


Operator Actions Scott Fruin Shift Operations Superintendent
Operator Actions Scott Fruin Shift Operations Superintendent


Procedures/Training 9 Prior to the event, an abnormal operating procedure existed (1/2 BOA PRI-7) that dealt with mitigation of SX system leakage 9 Alarm response procedures existed for responding to Auxiliary Building sump alarms 21
21 Procedures/Training 9 Prior to the event, an abnormal operating procedure existed (1/2 BOA PRI-7) that dealt with mitigation of SX system leakage 9 Alarm response procedures existed for responding to Auxiliary Building sump alarms  


Procedures/Training 9 Identification and isolation of components is a skill of the operators 9 Training was provided previously on flood mitigation in licensed operator requalification training
22 Procedures/Training 9 Identification and isolation of components is a skill of the operators 9 Training was provided previously on flood mitigation in licensed operator requalification training
* 2008 - SX leak on supply to 0A VC Chiller
* 2008 - SX leak on supply to 0A VC Chiller
* 2007 - SX header break between 1SX004 and 1SX007
* 2007 - SX header break between 1SX004 and 1SX007
* 2005 - SX pump suction leak
* 2005 - SX pump suction leak
* 2003 - SX header break between 1SX004 and 1SX007 9 Use of drawings to identify isolation points, for clearance and tagging, is a common task used routinely by Operations personnel 22
* 2003 - SX header break between 1SX004 and 1SX007 9 Use of drawings to identify isolation points, for clearance and tagging, is a common task used routinely by Operations personnel


Procedures/Training 9 Two new procedures were developed for flooding prior to the event to support a recent license amendment
23 Procedures/Training 9 Two new procedures were developed for flooding prior to the event to support a recent license amendment
* Abnormal operating procedure (0BOA PRI-8)
* Abnormal operating procedure (0BOA PRI-8)
* Operating Procedure (BOP SX-22)
* Operating Procedure (BOP SX-22)
Line 111: Line 111:
* 14 of 28 Reactor Operators
* 14 of 28 Reactor Operators
* 23 of 36 Senior Reactor Operators
* 23 of 36 Senior Reactor Operators
* Both shifts had personnel that received the training prior the event 23
* Both shifts had personnel that received the training prior the event


Procedures/Training 9 Post outage, a tabletop scenario was developed and administered to Operations personnel 9 Six operators were evaluated and all were able to diagnose the source of the leak and identify actions to take within a short period of time (within an hour)
24 Procedures/Training 9 Post outage, a tabletop scenario was developed and administered to Operations personnel 9 Six operators were evaluated and all were able to diagnose the source of the leak and identify actions to take within a short period of time (within an hour)
* Personnel utilized various tools including their plant knowledge, training, drawings and procedures to complete the scenario 24
* Personnel utilized various tools including their plant knowledge, training, drawings and procedures to complete the scenario


Procedures/Training 9 Conclusions of the table tops -
25 Procedures/Training 9 Conclusions of the table tops -
* Personnel were confident that they could get to, and isolate the necessary equipment within a short period of time (within an hour)
* Personnel were confident that they could get to, and isolate the necessary equipment within a short period of time (within an hour)
* No special equipment is needed to perform the isolation beyond fire boots, gloves, flashlights, etc.
* No special equipment is needed to perform the isolation beyond fire boots, gloves, flashlights, etc.
* Confirmed there is high confidence that a leak can be diagnosed in a sufficiently short time to allow substantial time for mitigation prior to reaching critical flood volume for charging pump impact
* Confirmed there is high confidence that a leak can be diagnosed in a sufficiently short time to allow substantial time for mitigation prior to reaching critical flood volume for charging pump impact
* No environmental issues were identified that would prevent successful mitigation of a leak 25
* No environmental issues were identified that would prevent successful mitigation of a leak


Additional Support 9 The period of time the 1SX033 and 1SX034 were unable to be closed from the main control room occurred during a refueling outage
26 Additional Support 9 The period of time the 1SX033 and 1SX034 were unable to be closed from the main control room occurred during a refueling outage
* Additional Operations personnel were available, at all times, in the plant to identify and respond to a leak Outage period - 14 SROs, 10 ROs, 21 EOs On-line period - 5 SROs, 4 ROs, 8 EOs
* Additional Operations personnel were available, at all times, in the plant to identify and respond to a leak Outage period - 14 SROs, 10 ROs, 21 EOs On-line period - 5 SROs, 4 ROs, 8 EOs
* Additional workers, who were in the plant, would aid in identifying the source of the leak 80 work activities in Auxiliary Building at 383 elevation or below 26
* Additional workers, who were in the plant, would aid in identifying the source of the leak 80 work activities in Auxiliary Building at 383 elevation or below  


