ML14174A832: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
(One intermediate revision by the same user not shown)
Line 21: Line 21:
   
   
EA-14-008  
EA-14-008  
   
   
Jeremy Browning, Site Vice President  
Jeremy Browning, Site Vice President  
Entergy Operations, Inc.  
Entergy Operations, Inc.  
Arkansas Nuclear One  
Arkansas Nuclear One  
1448 SR 333  
1448 SR 333  
Russellville, AR 72802-0967  
Russellville, AR 72802-0967  
   
   
SUBJECT:  ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 - FINAL SIGNIFICANCE  
SUBJECT:  ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 - FINAL SIGNIFICANCE  
DETERMINATION OF TWO YELLOW FINDINGS AND NOTICE OF VIOLATION;  
DETERMINATION OF TWO YELLOW FINDINGS AND NOTICE OF VIOLATION;  
NRC INSPECTION REPORT 05000313/2014008 AND 05000368/2014008  
NRC INSPECTION REPORT 05000313/2014008 AND 05000368/2014008  
   
   
Dear Mr. Browning:   
Dear Mr. Browning:   
   
   
This letter provides you the final significance determination of the preliminary Red and Yellow  
This letter provides you the final significance determination of the preliminary Red and Yellow  
findings identified in NRC Inspection Report 05000313/2013012; 05000368/2013012  
findings identified in NRC Inspection Report 05000313/2013012; 05000368/2013012  
(ML14083A409), dated March 24, 2014.  A detailed description of the findings is contained in  
(ML14083A409), dated March 24, 2014.  A detailed description of the findings is contained in  
Section 4OA3.9 of that report.  The findings are associated with the March 31, 2013, Unit 1  
Section 4OA3.9 of that report.  The findings are associated with the March 31, 2013, Unit 1  
 
stator drop that affected safety-related equipment on both units.  
stator drop that affected safety-related equipment on both units.
 
At your request, a Regulatory Conference was held on May 1, 2014, to further discuss your  
At your request, a Regulatory Conference was held on May 1, 2014, to further discuss your  
 
views on these findings.  A copy of your presentation provided at this meeting is attached to the  
views on these findings.  A copy of your presentat
ion provided at this meeting is attached to the  
summary of the Regulatory Conference (ML14128A512), dated May 9, 2014.  In your  
summary of the Regulatory Conference (ML14128A512), dated May 9, 2014.  In your  
presentation on the risk significance of the event related to Unit 1, you described four recovery  
presentation on the risk significance of the event related to Unit 1, you described four recovery  
actions that plant personnel could have implemented to establish and maintain cooling to the  
actions that plant personnel could have implemented to establish and maintain cooling to the  
reactor core in the event that the emergency diesel generators were not able to supply power to  
reactor core in the event that the emergency diesel generators were not able to supply power to  
the 4160V electrical buses.  Three of these methods involved restoring power to 4160V safety-
the 4160V electrical buses.  Three of these methods involved restoring power to 4160V safety-
related electrical buses from other sources.  The fourth recovery method involved providing  
related electrical buses from other sources.  The fourth recovery method involved providing  
temporary 480V ac power to a borated water recirculating pump, and establishing a source of  
temporary 480V ac power to a borated water recirculating pump, and establishing a source of  
water to the reactor from the borated water storage tank.   
water to the reactor from the borated water storage tank.   
   
   
Based on your staff's evaluation of the probability of success of the four recovery actions, and  
Based on your staff's evaluation of the probability of success of the four recovery actions, and  
the amount of time that existed to restore cooling to the core, your staff concluded that the  
the amount of time that existed to restore cooling to the core, your staff concluded that the  
 
change in core damage probability was 4.8 x 10-6.  As a result, you concluded that the  
change in core damage probability was 4.8 x 10
-6.  As a result, you concluded that the  
inspection finding should be characterized as White, low-to-moderate safety significance.   
inspection finding should be characterized as White, low-to-moderate safety significance.   
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION IV
1600 E LAMAR BLVD
ARLINGTON, TX 76011-4511


  UNITED STATES
J. Browning  
NUCLEAR REGULATORY COMMISSION REGION IV
-2-  
1600 E LAMAR BLVD
ARLINGTON, TX 76011-4511 
J. Browning -2-  
 
In your presentation on the risk significance of the event related to Unit 2, you described three  
In your presentation on the risk significance of the event related to Unit 2, you described three  
 
procedurally directed recovery strategies that plant personnel could have implemented to  
procedurally directed recovery strategies t
hat plant personnel could have implemented to  
restore electrical power in the event that power was lost to vital electrical buses.  These  
restore electrical power in the event that power was lost to vital electrical buses.  These  
strategies involved supplying power from the Startup 2 transformer, or the alternate ac diesel  
strategies involved supplying power from the Startup 2 transformer, or the alternate ac diesel  
generator to electrical buses, and cross connecting the vital 4160V buses to supply power to  
generator to electrical buses, and cross connecting the vital 4160V buses to supply power to  
equipment.  Based on your staff's evaluation of the probability of success of these three  
equipment.  Based on your staff's evaluation of the probability of success of these three  
procedurally directed recovery strategies, your staff concluded that the change in conditional  
procedurally directed recovery strategies, your staff concluded that the change in conditional  
 
core damage probability was 1.8 x 10-6.  As a result, you concluded that this inspection finding  
core damage probability was 1.8 x 10
-6.  As a result, you concluded that this inspection finding  
should also be characterized as White, low-to-moderate safety significance.  
should also be characterized as White, low-to-moderate safety significance.  
   
   
After considering the information developed during the inspection and the information you  
After considering the information developed during the inspection and the information you  
provided at the Regulatory Conference, we have concluded that the risk significance of each  
provided at the Regulatory Conference, we have concluded that the risk significance of each  
finding is appropriately characterized as Yellow, substantial safety significance, for both Units 1  
finding is appropriately characterized as Yellow, substantial safety significance, for both Units 1  
and 2.  Our evaluation of the risk significance of each inspection finding is provided in  
and 2.  Our evaluation of the risk significance of each inspection finding is provided in  
Enclosure 2 of this letter.   
Enclosure 2 of this letter.   
   
   
You have 30 calendar days from the date of this letter to appeal the staff's determination of  
You have 30 calendar days from the date of this letter to appeal the staffs determination of  
 
significance for the identified Yellow findings.  Such appeals will be considered to have merit  
significance for the identified Yellow findings.  Such appeals will be considered to have merit  
 
only if they meet the criteria given in Inspection Manual Chapter 0609, Significance  
only if they meet the criteria given in  
Determination Process, Attachment 2.  An appeal must be sent in writing to the Regional  
Inspection Manual Chapter 0609, "Significance  
Determination Process," Attachment 2.  An appeal must be sent in writing to the Regional  
Administrator, Region IV, 1600 E. Lamar Blvd., Arlington, TX 76011-4511.  
Administrator, Region IV, 1600 E. Lamar Blvd., Arlington, TX 76011-4511.  
   
   
The NRC has also determined that the failure to follow procedures to ensure that a temporary  
The NRC has also determined that the failure to follow procedures to ensure that a temporary  
lift assembly was designed to support the projected load and to perform a 125 percent load test  
lift assembly was designed to support the projected load and to perform a 125 percent load test  
for the projected load is a violation of Title 10 of the Code of Federal Regulations (CFR) Part 50,  
for the projected load is a violation of Title 10 of the Code of Federal Regulations (CFR) Part 50,  
Appendix B, Criteria V, "Instructions, Procedures and Drawings," as cited in the attached Notice  
Appendix B, Criteria V, Instructions, Procedures and Drawings, as cited in the attached Notice  
 
of Violation.  In accordance with the NRCs Enforcement Policy, the Notice is considered  
of Violation.  In accordance with the NRC's Enforcement Policy, the Notice is considered  
 
escalated enforcement action because it is associated with Yellow findings for Units 1 and 2.  
escalated enforcement action because it is associated with Yellow findings for Units 1 and 2.  
   
