ML15257A196: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:SDM B 3.1.1 B 3.1  REACTIVITY CONTROL SYSTEMS B 3.1.1  SHUTDOWN MARGIN (SDM)
{{#Wiki_filter:SDM B 3.1.1 B 3.1  REACTIVITY CONTROL SYSTEMS  
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-1 Revision 2 BACKGROUND The reactivity control systems must be redundant and capable of holding the reactor core subcritical when shut down under cold conditions, in accordance with Reference 1, Appendix 1C, Criteria 27, 29, and 30. Maintenance of the SDM ensures that postulated reactivity events will not damage the fuel. SHUTDOWN MARGIN requirements provide sufficient reactivity margin to ensure that acceptable fuel design limits will not be exceeded for normal shutdown and anticipated operational occurrences (AOOs). As such, the SDM defines the degree of subcriticality that would be obtained immediately following the insertion of all control element assemblies (CEAs), assuming the single CEA of highest reactivity worth is fully withdrawn.
 
The system design requires that two independent reactivity control systems be provided, and that one of these systems be capable of maintaining the core subcritical under cold conditions. These requirements are provided by the use of movable CEAs and soluble boric acid in the Reactor Coolant System (RCS). The CEA System provides the SDM during power operation and is capable of making the core subcritical rapidly enough to prevent exceeding acceptable fuel damage limits, assuming that the CEA of highest reactivity worth remains fully withdrawn.
B 3.1.1  SHUTDOWN MARGIN (SDM)  
The soluble boron system can compensate for fuel depletion during operation and all xenon burnout reactivity changes, and maintain the reactor subcritical under cold conditions.
 
During power operation, SDM control is ensured by operating with the shutdown CEAs fully withdrawn and the regulating CEAs within the limits of Limiting Condition for Operation (LCO) 3.1.6. When the unit is in the shutdown and refueling MODEs, the SDM requirements are met by means of adjustments to the RCS boron concentration. APPLICABLE The minimum required SDM is assumed as an initial condition SAFETY ANALYSIS in safety analysis. The safety analysis (Reference 1, Section 3.4) establishes a SDM that ensures specified acceptable fuel design limits (SAFDLs) are not exceeded for SDM B 3.1.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-2 Revision 43  normal operation and AOOs, with the assumption of the highest worth CEA stuck out following a reactor trip. For MODE 5, the primary safety analysis that relies on the SDM limit is the boron dilution analysis.
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-1 Revision 2 BACKGROUND The reactivity control systems must be redundant and capable of holding the reactor core subcritical when shut down under  
The acceptance criteria for the SDM requirements are that SAFDLs are maintained. This is done by ensuring that:  a. The reactor can be made subcritical from all operating conditions, transients, and Design Basis Events;  b. The reactivity transients associated with postulated accident conditions are controllable within acceptable limits (departure from nucleate boiling ratio [DNBR],
 
fuel centerline temperature limit AOOs, and an acceptable energy deposition for the CEA ejection accident [Reference 1, Chapter 14]); and  c. The reactor will be maintained sufficiently subcritical to preclude inadvertent criticality in the shutdown condition.
cold conditions, in accordance with Reference 1, Appendix 1C, Criteria 27, 29, and 30. Maintenance of the SDM ensures that postulated reactivity events will not  
The most limiting accident for the SDM requirements are based on a main steam line break (MSLB) or an Excess Load event (with failure of an MSIV to close), as described in the accident analysis (Reference 1, Chapter 14). The increased steam flow causes an increased energy removal from the affected steam generator, and consequently the RCS.
 
This results in a reduction of the reactor coolant temperature. The resultant coolant shrinkage causes a reduction in pressure. In the presence of a negative moderator temperature coefficient (MTC), this cooldown causes an increase in core reactivity. As RCS temperature decreases, the severity of the event decreases. The most limiting MSLB, with respect to potential fuel damage before a reactor trip occurs, is a guillotine break of a main steam line outside containment, initiated at the end of core life. Following the MSLB or Excess Load event, a post-trip return to power may occur; however, no fuel damage occurs as a result of the post-trip return to power, and THERMAL POWER does not violate the Safety Limit (SL) requirement of SL 2.1.1. The limiting Excess Load event with respect to potential return-to-power after reactor trip is the opening of all steam dump and bypass valves at full power with failure of an MSIV to close.
damage the fuel. SHUTDOWN MARGIN requirements provide  
SDM B 3.1.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-3 Revision 43   In addition to the limiting MSLB transient, the SDM requirement for MODEs 3 and 4 must also protect against an uncontrolled CEA withdrawal from a hot zero power or low power condition, and a CEA ejection. In the boron dilution analysis, the required SDM defines the reactivity difference between an initial subcritical boron concentration and the corresponding critical boron concentration. These values, in conjunction with the configuration of the RCS and the assumed dilution flow rate, directly affect the results of the analysis. This event is most limiting at the beginning of core life when critical boron concentrations are highest.
 
The withdrawal of CEAs from hot zero power or low power conditions adds reactivity to the reactor core, causing both the core power level and heat flux to increase with corresponding increases in reactor coolant temperatures and pressure. The withdrawal of CEAs also produces a time-dependent redistribution of core power.
sufficient reactivity margin to ensure that acceptable fuel  
The uncontrolled CEA withdrawal transient is terminated by the Variable High Power Trip. In all cases, power level, RCS pressure, linear heat rate (LHR), and the DNBR do not exceed allowable limits.
 
SHUTDOWN MARGIN satisfies 10 CFR 50.36(c)(2)(ii), Criterion 2.
design limits will not be exceeded for normal shutdown and  
LCO The MSLB (or the Excess Load event) and the boron dilution accidents (Reference 1, Chapter 14) are the most limiting analyses that establish the SDM value of the LCO. For MSLB accidents (or the Excess Load event), if the LCO is violated, there is a potential to exceed the DNBR limit and to exceed the acceptance criteria given in Reference 1, Chapter 14. For the boron dilution accident, if the LCO is violated, the minimum required time assumed for operator action to terminate dilution may no longer be applicable.
 
Because both initial RCS level and the dilution flow rate also significantly impact the boron dilution event in MODE 5 with pressurizer level < 90 inches from the bottom of the SDM B 3.1.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-4 Revision 43 pressurizer, the LCO also includes limits for these parameters during these conditions.
anticipated operational occurrences (AOOs). As such, the  
SHUTDOWN MARGIN is a core physics design condition that can be ensured through CEA positioning (regulating and shutdown CEA) in MODEs 1 and 2 and through the soluble boron concentration in all other MODEs. APPLICABILITY In MODEs 3, 4, and 5, the SDM requirements are applicable to provide sufficient negative reactivity to meet the assumptions of the safety analyses discussed above. In MODEs 1 and 2, SDM is ensured by complying with LCOs 3.1.5 and 3.1.6. In MODE 6, the shutdown reactivity requirements are given in LCO 3.9.1. ACTIONS A.1, A.2, and A.3  With non-borated water sources of > 88 gpm available, while the unit is in MODE 5 with the pressurizer level  
 
< 90 inches, the consequences of a boron dilution event may exceed the analysis results. Therefore, action must be initiated immediately to reduce the potential for such an event. To accomplish this, Required Action A.1 requires immediate suspension of positive reactivity additions.
SDM defines the degree of subcriticality that would be  
However, since Required Action A.1 only reduces the potential for the event and does not eliminate it, immediate action must also be initiated to increase the SDM to compensate for the non-borated water sources (Required Action A.2). Finally, Required Action A.3 requires periodic verification, once per 12 hours, that the SDM increase is maintained sufficient to compensate for the additional sources of non-borated water. Required Action A.1 is modified by a Note indicating that the suspension of positive reactivity additions is not required if SDM has been sufficiently increased to compensate for the additional sources of non-borated water. The immediate Completion Time reflects the urgency of the corrective actions. The periodic Completion Time of 12 hours is considered reasonable, based on other administrative controls available and operating experience.
 
SDM B 3.1.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-5 Revision 27  B.1 and B.2  With the RCS level at or below the bottom of the hot leg nozzles, while the unit is in MODE 5 with the pressurizer level < 90 inches, the consequences of a boron dilution event may exceed the analysis results. Therefore, action must be initiated immediately to reduce the potential for such an event. To accomplish this, Required Action B.1 requires immediate suspension of operations involving positive reactivity additions that could result in loss of the required SDM. Suspending positive reactivity additions that could result in failure to meet the minimum SDM limit is required to assure continued safe operation. Introduction of coolant inventory must be from sources that have boron concentration greater than that required in the RCS for the minimum SDM. This may result in an overall reduction in RCS boron concentration, but provides an acceptable margin to maintaining subcritical operation. Introduction of temperature changes including temperature increases when operating with a positive MTC must also be evaluated to ensure they do not result in a loss of the required SDM. However, since Required Action B.1 only reduces the potential for the event and does not eliminate it, immediate action must also be initiated to increase the RCS level to above the bottom of the hot leg nozzles (Required Action B.2). The immediate Completion Time reflects the urgency of the corrective actions.
obtained immediately following the insertion of all control  
C.1  If the SDM requirements are not met for reasons other than addressed in Condition A or B, boration must be initiated promptly. A Completion Time of immediately is required to meet the assumptions of the safety analysis. It is assumed that boration will be continued until the SDM requirements are met. In the determination of the required combination of boration flow rate and boron concentration, there is no unique requirement that must be satisfied. Since it is imperative to raise the boron concentration of the RCS as soon as possible, the boron concentration should be a highly concentrated solution, such as that normally found in the boric acid storage tank or the refueling water tank. The SDM B 3.1.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-6 Revision 55  operator should borate with the best source available for the plant conditions. However, as a minimum, the boration flow rate shall be  40 gpm and the boron concentration shall be  2300 ppm boric acid solution or equivalent. Assuming that a value of 1% k/k must be recovered and a boration flow rate of 40 gpm from the boric acid storage tank, it is possible to increase the boron concentration of the RCS by 100 ppm in approximately 15 minutes. If an inverse boron worth of 100 ppm/% k/k is assumed, this combination of parameters will increase the SDM by 1% k/k. These boration parameters of 40 gpm and 100 ppm represent typical values and are provided for the purpose of offering a specific example. SURVEILLANCE SR 3.1.1.1 REQUIREMENTS SHUTDOWN MARGIN is verified by performing a reactivity balance calculation, considering the listed reactivity effects:  a. RCS boron concentration;  
 
element assemblies (CEAs), assuming the single CEA of  
 
highest reactivity worth is fully withdrawn.  
 
The system design requires that two independent reactivity control systems be provided, and that one of these systems  
 
be capable of maintaining the core subcritical under cold  
 
conditions. These requirements are provided by the use of  
 
movable CEAs and soluble boric acid in the Reactor Coolant  
 
System (RCS). The CEA System provides the SDM during power  
 
operation and is capable of making the core subcritical  
 
rapidly enough to prevent exceeding acceptable fuel damage  
 
limits, assuming that the CEA of highest reactivity worth  
 
remains fully withdrawn.  
 
The soluble boron system can compensate for fuel depletion during operation and all xenon burnout reactivity changes,  
 
and maintain the reactor subcritical under cold conditions.  
 