Additional Support 9 Additional resources
27 Additional Support 9 Additional resources
* The Outage Control Center (OCC) was staffed for the outage, which would provide immediate support to mitigate a potential leak
* The Outage Control Center (OCC) was staffed for the outage, which would provide immediate support to mitigate a potential leak
* At least one of the three most knowledgeable engineers on the SX system were on site, at all times, during the event SX System Engineer SX back up System Engineer SX experienced Design Engineer 27
* At least one of the three most knowledgeable engineers on the SX system were on site, at all times, during the event SX System Engineer SX back up System Engineer SX experienced Design Engineer


Additional Support 9 Uncontrolled flooding in the Auxiliary Building would require entry into an Unusual Event 9 Escalation to an Alert would be declared if there was degraded safety system performance or industrial safety hazards that preclude monitoring of safety system performance 9 An Alert declaration would result in the Technical Support Center being staffed and additional resources being available to mitigate a leak 28
28 Additional Support 9 Uncontrolled flooding in the Auxiliary Building would require entry into an Unusual Event 9 Escalation to an Alert would be declared if there was degraded safety system performance or industrial safety hazards that preclude monitoring of safety system performance 9 An Alert declaration would result in the Technical Support Center being staffed and additional resources being available to mitigate a leak  


Additional Information 9 At least 1,300,000 (1.3 million) gallons of water would be needed to cause failure of the Chemical
29 Additional Information 9 At least 1,300,000 (1.3 million) gallons of water would be needed to cause failure of the Chemical  
  & Volume Control (CV) System
& Volume Control (CV) System
* The SX basin holds approximately 800,000 gallons of water
* The SX basin holds approximately 800,000 gallons of water
* At least 500,000 gallons of water would have to be added to the SX basin to reach the 1.3 million gallons needed
* At least 500,000 gallons of water would have to be added to the SX basin to reach the 1.3 million gallons needed
* Operators would need to continue to make up to basin to reach the level in Auxiliary Building to impact the CV pumps 29
* Operators would need to continue to make up to basin to reach the level in Auxiliary Building to impact the CV pumps


Past Experience 9 Previous Issue Reports
30 Past Experience 9 Previous Issue Reports
* 800016 - Steam Leak Actions
* 800016 - Steam Leak Actions
* 508273 - Steam Generator Tube Leak Actions
* 508273 - Steam Generator Tube Leak Actions
Line 146: Line 146:
* 351652 - Warehouse Number 3 Flooding
* 351652 - Warehouse Number 3 Flooding
* 177851 - Loop Level Indication Spill
* 177851 - Loop Level Indication Spill
* 573193 - Plugged Floor Drain 9 Indicates previous success in identifying and isolating component leakage 30
* 573193 - Plugged Floor Drain 9 Indicates previous success in identifying and isolating component leakage


Summary 9 Previous and continuing training is provided to build and maintain Operators skills regarding the ability diagnose and mitigate leaks 9 Procedures are adequate to support the identification and mitigation of leaks 9 No special equipment is required to isolate leakage 9 Any environmental conditions could have been mitigated based on our past experience 31
31 Summary 9 Previous and continuing training is provided to build and maintain Operators skills regarding the ability diagnose and mitigate leaks 9 Procedures are adequate to support the identification and mitigation of leaks 9 No special equipment is required to isolate leakage 9 Any environmental conditions could have been mitigated based on our past experience


Summary 9 Additional support was available to the Operators to assist in identifying and mitigating a leak 9 Sufficient time was available for the Operators to implement the training and procedures that were available 9 Additional water (500,000 gallons) would need to be added to the basin to flood the CV pumps 32
32 Summary 9 Additional support was available to the Operators to assist in identifying and mitigating a leak 9 Sufficient time was available for the Operators to implement the training and procedures that were available 9 Additional water (500,000 gallons) would need to be added to the basin to flood the CV pumps


SDP Evaluation Greg Krueger Exelon Corporate Risk Management
SDP Evaluation Greg Krueger Exelon Corporate Risk Management


IMC 0609, Appendix K Exelon Risk Evaluation 9 Exelon assessed the risk significance of the plant configuration using a Phase 3 evaluation
34 IMC 0609, Appendix K Exelon Risk Evaluation 9 Exelon assessed the risk significance of the plant configuration using a Phase 3 evaluation
* Employed PRA tools and insights that are more detailed than that modeled in the (a)(4) risk model used to support MRule requirements 9 IMC 0609, Appendix K is a Phase 1-2 screening tool 9 Appendix K does not provide guidance for performing a Phase 3 evaluation 9 Phase 3 guidance in IMC 0609, Appendix A, was used 34
* Employed PRA tools and insights that are more detailed than that modeled in the (a)(4) risk model used to support MRule requirements 9 IMC 0609, Appendix K is a Phase 1-2 screening tool 9 Appendix K does not provide guidance for performing a Phase 3 evaluation 9 Phase 3 guidance in IMC 0609, Appendix A, was used