   
You are required to respond to this letter and should follow the instructions specified in the  
You are required to respond to this letter and should follow the instructions specified in the  
 
enclosed Notice when preparing your response.  If you have additional information that you  
enclosed Notice when preparing your response.  
believe the NRC should consider, you may provide it in your response to the Notice.  The NRCs
  If you have additional information that you  
believe the NRC should consider, you may provide it in your response to the Notice.  The NRC's
 
review of your response to the Notice will also determine whether further enforcement action is  
review of your response to the Notice will also determine whether further enforcement action is  
necessary to ensure compliance with regulatory requirements.   
necessary to ensure compliance with regulatory requirements.   
   
   
Because plant performance at the Arkansas Nuclear One facility has been determined to be  
Because plant performance at the Arkansas Nuclear One facility has been determined to be  
 
beyond the "Licensee Response Column" of the NRCs Reactor Oversight Process Action  
beyond the "Licensee Response Column" of the NRC's Reactor Oversight Process Action  
 
Matrix, as the result of Units 1 and 2 Yellow significance findings, the NRC will use the Action  
Matrix, as the result of Units 1 and 2 Yellow significance findings, the NRC will use the Action  
Matrix to determine the most appropriate NRC response to the findings' significance.  We will  
Matrix to determine the most appropriate NRC response to the findings' significance.  We will  
notify you, by separate correspondence, of that determination.  
notify you, by separate correspondence, of that determination.  


 
J. Browning  
J. Browning -3-  
-3-  
 
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice and Procedure," a copy of  
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice and Procedure," a copy of  
 
this letter, its enclosures, and your response will be made available electronically for public  
this letter, its enclosures, and your response  
inspection in the NRCs Public Document Room or from the NRCs Agencywide Documents  
will be made available electronically for public  
inspection in the NRC's Public Document R
oom or from the NRC's Agencywide Documents  
Access and Management System (ADAMS), accessible from the NRC website at  
Access and Management System (ADAMS), accessible from the NRC website at  
http://www.nrc.gov/reading-rm/adams.html.  To the extent possible, your response should not  
http://www.nrc.gov/reading-rm/adams.html.  To the extent possible, your response should not  
include any personal privacy, proprietary, or sa
include any personal privacy, proprietary, or safeguards information so that it can be made  
feguards information so that it can be made  
available to the Public without redaction.   
available to the Public without redaction.   
 
Sincerely,   
Sincerely,   
  /RA/   
   
  Marc L. Dapas  
/RA/  
 
   
   
Marc L. Dapas  
Regional Administrator   
Regional Administrator   
   
   
Dockets:  50-313; 50-368  
Dockets:  50-313; 50-368  
Licenses:  DPR-51; NPF-6  
Licenses:  DPR-51; NPF-6  
   
   
Enclosures:   
Enclosures:  
 
   
1.  Notice of Violation  
1.  Notice of Violation  
2.  Final Significance Determination


2.  Final Significance Determination


 
SUNSI Review
By: 
ADAMS
Yes    No
Publicly Available
Non-Publicly Available
Non-Sensitive
Sensitive
Keyword:
OFFICE
SPE:PBE
SRA:TSB
SRRA:NRR/
DRA/APHB
SES:ACES
C:ACES
RC:ORA
C:PBE
NAME
MBloodgood
DLoveless
JMitman
RBrowder
VCampbell
KFuller
GWerner
SIGNATURE
/RA/ jm for
via email
via email
/RA/
/RA/
/RA/
/RA/ TRF for
DATE
06/4/14
06/12/14
06/12/14
06/2/14
06/4/14
06/3/14
06/12/14
OFFICE
TL:NRR/
DRA/APHB
DD:DRP
D:DRP
OE
NRR
RA
NAME
JCircle
TPruett
KKennedy
LCasey
CSanders
MDapas
SIGNATURE
via email
/RA/
/RA/
via email
via email
/RA/
DATE
06/12/14
06/12/14
06/13/14
06/13/14
06/18/14
6/23/14
   
   
 


    SUNSI Review By:  ADAMS  Yes    No  Publicly Available  Non-Publicly Available  Non-Sensitive  Sensitive Keyword:  OFFICE SPE:PBE SRA:TSB SRRA:NRR/
DRA/APHB SES:ACES C:ACES RC:ORA C:PBE NAME MBloodgood DLoveless JMitman RBrowder VCampbell KFuller GWerner SIGNATURE /RA/ jm for via email via email /RA/ /RA/ /RA/ /RA/ TRF for DATE 06/4/14 06/12/14
06/12/14 06/2/14 06/4/14 06/3/14 06/12/14 OFFICE TL:NRR/ DRA/APHB DD:DRP D:DRP OE NRR RA  NAME JCircle TPruett KKennedy LCasey CSanders MDapas  SIGNATURE via email /RA/ /RA/ via email via email /RA/  DATE 06/12/14 06/12/
14 06/13/14 06/13/14 06/18/14 6/23/14 
  Letter to Jeremy Browning from Marc L. Dapas dated June 23, 2014
   
   
SUBJECT: ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 - FINAL SIGNIFICANCE  
Letter to Jeremy Browning from Marc L. Dapas dated June 23, 2014
SUBJECT:  
ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 - FINAL SIGNIFICANCE  
DETERMINATION OF TWO YELLOW FINDINGS AND NOTICE OF VIOLATION;  
DETERMINATION OF TWO YELLOW FINDINGS AND NOTICE OF VIOLATION;  
NRC INSPECTION REPORT 05000313/2014008 AND 05000368/2014008  
NRC INSPECTION REPORT 05000313/2014008 AND 05000368/2014008  
   