During power operation, SDM control is ensured by operating with the shutdown CEAs fully withdrawn and the regulating  
 
CEAs within the limits of Limiting Condition for Operation (LCO) 3.1.6. When the unit is in the shutdown and refueling MODEs, the SDM requirements are met by means of adjustments to the RCS boron concentration.
APPLICABLE The minimum required SDM is assumed as an initial condition SAFETY ANALYSIS in safety analysis. The safety analysis (Reference 1, Section 3.4) establishes a SDM that ensures specified acceptable fuel design limits (SAFDLs) are not exceeded for SDM B 3.1.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-2 Revision 43  normal operation and AOOs, with the assumption of the highest worth CEA stuck out following a reactor trip. For  
 
MODE 5, the primary safety analysis that relies on the SDM  
 
limit is the boron dilution analysis.  
 
The acceptance criteria for the SDM requirements are that SAFDLs are maintained. This is done by ensuring that:  a. The reactor can be made subcritical from all operating conditions, transients, and Design Basis Events;  b. The reactivity transients associated with postulated accident conditions are controllable within acceptable  
 
limits (departure from nucleate boiling ratio [DNBR],  
 
fuel centerline temperature limit AOOs, and an  
 
acceptable energy deposition for the CEA ejection  
 
accident [Reference 1, Chapter 14]); and  c. The reactor will be maintained sufficiently subcritical to preclude inadvertent criticality in the shutdown  
 
condition.  
 
The most limiting accident for the SDM requirements are based on a main steam line break (MSLB) or an Excess Load event (with failure of an MSIV to close), as described in the accident analysis (Reference 1, Chapter 14). The  
 
increased steam flow causes an increased energy removal from the affected steam generator, and consequently the RCS.
 
This results in a reduction of the reactor coolant  
 
temperature. The resultant coolant shrinkage causes a  
 
reduction in pressure. In the presence of a negative  
 
moderator temperature coefficient (MTC), this cooldown  
 
causes an increase in core reactivity. As RCS temperature  
 
decreases, the severity of the event decreases. The most limiting MSLB, with respect to potential fuel damage before  
 
a reactor trip occurs, is a guillotine break of a main steam  
 
line outside containment, initiated at the end of core life.
Following the MSLB or Excess Load event, a post-trip return to power may occur; however, no fuel damage occurs as a  
 
result of the post-trip return to power, and THERMAL POWER  
 
does not violate the Safety Limit (SL) requirement of  
 
SL 2.1.1. The limiting Excess Load event with respect to potential return-to-power after reactor trip is the opening of all steam dump and bypass valves at full power with failure of an MSIV to close.
SDM B 3.1.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-3 Revision 43 In addition to the limiting MSLB transient, the SDM requirement for MODEs 3 and 4 must also protect against an  
 
uncontrolled CEA withdrawal from a hot zero power or low  
 
power condition, and a CEA ejection.
In the boron dilution analysis, the required SDM defines the reactivity difference between an initial subcritical boron  
 
concentration and the corresponding critical boron  
 
concentration. These values, in conjunction with the  
 
configuration of the RCS and the assumed dilution flow rate,  
 
directly affect the results of the analysis. This event is  
 
most limiting at the beginning of core life when critical  
 
boron concentrations are highest.  
 
The withdrawal of CEAs from hot zero power or low power conditions adds reactivity to the reactor core, causing both  
 
the core power level and heat flux to increase with  
 
corresponding increases in reactor coolant temperatures and  
 
pressure. The withdrawal of CEAs also produces a time-
 
dependent redistribution of core power.  
 
The uncontrolled CEA withdrawal transient is terminated by the Variable High Power Trip. In all cases, power level, RCS pressure, linear heat rate (LHR), and the DNBR do not  
 
exceed allowable limits.  
 
SHUTDOWN MARGIN satisfies 10 CFR 50.36(c)(2)(ii),
Criterion 2.  
 
LCO The MSLB (or the Excess Load event) and the boron dilution accidents (Reference 1, Chapter 14) are the most limiting analyses that establish the SDM value of the LCO. For MSLB  
 
accidents (or the Excess Load event), if the LCO is violated, there is a potential to exceed the DNBR limit and  
 
to exceed the acceptance criteria given in Reference 1,  
 
Chapter 14. For the boron dilution accident, if the LCO is  
 
violated, the minimum required time assumed for operator  
 
action to terminate dilution may no longer be applicable.
 
Because both initial RCS level and the dilution flow rate  
 
also significantly impact the boron dilution event in MODE 5  
 
with pressurizer level < 90 inches from the bottom of the SDM B 3.1.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-4 Revision 43 pressurizer, the LCO also includes limits for these parameters during these conditions.  
 
SHUTDOWN MARGIN is a core physics design condition that can be ensured through CEA positioning (regulating and shutdown  
 
CEA) in MODEs 1 and 2 and through the soluble boron concentration in all other MODEs.
APPLICABILITY In MODEs 3, 4, and 5, the SDM requirements are applicable to provide sufficient negative reactivity to meet the  
 
assumptions of the safety analyses discussed above. In  
 
MODEs 1 and 2, SDM is ensured by complying with LCOs 3.1.5  
 
and 3.1.6. In MODE 6, the shutdown reactivity requirements are given in LCO 3.9.1.
ACTIONS A.1, A.2, and A.3  With non-borated water sources of > 88 gpm available, while the unit is in MODE 5 with the pressurizer level  
 
< 90 inches, the consequences of a boron dilution event may  
 
exceed the analysis results. Therefore, action must be  
 
initiated immediately to reduce the potential for such an  
 
event. To accomplish this, Required Action A.1 requires  
 
immediate suspension of positive reactivity additions.
 
However, since Required Action A.1 only reduces the  
 
potential for the event and does not eliminate it, immediate action must also be initiated to increase the SDM to compensate for the non-borated water sources (Required  
 
Action A.2). Finally, Required Action A.3 requires periodic  
 
verification, once per 12 hours, that the SDM increase is  
 
maintained sufficient to compensate for the additional  
 
sources of non-borated water. Required Action A.1 is  
 
modified by a Note indicating that the suspension of  
 
positive reactivity additions is not required if SDM has  
 
been sufficiently increased to compensate for the additional  
 
sources of non-borated water. The immediate Completion Time  
 
reflects the urgency of the corrective actions. The  
 
periodic Completion Time of 12 hours is considered  
 
reasonable, based on other administrative controls available  
 
and operating experience.  
 
SDM B 3.1.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-5 Revision 27  B.1 and B.2  With the RCS level at or below the bottom of the hot leg nozzles, while the unit is in MODE 5 with the pressurizer  
 
level < 90 inches, the consequences of a boron dilution  
 
event may exceed the analysis results. Therefore, action  
 
must be initiated immediately to reduce the potential for such an event. To accomplish this, Required Action B.1 requires immediate suspension of operations involving positive reactivity additions that could result in loss of the required SDM. Suspending positive reactivity additions that could result in failure to meet the minimum SDM limit is required to assure continued safe operation.
Introduction of coolant inventory must be from sources that have boron concentration greater than that required in the RCS for the minimum SDM. This may result in an overall reduction in RCS boron concentration, but provides an acceptable margin to maintaining subcritical operation.
Introduction of temperature changes including temperature increases when operating with a positive MTC must also be evaluated to ensure they do not result in a loss of the required SDM. However, since Required Action B.1 only reduces the potential for the event and does not eliminate  
 
it, immediate action must also be initiated to increase the  
 
RCS level to above the bottom of the hot leg nozzles  
 
(Required Action B.2). The immediate Completion Time  
 
reflects the urgency of the corrective actions.  
 
C.1  If the SDM requirements are not met for reasons other than addressed in Condition A or B, boration must be initiated  
 
promptly. A Completion Time of immediately is required to  
 
meet the assumptions of the safety analysis. It is assumed  
 
that boration will be continued until the SDM requirements  
 
are met.
In the determination of the required combination of boration flow rate and boron concentration, there is no unique  
 
requirement that must be satisfied. Since it is imperative  
 
to raise the boron concentration of the RCS as soon as  
 
possible, the boron concentration should be a highly  
 
concentrated solution, such as that normally found in the  
 
boric acid storage tank or the refueling water tank. The SDM B 3.1.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-6 Revision 55  operator should borate with the best source available for the plant conditions. However, as a minimum, the boration flow rate shall be  40 gpm and the boron concentration shall be  2300 ppm boric acid solution or equivalent.
Assuming that a value of 1% k/k must be recovered and a boration flow rate of 40 gpm from the boric acid storage tank, it is possible to increase the boron concentration of  
 
the RCS by 100 ppm in approximately 15 minutes. If an inverse boron worth of 100 ppm/% k/k is assumed, this combination of parameters will increase the SDM by 1% k/k. These boration parameters of 40 gpm and 100 ppm represent  
 
typical values and are provided for the purpose of offering a specific example.
SURVEILLANCE SR 3.1.1.1 REQUIREMENTS SHUTDOWN MARGIN is verified by performing a reactivity balance calculation, considering the listed reactivity  
 
effects:  a. RCS boron concentration;  
: b. CEA positions;  
: b. CEA positions;  
: c. RCS average temperature;  
: c. RCS average temperature;  
Line 41: Line 264:
: e. Xenon concentration;  
: e. Xenon concentration;  
: f. Samarium concentration; and  
: f. Samarium concentration; and  
: g. Isothermal temperature coefficient.
: g. Isothermal temperature coefficient.  
Using the isothermal temperature coefficient accounts for Doppler reactivity in this calculation because the reactor is subcritical and the fuel temperature will be changing at the same rate as the RCS.
 
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
Using the isothermal temperature coefficient accounts for Doppler reactivity in this calculation because the reactor is subcritical and the fuel temperature will be changing at the same rate as the RCS.  
SR 3.1.1.2 and SR 3.1.1.3  These Surveillance Requirements (SRs) periodically verify the significant assumptions of a boron dilution event are SDM B 3.1.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-7 Revision 55 maintained. A non-borated water source of  88 gpm allows for only one charging pump to be capable of injection during these conditions since each charging pump is capable of an injection rate of 46 gpm. Each SR is modified by a Note indicating that it is only required when the unit is in MODE 5 with the pressurizer level < 90 inches. Since the applicable conditions for the SR may be attained while already in MODE 5, each SR is provided with a Frequency of once within 1 hour after achieving MODE 5 with pressurizer level < 90 inches. This provides a short period of time to verify compliance after the conditions are attained.
 
Additionally, each SR must be completed once each 12 hours after the initial verification. The Frequency of 12 hours is considered reasonable, in view of other administrative controls available and operating experience. REFERENCES 1. Updated Final Safety Analysis Report (UFSAR)
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
Reactivity Balance B 3.1.2 B 3.1  REACTIVITY CONTROL SYSTEMS B 3.1.2  Reactivity Balance BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-1 Revision 2 BACKGROUND According to Reference 1, Appendix 1C, Criteria 27, 29, and 30, reactivity shall be controllable, such that, subcriticality is maintained under cold conditions, and acceptable fuel design limits are not exceeded during normal operation and AOOs. Therefore, reactivity balance is used as a measure of the predicted versus measured core reactivity during power operation. The periodic confirmation of core reactivity is necessary to ensure that Design Basis Accident (DBA) and transient safety analyses remain valid. A large reactivity difference could be the result of unanticipated changes in fuel, CEA worth, or operation at conditions not consistent with those assumed in the predictions of core reactivity, and could potentially result in a loss of SDM or violation of acceptable fuel design limits. Comparing predicted versus measured core reactivity validates the nuclear methods used in the safety analysis and supports the SDM demonstrations (LCO 3.1.1) in ensuring the reactor can be brought safely to cold, subcritical conditions.
 
