{{#Wiki_filter:TSTF-557, Rev. 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program Original       Change   Change      Change                Reason Schedule      5/3/18     9/7/18     11/1/18 3/18/18 Submitted             12/19/17 RAIs                   4/17/18   No RAIs Draft SE               9/28/18             10/26/18   11/8/18             OGC then DORL delays Final SE             12/19/18 RAI Response to Final SE: 10 Months TSTF-563, Rev. 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program Original     Change Change Change        Change  Change Change                    Reason Schedule      7/3/17 2/15/18 7/3/18       8/2/18 9/20/18 10/12/18 7/3/17 Submitted             5/10/17 RAIs                   9/7/17 10/5/17 2/15/18                                             Draft RAIs from EICB and APLA.
{{#Wiki_filter:Page 1 EXCEL Services Corporation TSTF-557, Rev. 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program Original Schedule 3/18/18 Change 5/3/18 Change 9/7/18 Change 11/1/18 Reason Submitted 12/19/17 RAIs 4/17/18 No RAIs Draft SE 9/28/18 10/26/18 11/8/18 OGC then DORL delays Final SE 12/19/18 RAI Response to Final SE: 10 Months TSTF-563, Rev. 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program Original Schedule 7/3/17 Change 7/3/17 Change 2/15/18 Change 7/3/18 Change 8/2/18 Change 9/20/18 Change 10/12/18 Reason Submitted 5/10/17 RAIs 9/7/17 10/5/17 2/15/18 Draft RAIs from EICB and APLA.
Second round APLA RAI on 2/15/18.
Second round APLA RAI on 2/15/18.
TSTF                                   4/17/18                                              TSTF to respond to draft to save Response                                                                                                                time.
TSTF  
Draft SE                3/3/18                    8/31/18 10/31/18 9/20/18                                Actual on 9/20/18 Final SE              5/17/18                                                12/20/18 RAI Response to Final SE: 8 Months Page 1                                EXCEL Services Corporation


TSTF-564, Rev. 1, Safety Limit MCPR - High priority, plant startup related Original     Change Change      Change   Change  Change    Change                  Reason Schedule    4/12/18 6/8/18       7/3/18   9/7/18 10/4/18   10/24/18 11/18/17 Submitted             8/28/17 RAIs                 3/16/18 4/12/18                                                                       Draft RAI 3/20/18 TSTF                           5/29/18                                                         TSTF provided draft on 5/3/18.
===Response===
Response                                                                                      Revised draft response based on NRC comments Draft SE             5/30/18           6/29/18   8/31/18 9/30/18 10/4/18                                   Actual 10/4/18 Final SE             7/31/18                                                 11/26/18 RAI Response to Final SE: 6 Months TSTF-566, Rev. 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems Original     Change      Change      Change               Reason Schedule      4/5/18   10/29/18 3/26/18 Submitted             1/18/18 RAIs                   5/4/18         --                              Determined no RAI needed Draft SE             10/16/18               11/8/18                       On schedule as of 9/7/18 Final SE             1/18/19                               ??
4/17/18 TSTF to respond to draft to save time.
RAI Response to Final SE: 9 Months Page 2                                EXCEL Services Corporation}}
Draft SE 3/3/18 8/31/18 10/31/18 9/20/18 Actual on 9/20/18 Final SE 5/17/18 12/20/18 RAI Response to Final SE: 8 Months
 
Page 2 EXCEL Services Corporation TSTF-564, Rev. 1, Safety Limit MCPR - High priority, plant startup related Original Schedule 11/18/17 Change 4/12/18 Change 6/8/18 Change 7/3/18 Change 9/7/18 Change 10/4/18 Change 10/24/18 Reason Submitted 8/28/17 RAIs 3/16/18 4/12/18 Draft RAI 3/20/18 TSTF  
 
===Response===
5/29/18 TSTF provided draft on 5/3/18.
Revised draft response based on NRC comments Draft SE 5/30/18 6/29/18 8/31/18 9/30/18 10/4/18 Actual 10/4/18 Final SE 7/31/18 11/26/18 RAI Response to Final SE: 6 Months TSTF-566, Rev. 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems Original Schedule 3/26/18 Change 4/5/18 Change 10/29/18 Change Reason Submitted 1/18/18 RAIs 5/4/18 Determined no RAI needed Draft SE 10/16/18 11/8/18 On schedule as of 9/7/18 Final SE 1/18/19  
??
RAI Response to Final SE: 9 Months}}

Latest revision as of 09:46, 5 January 2025

Handout from 11/08/2018 TSTF Meeting for Agenda Item Ii.B.C November 2018 Traveler Review Schedule Changes
ML18312A367
Person / Time
Site: Technical Specifications Task Force
Issue date: 11/08/2018
From:
Technical Specifications Task Force
To:
Office of Nuclear Reactor Regulation
Honcharik M
Shared Package
ML18312A362 List:
References
Download: ML18312A367 (2)


Text

Page 1 EXCEL Services Corporation TSTF-557, Rev. 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program Original Schedule 3/18/18 Change 5/3/18 Change 9/7/18 Change 11/1/18 Reason Submitted 12/19/17 RAIs 4/17/18 No RAIs Draft SE 9/28/18 10/26/18 11/8/18 OGC then DORL delays Final SE 12/19/18 RAI Response to Final SE: 10 Months TSTF-563, Rev. 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program Original Schedule 7/3/17 Change 7/3/17 Change 2/15/18 Change 7/3/18 Change 8/2/18 Change 9/20/18 Change 10/12/18 Reason Submitted 5/10/17 RAIs 9/7/17 10/5/17 2/15/18 Draft RAIs from EICB and APLA.

Second round APLA RAI on 2/15/18.

TSTF

Response

4/17/18 TSTF to respond to draft to save time.

Draft SE 3/3/18 8/31/18 10/31/18 9/20/18 Actual on 9/20/18 Final SE 5/17/18 12/20/18 RAI Response to Final SE: 8 Months

Page 2 EXCEL Services Corporation TSTF-564, Rev. 1, Safety Limit MCPR - High priority, plant startup related Original Schedule 11/18/17 Change 4/12/18 Change 6/8/18 Change 7/3/18 Change 9/7/18 Change 10/4/18 Change 10/24/18 Reason Submitted 8/28/17 RAIs 3/16/18 4/12/18 Draft RAI 3/20/18 TSTF

Response

5/29/18 TSTF provided draft on 5/3/18.

Revised draft response based on NRC comments Draft SE 5/30/18 6/29/18 8/31/18 9/30/18 10/4/18 Actual 10/4/18 Final SE 7/31/18 11/26/18 RAI Response to Final SE: 6 Months TSTF-566, Rev. 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems Original Schedule 3/26/18 Change 4/5/18 Change 10/29/18 Change Reason Submitted 1/18/18 RAIs 5/4/18 Determined no RAI needed Draft SE 10/16/18 11/8/18 On schedule as of 9/7/18 Final SE 1/18/19

??

RAI Response to Final SE: 9 Months