   
Distribution
Distribution  
RidsOpaMail Resource; RidsOeMailCenter Resource;  
RidsOpaMail Resource;  
OEWEB Resource;  
RidsOeMailCenter Resource;  
RidsSecyMailCenter Resource; RidsOcaMailCenter Resource;  RidsOgcMailCenter Resource;   
OEWEB Resource;
RidsEdoMailCenter Resource;  EDO_Managers;   RidsOigMailCenter Resource;  
RidsSecyMailCenter Resource;  
RidsOiMailCenter Resource;  RidsRgn1MailCenter Resource; RidsOcfoMailCenter Resource;  RidsRgn2MailCenter Resource;  RidsRgn3MailCenter Resource; NRREnforcement.Resource;  
RidsOcaMailCenter Resource;   
RidsNrrDirsEnforcement Resource;
RidsOgcMailCenter Resource;   
Marc.Dapas@nrc.gov
RidsEdoMailCenter Resource;   
; Karla.Fuller@nrc.gov
EDO_Managers;  
; Roy.Zimmerman@nrc.gov
; Anton.Vegel@nrc.gov
;  Bill.Maier@nrc.gov
RidsOigMailCenter Resource;  
; Nick.Hilton@nrc.gov
RidsOiMailCenter Resource;   
; Kriss.Kennedy@nrc.gov
RidsRgn1MailCenter Resource;  
; Jeff.Clark@nrc.gov
RidsOcfoMailCenter Resource;   
; John.Wray@nrc.gov;
RidsRgn2MailCenter Resource;   
  Troy.Pruett@nrc.gov
RidsRgn3MailCenter Resource;  
;  Geoffrey.Miller@nrc.gov;
NRREnforcement.Resource;  
David.Furst@nrc.gov
RidsNrrDirsEnforcement Resource;  
; Vivian.Campbell@nrc.gov
Marc.Dapas@nrc.gov;
; Rachel.Browder@nrc.gov
Karla.Fuller@nrc.gov;
; Gerald.Gulla@nrc.gov
Roy.Zimmerman@nrc.gov;
; Christi.Maier@nrc.gov
Anton.Vegel@nrc.gov;   
; Victor.Dricks@nrc.gov
Bill.Maier@nrc.gov;
; Lauren.Casey@nrc.gov
Nick.Hilton@nrc.gov;
; Marisa.Herrera@nrc.gov
Kriss.Kennedy@nrc.gov;
; Lara.Uselding@nrc.gov
Jeff.Clark@nrc.gov ;
; Robert.Carpenter@nrc.gov
John.Wray@nrc.gov;
; R4Enforcement; Jeffrey.Clark@nrc.gov
Troy.Pruett@nrc.gov;   
;  Robert.Fretz@nrc.gov
Geoffrey.Miller@nrc.gov;  
; Brian.Tindell@nrc.gov
David.Furst@nrc.gov;
;  Matthew.Young@nrc.gov
Vivian.Campbell@nrc.gov;
;  Carleen.Sanders@nrc.gov
Rachel.Browder@nrc.gov;
; Abin.Fairbanks@nrc.gov
Gerald.Gulla@nrc.gov;
;  Greg.Werner@nrc.gov
Christi.Maier@nrc.gov;
;  Michael.Bloodgood@nrc.gov
Victor.Dricks@nrc.gov;
;  Joseph.Nick@nrc.gov
Lauren.Casey@nrc.gov;
; Jim.Melfi@nrc.gov;  Gloria.Hatfield@nrc.gov
Marisa.Herrera@nrc.gov;
;  Peter.Bamford@nrc.gov
Lara.Uselding@nrc.gov;
; Lorretta.Williams@nrc.gov
Robert.Carpenter@nrc.gov;
;  Jenny.Weil@nrc.gov
R4Enforcement;  
;   
Jeffrey.Clark@nrc.gov;   
Robert.Fretz@nrc.gov;
Brian.Tindell@nrc.gov;   
Matthew.Young@nrc.gov;   
Carleen.Sanders@nrc.gov;
Abin.Fairbanks@nrc.gov;   
Greg.Werner@nrc.gov;   
Michael.Bloodgood@nrc.gov;   
Joseph.Nick@nrc.gov;
Jim.Melfi@nrc.gov;   
Gloria.Hatfield@nrc.gov;   
Peter.Bamford@nrc.gov;
Lorretta.Williams@nrc.gov;   
Jenny.Weil@nrc.gov;
   
   
   
   
 
  Enclosure 1
  NOTICE OF VIOLATION


   
   
Entergy Operations, Inc.       Dockets: 05-313, 05-368  
Arkansas Nuclear One, Units 1 and 2   Licenses: DRP-51, NPF-6  
Enclosure 1
NOTICE OF VIOLATION
Entergy Operations, Inc.
Dockets: 05-313, 05-368  
Arkansas Nuclear One, Units 1 and 2  
Licenses: DRP-51, NPF-6  
EA-14-008  
EA-14-008  
   
   
During an NRC inspection conducted between July 22, 2013, and February 10, 2014, a violation  
During an NRC inspection conducted between July 22, 2013, and February 10, 2014, a violation  
 
of NRC requirements was identified.  In accordance with the NRCs Enforcement Policy, the  
of NRC requirements was identified.  In accordance with the NRC's Enforcement Policy, the  
 
violation is listed below:   
violation is listed below:   
 
10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures and Drawings,"
10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures and Drawings,  
 
states, in part, that activities affecting quality shall be prescribed by documented  
states, in part, that activities affecting quality shall be prescribed by documented  
instructions, procedures, or drawings of a type appropriate to the circumstances and  
instructions, procedures, or drawings of a type appropriate to the circumstances and  
shall be accomplished in accordance with these instructions, procedures, or drawings.   
shall be accomplished in accordance with these instructions, procedures, or drawings.   
   
   
Quality Procedure EN-MA-119, "Material Hand
Quality Procedure EN-MA-119, Material Handling Program, Section 5.2[7], Temporary  
ling Program," Section 5.2[7], "Temporary  
Hoisting Assemblies, Step (a) states, in part, that vendor supplied temporary overhead  
Hoisting Assemblies," Step (a) states, in part, that vendor supplied temporary overhead  
 
cranes or supports, winch-driven hoisting or swing equipment, and other assemblies are  
cranes or supports, winch-driven hoisting or swing equipment, and other assemblies are  
required to be designed or approved by engineering support personnel.  The design is  
required to be designed or approved by engineering support personnel.  The design is  
required to be supported by detailed drawings, specifications, evaluations, and/or  
required to be supported by detailed drawings, specifications, evaluations, and/or  
certifications.   
certifications.   
   
   
Quality Procedure EN-MA-119, "Material Hand
Quality Procedure EN-MA-119, Material Handling Program, Section 5.2[7], Temporary  
ling Program," Section 5.2[7], "Temporary  
Hoisting Assemblies, Step (b) states, in part, that the assembly shall be designed for at  
Hoisting Assemblies," Step (b) states, in part, that the assembly shall be designed for at  
 
least 125 percent of the projected hook load and should be load tested and held for at  
least 125 percent of the projected hook load and should be load tested and held for at  
least 5 minutes at 125 percent of the actual load rating before initial use.  The assembly  
least 5 minutes at 125 percent of the actual load rating before initial use.  The assembly  
shall be load tested in all configurations for which it will be used.   
shall be load tested in all configurations for which it will be used.   
   
   
Contrary to the above, on March 31, 2013, the licensee did not accomplish the Unit 1  
Contrary to the above, on March 31, 2013, the licensee did not accomplish the Unit 1  
main turbine generator stator lift and move, an activity affecting quality, as prescribed by  
main turbine generator stator lift and move, an activity affecting quality, as prescribed by  
documented instructions and procedures.  Specifically:  
documented instructions and procedures.  Specifically:  
   
   
A. The licensee approved a design for the temporary hoisting assembly that was not  
A. The licensee approved a design for the temporary hoisting assembly that was not  
supported by detailed drawings, specifications, evaluations, and/or certifications.  The  
supported by detailed drawings, specifications, evaluations, and/or certifications.  The  
licensee failed to identify the load deficiencies in vendor Calculation 27619-C1, "Heavy  
licensee failed to identify the load deficiencies in vendor Calculation 27619-C1, "Heavy  
Lift Gantry Calculation," and the incorrectly sized component in the north tower  
Lift Gantry Calculation," and the incorrectly sized component in the north tower  
structure of the temporary hoisting assembly.  In addition, the temporary hoisting  
structure of the temporary hoisting assembly.  In addition, the temporary hoisting  
assembly was not designed for at least 125 percent of the projected hook load.   
assembly was not designed for at least 125 percent of the projected hook load.   
   
   
Line 319: Line 348:
   
   
As a result, on March 31, 2013, while lifting and transferring the Unit 1 main turbine  
As a result, on March 31, 2013, while lifting and transferring the Unit 1 main turbine  
generator stator, the temporary overhead crane collapsed causing the 525-ton stator to  
generator stator, the temporary overhead crane collapsed causing the 525-ton stator to  
fall on and extensively damage portions of the plant, affecting safety-related equipment.  
fall on and extensively damage portions of the plant, affecting safety-related equipment.  
   
   
This violation is associated with a Yellow (Unit 1) and a Yellow (Unit 2) significance  
This violation is associated with a Yellow (Unit 1) and a Yellow (Unit 2) significance  
determination finding.


determination finding.  
   