When the reactor core is critical or in normal power operation, a reactivity balance exists and the net reactivity is zero. A comparison of predicted and measured reactivity is convenient under such a balance, since parameters are being maintained relatively stable under steady state power conditions. The positive reactivity inherent in the core design is balanced by the negative reactivity of the control components, thermal feedback, neutron leakage, and materials in the core that absorb neutrons, such as burnable absorbers producing zero net reactivity. Excess reactivity can be inferred from the critical boron curve, which provides an indication of the soluble boron concentration in the RCS versus cycle burnup. Periodic measurement of the RCS boron concentration for comparison with the predicted value with other variables fixed (such as CEA height, temperature, pressure, and power) provides a convenient method of ensuring that core reactivity is within design expectations, and that the calculational models used to generate the safety analysis are adequate.
SR 3.1.1.2 and SR 3.1.1.3  These Surveillance Requirements (SRs) periodically verify the significant assumptions of a boron dilution event are SDM B 3.1.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-7 Revision 55 maintained. A non-borated water source of  88 gpm allows for only one charging pump to be capable of injection during  
Reactivity Balance B 3.1.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-2 Revision 2   In order to achieve the required fuel cycle energy output, the uranium enrichment in the new fuel loading and in the fuel remaining from the previous cycle provides excess positive reactivity beyond that required to sustain steady state operation throughout the cycle. When the reactor is critical at hot full power, the excess positive reactivity is compensated by burnable absorbers (if any), CEAs, whatever neutron poisons (mainly xenon and samarium) are present in the fuel, and the RCS boron concentration.
 
When the core is producing THERMAL POWER, the fuel is being depleted and excess reactivity is decreasing. As the fuel depletes, the RCS boron concentration is reduced to decrease negative reactivity and maintain constant THERMAL POWER.
these conditions since each charging pump is capable of an  
The critical boron curve is based on steady state operation at RATED THERMAL POWER (RTP). Therefore, deviations from the predicted critical boron curve may indicate deficiencies in the design analysis, deficiencies in the calculational models, or abnormal core conditions, and must be evaluated. APPLICABLE Accurate prediction of core reactivity is either an explicit SAFETY ANALYSES or implicit assumption in the accident analysis evaluations. Most accident evaluations (Reference 1, Section 14.1) are, therefore, dependent upon accurate evaluation of core reactivity. In particular, SDM and reactivity transients, such as CEA withdrawal accidents or CEA ejection accidents, are very sensitive to accurate prediction of core reactivity. These accident analysis evaluations rely on computer codes that have been qualified against available test data, operating plant data, and analytical benchmarks. Monitoring reactivity balance additionally ensures that the nuclear methods provide an accurate representation of the core reactivity.
 
Design calculations and safety analyses are performed for each fuel cycle for the purpose of predetermining reactivity behavior and the RCS boron concentration requirements for reactivity control during fuel depletion.
injection rate of 46 gpm. Each SR is modified by a Note  
The comparison between measured and predicted initial core reactivity provides a normalization for calculational models used to predict core reactivity. If the measured and Reactivity Balance B 3.1.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-3 Revision 2 predicted RCS boron concentrations for identical core conditions at beginning-of-cycle (BOC) do not agree, the assumptions used in the reload cycle design analysis or the calculational models used to predict soluble boron requirements may not be accurate. If reasonable agreement between measured and predicted core reactivity exists at BOC, the prediction may be normalized to the measured boron concentration. Thereafter, any significant deviations in the measured boron concentration from the predicted critical boron curve that develop during fuel depletion may be an indication that the calculational model is not adequate for core burnups beyond BOC, or that an unexpected change in core conditions has occurred.
 
The normalization of predicted RCS boron concentration to the measured value is typically performed after reaching RTP following startup from a refueling outage, with the CEAs in their normal positions for power operation. The normalization is performed at BOC conditions, so that core reactivity relative to predicted values can be continually monitored and evaluated as core conditions change during the cycle.
indicating that it is only required when the unit is in  
The reactivity balance satisfies 10 CFR 50.36(c)(2)(ii), Criterion 2. LCO The reactivity balance limit is established to ensure plant operation is maintained within the assumptions of the safety analyses. Large differences between actual and predicted core reactivity may indicate that the assumptions of the DBA and transient analyses are no longer valid, or that the uncertainties in the nuclear design methodology are larger than expected. A limit on the reactivity balance of +/- 1% k/k has been established, based on engineering judgment. A 1% deviation in reactivity from that predicted is larger than expected for normal operation and should, therefore, be evaluated. When measured core reactivity is within 1% k/k of the predicted value at steady state thermal conditions, the core is considered to be operating within acceptable design limits. Since deviations from the limit are normally detected by comparing predicted and measured steady state Reactivity Balance B 3.1.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-4 Revision 2 RCS critical boron concentrations, the difference between measured and predicted values would be approximately 100 ppm (depending on the boron worth) before the limit is reached.
 
These values are well within the uncertainty limits for analysis of boron concentration samples, so that spurious violations of the limit due to uncertainty in measuring the RCS boron concentration are unlikely. APPLICABILITY The limits on core reactivity must be maintained during MODE 1 because a reactivity balance must exist when the reactor is critical or producing THERMAL POWER. As the fuel depletes, core conditions are changing, and confirmation of the reactivity balance ensures the core is operating as designed. This Specification does not apply in MODE 2 because enough operating margin exists to limit the effects of a reactivity anomaly, and THERMAL POWER is low enough ( 5% RTP) such that reactivity anomalies are unlikely to occur. This Specification does not apply in MODEs 3, 4, and 5 because the reactor is shut down and the reactivity balance is not changing.
MODE 5 with the pressurizer level < 90 inches. Since the applicable conditions for the SR may be attained while already in MODE 5, each SR is provided with a Frequency of  
In MODE 6, fuel loading results in a continually changing core reactivity. Boron concentration requirements (LCO 3.9.1) ensure that fuel movements are performed within the bounds of the safety analysis. A SDM demonstration is required during the first startup following operations that could have altered core reactivity (e.g., fuel movement, or CEA replacement, or shuffling). ACTIONS A.1 and A.2 Should an anomaly develop between measured and predicted core reactivity, an evaluation of the core design and safety analysis must be performed. Core conditions are evaluated to determine their consistency with input to design calculations. Measured core and process parameters are evaluated to determine that they are within the bounds of the safety analysis, and safety analysis calculational models are reviewed to verify that they are adequate for representation of the core conditions. The required Completion Time of 7 days is based on the low probability of a DBA occurring during this period, and allows sufficient Reactivity Balance B 3.1.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-5 Revision 2 time to assess the physical condition of the reactor and to complete the evaluation of the core design and safety analysis.
 
Following evaluations of the core design and safety analysis, the cause of the reactivity anomaly may be resolved. If the cause of the reactivity anomaly is a mismatch in core conditions at the time of RCS boron concentration sampling, a recalculation of the RCS boron concentration requirements may be performed to demonstrate that core reactivity is behaving as expected. If an unexpected physical change in the condition of the core has occurred, it must be evaluated and corrected, if possible.
once within 1 hour after achieving MODE 5 with pressurizer  
If the cause of the reactivity anomaly is in the calculation technique, the calculational models must be revised to provide more accurate predictions. If any of these results are demonstrated, and it is concluded that the reactor core is acceptable for continued operation, the boron letdown curve may be renormalized, and power operation may continue. If operational restrictions or additional SRs are necessary to ensure the reactor core is acceptable for continued operation, they must be defined. The required Completion Time of 7 days is adequate for preparing whatever operating restrictions or SRs may be required to allow continued reactor operation.
 
B.1  If the core reactivity cannot be restored to within the 1% k/k limit, the plant must be brought to a MODE in which the LCO does not apply. To achieve this status, the plant must be brought to at least MODE 2 within 6 hours. The allowed Completion Time is reasonable, based on operating experience, for reaching MODE 2 from full power conditions in an orderly manner and without challenging plant systems. SURVEILLANCE SR 3.1.2.1 REQUIREMENTS Core reactivity is verified by periodic comparisons of measured and predicted RCS boron concentrations. The comparison is made considering that other core conditions are fixed or stable, including CEA position, moderator Reactivity Balance B 3.1.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-6 Revision 3  temperature, fuel temperature, fuel depletion, xenon concentration, and samarium concentration. The SR is performed prior to entering MODE 1 as an initial check on core conditions and design calculations at BOC and every 31 days after 60 effective full power days (EFPD). The SR is modified by two Notes. The Note in the SR column indicates that the normalization of predicted core reactivity to the measured value may take place within the first 60 EFPD after each fuel loading. This allows sufficient time for core conditions to reach steady state, but prevents operation for a large fraction of the fuel cycle without establishing a benchmark for the design calculations. The required subsequent Frequency of 31 EFPD following the initial 60 EFPD, after entering MODE 1, is acceptable, based on the slow rate of core changes due to fuel depletion and the presence of other indicators (e.g., quadrant power tilt ratio, etc.) for prompt indication of an anomaly. The Frequency Note, "only required after 60 EFPD after each fuel loading," is added to the Frequency column to allow this. REFERENCES 1. UFSAR MTC B 3.1.3 B 3.1  REACTIVITY CONTROL SYSTEMS B 3.1.3  Moderator Temperature Coefficient (MTC)
level < 90 inches. This provides a short period of time to  
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-1 Revision 29 BACKGROUND The MTC relates a change in core reactivity to a change in reactor coolant temperature. A positive MTC means that reactivity increases with increasing moderator temperature; conversely, a negative MTC means that reactivity decreases with increasing moderator temperature. The reactor is designed to operate with a negative MTC over a large range of fuel cycle operation. Therefore, a coolant temperature increase will cause a reactivity decrease, so that the coolant temperature tends to return toward its initial value. Reactivity increases that cause a coolant temperature increase will thus be self limiting, and stable power operation will result.
 
Moderator temperature coefficient values are predicted at selected burnups during the safety evaluation analysis and are confirmed to be acceptable by measurements. Reload cores are designed so that the MTC is less positive than that allowed by the LCO. The actual value of the MTC is dependent on core characteristics, such as fuel loading and reactor coolant soluble boron concentration. The core design may require additional fixed distributed poisons (burnable poison) to yield an MTC at the BOC within the range analyzed in the plant accident analysis. The end-of-cycle (EOC) MTC is also limited by the requirements of the accident analysis. Fuel cycles that are designed to achieve high burnups or that have changes to other characteristics are evaluated to ensure that the MTC does not exceed the EOC limit. APPLICABLE The acceptance criteria for the specified MTC are:
verify compliance after the conditions are attained.
 
