ML17300A036: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(One intermediate revision by the same user not shown) | |||
Line 2: | Line 2: | ||
| number = ML17300A036 | | number = ML17300A036 | ||
| issue date = 10/31/2017 | | issue date = 10/31/2017 | ||
| title = | | title = Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment Request Related to Emergency Diesel Generator Technical Specifications | ||
| author name = Kuntz R | | author name = Kuntz R | ||
| author affiliation = NRC/NRR/DORL/LPLIII | | author affiliation = NRC/NRR/DORL/LPLIII | ||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 31, 2017 LICENSEE: | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 31, 2017 LICENSEE: Northern States Power Company, doing business as Xcel Energy FACILITY: Monticello Nuclear Generating Plant | ||
Northern States Power Company, doing business as Xcel Energy FACILITY: | |||
Monticello Nuclear Generating Plant | |||
==SUBJECT:== | ==SUBJECT:== | ||
Line 26: | Line 24: | ||
==SUMMARY== | ==SUMMARY== | ||
OF OCTOBER 23, 2017, MEETING WITH NORTHERN STATES POWER COMPANY, DOING BUSINESS AS XCEL ENERGY, ON POTENTIAL LICENSE AMENDMENT REQUEST RELATED TO EMERGENCY DIESEL GENERATOR TECHNICAL SPECIFICATIONS (EPID L-2017-LRM-0031) | OF OCTOBER 23, 2017, MEETING WITH NORTHERN STATES POWER COMPANY, DOING BUSINESS AS XCEL ENERGY, ON POTENTIAL LICENSE AMENDMENT REQUEST RELATED TO EMERGENCY DIESEL GENERATOR TECHNICAL SPECIFICATIONS (EPID L-2017-LRM-0031) | ||
On October 23, 2017, a Category 1 teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Northern States Power Company. The purpose of the meeting was to discuss a potential license amendment request to remove technical specification (TS) operating mode restrictions for emergency diesel generator (EOG) surveillance testing for the Monticello Nuclear Generating Plant (Monticello). | On October 23, 2017, a Category 1 teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Northern States Power Company. The purpose of the meeting was to discuss a potential license amendment request to remove technical specification (TS) operating mode restrictions for emergency diesel generator (EOG) surveillance testing for the Monticello Nuclear Generating Plant (Monticello). The meeting notice and agenda, dated October 27, 2016, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML17283A262. A list of attendees is provided as Enclosure 1. | ||
The meeting notice and agenda, dated October 27, 2016, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML17283A262. | The licensee presented information (ADAMS Accession No. ML17293A429) related to the potential amendment request. The licensee stated that the proposed change would remove the mode restrictions from the notes on surveillance requirements 3.8.1.7 and 3.8.1.9 in the Monticello TSs. Surveillance requirement 3.8.1.7 requires demonstrating that the EOG can reject its single largest load without the EOG output frequency exceeding a specific limit. | ||
A list of attendees is provided as Enclosure 1 . The licensee presented information (ADAMS Accession No. ML17293A429) related to the potential amendment request. The licensee stated that the proposed change would remove the mode restrictions from the notes on surveillance requirements 3.8.1.7 and 3.8.1.9 in the Monticello TSs. Surveillance requirement 3.8.1.7 requires demonstrating that the EOG can reject its single largest load without the EOG output frequency exceeding a specific limit. Surveillance requirement 3.8.1.9 requires starting and then running the EOG continuously at, or near, full-load capability for greater than or equal to 8 hours. The NRC staff provided the licensee comments about the proposed amendment. | Surveillance requirement 3.8.1.9 requires starting and then running the EOG continuously at, or near, full-load capability for greater than or equal to 8 hours. | ||
Specifically, the staff noted that the proposed amendment request should consider past precedents, including any requests for additional information issued by the NRC staff and the responses, and how the precedent applies in this case. The NRC staff also noted that the application should include any mitigative actions that would be done during any testing in Modes 1 or 2, and what is unique about the configuration at Monticello that should be considered for this deviation from the standard TSs. Members of the public were not in attendance. | The NRC staff provided the licensee comments about the proposed amendment. Specifically, the staff noted that the proposed amendment request should consider past precedents, including any requests for additional information issued by the NRC staff and the responses, and how the precedent applies in this case. The NRC staff also noted that the application should include any mitigative actions that would be done during any testing in Modes 1 or 2, and what is unique about the configuration at Monticello that should be considered for this deviation from the standard TSs. | ||