  2 Pursuant to the provisions of 10 CFR 2.201, Entergy Operations, Inc., is hereby required to  
2  
Pursuant to the provisions of 10 CFR 2.201, Entergy Operations, Inc., is hereby required to  
submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN:   
submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN:   
Document Control Desk, Washington, DC 20555-0001 with a copy to the Regional  
Document Control Desk, Washington, DC 20555-0001 with a copy to the Regional  
Administrator, Region IV, and a copy to the NRC resident inspector at the facility that is the  
Administrator, Region IV, and a copy to the NRC resident inspector at the facility that is the  
subject of this Notice, within 30 days of the date of the letter transmitting this Notice of Violation  
subject of this Notice, within 30 days of the date of the letter transmitting this Notice of Violation  
(Notice).  This reply should be clearly marked as a "Reply to a Notice of Violation; EA-14-008"  
(Notice).  This reply should be clearly marked as a "Reply to a Notice of Violation; EA-14-008"  
and should include for each violation:  (1) the reason for the violation, or, if contested, the basis  
and should include for each violation:  (1) the reason for the violation, or, if contested, the basis  
for disputing the violation or severity level; (2) the corrective steps that have been taken and the  
for disputing the violation or severity level; (2) the corrective steps that have been taken and the  
results achieved; (3) the corrective steps that will be taken; and (4) the date when full  
results achieved; (3) the corrective steps that will be taken; and (4) the date when full  
compliance will be achieved.   
compliance will be achieved.   
   
   
Your response may reference or include previous docketed correspondence, if the  
Your response may reference or include previous docketed correspondence, if the  
correspondence adequately addresses the required response.  If an adequate reply is not  
correspondence adequately addresses the required response.  If an adequate reply is not  
received within the time specified in this Notice, an order or a Demand for Information may be  
received within the time specified in this Notice, an order or a Demand for Information may be  
issued as to why the license should not be modified, suspended, or revoked, or why such other  
issued as to why the license should not be modified, suspended, or revoked, or why such other  
action as may be proper should not be taken.  Where good cause is shown, consideration will  
action as may be proper should not be taken.  Where good cause is shown, consideration will  
be given to extending the response time.   
be given to extending the response time.   
   
   
If you contest this enforcement action, you should  
If you contest this enforcement action, you should also provide a copy of your response, with  
also provide a copy of your response, with  
the basis for your denial, to the Director, Office of Enforcement, United States Nuclear  
the basis for your denial, to the Director, Office of Enforcement, United States Nuclear  
Regulatory Commission, Washington, DC 20555-0001.  
Regulatory Commission, Washington, DC 20555-0001.  
   
   
Because your response will be made available electronically for public inspection in the NRC's
Because your response will be made available electronically for public inspection in the NRCs
 
Public Document Room or from the NRCs document system (ADAMS), accessible from the  
Public Document Room or from the NRC's doc
NRC website at http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not  
ument system (ADAMS), accessible from the  
include any personal privacy, proprietary, or safeguards information so that it can be made  
NRC website at  
http://www.nrc.gov/reading-rm/adams.html , to the extent possible, it should not  
include any personal privacy, proprietary, or sa
feguards information so that it can be made  
available to the public without redaction.  If personal privacy or proprietary information is  
available to the public without redaction.  If personal privacy or proprietary information is  
 
necessary to provide an acceptable response, then please provide a bracketed copy of your  
necessary to provide an acceptable response, t
hen please provide a bracketed copy of your  
response that identifies the information that should be protected and a redacted copy of your  
response that identifies the information that should be protected and a redacted copy of your  
response that deletes such information.   
response that deletes such information.   
   
   
If you request withholding of such material, you must
If you request withholding of such material, you must specifically identify the portions of your  
specifically identify the portions of your  
response that you seek to have withheld and provide in detail the bases for your claim of  
response that you seek to have withheld and provide in detail the bases for your claim of  
withholding (e.g., explain why the disclosure of information will create an unwarranted invasion  
withholding (e.g., explain why the disclosure of information will create an unwarranted invasion  
of personal privacy or provide the information required by 10 CFR 2.390(b) to support a request  
of personal privacy or provide the information required by 10 CFR 2.390(b) to support a request  
for withholding confidential commercial or financial information).  If safeguards information is  
for withholding confidential commercial or financial information).  If safeguards information is  
necessary to provide an acceptable response, please provide the level of protection described  
necessary to provide an acceptable response, please provide the level of protection described  
in 10 CFR 73.21.   
in 10 CFR 73.21.   
Dated this 23rd day of June 2014


   
   
Dated this 23rd day of June 2014  
   
  Enclosure 2  
Enclosure 2  
Arkansas Nuclear One Dropped Stator  
Arkansas Nuclear One Dropped Stator  
Final Significance Determination  
Final Significance Determination  
Line 404: Line 408:
   
   
During the regulatory conference held on May 1, 2014, your staff described their assessment of  
During the regulatory conference held on May 1, 2014, your staff described their assessment of  
the significance of the finding for each unit.  Specifically, your staff discussed differences for  
the significance of the finding for each unit.  Specifically, your staff discussed differences for  
 
Units 1 and 2 that existed between the NRCs preliminary significance determination and  
Units 1 and 2 that existed between the NRC's preliminary significance determination and  
Arkansas Nuclear Ones risk assessment.  The differences for each unit were evaluated and are  
 
Arkansas Nuclear One's risk assessment.  The differences for each unit were evaluated and are  
 
discussed below.  
discussed below.  
 
Unit 1  1. Your staff specified a time to boil of 12 hours and a time to core uncovery of 115 hours  
Unit 1  
   
1. Your staff specified a time to boil of 12 hours and a time to core uncovery of 115 hours  
versus NRC values of 11 hours and 96 hours, respectively.  
versus NRC values of 11 hours and 96 hours, respectively.  
  We determined that the change in the time to boil had minimal impact on the risk evaluation.  
   
 
We determined that the change in the time to boil had minimal impact on the risk evaluation.  
Using the 115 hours for time to core uncovery, the total conditional core damage probability  
Using the 115 hours for time to core uncovery, the total conditional core damage probability  
 
was reduced from 3.8 x 10-4 to 2.6 x 10-4.
was reduced from 3.8 x 10
-4 to 2.6 x 10
-4.  
2. Your staff described three success paths to recover offsite power, and that during the actual  
2. Your staff described three success paths to recover offsite power, and that during the actual  
event, Entergy Operations, Inc., personnel were successful in establishing a temporary  
event, Entergy Operations, Inc., personnel were successful in establishing a temporary  
electrical connection between the switchyard and the 4160V safety buses within 4.4 days of  
electrical connection between the switchyard and the 4160V safety buses within 4.4 days of  
the event initiation, contrary to the NRC using 6 days in our preliminary risk analysis.  As  
the event initiation, contrary to the NRC using 6 days in our preliminary risk analysis.  As  
part of their analysis, your staff developed an estimated probability of successful recovery of  
part of their analysis, your staff developed an estimated probability of successful recovery of  
97 percent.   
97 percent.   
  After reviewing the information that your staff provided during the regulatory conference, we  
   
 
After reviewing the information that your staff provided during the regulatory conference, we  
agree that the recovery of offsite power was feasible within the time to core uncovery.  It is  
agree that the recovery of offsite power was feasible within the time to core uncovery.  It is  
important to note that there was an extended period of time before core uncovery would  
important to note that there was an extended period of time before core uncovery would  
occur and this was the primary reason that we determined you could recover offsite power  
occur and this was the primary reason that we determined you could recover offsite power  
with a high chance of success.  Accordingly, we determined that a 90 percent probability of  
with a high chance of success.  Accordingly, we determined that a 90 percent probability of  
success for recovering electrical power best reflects the broader spectrum of possible  
success for recovering electrical power best reflects the broader spectrum of possible  
scenarios that could be present during a station blackout where the environmental  
scenarios that could be present during a station blackout where the environmental  
conditions would be degraded; fewer personnel would be available to respond based on the  
conditions would be degraded; fewer personnel would be available to respond based on the  
escalation of emergency action level classification; and a higher level of stress would be  
escalation of emergency action level classification; and a higher level of stress would be  
imposed on those planning, implementing, testing, and approving the new and non-
imposed on those planning, implementing, testing, and approving the new and non-
procedural modifications for recovering offsite power.  Using this high probability of success,  
procedural modifications for recovering offsite power.  Using this high probability of success,  
we determined that the risk estimate should be reduced to 6 x 10
we determined that the risk estimate should be reduced to 6 x 10-5.    
-5.    
3. Your staff also described a success path to restore power to the borated water recirculation  
3. Your staff also described a success path to restore power to the borated water recirculation  
pump for reactor coolant system makeup.  
pump for reactor coolant system makeup.  
  During the conference, your staff indicated that temporary 480V power could be supplied  
   