IMC 0609, Appendix A Phase 3 Guidance 9 Credit for recovery should be given only if the following criteria are satisfied
35 IMC 0609, Appendix A Phase 3 Guidance 9 Credit for recovery should be given only if the following criteria are satisfied
* Sufficient time is available
* Sufficient time is available
* Environmental conditions allow access, where needed
* Environmental conditions allow access, where needed
* Procedures describing the appropriate operator action exist
* Procedures describing the appropriate operator action exist
* Training is conducted on the existing procedures under similar conditions
* Training is conducted on the existing procedures under similar conditions
* Any equipment needed to perform these actions is available and ready to use 35
* Any equipment needed to perform these actions is available and ready to use


Operator Action 9 It is reasonable to credit operator action for diagnosing and isolating the SX leak 9 Plant-specific and scenario-specific factors clearly demonstrate a success path is feasible, per the requirements of the ASME PRA Standard and NUREG-1852, Demonstrating the Feasibility and Reliability of Operator Manual Actions in Response to Fire
36 Operator Action 9 It is reasonable to credit operator action for diagnosing and isolating the SX leak 9 Plant-specific and scenario-specific factors clearly demonstrate a success path is feasible, per the requirements of the ASME PRA Standard and NUREG-1852, Demonstrating the Feasibility and Reliability of Operator Manual Actions in Response to Fire
* There is an extended period of time available for diagnosis and execution of the required actions
* There is an extended period of time available for diagnosis and execution of the required actions
* There are procedures in place that guide the operators to success, and training is provided
* There are procedures in place that guide the operators to success, and training is provided
* There is sufficient manpower available to assist with diagnosis and execution
* There is sufficient manpower available to assist with diagnosis and execution
* There are sufficient cues and indications available for diagnosis   36
* There are sufficient cues and indications available for diagnosis  


Industry Experience 9 NUREG CR-4674, Volume 27, Precursors to Severe Core Damage Accidents: 1998-A Status Report
37 Industry Experience 9 NUREG CR-4674, Volume 27, Precursors to Severe Core Damage Accidents: 1998-A Status Report
* Columbia Station 1998 Fire Protection system rupture due to water hammer Rupture resulted in flooding in the reactor building Flooding noted by Shift Supervisor Source of flooding was isolated by control room by securing fire pumps within 16 minutes Some equipment failures occurred that complicated response Water level in plant was mitigated by valve isolation and temporary pumps within 8 hours 37
* Columbia Station 1998 Fire Protection system rupture due to water hammer Rupture resulted in flooding in the reactor building Flooding noted by Shift Supervisor Source of flooding was isolated by control room by securing fire pumps within 16 minutes Some equipment failures occurred that complicated response Water level in plant was mitigated by valve isolation and temporary pumps within 8 hours


Flooding Model 9 Summary of Byron Auxiliary Building SX Flooding Scenarios in the Flooding Analysis (1)
38 Flooding Model 9 Summary of Byron Auxiliary Building SX Flooding Scenarios in the Flooding Analysis 646-27 1296-646 Time to CFV2 (1)
Source          Size (gpm)      Length (ft) Frequency Time to CFV2 (min)
(min) 9.6E-06 2261 2000-48000 SX 7.6E-04 3988 100-2000 SX Frequency Length (ft)
SX            100-2000        3988      7.6E-04    1296-646 SX          2000-48000         2261      9.6E-06      646-27 (1) Time needed to reach the CV pumps 38
Size (gpm)
Source (1) Time needed to reach the CV pumps


Flooding Model 9 Isolation of Fire Protection (FP) or Non-essential Service Water (WS) leaks accomplished by turning off the pumps which terminates the driving force for water entering the Auxiliary Building 9 Isolation for SX leaks requires turning off pumps in the affected train and isolating that train from the other operating SX train. This is the portion modeled in the PRA 39
39 Flooding Model 9 Isolation of Fire Protection (FP) or Non-essential Service Water (WS) leaks accomplished by turning off the pumps which terminates the driving force for water entering the Auxiliary Building 9 Isolation for SX leaks requires turning off pumps in the affected train and isolating that train from the other operating SX train. This is the portion modeled in the PRA