Additionally, each SR must be completed once each 12 hours  
 
after the initial verification. The Frequency of 12 hours  
 
is considered reasonable, in view of other administrative controls available and operating experience.
REFERENCES 1. Updated Final Safety Analysis Report (UFSAR)  
 
Reactivity Balance B 3.1.2 B 3.1  REACTIVITY CONTROL SYSTEMS  
 
B 3.1.2  Reactivity Balance  
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-1 Revision 2 BACKGROUND According to Reference 1
, Appendix 1C, Criteria 27, 29, and 30, reactivity shall be controllable, such that, subcriticality is maintained under cold conditions, and acceptable fuel design limits are not exceeded during normal operation and AOOs. Therefore, reactivity balance is used as a measure of the predicted versus measured core reactivity during power operation. The periodic  
 
confirmation of core reactivity is necessary to ensure that  
 
Design Basis Accident (DBA) and transient safety analyses  
 
remain valid. A large reactivity difference could be the  
 
result of unanticipated changes in fuel, CEA worth, or operation at conditions not consistent with those assumed in the predictions of core reactivity, and could potentially  
 
result in a loss of SDM or violation of acceptable fuel  
 
design limits. Comparing predicted versus measured core  
 
reactivity validates the nuclear methods used in the safety  
 
analysis and supports the SDM demonstrations (LCO 3.1.1
) in ensuring the reactor can be brought safely to cold, subcritical conditions.  
 
When the reactor core is critical or in normal power operation, a reactivity balance exists and the net  
 
reactivity is zero. A comparison of predicted and measured  
 
reactivity is convenient under such a balance, since  
 
parameters are being maintained relatively stable under  
 
steady state power conditions. The positive reactivity  
 
inherent in the core design is balanced by the negative  
 
reactivity of the control components, thermal feedback,  
 
neutron leakage, and materials in the core that absorb  
 
neutrons, such as burnable absorbers producing zero net  
 
reactivity. Excess reactivity can be inferred from the  
 
critical boron curve, which provides an indication of the soluble boron concentration in the RCS versus cycle burnup.
Periodic measurement of the RCS boron concentration for comparison with the predicted value with other variables  
 
fixed (such as CEA height, temperature, pressure, and power)  
 
provides a convenient method of ensuring that core  
 
reactivity is within design expectations, and that the  
 
calculational models used to generate the safety analysis  
 
are adequate.
Reactivity Balance B 3.1.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-2 Revision 2 In order to achieve the required fuel cycle energy output, the uranium enrichment in the new fuel loading and in the  
 
fuel remaining from the previous cycle provides excess positive reactivity beyond that required to sustain steady state operation throughout the cycle. When the reactor is critical at hot full power, the excess positive reactivity is compensated by burnable absorbers (if any), CEAs,  
 
whatever neutron poisons (mainly xenon and samarium) are  
 
present in the fuel, and the RCS boron concentration.  
 
When the core is producing THERMAL POWER, the fuel is being depleted and excess reactivity is decreasing. As the fuel  
 
depletes, the RCS boron concentration is reduced to decrease  
 
negative reactivity and maintain constant THERMAL POWER.
 
The critical boron curve is based on steady state operation  
 
at RATED THERMAL POWER (
RTP). Therefore, deviations from the predicted critical boron curve may indicate deficiencies in the design analysis, deficiencies in the calculational models, or abnormal core conditions, and must be evaluated.
APPLICABLE Accurate prediction of core reactivity is either an explicit SAFETY ANALYSES or implicit assumption in the accident analysis evaluations.
Most accident evaluations (Reference 1, Section 14.1
) are, therefore, dependent upon accurate evaluation of core reactivity. In particular, SDM and reactivity transients,  
 
such as CEA withdrawal accidents or CEA ejection accidents,  
 
are very sensitive to accurate prediction of core  
 
reactivity. These accident analysis evaluations rely on  
 
computer codes that have been qualified against available test data, operating plant data, and analytical benchmarks.
Monitoring reactivity balance additionally ensures that the  
 
nuclear methods provide an accurate representation of the  
 
core reactivity.  
 
Design calculations and safety analyses are performed for each fuel cycle for the purpose of predetermining reactivity  
 
behavior and the RCS boron concentration requirements for  
 
reactivity control during fuel depletion.  
 
The comparison between measured and predicted initial core reactivity provides a normalization for calculational models  
 
used to predict core reactivity. If the measured and Reactivity Balance B 3.1.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-3 Revision 2 predicted RCS boron concentrations for identical core conditions at beginning
-of-cycle (BOC) do not agree, the assumptions used in the reload cycle design analysis or the calculational models used to predict soluble boron  
 
requirements may not be accurate. If reasonable agreement  
 
between measured and predicted core reactivity exists at BOC, the prediction may be normalized to the measured boron concentration. Thereafter, any significant deviations in the measured boron concentration from the predicted critical  
 
boron curve that develop during fuel depletion may be an  
 
indication that the calculational model is not adequate for  
 
core burnups beyond BOC, or that an unexpected change in  
 
core conditions has occurred.  
 
The normalization of predicted RCS boron concentration to the measured value is typically performed after reaching RTP  
 
following startup from a refueling outage, with the CEAs in  
 
their normal positions for power operation. The  
 
normalization is performed at BOC conditions, so that core  
 
reactivity relative to predicted values can be continually  
 
monitored and evaluated as core conditions change during the  
 
cycle.
The reactivity balance satisfies 10 CFR 50.36(c)(2)(ii),
Criterion 2.
LCO The reactivity balance limit is established to ensure plant operation is maintained within the assumptions of the safety  
 
analyses. Large differences between actual and predicted  
 
core reactivity may indicate that the assumptions of the DBA and transient analyses are no longer valid, or that the uncertainties in the nuclear design methodology are larger  
 
than expected. A limit on the reactivity balance of  
+/- 1% k/k has been established, based on engineering judgment. A 1% deviation in reactivity from that predicted  
 
is larger than expected for normal operation and should
, therefore
, be evaluated.
When measured core reactivity is within 1% k/k of the predicted value at steady state thermal conditions, the core  
 
is considered to be operating within acceptable design  
 
limits. Since deviations from the limit are normally  
 
detected by comparing predicted and measured steady state Reactivity Balance B 3.1.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-4 Revision 2 RCS critical boron concentrations, the difference between measured and predicted values would be approximately 100 ppm  
 
(depending on the boron worth) before the limit is reached.  
 
These values are well within the uncertainty limits for analysis of boron concentration samples, so that spurious violations of the limit due to uncertainty in measuring the  
 
RCS boron concentration are unlikely.
APPLICABILITY The limits on core reactivity must be maintained during MODE 1 because a reactivity balance must exist when the  
 
reactor is critical or producing THERMAL POWER. As the fuel  
 
depletes, core conditions are changing, and confirmation of  
 
the reactivity balance ensures the core is operating as  
 
designed. This Specification does not apply in MODE 2  
 
because enough operating margin exists to limit the effects  
 
of a reactivity anomaly, and THERMAL POWER is low enough  
( 5% RTP) such that reactivity anomalies are unlikely to occur. This Specification does not apply in MODEs 3, 4, and 5 because the reactor is shut down and the reactivity balance is not changing.  
 
In MODE 6, fuel loading results in a continually changing core reactivity. Boron concentration requirements  
 
(LCO 3.9.1
) ensure that fuel movements are performed within the bounds of the safety analysis. A SDM demonstration is required during the first startup following operations that  
 
could have altered core reactivity (e.g., fuel movement, or CEA replacement, or shuffling).
ACTIONS A.1 and A.2 Should an anomaly develop between measured and predicted core reactivity, an evaluation of the core design and safety  
 
analysis must be performed. Core conditions are evaluated  
 
to determine their consistency with input to design  
 
calculations. Measured core and process parameters are  
 
evaluated to determine that they are within the bounds of  
 
the safety analysis, and safety analysis calculational  
 
models are reviewed to verify that they are adequate for  
 
representation of the core conditions. The required  
 
Completion Time of 7 days is based on the low probability of  
 
a DBA occurring during this period, and allows sufficient Reactivity Balance B 3.1.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-5 Revision 2 time to assess the physical condition of the reactor and to complete the evaluation of the core design and safety analysis.  
 
Following evaluations of the core design and safety analysis, the cause of the reactivity anomaly may be resolved. If the cause of the reactivity anomaly is a mismatch in core conditions at the time of RCS boron  
 
concentration sampling, a recalculation of the RCS boron concentration requirements may be performed to demonstrate that core reactivity is behaving as expected. If an  
 
unexpected physical change in the condition of the core has  
 
occurred, it must be evaluated and corrected, if possible.
 
If the cause of the reactivity anomaly is in the calculation  
 
technique, the calculational models must be revised to provide more accurate predictions. If any of these results are demonstrated, and it is concluded that the reactor core  
 
is acceptable for continued operation, the boron letdown curve may be renormalized, and power operation may continue.
If operational restrictions or additional SRs are necessary  
 
to ensure the reactor core is acceptable for continued  
 
operation, they must be defined.
The required Completion Time of 7 days is adequate for preparing whatever operating restrictions or SRs may be required to allow continued reactor operation.  
 
B.1  If the core reactivity cannot be restored to within the 1% k/k limit, the plant must be brought to a MODE in which the LCO does not apply. To achieve this status, the plant  
 
must be brought to at least MODE 2 within 6 hours. The  
 
allowed Completion Time is reasonable, based on operating  
 
experience, for reaching MODE 2 from full power conditions in an orderly manner and without challenging plant systems.
SURVEILLANCE SR 3.1.2.1 REQUIREMENTS Core reactivity is verified by periodic comparisons of measured and predicted RCS boron concentrations. The  
 
comparison is made considering that other core conditions are fixed or stable
, including CEA position, moderator Reactivity Balance B 3.1.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-6 Revision 3  temperature, fuel temperature, fuel depletion, xenon concentration, and samarium concentration. The SR is  
 
performed prior to entering MODE 1 as an initial check on  
 
core conditions and design calculations at BOC and every  
 
31 days after 60 effective full power days (EFPD). The SR  
 
is modified by two Notes. The Note in the SR column indicates that the normalization of predicted core reactivity to the measured value may take place within the first 60 EFPD after each fuel loading. This allows sufficient time for core conditions to reach steady state,  
 
but prevents operation for a large fraction of the fuel  
 
cycle without establishing a benchmark for the design  
 
calculations. The required subsequent Frequency of 31 EFPD  
 
following the initial 60 EFPD, after entering MODE 1, is  
 
acceptable, based on the slow rate of core changes due to  
 
fuel depletion and the presence of other indicators  
 
(e.g., quadrant power tilt ratio, etc.) for prompt  
 
indication of an anomaly. The Frequency Note, "only  
 
required after 60 EFPD after each fuel loading," is added to the Frequency column to allow this.
REFERENCES 1. UFSAR  
 
MTC B 3.1.3 B 3.1  REACTIVITY CONTROL SYSTEMS  
 
B 3.1.3  Moderator Temperature Coefficient (MTC)  
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-1 Revision 29 BACKGROUND The MTC relates a change in core reactivity to a change in reactor coolant temperature. A positive MTC means that  
 
reactivity increases with increasing moderator temperature;  
 
conversely, a negative MTC means that reactivity decreases with increasing moderator temperature. The reactor is designed to operate with a negative MTC over a large range  
 
of fuel cycle operation. Therefore, a coolant temperature  
 
increase will cause a reactivity decrease, so that the  
 
coolant temperature tends to return toward its initial  
 
value. Reactivity increases that cause a coolant  
 
temperature increase will thus be self limiting, and stable  
 
power operation will result.  
 