 
During the conference, your staff indicated that temporary 480V power could be supplied  
to the borated water recirculation pump and water could be supplied to the reactor from  
to the borated water recirculation pump and water could be supplied to the reactor from  
the borated water storage tank; however, your staff discussed that restoration of the  
the borated water storage tank; however, your staff discussed that restoration of the  
4160V buses would be the priority because of the varied equipment that could be powered  
4160V buses would be the priority because of the varied equipment that could be powered  
and used to keep the core covered.  Although at the regulatory conference, your staff  
and used to keep the core covered.  Although at the regulatory conference, your staff  
presented power restoration to the borated water recirculation pump as a potential success  
presented power restoration to the borated water recirculation pump as a potential success  
path to establishing makeup water to the reactor, they indicated that this option was not  
path to establishing makeup water to the reactor, they indicated that this option was not  
evaluated, during the event.  Similar to the three success paths for recovering offsite power


evaluated, during the event. Similar to the three success paths for recovering offsite power  
   
  2 referenced above, temporary power cables w
ould have to be run from an offsite power  
   
2  
referenced above, temporary power cables would have to be run from an offsite power  
source into the plant in order to energize the 480V bus associated with the borated water  
source into the plant in order to energize the 480V bus associated with the borated water  
recirculation pump.  This evolution would need to be conducted during challenging adverse  
recirculation pump.  This evolution would need to be conducted during challenging adverse  
plant conditions associated with flood water accumulation from a ruptured fire protection  
plant conditions associated with flood water accumulation from a ruptured fire protection  
 
header, as well as reduced lighting and elevated room temperatures resulting from a station  
header, as well as reduced lighting and elevated room
temperatures resulting from a station  
blackout.  These adverse plant conditions, in our view, would affect the probability of  
blackout.  These adverse plant conditions, in our view, would affect the probability of  
success in pursuing this path to provide for reactor coolant system makeup, and as such,  
success in pursuing this path to provide for reactor coolant system makeup, and as such,  
the appropriate probability of success is 90 percent.  Consequently, we determined that this  
the appropriate probability of success is 90 percent.  Consequently, we determined that this  
was affectively another method of restoring offsite power, so no additional credit was  
was affectively another method of restoring offsite power, so no additional credit was  
warranted.   
warranted.   
   
   
In summary, we reduced our Unit 1 preliminary risk assessment to 6 x 10
In summary, we reduced our Unit 1 preliminary risk assessment to 6 x 10-5 (Yellow) because we  
-5 (Yellow) because we  
determined a high likelihood of success (90 percent) existed for recovering electrical power  
determined a high likelihood of success (90 percent) existed for recovering electrical power  
based on the time available to complete those actions prior to core uncovery.  
based on the time available to complete those actions prior to core uncovery.  
 
Unit 2  Your staff stated during the regulatory conference, that there were three methods of restoring  
Unit 2  
   
Your staff stated during the regulatory conference, that there were three methods of restoring  
vital power to risk-important equipment that were not credited by the NRC in the preliminary  
vital power to risk-important equipment that were not credited by the NRC in the preliminary  
significance determination:  
significance determination:  
   
   
1. Your staff indicated that Switchgear 2A2, while not powered throughout the event, was  
1. Your staff indicated that Switchgear 2A2, while not powered throughout the event, was  
always capable of being restored via the Startup 2 transformer.  Additionally, your staff  
always capable of being restored via the Startup 2 transformer.  Additionally, your staff  
stated that changes in your probabilistic risk model of record were made to account for  
stated that changes in your probabilistic risk model of record were made to account for  
operator actions specifically related to the load shed breakers on 4160V Bus 2A2.  This  
operator actions specifically related to the load shed breakers on 4160V Bus 2A2.  This  
change added a non-recovery probability for operators to manually manipulate the breakers  
change added a non-recovery probability for operators to manually manipulate the breakers  
should they fail to operate automatically.  
should they fail to operate automatically.  
  We reviewed the NRC's standardized plant analysis risk model and determined that  
   
 
We reviewed the NRC's standardized plant analysis risk model and determined that  
operators aligning Bus 2A2 to offsite power (Startup 2 transformer) and the human error  
operators aligning Bus 2A2 to offsite power (Startup 2 transformer) and the human error  
probability of operators failing to align 4160V Bus 2A2 to offsite power under conditions  
probability of operators failing to align 4160V Bus 2A2 to offsite power under conditions  
following the stator drop were already incorporated into our preliminary significance  
following the stator drop were already incorporated into our preliminary significance  
determination.  The environmental conditions of debris and water surrounding the  
determination.  The environmental conditions of debris and water surrounding the  
switchgear area after the load drop event and the increased stress level of operations  
switchgear area after the load drop event and the increased stress level of operations  
personnel could complicate recovery.  Taking these factors into account would increase the  
personnel could complicate recovery.  Taking these factors into account would increase the  
probability of non-recovery of 4160V Bus 2A2.  Therefore, we determined that no additional  
probability of non-recovery of 4160V Bus 2A2.  Therefore, we determined that no additional  
reduction of the human error probability for recovery of 4160V Bus 2A2 involving manual  
reduction of the human error probability for recovery of 4160V Bus 2A2 involving manual  
action to manipulate the associated load shed breakers, relative to the human error  
action to manipulate the associated load shed breakers, relative to the human error  
probability used in our preliminary significance determination, was warranted.   
probability used in our preliminary significance determination, was warranted.   
 
2. Your staff indicated that the alternate ac diesel generator and the 4160V Bus 2A9 supply to  
2. Your staff indicated that the alternate ac diesel generator and the 4160V Bus 2A9 supply to  
Unit 2 buses were damaged, but available throughout the event.  Your staff also stated that  
Unit 2 buses were damaged, but available throughout the event.  Your staff also stated that  
Unit 2 control room operators would have used the alternate ac diesel generator in the event  
Unit 2 control room operators would have used the alternate ac diesel generator in the event  
of a station blackout because they were unaware of any damage to 4160V Bus 2A9.  
of a station blackout because they were unaware of any damage to 4160V Bus 2A9.  
  We determined that plant staff were aware of the potential damage to 4160V Bus 2A1,  
   
We determined that plant staff were aware of the potential damage to 4160V Bus 2A1,  
located next to Bus 2A9, and operators at both units would have been notified of damage to  
located next to Bus 2A9, and operators at both units would have been notified of damage to  
4160V Bus 2A9, in accordance with site procedures.  This is based on the fact that Unit 1  
4160V Bus 2A9, in accordance with site procedures.  This is based on the fact that Unit 1  
operators were aware of the damage to alternate ac diesel generator output electrical  
operators were aware of the damage to alternate ac diesel generator output electrical  
connections to Bus 2A9 for Unit 1, and that Procedure 2104.037, Alternate AC Diesel


connections to Bus 2A9 for Unit 1, and that Procedure 2104.037, "Alternate AC Diesel  
   
  3 Generator Operations," contains a number of steps for the Unit 2 operators to notify and  
3  
Generator Operations, contains a number of steps for the Unit 2 operators to notify and  
coordinate with the Unit 1 operators before starting and loading the alternate ac diesel  
coordinate with the Unit 1 operators before starting and loading the alternate ac diesel  
generator.  We believe that the Unit 1 operators would have informed the Unit 2 operators of  
generator.  We believe that the Unit 1 operators would have informed the Unit 2 operators of  
the damage to electrical buses.  We further concluded that it was reasonable to assume that  
the damage to electrical buses.  We further concluded that it was reasonable to assume that  
the Unit 2 operators would have requested an investigation of the bus condition before using  
the Unit 2 operators would have requested an investigation of the bus condition before using  
the alternate ac diesel generator.   
the alternate ac diesel generator.   
   