Phase 3 Evaluation 9 Exelon determined that appropriate credit for operator action is warranted since each of the criteria specified in IMC 0609, Appendix A, have been satisfied
40 Phase 3 Evaluation 9 Exelon determined that appropriate credit for operator action is warranted since each of the criteria specified in IMC 0609, Appendix A, have been satisfied
* Exelons evaluation determined that the frequency of a leak of greater than 2000 gpm would fall below the White threshold
* Exelons evaluation determined that the frequency of a leak of greater than 2000 gpm would fall below the White threshold
* Leakage between 100 and 2000 gpm were further evaluated 40
* Leakage between 100 and 2000 gpm were further evaluated


Phase 3 Evaluation 9 A total of 1.3 million gallons of water would be needed prior to affecting the CV pumps; the PRA treats loss of the CV pumps following any SX flooding event as core damage 9 For the range of leakages pertinent to the analysis, the leak would need to exist for the following durations to cause an impact on the CV pumps
41 Phase 3 Evaluation 9 A total of 1.3 million gallons of water would be needed prior to affecting the CV pumps; the PRA treats loss of the CV pumps following any SX flooding event as core damage 9 For the range of leakages pertinent to the analysis, the leak would need to exist for the following durations to cause an impact on the CV pumps
* For a 100 gpm leak - 216 hours
* For a 100 gpm leak - 216 hours
* For a 2000 gpm leak - 10.8 hours 41
* For a 2000 gpm leak - 10.8 hours


Phase 3 Conservatisms 9 No reduction in leak flow credited when SX pumps fail 9 Leaks in SX pump rooms require more than 1.3 million gallons to reach CV pumps (additional volume not credited in timing analysis and ignores efficacy of SX room water tight doors)
42 Phase 3 Conservatisms 9 No reduction in leak flow credited when SX pumps fail 9 Leaks in SX pump rooms require more than 1.3 million gallons to reach CV pumps (additional volume not credited in timing analysis and ignores efficacy of SX room water tight doors)
* SX piping in SX pump rooms is 30% of all SX piping in the Auxiliary Building 9 Additional 500,000 gallons from make-up systems to SX basins would be required to reach critical flood volumes (this could be prevented by turning off the make-up pumps) 42
* SX piping in SX pump rooms is 30% of all SX piping in the Auxiliary Building 9 Additional 500,000 gallons from make-up systems to SX basins would be required to reach critical flood volumes (this could be prevented by turning off the make-up pumps)


SDP Results SX flow rate Frequency Duration      Isolation SDP Result (gpm)      (per/yr)  (hrs)          Failure    (CDP)
43 SDP Results Total Using Byron HRA 1.3E-07 2.7E-07 Total Using SPAR-H 4.6E-08 1.0 42.3 9.6E-06 2000-48000 8.4E-08 2.3E-02 (Byron HRA) 42.3 7.6E-04 100-2000 2.2E-07 6.0E-02 (SPAR-H) 42.3 7.6E-04 100-2000 SDP Result (CDP)
Probability 100-2000    7.6E-04    42.3          6.0E-02  2.2E-07 (SPAR-H) 100-2000    7.6E-04    42.3         2.3E-02  8.4E-08 (Byron HRA) 2000-48000    9.6E-06    42.3           1.0    4.6E-08 Total Using SPAR-2.7E-07 Total Using Byron HRA    1.3E-07 43
Isolation Failure Probability Duration (hrs)
Frequency (per/yr)
SX flow rate (gpm)


SDP Conclusions 9 Risk significance of the event is below the Green/White threshold (i.e., low safety significance) given limited credit for operator response 9 Credit for operator action is warranted because:
44 SDP Conclusions 9 Risk significance of the event is below the Green/White threshold (i.e., low safety significance) given limited credit for operator response 9 Credit for operator action is warranted because:
* Sufficient time is available to recognize and mitigate a significant number of potential flooding scenarios
* Sufficient time is available to recognize and mitigate a significant number of potential flooding scenarios
* Procedures were available and training was provided to help guide plant staff to isolate leakage paths
* Procedures were available and training was provided to help guide plant staff to isolate leakage paths
* Sufficient manpower was available to support isolation of a flooding event
* Sufficient manpower was available to support isolation of a flooding event
* A spectrum of physical and equipment configurations were possible to mitigate an event 9 Independent review has confirmed these results/assumptions                                                     44
* A spectrum of physical and equipment configurations were possible to mitigate an event 9 Independent review has confirmed these results/assumptions