Moderator temperature coefficient values are predicted at selected burnups during the safety evaluation analysis and  
 
are confirmed to be acceptable by measurements.
Reload cores are designed so that the MTC is less positive than that allowed by the LCO. The actual value of the MTC is dependent on core characteristics, such as fuel loading and  
 
reactor coolant soluble boron concentration. The core  
 
design may require additional fixed distributed poisons  
 
(burnable poison) to yield an MTC at the BOC within the  
 
range analyzed in the plant accident analysis. The end-of-
 
cycle (EOC) MTC is also limited by the requirements of the  
 
accident analysis. Fuel cycles that are designed to achieve  
 
high burnups or that have changes to other characteristics  
 
are evaluated to ensure that the MTC does not exceed the EOC limit. APPLICABLE The acceptance criteria for the specified MTC are:  
 
SAFETY ANALYSES  
SAFETY ANALYSES  
: a. The MTC values must remain within the bounds of those used in the accident analysis (Reference 1, Section 14.2.2); and  b. The MTC must be such that inherently stable power operations result during normal operation and during accidents, such as overheating and overcooling events.
: a. The MTC values must remain within the bounds of those used in the accident analysis (Reference 1,  
MTC B 3.1.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-2 Revision 43  Reference 1, Section 14.1.2 contains analyses of accidents that result in both overheating and overcooling of the reactor core. Moderator temperature coefficient is one of the controlling parameters for core reactivity in these accidents. Both the most positive value and most negative value of the MTC are important to safety, and both values must be bounded. Values used in the analyses consider worst-case conditions, such as very large soluble boron concentrations, to ensure the accident results are bounding.
 
Accidents that cause core overheating, either by decreased heat removal or increased power production, must be evaluated for results when the MTC is positive. Reactivity accidents that cause increased power production include the CEA withdrawal and CEA ejection transients from either zero or full THERMAL POWER. The limiting overheating event relative to plant response is based on the maximum difference between core power and steam generator heat removal during a transient. The most limiting event with respect to a positive MTC is a CEA ejection accident from full power (Reference 1, Section 14.13). Accidents that cause core overcooling must be evaluated for results when the MTC is most negative. The event that produces the most rapid cooldown of the RCS, and is therefore the most limiting event with respect to the negative MTC, is a steam line break (SLB) event. Following the reactor trip for the postulated EOC SLB event, the large moderator temperature reduction combined with the large negative MTC may produce reactivity increases that are as much as the shutdown reactivity. When this occurs, a substantial fraction of core power is produced with all CEAs inserted, except the most reactive one, which is assumed withdrawn. Even if the reactivity increase produces slightly subcritical conditions, a large fraction of core power may be produced through the effects of subcritical neutron multiplication.
Section 14.2.2); and  b. The MTC must be such that inherently stable power operations result during normal operation and during  
Moderator temperature coefficient values are bounded in reload safety evaluations assuming steady state conditions at BOC, peak RCS boron, and EOC. A 2/3 core burnup MTC measurement is conducted and the measured value may be MTC B 3.1.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-3 Revision 29  extrapolated to project the EOC value, in order to confirm reload design predictions. The MTC satisfies 10 CFR 50.36(c)(2)(ii), Criterion 2. LCO Limiting Condition for Operation 3.1.3 requires the MTC to be within specified limits of the Core Operating Limits Report (COLR), with the maximum positive limit specified in Figure 3.1.3-1, to ensure the core operates within the assumptions of the accident analysis. During the reload core safety evaluation, the MTC is analyzed to determine that its values remain within the bounds of the original accident analysis during operation. The limit on a positive MTC ensures that core overheating accidents will not violate the accident analysis assumptions. The negative MTC limit for EOC specified in the COLR ensures that core overcooling accidents will not violate the accident analysis assumptions.
 
Moderator temperature coefficient is a core physics parameter determined by the fuel and fuel cycle design and cannot be easily controlled once the core design is fixed.
accidents, such as overheating and overcooling events.  
During operation, therefore, the LCO can only be ensured through measurement. The surveillance checks at BOC and 2/3 core burnup provide confirmation that the MTC is behaving as anticipated, so that the acceptance criteria are met. APPLICABILITY In MODE 1, the limits on the MTC must be maintained to ensure that any accident initiated from THERMAL POWER operation will not violate the design assumptions of the accident analysis. In MODE 2, the limits must also be maintained to ensure startup accidents, such as the uncontrolled CEA or group withdrawal, will not violate the assumptions of the accident analysis. In MODEs 3, 4, 5, and 6, this LCO is not applicable, since no DBAs using the MTC as an analysis assumption are initiated from these MODEs. However, the variation of the MTC, with temperature in MODEs 3, 4, and 5 for DBAs initiated in MODEs 1 and 2, is accounted for in the accident analysis. The variation of the MTC, with temperature assumed in the safety analysis, is accepted as valid once the BOC and 2/3 core burnup measurements are used for normalization.
 
MTC B 3.1.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-4 Revision 29 ACTIONS A.1 Moderator temperature coefficient is a function of the fuel and fuel cycle designs, and cannot be controlled directly once the designs have been implemented in the core. If MTC exceeds its limits, the reactor must be placed in MODE 3. This eliminates the potential for violation of the accident analysis bounds. The associated Completion Time of 6 hours is reasonable, considering the probability of an accident occurring during the time period that would require an MTC value within the LCO limits, and the time for reaching MODE 3 from full power conditions in an orderly manner and without challenging plant systems. SURVEILLANCE SR 3.1.3.1 and SR 3.1.3.2 REQUIREMENTS The SRs for measurement of the MTC at the beginning and 2/3 core burnup of each fuel cycle provide for confirmation of the limiting MTC values. The MTC varies with boron concentration during fuel cycle operation. The MTC becomes more negative as the RCS boron concentration is reduced. The requirement for measurement prior to entering MODE 1 after each fuel loading satisfies the confirmatory check on the most positive (least negative) MTC value. The requirement for measurement, within 7 EFPD of initially reaching an equilibrium condition with THERMAL POWER  90% RTP, and within 7 EFPD of reaching 2/3 core burnup, satisfies the confirmatory check of the most negative MTC value. The 2/3 core burnup measurement is performed at any THERMAL POWER, so that the projected EOC MTC may be evaluated before the reactor actually reaches the EOC condition. Moderator temperature coefficient values may be extrapolated and compensated to permit direct comparison to the specified MTC limits.
MTC B 3.1.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-2 Revision 43  Reference 1, Section 14.1.2 contains analyses of accidents that result in both overheating and overcooling of the  
Surveillance Requirement 3.1.3.2 is modified by a Note, which indicates that if the extrapolated MTC is more negative than the EOC COLR limit, the SR may be repeated, and that shutdown must occur prior to exceeding the minimum allowable boron concentration at which MTC is projected to exceed the lower limit. An engineering evaluation is MTC B 3.1.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-5 Revision 29 performed if the extrapolated value of MTC exceeds the Specification limits. REFERENCES 1. UFSAR CEA Alignment B 3.1.4 B 3.1  REACTIVITY CONTROL SYSTEMS B 3.1.4  Control Element Assembly (CEA) Alignment BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-1 Revision 2 BACKGROUND The OPERABILITY (e.g., trippability) of the shutdown and regulating CEAs is an initial assumption in all safety analyses that assume CEA insertion upon reactor trip. The applicable criteria for these reactivity and power distribution design requirements are found in Reference 1, Appendix 1C, Criteria 6, 27, 29, and 30, and Reference 2.
 
Mechanical or electrical failures may cause a CEA to become inoperable or to become misaligned from its group. Control element assembly inoperability or misalignment may cause increased power peaking, due to the asymmetric reactivity distribution and a reduction in the total available CEA worth for reactor shutdown. Therefore, CEA alignment and OPERABILITY are related to core operation in design power peaking limits and the core design requirement of a minimum SDM.
reactor core. Moderator temperature coefficient is one of  
Limits on CEA alignment and OPERABILITY have been established, and all CEA positions are monitored and controlled during power operation to ensure that the power distribution and reactivity limits defined by the design power peaking and SDM limits are preserved.
 
Control element assemblies are moved by their control element drive mechanisms (CEDMs). Each CEDM moves its CEA one step (approximately 3/4-inch) at a time.
the controlling parameters for core reactivity in these  
The CEAs are arranged into groups that are radially symmetric. Therefore, movement of the CEA groups do not introduce radial asymmetries in the core power distribution.
 
The shutdown and regulating CEAs provide the required reactivity worth for immediate reactor shutdown upon a reactor trip. The regulating CEAs also provide reactivity (power level) control during normal operation and transients.
accidents. Both the most positive value and most negative  
The axial position of shutdown and regulating CEAs is indicated by two separate and independent systems, which are CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-2 Revision 2 the Plant Computer CEA Position Indication System and the Reed Switch Position Indication System.
 
The Plant Computer CEA Position Indication System counts the commands sent to the CEA gripper coils from the CEDM Control System that moves the CEAs. There is a one step counter for each CEA. Individual CEAs in a group all receive the same signal to move and should, therefore, all be at the same position indicated by the group step counter for that group.
value of the MTC are important to safety, and both values must be bounded. Values used in the analyses consider worst-case conditions, such as very large soluble boron  
Plant Computer CEA Position Indication System is considered highly precise (+/- 1 step or +/- 3/4-inch). If a CEA does not move one step for each command signal, the step counter will still count the command and incorrectly reflect the position of the CEA.
 
The Reed Switch Position Indication System provides a highly accurate indication of actual CEA position, but at a lower precision than the step counters. This system is based on inductive analog signals from a series of reed switches spaced along a tube with a center-to-center distance of 1.5 inches, which is two steps. To increase the reliability of the system, there are redundant reed switches at each position. APPLICABLE Control element assembly misalignment accidents are SAFETY ANALYSES analyzed in the safety analysis (Reference 1, Sections 14.2, 14.11, and 14.13). The accident analysis defines CEA misoperation as any event, with the exception of sequential group withdraws, which could result from a single malfunction in the reactivity control systems. For example, CEA misalignment may be caused by a malfunction of the CEDM, CEDM Control System, or by operator error. A stuck CEA may be caused by mechanical jamming of the CEA fingers or of the gripper. A dropped CEA could be caused by an electrical failure in the CEA coil power programmers.
concentrations, to ensure the accident results are bounding.  
The acceptance criteria for addressing CEA inoperability/ misalignment are that:  a. There shall be no violations of:  
 
: 1. SAFDLs, or  2. RCS pressure boundary integrity; and CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-3 Revision 2  b. The core must remain subcritical after accidents or transients.
Accidents that cause core overheating, either by decreased heat removal or increased power production, must be  
Two types of misalignment are distinguished in the safety analysis (Reference 1, Appendix 1C). The first type of misalignment occurs if one CEA fails to insert upon a reactor trip and remains stuck fully withdrawn. This condition requires an evaluation to determine that sufficient reactivity worth is held in the remaining CEAs to meet the SDM requirement with the maximum worth CEA stuck fully withdrawn. If a CEA is stuck in the fully withdrawn position, its worth is added to the SDM requirement, since the safety analysis does not take two stuck CEAs into account. The second type of misalignment occurs when one CEA drops partially or fully into the reactor core. This event causes an initial power reduction followed by a return toward the original power, due to positive reactivity feedback from the negative MTC. Increased peaking during the power increase may result in excessive local LHRs (Reference 1, Section 14.14).
 
