ML18354B207: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 1: Line 1:
{{Adams package
{{Adams package
| number = ML18354B207
| number = ML18354B207
| title = Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendments Technical Specification Changes for Physics Tests Exceptions and Nomenclature (LAR 18-020)
| title = Issuance of Amendments Technical Specification Changes for Physics Tests Exceptions and Nomenclature (LAR 18-020)
| release date = 02/07/2019
| release date = 02/07/2019
| package contents = {{Adams package content
| package contents = {{Adams package content
| number = ML18354B224
| number = ML18354B224
| issue date = 01/30/2019
| issue date = 01/30/2019
| title = Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendments Technical Specification Changes for Physics Tests Exceptions and Nomenclature (LAR 18-020)
| title = Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 18-020)
| author name = Dixon-Herrity J
| author name = Dixon-Herrity J
| author affiliation = NRC/NRO/DLSE/LB4
| author affiliation = NRC/NRO/DLSE/LB4
Line 20: Line 20:
| number = ML18354B212
| number = ML18354B212
| issue date = 01/30/2019
| issue date = 01/30/2019
| title = Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendments Technical Specification Changes for Physics Tests Exceptions and Nomenclature (LAR 18-020)
| title = Safety Evaluation - Vogtle Electric Generating Plant Units 3 and 4 (LAR 18-020)
| author name = Hoellman J
| author name = Hoellman J
| author affiliation = NRC/NRO/DLSE/LB4
| author affiliation = NRC/NRO/DLSE/LB4
Line 35: Line 35:
| number = ML18354B211
| number = ML18354B211
| issue date = 01/30/2019
| issue date = 01/30/2019
| title = Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendments Technical Specification Changes for Physics Tests Exceptions and Nomenclature (LAR 18-020)
| title = Attachment - Vogtle Electric Generating Plant Unit 4 (LAR 18-020)
| author name = Hoellman J
| author name = Hoellman J
| author affiliation = NRC/NRO/DLSE/LB4
| author affiliation = NRC/NRO/DLSE/LB4
Line 50: Line 50:
| number = ML18354B210
| number = ML18354B210
| issue date = 01/30/2019
| issue date = 01/30/2019
| title = Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendments Technical Specification Changes for Physics Tests Exceptions and Nomenclature (LAR 18-020)
| title = Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 18-020)
| author name = Hoellman J
| author name = Hoellman J
| author affiliation = NRC/NRO/DLSE/LB4
| author affiliation = NRC/NRO/DLSE/LB4
Line 65: Line 65:
| number = ML18354B209
| number = ML18354B209
| issue date = 01/30/2019
| issue date = 01/30/2019
| title = Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendments Technical Specification Changes for Physics Tests Exceptions and Nomenclature (LAR 18-020)
| title = Attachment - Vogtle Electric Generating Plant Unit 3 (LAR 18-020)
| author name = Hoellman J
| author name = Hoellman J
| author affiliation = NRC/NRO/DLSE/LB4
| author affiliation = NRC/NRO/DLSE/LB4
Line 80: Line 80:
| number = ML18354B208
| number = ML18354B208
| issue date = 01/30/2019
| issue date = 01/30/2019
| title = Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendments Technical Specification Changes for Physics Tests Exceptions and Nomenclature (LAR 18-020)
| title = Cover Letter - Vogtle Electric Generating Plant Units 3 and 4 (LAR 18-020) - TS Changes for Physics Tests Exceptions and Nomenclature
| author name = Hoellman J
| author name = Hoellman J
| author affiliation = NRC/NRO/DLSE/LB4
| author affiliation = NRC/NRO/DLSE/LB4

Latest revision as of 18:14, 24 January 2020

Issuance of Amendments Technical Specification Changes for Physics Tests Exceptions and Nomenclature (LAR 18-020)
Date released: 02/07/2019 Download: ML18354B207



Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 18-020)
ML18354B224
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 01/30/2019
From: Jennifer Dixon-Herrity
NRC/NRO/DLSE/LB4
To:
Southern Nuclear Operating Co
hoellman j/415-5481
References
EPID L-2018-LLA-0214, LAR 18-020
Download: ML18354B224 (3)
Safety Evaluation - Vogtle Electric Generating Plant Units 3 and 4 (LAR 18-020)
ML18354B212
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 01/30/2019
From: Jordan Hoellman
NRC/NRO/DLSE/LB4
To:
City of Dalton, GA, Georgia Power Co, MEAG Power, Oglethorpe Power Corp, Southern Nuclear Operating Co
hoellman j/415-5481
References
EPID L-2018-LLA-0214, LAR 18-020
Download: ML18354B212 (7)
Attachment - Vogtle Electric Generating Plant Unit 4 (LAR 18-020)
ML18354B211
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 01/30/2019
From: Jordan Hoellman
NRC/NRO/DLSE/LB4
To:
Southern Nuclear Operating Co
hoellman j/415-5481
References
EPID L-2018-LLA-0214, LAR 18-020
Download: ML18354B211 (4)
Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 18-020)
ML18354B210
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 01/30/2019
From: Jordan Hoellman
NRC/NRO/DLSE/LB4
To:
Southern Nuclear Operating Co
hoellman j/415-5481
References
EPID L-2018-LLA-0214, LAR 18-020
Download: ML18354B210 (2)
Attachment - Vogtle Electric Generating Plant Unit 3 (LAR 18-020)
ML18354B209
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 01/30/2019
From: Jordan Hoellman
NRC/NRO/DLSE/LB4
To:
Southern Nuclear Operating Co
hoellman j/415-5481
References
EPID L-2018-LLA-0214, LAR 18-020
Download: ML18354B209 (4)
Cover Letter - Vogtle Electric Generating Plant Units 3 and 4 (LAR 18-020) - TS Changes for Physics Tests Exceptions and Nomenclature
ML18354B208
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 01/30/2019
From: Jordan Hoellman
NRC/NRO/DLSE/LB4
To: Whitley B H
Southern Nuclear Operating Co
hoellman j/415-5481
References
EPID L-2018-LLA-0214, LAR 18-020
Download: ML18354B208 (6)