Conclusion Brad Adams Plant Manager
Conclusion Brad Adams Plant Manager


Conclusion 9 The event identified weakness in our knowledge and teamwork associated with the configuration risk program, we continue to:
46 Conclusion 9 The event identified weakness in our knowledge and teamwork associated with the configuration risk program, we continue to:
* Train our personnel
* Train our personnel
* Improve our processes
* Improve our processes
* Monitor our progress 9 Operations personnel have the necessary training and skills to identify and respond to system leakage 46
* Monitor our progress 9 Operations personnel have the necessary training and skills to identify and respond to system leakage  


Conclusion (cont.)
47 Conclusion (cont.)
9 The tools needed to identify and respond to leaks (drawings, procedures) have been shown to be effective 9 The Phase 3 SDP has shown that there is a substantial amount of time that a leak would need to exist prior to any potential for core damage 47
9 The tools needed to identify and respond to leaks (drawings, procedures) have been shown to be effective 9 The Phase 3 SDP has shown that there is a substantial amount of time that a leak would need to exist prior to any potential for core damage


Conclusion (cont.)
48 Conclusion (cont.)
9 Additional personnel were available to help in identifying and responding to a potential leak 9 Based on the information provided, it is appropriate to allow credit for operator actions, which results in the event being of low safety significance (i.e., Green) 9 We recognize the importance of the event and have and continue to take appropriate corrective actions 48}}
9 Additional personnel were available to help in identifying and responding to a potential leak 9 Based on the information provided, it is appropriate to allow credit for operator actions, which results in the event being of low safety significance (i.e., Green) 9 We recognize the importance of the event and have and continue to take appropriate corrective actions}}

Latest revision as of 15:02, 14 January 2025

Exelons Public Meeting Slides for Byron Regulatory Conference - 9/16/2008
ML082620687
Person / Time
Site: Byron Constellation icon.png
Issue date: 09/16/2008
From:
Exelon Nuclear
To:
NRC/RGN-III
References
Download: ML082620687 (48)


Text

Byron Station Regulatory Conference Unit 2 Inadvertent Entry Into An Elevated Risk Condition September 16, 2008

2 Agenda 9 Introduction D. Hoots 9 Finding and Root Cause Evaluation B. Adams 9 Operations Actions S. Fruin 9 Risk Assessment G. Krueger 9 Conclusion B. Adams

Introduction David Hoots Site Vice President

4 Introduction 9 Provide information regarding the event, root cause evaluation and corrective actions taken 9 Provide insights gained from risk significance determination process evaluation 9 Provide information as to our ability to carry out mitigating actions in a timely manner 9 Provide additional technical information requested by NRC August 14, 2008 letter 9 Provide information indicating that credit for Operation actions is appropriate

Finding and Root Cause Evaluation Brad Adams Plant Manager

6 Finding 9 Potentially Greater Than Green Finding

  • Failure to perform an updated risk evaluation prior to surveillance testing of the Unit 1 Train A Emergency Diesel Generator (EDG) based on existing plant conditions
  • Resulted in inadvertently entering an elevated risk condition on Unit 2 due to degraded internal flood mitigation capability

7 Essential Service Water (SX)

System Information 9 Provides cooling water to safety related components 9 Two trains per unit with mechanical draft cooling towers providing the ultimate heat sink 9 Valves 1SX033 and 1SX034 are Unit 1 train cross-tie discharge isolation valves for the 1A and 1B SX trains 9 Valves 1SX033 and 1SX034 are located on 330 elevation in the Auxiliary Building

8 Event Background 9 Replacement of 1SX034 scheduled during Unit 1 spring 2008 refueling outage 9 Part of material condition improvement project to replace SX system butterfly valves 9 Two clearance orders generated for electrical and mechanical isolation of 1SX033 9 During clearance order placement, valve 1SX033 was electrically closed to support work on 1SX034

9 Event Timeline 9 March 28, 2008

  • Risk configuration assessment conducted to support work on 1SX034
  • Leak-by noted and an attempt to manually close 1SX033 to reduce leak-by performed
  • During manual operation of 1SX033, an abnormal noise heard from the valve actuator, which prompted the decision to conduct troubleshooting on the actuator

10 Event Timeline (cont.)

9 April 1, 2008

  • Revision to the risk assessment performed to cover the 1SX033 troubleshooting and potential repair 9 April 2, 2008
  • 1SX033 and 1SX034 were left in the closed position and electrically de-energized to support the troubleshooting on 1SX033 9 April 4, 2008
  • The outage schedule contained a task to perform a clearance order to electrically open 1SX033 and manually open 1SX034 to support (1A EDG) testing
  • However, the scheduled task could not be executed as written because, both valves were maintained in the closed position, electrically de-energized and incapable of opening from the main control room