None of the above CEA misoperations will result in an automatic reactor trip. In the case of the full-length CEA drop, a prompt decrease in core average power and a distortion in radial power are initially produced, which, when conservatively coupled, result in a local power and heat flux increase, and a decrease in DNBR parameters.
evaluated for results when the MTC is positive. Reactivity  
The results of the CEA misoperation analysis show that, during the most limiting misoperation events, no violations of the SAFDLs, fuel centerline temperature, or RCS pressure occur.
 
Control element assembly alignment satisfies 10 CFR 50.36(c)(2)(ii), Criteria 2 and 3.
accidents that cause increased power production include the  
LCO The limits on shutdown and regulating CEA alignments ensure that the assumptions in the safety analysis will remain valid. The requirements on OPERABILITY ensure that upon reactor trip, the CEAs will be available and will be inserted to provide enough negative reactivity to shut down the reactor. The OPERABILITY requirements also ensure that CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-4 Revision 43  the CEA banks maintain the correct power distribution and CEA alignment.
 
The requirement is to maintain the CEA alignment to within 7.5 inches between any CEA and its group. Failure to meet the requirements of this LCO may produce unacceptable power peaking factors and LHRs, or unacceptable SDMs, all of which may constitute initial conditions inconsistent with the safety analysis. APPLICABILITY The requirements on CEA OPERABILITY and alignment are applicable in MODEs 1 and 2 because these are the only MODEs in which neutron (or fission) power is generated, and the OPERABILITY (e.g., trippability) and alignment of CEAs have the potential to affect the safety of the plant. In MODEs 3, 4, 5, and 6, the alignment limits do not apply because the CEAs are bottomed, and the reactor is shut down and not producing fission power. In the shutdown MODEs, the OPERABILITY of the shutdown and regulating CEAs has the potential to affect the required SDM, but this effect can be compensated for by an increase in the boron concentration of the RCS. See LCO 3.1.1 for SDM in MODEs 3, 4, and 5, and LCO 3.9.1 for boron concentration requirements during refueling. ACTIONS A.1 and B.1  A CEA may become misaligned, yet remain trippable. In this condition, the CEA can still perform its required function of adding negative reactivity should a reactor trip be necessary.
CEA withdrawal and CEA ejection transient s from either zero or full THERMAL POWER. The limiting overheating event relative to plant response is based on the maximum  
If one or more regulating or shutdown CEAs are misaligned by > 7.5 inches and  15 inches but trippable, or one CEA is misaligned by > 15 inches but trippable, continued operation in MODEs 1 and 2 may continue, provided CEA alignment is restored within 1 hour for CEAs misaligned  15 inches and within the time specified in the COLR for CEAs misaligned > 15 inches.  (The maximum time provided in the COLR is 2 hours.)
 
CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-5 Revision 43  Regulating and shutdown CEA alignment is restored by either aligning the misaligned CEA(s) to within 7.5 inches of its group or aligning the misaligned CEAs group to within 7.5 inches of the misaligned CEA.
difference between core power and steam generator heat  
Xenon redistribution in the core starts to occur as soon as a CEA becomes misaligned. Restoring CEA alignment ensures acceptable power distributions are maintained. For small misalignments ( 15 inches) of the CEAs, there is:  a. A small effect on the time-dependent, long-term power distributions relative to those used in generating LCOs and limiting safety system settings setpoints;  b. A negligible effect on the available SDM; and  
 
: c. A small effect on the ejected CEA worth used in the accident analysis. With a large CEA misalignment (> 15 inches), however, this misalignment would cause distortion of the core power distribution. This distortion may, in turn, have a significant effect on the time-dependent, long-term power distributions relative to those used in generating LCOs and limiting safety system settings setpoints.
removal during a transient. The most limiting event with  
The effect on the available SDM and the ejected CEA worth used in the accident analysis remains small.
 
Therefore, this condition is limited to a single CEA misalignment, while still allowing time for recovery.
respect to a positive MTC is a CEA ejection accident from full power (Reference 1, Section 14.
In both cases, the allowed time period is sufficient to:  a. Identify cause of a misaligned CEA;  b. Take appropriate corrective action to realign the CEAs; and  c. Minimize the effects of xenon redistribution. If a CEA is untrippable, it is not available for reactivity insertion during a reactor trip. With an untrippable CEA, meeting the insertion limits of LCOs 3.1.5 and 3.1.6 does not ensure that adequate SDM exists. Condition F must be entered.
13). Accidents that cause core overcooling must be evaluated for results when the MTC is most negative. The event that  
CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-6 Revision 37  C.1 and C.2  If any CEA is not restored to within its alignment limits within the Completion Time provided in Required Action A.1 or B.1, an additional 2 hours is allowed to restore CEA alignment, provided THERMAL POWER is reduced  70% RTP. Prompt action must be taken to reduce THERMAL POWER, and the reduction must be completed within 1 hour. Reducing THERMAL POWER ensures acceptable power distributions are maintained during the additional time provided to restore alignment.
 
The Completion Times are acceptable based on the reasons provided in the Bases for Required Actions A.1 and B.1.
produces the most rapid cooldown of the RCS, and is  
D.1, D.2.1, and D.2.2  The CEA motion inhibit permits CEA motion within the requirements of LCO 3.1.6, and prevents regulating CEAs from being misaligned from other CEAs in the group.
 
Performing SR 3.1.4.1 within 1 hour and every 4 hours thereafter is considered acceptable, in view of other information continuously available to the operator in the Control Room.
therefore the most limiting event with respect to the  
With the CEA motion inhibit inoperable, a Completion Time of 6 hours is allowed for restoring the CEA motion inhibit to OPERABLE status, or fully withdrawing the CEAs in groups 3 and 4, and withdrawing all CEAs in group 5 to < 5%
 
insertion.
negative MTC, is a steam line break (SLB) event. Following  
Withdrawal of the CEAs to the positions required in Required Action D.2.2 provides additional assurance that core perturbations in local burnup, peaking factors, and SDM will not be more adverse than the Conditions assumed in the safety analyses and LCO setpoint determination (Reference 1, Chapter 14). The 6-hour Completion Time takes into account Required Action D.1, the protection afforded by the CEA deviation circuits, and other information continuously available to the operator in the Control Room, so that during actual CEA motion, deviations can be detected.
 
CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-7 Revision 55  Required Action D.2.2 is modified by a Note indicating that performing this Required Action is not required when in conflict with Required Actions A.1, B.1, C.2, or E.1.
the reactor trip for the postulated EOC SLB event, the large  
E.1  When the CEA deviation circuit is inoperable, performing SR 3.1.4.1 within 1 hour and every 4 hours thereafter ensures improper CEA alignments are identified before unacceptable flux distributions occur. The specified Completion Times take into account other information continuously available to the operator in the Control Room, so that during CEA movement, deviations can be detected, and the protection provided by the CEA inhibit and deviation circuit is not required.
 
F.1  If any Required Action and associated Completion Time of Condition C, Condition D, or Condition E is not met, one or more regulating or shutdown CEAs are untrippable, two or more CEAs are misaligned by > 15 inches, the unit is required to be brought to MODE 3. By being brought to MODE 3, the unit is brought outside the MODE of applicability. Continued operation is not allowed in the case of more than one CEA misaligned from any other CEA in its group by > 15 inches, or one or more CEAs untrippable.
moderator temperature reduction combined with the large  
This is because these cases could result in a loss of SDM and power distribution and a loss of safety function, respectively.
 
When a Required Action cannot be completed within the required Completion Time, a controlled shutdown should be commenced. The allowed Completion Time of 6 hours is reasonable, based on operating experience, for reaching MODE 3 from full power conditions in an orderly manner and without challenging plant systems. SURVEILLANCE SR 3.1.4.1 REQUIREMENTS Verification is required that individual CEA positions are within 7.5 inches (indicated reed switch positions) of all other CEAs in the group within 1 hour of any CEA movement of > 7.5 inches. The CEA position verification after each CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-8 Revision 55 movement of > 7.5 inches ensure that the CEAs in that group are properly aligned at the time when CEA misalignments are most likely to have occurred. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
negative MTC may produce reactivity increases that are as  
SR 3.1.4.2  Demonstrating the CEA motion inhibit OPERABLE verifies that the CEA motion inhibit is functional, even if it is not regularly operated. The verification shall ensure that the motion inhibit circuit maintains the CEA group overlap and sequencing requirements of LCO 3.1.6, and prevents any regulating CEA from being misaligned from all other CEAs in its group by > 7.5 inches (indicated position). The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. SR 3.1.4.3  Demonstrating the CEA deviation circuit is OPERABLE verifies the circuit is functional. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
SR 3.1.4.4  Verifying each CEA is trippable would require that each CEA be tripped. In MODEs 1 and 2, tripping each CEA would result in radial or axial power tilts or oscillations.
much as the shutdown reactivity. When this occurs, a  
Therefore, individual CEAs are exercised to provide increased confidence that all CEAs continue to be trippable, even if they are not regularly tripped. A movement of 7.5 inches is adequate to demonstrate motion without exceeding the alignment limit when only one CEA is being moved. For the purposes of performing the CEA operability test, if the CEA has an inoperable position indicator channel, the alternate indication system (pulse counter or voltage dividing network) will be used to monitor position.
 
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. Between required performances of SR 3.1.4.4, if a CEA(s)is discovered to be immovable, but remains trippable and aligned, the CEA is considered to be OPERABLE. At any time, if a CEA(s) is immovable, a determination of the trippability (OPERABILITY) of the CEA(s) must be made, and appropriate action taken.
substantial fraction of core power is produced with all CEAs  
CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-9 Revision 55  SR 3.1.4.5  Performance of a CHANNEL FUNCTIONAL TEST of each reed switch position transmitter channel ensures the channel is OPERABLE and capable of indicating CEA position over the entire length of the CEA's travel. A successful test of the required contact(s) of a channel relay may be performed by the verification of the change of state of a single contact of the relay. This clarifies what is an acceptable CHANNEL FUNCTIONAL TEST of a relay. This is acceptable because all of the other required contacts of the relay are verified by other Technical Specification tests at least once per refueling interval with applicable extensions. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
SR 3.1.4.6  Verification of CEA drop times determined that the maximum CEA drop time permitted is consistent with the assumed drop time used in that safety analysis (Reference 1, Chapter 14).
inserted, except the most reactive one, which is assumed  
Control element assembly drop time is measured from the time when electrical power is interrupted to the CEDM until the CEA reaches its 90% insertion position, from a fully withdrawn position, with Tave  515&deg;F and all reactor coolant pumps operating. Measuring drop times prior to reactor criticality, after reactor vessel head removal, ensures that reactor internals and CEDM will not interfere with CEA motion or drop time, and that no degradation in these systems has occurred that would adversely affect CEA motion or drop time. Individual CEAs whose drop times are greater than safety analysis assumptions are not OPERABLE. This SR is performed prior to criticality, based on the need to perform this SR under the conditions that apply during a unit outage and because of the potential for an unplanned unit transient if the SR were performed with the reactor at power. REFERENCES 1. UFSAR  2. 10 CFR 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Plants" Shutdown CEA Insertion Limits B 3.1.5 B 3.1  REACTIVITY CONTROL SYSTEMS B 3.1.5  Shutdown Control Element Assembly (CEA) Insertion Limits BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-1 Revision 2 BACKGROUND The insertion limits of the shutdown CEAs are initial assumptions in all safety analyses that assume CEA insertion upon reactor trip. The insertion limits directly affect core power distributions and assumptions of available SDM, ejected CEA worth, and initial reactivity insertion rate.
 