   
We determined that investigation, repair, and/or testing of the bus condition by maintenance  
We determined that investigation, repair, and/or testing of the bus condition by maintenance  
personnel would have taken longer than the time to core damage following a postulated  
personnel would have taken longer than the time to core damage following a postulated  
station blackout with failure of the turbine-driven emergency feedwater pump.  Therefore, no  
station blackout with failure of the turbine-driven emergency feedwater pump.  Therefore, no  
recovery credit was applied to short (1 hour) core damage sequences.  However, we did  
recovery credit was applied to short (1 hour) core damage sequences.  However, we did  
determine that applying recovery credit for 8-hour sequences would reduce the conditional  
determine that applying recovery credit for 8-hour sequences would reduce the conditional  
core damage probability to 1.2 X 10
core damage probability to 1.2 X 10-5 (Yellow).  
-5 (Yellow).  
   
  3. Your staff indicated that the ability to cross-tie vital 4160V Buses 2A3 and 2A4 was available  
3. Your staff indicated that the ability to cross-tie vital 4160V Buses 2A3 and 2A4 was available  
to the operators and not credited in the NRC's preliminary significance determination.  
to the operators and not credited in the NRC's preliminary significance determination.  
   
   
We determined that the ability to cross-tie the 4160V vital buses would not significantly  
We determined that the ability to cross-tie the 4160V vital buses would not significantly  
impact the final results.  In the dominant accident sequence, having one energized vital bus  
impact the final results.  In the dominant accident sequence, having one energized vital bus  
 
was already considered "electrical success," and any additional electrical system recovery  
was already considered "electrical success," and  
to power the opposite vital bus would have a minimal impact on the overall risk assessment  
any additional electrical system recovery  
to power the opposite vital bus would have a  
minimal impact on the overall risk assessment  
result.   
result.   
   
   
In summary, we concluded that our Unit 2 preliminary risk assessment of 2.8 x 10
In summary, we concluded that our Unit 2 preliminary risk assessment of 2.8 x 10-5 (Yellow)  
-5 (Yellow) appropriately characterized the risk significance of the finding and that the information presented  
appropriately characterized the risk significance of the finding and that the information presented  
 
at the regulatory conference did not appreciably change the final risk determination.
at the regulatory conference did not appreciably change the final risk determination.
}}
}}

Latest revision as of 20:12, 10 January 2025

EA-14-008_Arkansas Nuclear One, Units 1 and 2 - Final Significance Determination of Two Yellow Findings and Notice of Violation; NRC Inspection Report 05000313/2014008 and 05000368/2014008
ML14174A832
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 06/23/2014
From: Dapas M
NRC Region 4
To: Jeremy G. Browning
Entergy Operations
References
EA-14-008 IR-14-008
Download: ML14174A832 (10)


See also: IR 05000313/2014008

Text

June 23, 2014

EA-14-008

Jeremy Browning, Site Vice President

Entergy Operations, Inc.

Arkansas Nuclear One

1448 SR 333

Russellville, AR 72802-0967

SUBJECT: ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 - FINAL SIGNIFICANCE

DETERMINATION OF TWO YELLOW FINDINGS AND NOTICE OF VIOLATION;

NRC INSPECTION REPORT 05000313/2014008 AND 05000368/2014008

Dear Mr. Browning:

This letter provides you the final significance determination of the preliminary Red and Yellow

findings identified in NRC Inspection Report 05000313/2013012; 05000368/2013012

(ML14083A409), dated March 24, 2014. A detailed description of the findings is contained in

Section 4OA3.9 of that report. The findings are associated with the March 31, 2013, Unit 1

stator drop that affected safety-related equipment on both units.

At your request, a Regulatory Conference was held on May 1, 2014, to further discuss your

views on these findings. A copy of your presentation provided at this meeting is attached to the

summary of the Regulatory Conference (ML14128A512), dated May 9, 2014. In your

presentation on the risk significance of the event related to Unit 1, you described four recovery

actions that plant personnel could have implemented to establish and maintain cooling to the

reactor core in the event that the emergency diesel generators were not able to supply power to

the 4160V electrical buses. Three of these methods involved restoring power to 4160V safety-

related electrical buses from other sources. The fourth recovery method involved providing

temporary 480V ac power to a borated water recirculating pump, and establishing a source of

water to the reactor from the borated water storage tank.

Based on your staff's evaluation of the probability of success of the four recovery actions, and

the amount of time that existed to restore cooling to the core, your staff concluded that the

change in core damage probability was 4.8 x 10-6. As a result, you concluded that the

inspection finding should be characterized as White, low-to-moderate safety significance.

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

1600 E LAMAR BLVD

ARLINGTON, TX 76011-4511

J. Browning

-2-

In your presentation on the risk significance of the event related to Unit 2, you described three

procedurally directed recovery strategies that plant personnel could have implemented to

restore electrical power in the event that power was lost to vital electrical buses. These

strategies involved supplying power from the Startup 2 transformer, or the alternate ac diesel

generator to electrical buses, and cross connecting the vital 4160V buses to supply power to

equipment. Based on your staff's evaluation of the probability of success of these three

procedurally directed recovery strategies, your staff concluded that the change in conditional

core damage probability was 1.8 x 10-6. As a result, you concluded that this inspection finding

should also be characterized as White, low-to-moderate safety significance.

After considering the information developed during the inspection and the information you

provided at the Regulatory Conference, we have concluded that the risk significance of each

finding is appropriately characterized as Yellow, substantial safety significance, for both Units 1

and 2. Our evaluation of the risk significance of each inspection finding is provided in

Enclosure 2 of this letter.

You have 30 calendar days from the date of this letter to appeal the staffs determination of

significance for the identified Yellow findings. Such appeals will be considered to have merit

only if they meet the criteria given in Inspection Manual Chapter 0609, Significance

Determination Process, Attachment 2. An appeal must be sent in writing to the Regional

Administrator, Region IV, 1600 E. Lamar Blvd., Arlington, TX 76011-4511.

The NRC has also determined that the failure to follow procedures to ensure that a temporary

lift assembly was designed to support the projected load and to perform a 125 percent load test

for the projected load is a violation of Title 10 of the Code of Federal Regulations (CFR) Part 50,

Appendix B, Criteria V, Instructions, Procedures and Drawings, as cited in the attached Notice

of Violation. In accordance with the NRCs Enforcement Policy, the Notice is considered

escalated enforcement action because it is associated with Yellow findings for Units 1 and 2.

You are required to respond to this letter and should follow the instructions specified in the

enclosed Notice when preparing your response. If you have additional information that you

believe the NRC should consider, you may provide it in your response to the Notice. The NRCs

review of your response to the Notice will also determine whether further enforcement action is

necessary to ensure compliance with regulatory requirements.

Because plant performance at the Arkansas Nuclear One facility has been determined to be

beyond the "Licensee Response Column" of the NRCs Reactor Oversight Process Action

Matrix, as the result of Units 1 and 2 Yellow significance findings, the NRC will use the Action

Matrix to determine the most appropriate NRC response to the findings' significance. We will

notify you, by separate correspondence, of that determination.