11 Event Timeline (cont.)

9 April 5, 2008, at 02:19

  • Equipment Status Tags (ESTs) were hung on valves 1SX033 and 1SX034 9 April 5, 2008, at 03:04
  • To support EDG testing, both 1SX033 and 1SX034 valves were opened manually
  • This configuration change was not evaluated for Unit 2 on-line risk impact 9 April 6, 2008
  • During Work Control Cycle Manager review of risk configurations for the next week, the configuration change was recognized as a potential risk impact and the Station Risk Engineer was consulted

12 Event Timeline (cont.)

9 April 6, 2008

  • At 16:52, based on input from the Station Risk Engineer and Work Control Cycle Manager, Operations declared Unit 2 on-line risk to be Orange due to 1SX033 and 1SX034 being unable to close from the main control room
  • At 17:12, operator stationed at valve 1SX033 and Unit 2 on-line risk was evaluated as being Green (38 hours4.398148e-4 days <br />0.0106 hours <br />6.283069e-5 weeks <br />1.4459e-5 months <br />)
  • At 21:24, 1SX034 was manually closed (42.3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />)

13 Root Cause Evaluation 9 Root Cause

  • Less than adequate Operations ownership of on-line risk process when plant configuration changed 9 Contributing Causes
  • Less than adequate training provided for work groups which led to a lack of knowledge of configuration risk management
  • Work Management procedural guidance associated with configuration risk management lacked specificity
  • Equipment difficulty associated with emergent work on 1SX033

14 Root Cause Evaluation (cont.)

9 Organizational and Programmatic Issues

  • Less than adequate site awareness of Auxiliary Building internal flooding with respect to processes and procedures
  • Limited management oversight of configuration risk management process

15 Immediate Corrective Actions 9 Performance management performed for personnel involved in event 9 Increased awareness provided for risk management reviews

  • Formal Standing Order issued to the Operations Shift
  • Clear expectations for ownership communicated to all Operations Shift Managers by the Shift Operations Superintendent

16 Interim Corrective Action to Prevent Recurrence (CAPR) 9 Developed and implemented Byron-specific revisions to Exelon CAP and Online Work Control Process procedures to include expectations and clear guidance for Operations Shift Management roles and responsibilities regarding risk management

  • Specific guidance on the use of Paragon risk program
  • Specific guidance for review of the Risk Summary Sheet that Work Management generates
  • Specific guidance for communications
  • The change management process is being utilized to incorporate this interim action prior to the upcoming refueling outage

17 Corrective Actions 9 CAPR - Revise the corporate procedures (CAP and Online Work Control Process) to include

  • Specific guidance on the use of Paragon risk program
  • Specific guidance for review of the Risk Summary Sheet that Work Management generates
  • Specific guidance for communications
  • Responsible - Operations Due 11/19/08

18 Additional Corrective Actions 9 Perform and document observations, including targeted observations during the refueling outage

  • Perform periodic roll-ups of the observations 9 Used the Systematic Approach to Training (SAT) process to include enhanced training in the 1st quarter, 2009 licensed operator requalification training

19 Summary 9 Lessons Learned

  • Did not maintain proper Operations focus for evaluating risk when conditions changed Primarily focused on Technical Specifications applicability
  • Improvements needed in teamwork between site groups to assure focus includes evaluating risk
  • Going forward Performance management has been applied Procedures have been improved Training program is being strengthened Progress is being monitored

Operator Actions Scott Fruin Shift Operations Superintendent

21 Procedures/Training 9 Prior to the event, an abnormal operating procedure existed (1/2 BOA PRI-7) that dealt with mitigation of SX system leakage 9 Alarm response procedures existed for responding to Auxiliary Building sump alarms

22 Procedures/Training 9 Identification and isolation of components is a skill of the operators 9 Training was provided previously on flood mitigation in licensed operator requalification training

  • 2008 - SX leak on supply to 0A VC Chiller
  • 2007 - SX header break between 1SX004 and 1SX007
  • 2005 - SX pump suction leak
  • 2003 - SX header break between 1SX004 and 1SX007 9 Use of drawings to identify isolation points, for clearance and tagging, is a common task used routinely by Operations personnel

23 Procedures/Training 9 Two new procedures were developed for flooding prior to the event to support a recent license amendment

  • Abnormal operating procedure (0BOA PRI-8)
  • Operating Procedure (BOP SX-22)
  • Procedures cover assessment of environmental conditions 9 Many licensed operators received classroom training on new Byron specific operating and abnormal operating procedures during requalification training prior to the outage
  • 14 of 28 Reactor Operators
  • 23 of 36 Senior Reactor Operators
  • Both shifts had personnel that received the training prior the event