The applicable criteria for these reactivity and power distribution design requirements are in Reference 1, Appendix 1C, Criteria 6, 27, 28, 29, and 30, and Reference 2. Limits on shutdown CEA insertion have been established, and all CEA positions are monitored and controlled during power operation to ensure that the reactivity limits, ejected CEA worth, and SDM limits are preserved.
withdrawn. Even if the reactivity increase produces slightly subcritical conditions, a large fraction of core power may be produced through the effects of subcritical  
The shutdown CEAs are arranged into groups that are radially symmetric. Therefore, movement of the shutdown CEAs does not introduce radial asymmetries in the core power distribution. The shutdown and regulating CEAs provide the required reactivity worth for immediate reactor shutdown upon a reactor trip.
 
The design calculations are performed with the assumption that the shutdown CEAs are withdrawn prior to the regulating CEAs. The shutdown CEAs can be fully withdrawn without the core going critical. The shutdown CEAs are controlled manually by the Control Room operator. During normal unit operation, the shutdown CEAs are fully withdrawn. The shutdown CEAs must be completely withdrawn from the core prior to withdrawing any regulating CEAs during an approach to criticality. The shutdown CEAs are left in this position until the reactor is shut down. They affect core power, burnup distribution, and add negative reactivity to shut down the reactor upon receipt of a reactor trip signal.
neutron multiplication.  
 
Moderator temperature coefficient values are bounded in reload safety evaluations assuming steady state conditions  
 
at BOC, peak RCS boron, and EOC. A 2/3 core burnup MTC  
 
measurement is conducted and the measured value may be MTC B 3.1.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-3 Revision 29  extrapolated to project the EOC value, in order to confirm reload design predictions.
The MTC satisfies 10 CFR 50.36(c)(2)(ii), Criterion 2.
LCO Limiting Condition for Operation 3.1.3 requires the MTC to be within specified limits of the Core Operating Limits  
 
Report (COLR), with the maximum positive limit specified in  
 
Figure 3.1.3-1, to ensure the core operates within the  
 
assumptions of the accident analysis. During the reload  
 
core safety evaluation, the MTC is analyzed to determine  
 
that its values remain within the bounds of the original  
 
accident analysis during operation. The limit on a positive  
 
MTC ensures that core overheating accidents will not violate  
 
the accident analysis assumptions. The negative MTC limit  
 
for EOC specified in the COLR ensures that core overcooling  
 
accidents will not violate the accident analysis  
 
assumptions.  
 
Moderator temperature coefficient is a core physics parameter determined by the fuel and fuel cycle design and  
 
cannot be easily controlled once the core design is fixed.
 
During operation, therefore, the LCO can only be ensured  
 
through measurement. The surveillance checks at BOC and  
 
2/3 core burnup provide confirmation that the MTC is behaving as anticipated, so that the acceptance criteria are met. APPLICABILITY In MODE 1, the limits on the MTC must be maintained to ensure that any accident initiated from THERMAL POWER  
 
operation will not violate the design assumptions of the  
 
accident analysis. In MODE 2, the limits must also be  
 
maintained to ensure startup accidents, such as the  
 
uncontrolled CEA or group withdrawal, will not violate the  
 
assumptions of the accident analysis. In MODEs 3, 4, 5,  
 
and 6, this LCO is not applicable, since no DBAs using the  
 
MTC as an analysis assumption are initiated from these  
 
MODEs. However, the variation of the MTC, with temperature  
 
in MODEs 3, 4, and 5 for DBAs initiated in MODEs 1 and 2, is  
 
accounted for in the accident analysis. The variation of  
 
the MTC, with temperature assumed in the safety analysis, is  
 
accepted as valid once the BOC and 2/3 core burnup measurements are used for normalization.
MTC B 3.1.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-4 Revision 29 ACTIONS A.1 Moderator temperature coefficient is a function of the fuel and fuel cycle designs, and cannot be controlled directly  
 
once the designs have been implemented in the core. If MTC  
 
exceeds its limits, the reactor must be placed in MODE 3.
This eliminates the potential for violation of the accident analysis bounds. The associated Completion Time of 6 hours  
 
is reasonable, considering the probability of an accident  
 
occurring during the time period that would require an MTC  
 
value within the LCO limits, and the time for reaching  
 
MODE 3 from full power conditions in an orderly manner and without challenging plant systems.
SURVEILLANCE SR 3.1.3.1 and SR 3.1.3.2 REQUIREMENTS The SRs for measurement of the MTC at the beginning and 2/3 core burnup of each fuel cycle provide for confirmation of the limiting MTC values. The MTC varies with boron concentration during fuel cycle operation
. The MTC becomes more negative as the RCS boron concentration is reduced
. The requirement for measurement prior to entering MODE 1 after each fuel loading satisfies the confirmatory check on the most positive (least negative) MTC value. The requirement for measurement, within 7 EFPD of initially reaching an equilibrium condition with THERMAL POWER  90% RTP, and within 7 EFPD of reaching 2/3 core burnup, satisfies the confirmatory check of the most negative MTC value. The 2/3 core burnup measurement is performed at any THERMAL POWER, so that the projected EOC MTC may be evaluated before the reactor actually reaches the EOC condition. Moderator temperature coefficient values may be  
 
extrapolated and compensated to permit direct comparison to  
 
the specified MTC limits.  
 
Surveillance Requirement 3.1.3.2 is modified by a Note, which indicates that if the extrapolated MTC is more  
 
negative than the EOC COLR limit, the SR may be repeated,  
 
and that shutdown must occur prior to exceeding the minimum  
 
allowable boron concentration at which MTC is projected to  
 
exceed the lower limit. An engineering evaluation is MTC B 3.1.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-5 Revision 29 performed if the extrapolated value of MTC exceeds the Specification limits.
REFERENCES 1. UFSAR  
 
CEA Alignment B 3.1.4 B 3.1  REACTIVITY CONTROL SYSTEMS  
 
B 3.1.4  Control Element Assembly (CEA) Alignment  
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-1 Revision 2 BACKGROUND The OPERABILITY (e.g., trippability) of the shutdown and regulating CEAs is an initial assumption in all safety  
 
analyses that assume CEA insertion upon reactor trip.
The applicable criteria for these reactivity and power distribution design requirements are found in Reference 1, Appendix 1C, Criteria 6, 27, 29, and 30, and Reference 2.  
 
Mechanical or electrical failures may cause a CEA to become inoperable or to become misaligned from its group. Control element assembly inoperability or misalignment may cause increased power peaking, due to the asymmetric reactivity  
 
distribution and a reduction in the total available CEA  
 
worth for reactor shutdown. Therefore, CEA alignment and  
 
OPERABILITY are related to core operation in design power  
 
peaking limits and the core design requirement of a minimum  
 
SDM.
Limits on CEA alignment and OPERABILITY have been established, and all CEA positions are monitored and  
 
controlled during power operation to ensure that the power  
 
distribution and reactivity limits defined by the design  
 
power peaking and SDM limits are preserved.  
 
Control element assemblies are moved by their control element drive mechanisms (CEDMs). Each CEDM moves its CEA  
 
one step (approximately 3/4-inch) at a time.  
 
The CEAs are arranged into groups that are radially symmetric. Therefore, movement of the CEA groups do not  
 
introduce radial asymmetries in the core power distribution.
 
The shutdown and regulating CEAs provide the required reactivity worth for immediate reactor shutdown upon a reactor trip. The regulating CEAs also provide reactivity  
 
(power level) control during normal operation and  
 
transients.  
 
The axial position of shutdown and regulating CEAs is indicated by two separate and independent systems, which are CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-2 Revision 2 the Plant Computer CEA Position Indication System and the Reed Switch Position Indication System.  
 
The Plant Computer CEA Position Indication System counts the commands sent to the CEA gripper coils from the CEDM Control  
 
System that moves the CEAs. There is a one step counter for each CEA. Individual CEAs in a group all receive the same signal to move and should, therefore, all be at the same  
 
position indicated by the group step counter for that group.
 
Plant Computer CEA Position Indication System is considered  
 
highly precise (+/- 1 step or +/- 3/4-inch). If a CEA does not move one step for each command signal, the step counter will  
 
still count the command and incorrectly reflect the position  
 
of the CEA.  
 
The Reed Switch Position Indication System provides a highly accurate indication of actual CEA position, but at a lower  
 
precision than the step counters. This system is based on  
 
inductive analog signals from a series of reed switches  
 
spaced along a tube with a center-to-center distance of 1.5 inches, which is two steps. To increase the reliability  
 
of the system, there are redundant reed switches at each position.
APPLICABLE Control element assembly misalignment accidents are SAFETY ANALYSES analyzed in the safety analysis (Reference 1, Sections 14.2, 14.11, and 14.13). The accident analysis defines CEA misoperation as any event, with the exception of sequential  
 
group withdraws, which could result from a single  
 
malfunction in the reactivity control systems. For example, CEA misalignment may be caused by a malfunction of the CEDM, CEDM Control System, or by operator error. A stuck CEA may be caused by mechanical jamming of the CEA fingers or of the  
 
gripper. A dropped CEA could be caused by an electrical  
 
failure in the CEA coil power programmers.  
 
The acceptance criteria for addressing CEA inoperability/
misalignment are that:  a. There shall be no violations of:  
: 1. SAFDLs, or  2. RCS pressure boundary integrity; and CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-3 Revision 2  b. The core must remain subcritical after accidents or transients.  
 
Two types of misalignment are distinguished in the safety analysis (Reference 1, Appendix 1C). The first type of misalignment occurs if one CEA fails to insert upon a reactor trip and remains stuck fully withdrawn. This condition requires an evaluation to determine that  
 
sufficient reactivity worth is held in the remaining CEAs to  
 
meet the SDM requirement with the maximum worth CEA stuck  
 
fully withdrawn. If a CEA is stuck in the fully withdrawn  
 
position, its worth is added to the SDM requirement, since  
 
the safety analysis does not take two stuck CEAs into  
 
account. The second type of misalignment occurs when one  
 
CEA drops partially or fully into the reactor core. This  
 
event causes an initial power reduction followed by a return  
 
toward the original power, due to positive reactivity feedback from the negative MTC. Increased peaking during the power increase may result in excessive local LHRs (Reference 1, Section 14.14).  
 
None of the above CEA misoperations will result in an automatic reactor trip. In the case of the full-length CEA drop, a prompt decrease in core average power and a  
 
distortion in radial power are initially produced, which,  
 
when conservatively coupled, result in a local power and  
 
heat flux increase, and a decrease in DNBR parameters.  
 
The results of the CEA misoperation analysis show that, during the most limiting misoperation events, no violations  
 
of the SAFDLs, fuel centerline temperature, or RCS pressure  
 
occur.
Control element assembly alignment satisfies 10 CFR 50.36(c)(2)(ii), Criteria 2 and 3.  
 
LCO The limits on shutdown and regulating CEA alignments ensure that the assumptions in the safety analysis will remain  
 
valid. The requirements on OPERABILITY ensure that upon  
 
reactor trip, the CEAs will be available and will be  
 
inserted to provide enough negative reactivity to shut down  
 
the reactor. The OPERABILITY requirements also ensure that CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-4 Revision 43  the CEA banks maintain the correct power distribution and CEA alignment.  
 