J. Browning

-3-

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice and Procedure," a copy of

this letter, its enclosures, and your response will be made available electronically for public

inspection in the NRCs Public Document Room or from the NRCs Agencywide Documents

Access and Management System (ADAMS), accessible from the NRC website at

http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not

include any personal privacy, proprietary, or safeguards information so that it can be made

available to the Public without redaction.

Sincerely,

/RA/

Marc L. Dapas

Regional Administrator

Dockets: 50-313; 50-368

Licenses: DPR-51; NPF-6

Enclosures:

1. Notice of Violation

2. Final Significance Determination

SUNSI Review

By:

ADAMS

Yes No

Publicly Available

Non-Publicly Available

Non-Sensitive

Sensitive

Keyword:

OFFICE

SPE:PBE

SRA:TSB

SRRA:NRR/

DRA/APHB

SES:ACES

C:ACES

RC:ORA

C:PBE

NAME

MBloodgood

DLoveless

JMitman

RBrowder

VCampbell

KFuller

GWerner

SIGNATURE

/RA/ jm for

via email

via email

/RA/

/RA/

/RA/

/RA/ TRF for

DATE

06/4/14

06/12/14

06/12/14

06/2/14

06/4/14

06/3/14

06/12/14

OFFICE

TL:NRR/

DRA/APHB

DD:DRP

D:DRP

OE

NRR

RA

NAME

JCircle

TPruett

KKennedy

LCasey

CSanders

MDapas

SIGNATURE

via email

/RA/

/RA/

via email

via email

/RA/

DATE

06/12/14

06/12/14

06/13/14

06/13/14

06/18/14

6/23/14

Letter to Jeremy Browning from Marc L. Dapas dated June 23, 2014

SUBJECT:

ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 - FINAL SIGNIFICANCE

DETERMINATION OF TWO YELLOW FINDINGS AND NOTICE OF VIOLATION;

NRC INSPECTION REPORT 05000313/2014008 AND 05000368/2014008

Distribution

RidsOpaMail Resource;

RidsOeMailCenter Resource;

OEWEB Resource;

RidsSecyMailCenter Resource;

RidsOcaMailCenter Resource;

RidsOgcMailCenter Resource;

RidsEdoMailCenter Resource;

EDO_Managers;

RidsOigMailCenter Resource;

RidsOiMailCenter Resource;

RidsRgn1MailCenter Resource;

RidsOcfoMailCenter Resource;

RidsRgn2MailCenter Resource;

RidsRgn3MailCenter Resource;

NRREnforcement.Resource;

RidsNrrDirsEnforcement Resource;

Marc.Dapas@nrc.gov;

Karla.Fuller@nrc.gov;

Roy.Zimmerman@nrc.gov;

Anton.Vegel@nrc.gov;

Bill.Maier@nrc.gov;

Nick.Hilton@nrc.gov;

Kriss.Kennedy@nrc.gov;

Jeff.Clark@nrc.gov ;

John.Wray@nrc.gov;

Troy.Pruett@nrc.gov;

Geoffrey.Miller@nrc.gov;

David.Furst@nrc.gov;

Vivian.Campbell@nrc.gov;

Rachel.Browder@nrc.gov;

Gerald.Gulla@nrc.gov;

Christi.Maier@nrc.gov;

Victor.Dricks@nrc.gov;

Lauren.Casey@nrc.gov;

Marisa.Herrera@nrc.gov;

Lara.Uselding@nrc.gov;

Robert.Carpenter@nrc.gov;

R4Enforcement;

Jeffrey.Clark@nrc.gov;

Robert.Fretz@nrc.gov;

Brian.Tindell@nrc.gov;

Matthew.Young@nrc.gov;

Carleen.Sanders@nrc.gov;

Abin.Fairbanks@nrc.gov;

Greg.Werner@nrc.gov;

Michael.Bloodgood@nrc.gov;

Joseph.Nick@nrc.gov;

Jim.Melfi@nrc.gov;

Gloria.Hatfield@nrc.gov;

Peter.Bamford@nrc.gov;

Lorretta.Williams@nrc.gov;

Jenny.Weil@nrc.gov;

Enclosure 1

NOTICE OF VIOLATION

Entergy Operations, Inc.

Dockets: 05-313,05-368

Arkansas Nuclear One, Units 1 and 2

Licenses: DRP-51, NPF-6

EA-14-008

During an NRC inspection conducted between July 22, 2013, and February 10, 2014, a violation

of NRC requirements was identified. In accordance with the NRCs Enforcement Policy, the

violation is listed below:

10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures and Drawings,

states, in part, that activities affecting quality shall be prescribed by documented

instructions, procedures, or drawings of a type appropriate to the circumstances and

shall be accomplished in accordance with these instructions, procedures, or drawings.

Quality Procedure EN-MA-119, Material Handling Program, Section 5.2[7], Temporary

Hoisting Assemblies, Step (a) states, in part, that vendor supplied temporary overhead

cranes or supports, winch-driven hoisting or swing equipment, and other assemblies are

required to be designed or approved by engineering support personnel. The design is

required to be supported by detailed drawings, specifications, evaluations, and/or

certifications.

Quality Procedure EN-MA-119, Material Handling Program, Section 5.2[7], Temporary

Hoisting Assemblies, Step (b) states, in part, that the assembly shall be designed for at

least 125 percent of the projected hook load and should be load tested and held for at

least 5 minutes at 125 percent of the actual load rating before initial use. The assembly

shall be load tested in all configurations for which it will be used.

Contrary to the above, on March 31, 2013, the licensee did not accomplish the Unit 1

main turbine generator stator lift and move, an activity affecting quality, as prescribed by

documented instructions and procedures. Specifically:

A. The licensee approved a design for the temporary hoisting assembly that was not

supported by detailed drawings, specifications, evaluations, and/or certifications. The

licensee failed to identify the load deficiencies in vendor Calculation 27619-C1, "Heavy

Lift Gantry Calculation," and the incorrectly sized component in the north tower

structure of the temporary hoisting assembly. In addition, the temporary hoisting

assembly was not designed for at least 125 percent of the projected hook load.

B. The licensee failed to perform a load test in all configurations for which the

temporary hoisting assembly would be used.

As a result, on March 31, 2013, while lifting and transferring the Unit 1 main turbine

generator stator, the temporary overhead crane collapsed causing the 525-ton stator to

fall on and extensively damage portions of the plant, affecting safety-related equipment.

This violation is associated with a Yellow (Unit 1) and a Yellow (Unit 2) significance

determination finding.

2

Pursuant to the provisions of 10 CFR 2.201, Entergy Operations, Inc., is hereby required to

submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001 with a copy to the Regional

Administrator, Region IV, and a copy to the NRC resident inspector at the facility that is the

subject of this Notice, within 30 days of the date of the letter transmitting this Notice of Violation

(Notice). This reply should be clearly marked as a "Reply to a Notice of Violation; EA-14-008"

and should include for each violation: (1) the reason for the violation, or, if contested, the basis

for disputing the violation or severity level; (2) the corrective steps that have been taken and the

results achieved; (3) the corrective steps that will be taken; and (4) the date when full

compliance will be achieved.

Your response may reference or include previous docketed correspondence, if the

correspondence adequately addresses the required response. If an adequate reply is not

received within the time specified in this Notice, an order or a Demand for Information may be

issued as to why the license should not be modified, suspended, or revoked, or why such other

action as may be proper should not be taken. Where good cause is shown, consideration will

be given to extending the response time.

If you contest this enforcement action, you should also provide a copy of your response, with

the basis for your denial, to the Director, Office of Enforcement, United States Nuclear

Regulatory Commission, Washington, DC 20555-0001.