24 Procedures/Training 9 Post outage, a tabletop scenario was developed and administered to Operations personnel 9 Six operators were evaluated and all were able to diagnose the source of the leak and identify actions to take within a short period of time (within an hour)

  • Personnel utilized various tools including their plant knowledge, training, drawings and procedures to complete the scenario

25 Procedures/Training 9 Conclusions of the table tops -

  • Personnel were confident that they could get to, and isolate the necessary equipment within a short period of time (within an hour)
  • No special equipment is needed to perform the isolation beyond fire boots, gloves, flashlights, etc.
  • Confirmed there is high confidence that a leak can be diagnosed in a sufficiently short time to allow substantial time for mitigation prior to reaching critical flood volume for charging pump impact
  • No environmental issues were identified that would prevent successful mitigation of a leak

26 Additional Support 9 The period of time the 1SX033 and 1SX034 were unable to be closed from the main control room occurred during a refueling outage

  • Additional Operations personnel were available, at all times, in the plant to identify and respond to a leak Outage period - 14 SROs, 10 ROs, 21 EOs On-line period - 5 SROs, 4 ROs, 8 EOs
  • Additional workers, who were in the plant, would aid in identifying the source of the leak 80 work activities in Auxiliary Building at 383 elevation or below

27 Additional Support 9 Additional resources

  • The Outage Control Center (OCC) was staffed for the outage, which would provide immediate support to mitigate a potential leak
  • At least one of the three most knowledgeable engineers on the SX system were on site, at all times, during the event SX System Engineer SX back up System Engineer SX experienced Design Engineer

28 Additional Support 9 Uncontrolled flooding in the Auxiliary Building would require entry into an Unusual Event 9 Escalation to an Alert would be declared if there was degraded safety system performance or industrial safety hazards that preclude monitoring of safety system performance 9 An Alert declaration would result in the Technical Support Center being staffed and additional resources being available to mitigate a leak

29 Additional Information 9 At least 1,300,000 (1.3 million) gallons of water would be needed to cause failure of the Chemical

& Volume Control (CV) System

  • The SX basin holds approximately 800,000 gallons of water
  • At least 500,000 gallons of water would have to be added to the SX basin to reach the 1.3 million gallons needed
  • Operators would need to continue to make up to basin to reach the level in Auxiliary Building to impact the CV pumps

30 Past Experience 9 Previous Issue Reports

  • 800016 - Steam Leak Actions
  • 433581 - Significant Instrument Air Leak
  • 663146 - Flooding the Mechanical Maintenance Office
  • 494214 - Flooding in the Warehouse
  • 351652 - Warehouse Number 3 Flooding
  • 177851 - Loop Level Indication Spill
  • 573193 - Plugged Floor Drain 9 Indicates previous success in identifying and isolating component leakage

31 Summary 9 Previous and continuing training is provided to build and maintain Operators skills regarding the ability diagnose and mitigate leaks 9 Procedures are adequate to support the identification and mitigation of leaks 9 No special equipment is required to isolate leakage 9 Any environmental conditions could have been mitigated based on our past experience

32 Summary 9 Additional support was available to the Operators to assist in identifying and mitigating a leak 9 Sufficient time was available for the Operators to implement the training and procedures that were available 9 Additional water (500,000 gallons) would need to be added to the basin to flood the CV pumps

SDP Evaluation Greg Krueger Exelon Corporate Risk Management

34 IMC 0609, Appendix K Exelon Risk Evaluation 9 Exelon assessed the risk significance of the plant configuration using a Phase 3 evaluation

  • Employed PRA tools and insights that are more detailed than that modeled in the (a)(4) risk model used to support MRule requirements 9 IMC 0609, Appendix K is a Phase 1-2 screening tool 9 Appendix K does not provide guidance for performing a Phase 3 evaluation 9 Phase 3 guidance in IMC 0609, Appendix A, was used

35 IMC 0609, Appendix A Phase 3 Guidance 9 Credit for recovery should be given only if the following criteria are satisfied

  • Sufficient time is available
  • Environmental conditions allow access, where needed
  • Procedures describing the appropriate operator action exist
  • Training is conducted on the existing procedures under similar conditions
  • Any equipment needed to perform these actions is available and ready to use

36 Operator Action 9 It is reasonable to credit operator action for diagnosing and isolating the SX leak 9 Plant-specific and scenario-specific factors clearly demonstrate a success path is feasible, per the requirements of the ASME PRA Standard and NUREG-1852, Demonstrating the Feasibility and Reliability of Operator Manual Actions in Response to Fire