Docket No. 50-263 | Members of the public were not in attendance. | ||
Ro ert F. Kuntz, Seni Plant Licensing Branc Division of Operating R ctor Licensing Office of Nuclear Reactor Regulation Docket No. 50-263 | |||
==Enclosure:== | ==Enclosure:== | ||
List of Attendees cc w/encl: Distribution via Listserv | |||
LIST OF ATTENDEES OCTOBER 23, 2017, MEETING WITH NORTHERN STATES POWER COMPANY, DOING BUSINESS AS XCEL ENERGY POTENTIAL LICENSE AMENDMENT FOR THE MONTICELLO NUCLEAR GENERATING PLANT Robert Kuntz Nuclear Regulatory Commission (NRC) | |||
Peter Syder NRC Prem Sahay NRC Sara Scott Xcel Energy Peter Gohdes Xcel Energy Bobbi Jo Halvorson Xcel Energy Chris Troy Xcel Energy Enclosure | |||
Meeting Notice ML17283A262 Meeting Summary ML17300A036 Handouts ML17293A429 OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA NRR/DORL/LPL3/BC NRR/DORL/LPL3/PM NAME RKuntz SRohrer DWrona RKuntz DATE 10/30/2017 10/30/2017 10/30/2017 10/31/2017}} | |||
Latest revision as of 20:53, 2 December 2019
ML17300A036 | |
Person / Time | |
---|---|
Site: | Monticello |
Issue date: | 10/31/2017 |
From: | Robert Kuntz Plant Licensing Branch III |
To: | Northern States Power Co |
Kuntz R | |
References | |
EPID L-2017-LRM-0031 | |
Download: ML17300A036 (4) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 31, 2017 LICENSEE: Northern States Power Company, doing business as Xcel Energy FACILITY: Monticello Nuclear Generating Plant
SUBJECT:
SUMMARY
OF OCTOBER 23, 2017, MEETING WITH NORTHERN STATES POWER COMPANY, DOING BUSINESS AS XCEL ENERGY, ON POTENTIAL LICENSE AMENDMENT REQUEST RELATED TO EMERGENCY DIESEL GENERATOR TECHNICAL SPECIFICATIONS (EPID L-2017-LRM-0031)
On October 23, 2017, a Category 1 teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Northern States Power Company. The purpose of the meeting was to discuss a potential license amendment request to remove technical specification (TS) operating mode restrictions for emergency diesel generator (EOG) surveillance testing for the Monticello Nuclear Generating Plant (Monticello). The meeting notice and agenda, dated October 27, 2016, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML17283A262. A list of attendees is provided as Enclosure 1.
The licensee presented information (ADAMS Accession No. ML17293A429) related to the potential amendment request. The licensee stated that the proposed change would remove the mode restrictions from the notes on surveillance requirements 3.8.1.7 and 3.8.1.9 in the Monticello TSs. Surveillance requirement 3.8.1.7 requires demonstrating that the EOG can reject its single largest load without the EOG output frequency exceeding a specific limit.
Surveillance requirement 3.8.1.9 requires starting and then running the EOG continuously at, or near, full-load capability for greater than or equal to 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.
The NRC staff provided the licensee comments about the proposed amendment. Specifically, the staff noted that the proposed amendment request should consider past precedents, including any requests for additional information issued by the NRC staff and the responses, and how the precedent applies in this case. The NRC staff also noted that the application should include any mitigative actions that would be done during any testing in Modes 1 or 2, and what is unique about the configuration at Monticello that should be considered for this deviation from the standard TSs.
Members of the public were not in attendance.
Ro ert F. Kuntz, Seni Plant Licensing Branc Division of Operating R ctor Licensing Office of Nuclear Reactor Regulation Docket No. 50-263
Enclosure:
List of Attendees cc w/encl: Distribution via Listserv
LIST OF ATTENDEES OCTOBER 23, 2017, MEETING WITH NORTHERN STATES POWER COMPANY, DOING BUSINESS AS XCEL ENERGY POTENTIAL LICENSE AMENDMENT FOR THE MONTICELLO NUCLEAR GENERATING PLANT Robert Kuntz Nuclear Regulatory Commission (NRC)
Peter Syder NRC Prem Sahay NRC Sara Scott Xcel Energy Peter Gohdes Xcel Energy Bobbi Jo Halvorson Xcel Energy Chris Troy Xcel Energy Enclosure
Meeting Notice ML17283A262 Meeting Summary ML17300A036 Handouts ML17293A429 OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA NRR/DORL/LPL3/BC NRR/DORL/LPL3/PM NAME RKuntz SRohrer DWrona RKuntz DATE 10/30/2017 10/30/2017 10/30/2017 10/31/2017