Because your response will be made available electronically for public inspection in the NRCs

Public Document Room or from the NRCs document system (ADAMS), accessible from the

NRC website at http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not

include any personal privacy, proprietary, or safeguards information so that it can be made

available to the public without redaction. If personal privacy or proprietary information is

necessary to provide an acceptable response, then please provide a bracketed copy of your

response that identifies the information that should be protected and a redacted copy of your

response that deletes such information.

If you request withholding of such material, you must specifically identify the portions of your

response that you seek to have withheld and provide in detail the bases for your claim of

withholding (e.g., explain why the disclosure of information will create an unwarranted invasion

of personal privacy or provide the information required by 10 CFR 2.390(b) to support a request

for withholding confidential commercial or financial information). If safeguards information is

necessary to provide an acceptable response, please provide the level of protection described

in 10 CFR 73.21.

Dated this 23rd day of June 2014

Enclosure 2

Arkansas Nuclear One Dropped Stator

Final Significance Determination

During the regulatory conference held on May 1, 2014, your staff described their assessment of

the significance of the finding for each unit. Specifically, your staff discussed differences for

Units 1 and 2 that existed between the NRCs preliminary significance determination and

Arkansas Nuclear Ones risk assessment. The differences for each unit were evaluated and are

discussed below.

Unit 1

1. Your staff specified a time to boil of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and a time to core uncovery of 115 hours0.00133 days <br />0.0319 hours <br />1.901455e-4 weeks <br />4.37575e-5 months <br />

versus NRC values of 11 hours1.273148e-4 days <br />0.00306 hours <br />1.818783e-5 weeks <br />4.1855e-6 months <br /> and 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br />, respectively.

We determined that the change in the time to boil had minimal impact on the risk evaluation.

Using the 115 hours0.00133 days <br />0.0319 hours <br />1.901455e-4 weeks <br />4.37575e-5 months <br /> for time to core uncovery, the total conditional core damage probability

was reduced from 3.8 x 10-4 to 2.6 x 10-4.

2. Your staff described three success paths to recover offsite power, and that during the actual

event, Entergy Operations, Inc., personnel were successful in establishing a temporary

electrical connection between the switchyard and the 4160V safety buses within 4.4 days of

the event initiation, contrary to the NRC using 6 days in our preliminary risk analysis. As

part of their analysis, your staff developed an estimated probability of successful recovery of

97 percent.

After reviewing the information that your staff provided during the regulatory conference, we

agree that the recovery of offsite power was feasible within the time to core uncovery. It is

important to note that there was an extended period of time before core uncovery would

occur and this was the primary reason that we determined you could recover offsite power

with a high chance of success. Accordingly, we determined that a 90 percent probability of

success for recovering electrical power best reflects the broader spectrum of possible

scenarios that could be present during a station blackout where the environmental

conditions would be degraded; fewer personnel would be available to respond based on the

escalation of emergency action level classification; and a higher level of stress would be

imposed on those planning, implementing, testing, and approving the new and non-

procedural modifications for recovering offsite power. Using this high probability of success,

we determined that the risk estimate should be reduced to 6 x 10-5.

3. Your staff also described a success path to restore power to the borated water recirculation

pump for reactor coolant system makeup.

During the conference, your staff indicated that temporary 480V power could be supplied

to the borated water recirculation pump and water could be supplied to the reactor from

the borated water storage tank; however, your staff discussed that restoration of the

4160V buses would be the priority because of the varied equipment that could be powered

and used to keep the core covered. Although at the regulatory conference, your staff

presented power restoration to the borated water recirculation pump as a potential success

path to establishing makeup water to the reactor, they indicated that this option was not

evaluated, during the event. Similar to the three success paths for recovering offsite power

2

referenced above, temporary power cables would have to be run from an offsite power

source into the plant in order to energize the 480V bus associated with the borated water

recirculation pump. This evolution would need to be conducted during challenging adverse

plant conditions associated with flood water accumulation from a ruptured fire protection

header, as well as reduced lighting and elevated room temperatures resulting from a station

blackout. These adverse plant conditions, in our view, would affect the probability of

success in pursuing this path to provide for reactor coolant system makeup, and as such,

the appropriate probability of success is 90 percent. Consequently, we determined that this

was affectively another method of restoring offsite power, so no additional credit was

warranted.

In summary, we reduced our Unit 1 preliminary risk assessment to 6 x 10-5 (Yellow) because we

determined a high likelihood of success (90 percent) existed for recovering electrical power

based on the time available to complete those actions prior to core uncovery.

Unit 2

Your staff stated during the regulatory conference, that there were three methods of restoring

vital power to risk-important equipment that were not credited by the NRC in the preliminary

significance determination:

1. Your staff indicated that Switchgear 2A2, while not powered throughout the event, was

always capable of being restored via the Startup 2 transformer. Additionally, your staff

stated that changes in your probabilistic risk model of record were made to account for

operator actions specifically related to the load shed breakers on 4160V Bus 2A2. This

change added a non-recovery probability for operators to manually manipulate the breakers

should they fail to operate automatically.

We reviewed the NRC's standardized plant analysis risk model and determined that

operators aligning Bus 2A2 to offsite power (Startup 2 transformer) and the human error

probability of operators failing to align 4160V Bus 2A2 to offsite power under conditions

following the stator drop were already incorporated into our preliminary significance

determination. The environmental conditions of debris and water surrounding the

switchgear area after the load drop event and the increased stress level of operations

personnel could complicate recovery. Taking these factors into account would increase the

probability of non-recovery of 4160V Bus 2A2. Therefore, we determined that no additional

reduction of the human error probability for recovery of 4160V Bus 2A2 involving manual

action to manipulate the associated load shed breakers, relative to the human error

probability used in our preliminary significance determination, was warranted.

2. Your staff indicated that the alternate ac diesel generator and the 4160V Bus 2A9 supply to

Unit 2 buses were damaged, but available throughout the event. Your staff also stated that

Unit 2 control room operators would have used the alternate ac diesel generator in the event

of a station blackout because they were unaware of any damage to 4160V Bus 2A9.

We determined that plant staff were aware of the potential damage to 4160V Bus 2A1,

located next to Bus 2A9, and operators at both units would have been notified of damage to

4160V Bus 2A9, in accordance with site procedures. This is based on the fact that Unit 1

operators were aware of the damage to alternate ac diesel generator output electrical

connections to Bus 2A9 for Unit 1, and that Procedure 2104.037, Alternate AC Diesel

3

Generator Operations, contains a number of steps for the Unit 2 operators to notify and

coordinate with the Unit 1 operators before starting and loading the alternate ac diesel

generator. We believe that the Unit 1 operators would have informed the Unit 2 operators of

the damage to electrical buses. We further concluded that it was reasonable to assume that

the Unit 2 operators would have requested an investigation of the bus condition before using

the alternate ac diesel generator.

We determined that investigation, repair, and/or testing of the bus condition by maintenance

personnel would have taken longer than the time to core damage following a postulated

station blackout with failure of the turbine-driven emergency feedwater pump. Therefore, no

recovery credit was applied to short (1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />) core damage sequences. However, we did

determine that applying recovery credit for 8-hour sequences would reduce the conditional

core damage probability to 1.2 X 10-5 (Yellow).

3. Your staff indicated that the ability to cross-tie vital 4160V Buses 2A3 and 2A4 was available

to the operators and not credited in the NRC's preliminary significance determination.

We determined that the ability to cross-tie the 4160V vital buses would not significantly

impact the final results. In the dominant accident sequence, having one energized vital bus

was already considered "electrical success," and any additional electrical system recovery

to power the opposite vital bus would have a minimal impact on the overall risk assessment

result.

In summary, we concluded that our Unit 2 preliminary risk assessment of 2.8 x 10-5 (Yellow)

appropriately characterized the risk significance of the finding and that the information presented

at the regulatory conference did not appreciably change the final risk determination.