  • There is an extended period of time available for diagnosis and execution of the required actions
  • There are procedures in place that guide the operators to success, and training is provided
  • There is sufficient manpower available to assist with diagnosis and execution
  • There are sufficient cues and indications available for diagnosis

37 Industry Experience 9 NUREG CR-4674, Volume 27, Precursors to Severe Core Damage Accidents: 1998-A Status Report

  • Columbia Station 1998 Fire Protection system rupture due to water hammer Rupture resulted in flooding in the reactor building Flooding noted by Shift Supervisor Source of flooding was isolated by control room by securing fire pumps within 16 minutes Some equipment failures occurred that complicated response Water level in plant was mitigated by valve isolation and temporary pumps within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

38 Flooding Model 9 Summary of Byron Auxiliary Building SX Flooding Scenarios in the Flooding Analysis 646-27 1296-646 Time to CFV2 (1)

(min) 9.6E-06 2261 2000-48000 SX 7.6E-04 3988 100-2000 SX Frequency Length (ft)

Size (gpm)

Source (1) Time needed to reach the CV pumps

39 Flooding Model 9 Isolation of Fire Protection (FP) or Non-essential Service Water (WS) leaks accomplished by turning off the pumps which terminates the driving force for water entering the Auxiliary Building 9 Isolation for SX leaks requires turning off pumps in the affected train and isolating that train from the other operating SX train. This is the portion modeled in the PRA

40 Phase 3 Evaluation 9 Exelon determined that appropriate credit for operator action is warranted since each of the criteria specified in IMC 0609, Appendix A, have been satisfied

  • Exelons evaluation determined that the frequency of a leak of greater than 2000 gpm would fall below the White threshold
  • Leakage between 100 and 2000 gpm were further evaluated

41 Phase 3 Evaluation 9 A total of 1.3 million gallons of water would be needed prior to affecting the CV pumps; the PRA treats loss of the CV pumps following any SX flooding event as core damage 9 For the range of leakages pertinent to the analysis, the leak would need to exist for the following durations to cause an impact on the CV pumps

  • For a 100 gpm leak - 216 hours0.0025 days <br />0.06 hours <br />3.571429e-4 weeks <br />8.2188e-5 months <br />
  • For a 2000 gpm leak - 10.8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

42 Phase 3 Conservatisms 9 No reduction in leak flow credited when SX pumps fail 9 Leaks in SX pump rooms require more than 1.3 million gallons to reach CV pumps (additional volume not credited in timing analysis and ignores efficacy of SX room water tight doors)

  • SX piping in SX pump rooms is 30% of all SX piping in the Auxiliary Building 9 Additional 500,000 gallons from make-up systems to SX basins would be required to reach critical flood volumes (this could be prevented by turning off the make-up pumps)

43 SDP Results Total Using Byron HRA 1.3E-07 2.7E-07 Total Using SPAR-H 4.6E-08 1.0 42.3 9.6E-06 2000-48000 8.4E-08 2.3E-02 (Byron HRA) 42.3 7.6E-04 100-2000 2.2E-07 6.0E-02 (SPAR-H) 42.3 7.6E-04 100-2000 SDP Result (CDP)

Isolation Failure Probability Duration (hrs)

Frequency (per/yr)

SX flow rate (gpm)

44 SDP Conclusions 9 Risk significance of the event is below the Green/White threshold (i.e., low safety significance) given limited credit for operator response 9 Credit for operator action is warranted because:

  • Sufficient time is available to recognize and mitigate a significant number of potential flooding scenarios
  • Procedures were available and training was provided to help guide plant staff to isolate leakage paths
  • Sufficient manpower was available to support isolation of a flooding event
  • A spectrum of physical and equipment configurations were possible to mitigate an event 9 Independent review has confirmed these results/assumptions

Conclusion Brad Adams Plant Manager

46 Conclusion 9 The event identified weakness in our knowledge and teamwork associated with the configuration risk program, we continue to:

  • Train our personnel
  • Improve our processes
  • Monitor our progress 9 Operations personnel have the necessary training and skills to identify and respond to system leakage

47 Conclusion (cont.)

9 The tools needed to identify and respond to leaks (drawings, procedures) have been shown to be effective 9 The Phase 3 SDP has shown that there is a substantial amount of time that a leak would need to exist prior to any potential for core damage

48 Conclusion (cont.)

9 Additional personnel were available to help in identifying and responding to a potential leak 9 Based on the information provided, it is appropriate to allow credit for operator actions, which results in the event being of low safety significance (i.e., Green) 9 We recognize the importance of the event and have and continue to take appropriate corrective actions