The requirement is to maintain the CEA alignment to within 7.5 inches between any CEA and its group.
Failure to meet the requirements of this LCO may produce unacceptable power peaking factors and LHRs, or unacceptable  
 
SDMs, all of which may constitute initial conditions inconsistent with the safety analysis.
APPLICABILITY The requirements on CEA OPERABILITY and alignment are applicable in MODEs 1 and 2 because these are the only MODEs  
 
in which neutron (or fission) power is generated, and the  
 
OPERABILITY (e.g., trippability) and alignment of CEAs have  
 
the potential to affect the safety of the plant. In  
 
MODEs 3, 4, 5, and 6, the alignment limits do not apply  
 
because the CEAs are bottomed, and the reactor is shut down  
 
and not producing fission power. In the shutdown MODEs, the  
 
OPERABILITY of the shutdown and regulating CEAs has the  
 
potential to affect the required SDM, but this effect can be  
 
compensated for by an increase in the boron concentration of  
 
the RCS. See LCO 3.1.1 for SDM in MODEs 3, 4, and 5, and  
 
LCO 3.9.1 for boron concentration requirements during refueling.
ACTIONS A.1 and B.1  A CEA may become misaligned, yet remain trippable. In this condition, the CEA can still perform its required function  
 
of adding negative reactivity should a reactor trip be  
 
necessary.  
 
If one or more regulating or shutdown CEAs are misaligned by  
> 7.5 inches and  15 inches but trippable, or one CEA is misaligned by > 15 inches but trippable, continued operation  
 
in MODEs 1 and 2 may continue, provided CEA alignment is restored within 1 hour for CEAs misaligned  15 inches and within the time specified in the COLR for CEAs misaligned  
> 15 inches.  (The maximum time provided in the COLR is 2 hours.)  
 
CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-5 Revision 43  Regulating and shutdown CEA alignment is restored by either aligning the misaligned CEA(s) to within 7.5 inches of its  
 
group or aligning the misaligned CEAs group to within  
 
7.5 inches of the misaligned CEA.  
 
Xenon redistribution in the core starts to occur as soon as a CEA becomes misaligned. Restoring CEA alignment ensures acceptable power distributions are maintained. For small misalignments ( 15 inches) of the CEAs, there is:  a. A small effect on the time-dependent, long-term power distributions relative to those used in generating LCOs  
 
and limiting safety system settings setpoints;  b. A negligible effect on the available SDM; and  
: c. A small effect on the ejected CEA worth used in the accident analysis.
With a large CEA misalignment (
> 15 inches), however, this misalignment would cause distortion of the core power  
 
distribution. This distortion may, in turn, have a  
 
significant effect on the time-dependent, long-term power  
 
distributions relative to those used in generating LCOs and  
 
limiting safety system settings setpoints.  
 
The effect on the available SDM and the ejected CEA worth used in the accident analysis remains small.  
 
Therefore, this condition is limited to a single CEA misalignment, while still allowing time for recovery.  
 
In both cases, the allowed time period is sufficient to:  a. Identify cause of a misaligned CEA;  b. Take appropriate corrective action to realign the CEAs; and  c. Minimize the effects of xenon redistribution.
If a CEA is untrippable, it is not available for reactivity insertion during a reactor trip. With an untrippable CEA,  
 
meeting the insertion limits of LCOs 3.1.5 and 3.1.6 does  
 
not ensure that adequate SDM exists. Condition F must be  
 
entered.  
 
CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-6 Revision 37  C.1 and C.2  If any CEA is not restored to within its alignment limits within the Completion Time provided in Required Action A.1  
 
or B.1, an additional 2 hours is allowed to restore CEA alignment, provided THERMAL POWER is reduced  70% RTP.
Prompt action must be taken to reduce THERMAL POWER, and the reduction must be completed within 1 hour. Reducing THERMAL POWER ensures acceptable power distributions are maintained  
 
during the additional time provided to restore alignment.
 
The Completion Times are acceptable based on the reasons  
 
provided in the Bases for Required Actions A.1 and B.1.  
 
D.1, D.2.1, and D.2.2  The CEA motion inhibit permits CEA motion within the requirements of LCO 3.1.6, and prevents regulating CEAs from  
 
being misaligned from other CEAs in the group.  
 
Performing SR 3.1.4.1 within 1 hour and every 4 hours thereafter is considered acceptable, in view of other  
 
information continuously available to the operator in the  
 
Control Room.  
 
With the CEA motion inhibit inoperable, a Completion Time of 6 hours is allowed for restoring the CEA motion inhibit to  
 
OPERABLE status, or fully withdrawing the CEAs in groups 3  
 
and 4, and withdrawing all CEAs in group 5 to < 5%  
 
insertion.  
 
Withdrawal of the CEAs to the positions required in Required Action D.2.2 provides additional assurance that core  
 
perturbations in local burnup, peaking factors, and SDM will  
 
not be more adverse than the Conditions assumed in the  
 
safety analyses and LCO setpoint determination (Reference 1,  
 
Chapter 14).
The 6-hour Completion Time takes into account Required Action D.1, the protection afforded by the CEA deviation  
 
circuits, and other information continuously available to
 
the operator in the Control Room, so that during actual CEA  
 
motion, deviations can be detected.  
 
CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-7 Revision 55  Required Action D.2.2 is modified by a Note indicating that performing this Required Action is not required when in  
 
conflict with Required Actions A.1, B.1, C.2, or E.1.  
 
E.1  When the CEA deviation circuit is inoperable, performing SR 3.1.4.1 within 1 hour and every 4 hours thereafter ensures improper CEA alignments are identified before  
 
unacceptable flux distributions occur. The specified  
 
Completion Times take into account other information  
 
continuously available to the operator in the Control Room,  
 
so that during CEA movement, deviations can be detected, and  
 
the protection provided by the CEA inhibit and deviation  
 
circuit is not required.  
 
F.1  If any Required Action and associated Completion Time of Condition C, Condition D, or Condition E is not met, one or  
 
more regulating or shutdown CEAs are untrippable, two or  
 
more CEAs are misaligned by > 15 inches, the unit is  
 
required to be brought to MODE 3. By being brought to  
 
MODE 3, the unit is brought outside the MODE of  
 
applicability. Continued operation is not allowed in the  
 
case of more than one CEA misaligned from any other CEA in  
 
its group by > 15 inches, or one or more CEAs untrippable.
 
This is because these cases could result in a loss of SDM  
 
and power distribution and a loss of safety function,  
 
respectively.  
 
When a Required Action cannot be completed within the required Completion Time, a controlled shutdown should be  
 
commenced. The allowed Completion Time of 6 hours is  
 
reasonable, based on operating experience, for reaching  
 
MODE 3 from full power conditions in an orderly manner and without challenging plant systems.
SURVEILLANCE SR 3.1.4.1 REQUIREMENTS Verification is required that individual CEA positions are within 7.5 inches (indicated reed switch positions) of all  
 
other CEAs in the group within 1 hour of any CEA movement of  
> 7.5 inches. The CEA position verification after each CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-8 Revision 55 movement of  
> 7.5 inches ensure that the CEAs in that group are properly aligned at the time when CEA misalignments are  
 
most likely to have occurred. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
SR 3.1.4.2  Demonstrating the CEA motion inhibit OPERABLE verifies that the CEA motion inhibit is functional, even if it is not  
 
regularly operated. The verification shall ensure that the  
 
motion inhibit circuit maintains the CEA group overlap and  
 
sequencing requirements of LCO 3.1.6, and prevents any  
 
regulating CEA from being misaligned from all other CEAs in its group by  
> 7.5 inches (indicated position). The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
SR 3.1.4.3  Demonstrating the CEA deviation circuit is OPERABLE verifies the circuit is functional. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
SR 3.1.4.4  Verifying each CEA is trippable would require that each CEA be tripped. In MODEs 1 and 2, tripping each CEA would  
 
result in radial or axial power tilts or oscillations.
 
Therefore, individual CEAs are exercised to provide increased confidence that all CEAs continue to be trippable,  
 
even if they are not regularly tripped. A movement of  
 
7.5 inches is adequate to demonstrate motion without  
 
exceeding the alignment limit when only one CEA is being  
 
moved. For the purposes of performing the CEA operability  
 
test, if the CEA has an inoperable position indicator  
 
channel, the alternate indication system (pulse counter or  
 
voltage dividing network) will be used to monitor position.
 
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. Between required performances of SR 3.1.4.4, if a CEA(s)is discovered to be immovable, but remains trippable and aligned, the CEA is  
 
considered to be OPERABLE. At any time, if a CEA(s) is  
 
immovable, a determination of the trippability (OPERABILITY)  
 
of the CEA(s) must be made, and appropriate action taken.  
 
CEA Alignment B 3.1.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-9 Revision 55  SR 3.1.4.5  Performance of a CHANNEL FUNCTIONAL TEST of each reed switch position transmitter channel ensures the channel is OPERABLE  
 
and capable of indicating CEA position over the entire  
 
length of the CEA's travel. A successful test of the  
 
required contact(s) of a channel relay may be performed by the verification of the change of state of a single contact of the relay. This clarifies what is an acceptable CHANNEL  
 
FUNCTIONAL TEST of a relay. This is acceptable because all  
 
of the other required contacts of the relay are verified by  
 
other Technical Specification tests at least once per  
 
refueling interval with applicable extensions. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
SR 3.1.4.6  Verification of CEA drop times determined that the maximum CEA drop time permitted is consistent with the assumed drop  
 
time used in that safety analysis (Reference 1, Chapter 14).
 
Control element assembly drop time is measured from the time  
 
when electrical power is interrupted to the CEDM until the  
 
CEA reaches its 90% insertion position, from a fully withdrawn position, with Tave  515&deg;F and all reactor coolant pumps operating. Measuring drop times prior to reactor  
 
criticality, after reactor vessel head removal, ensures that  
 
reactor internals and CEDM will not interfere with CEA  
 
motion or drop time, and that no degradation in these  
 
systems has occurred that would adversely affect CEA motion  
 
or drop time. Individual CEAs whose drop times are greater  
 
than safety analysis assumptions are not OPERABLE. This SR  
 
is performed prior to criticality, based on the need to  
 
perform this SR under the conditions that apply during a  
 
unit outage and because of the potential for an unplanned  
 
unit transient if the SR were performed with the reactor at power. REFERENCES 1. UFSAR  2. 10 CFR 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Plants"  
 
Shutdown CEA Insertion Limits B 3.1.5 B 3.1  REACTIVITY CONTROL SYSTEMS  
 
B 3.1.5  Shutdown Control Element Assembly (CEA) Insertion Limits  
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-1 Revision 2 BACKGROUND The insertion limits of the shutdown CEAs are initial assumptions in all safety analyses that assume CEA insertion  
 
upon reactor trip. The insertion limits directly affect  
 
core power distributions and assumptions of available SDM, ejected CEA worth, and initial reactivity insertion rate.  
 
The applicable criteria for these reactivity and power distribution design requirements are in Reference 1, Appendix 1C, Criteria 6, 27, 28, 29, and 30, and Reference 2. Limits on shutdown CEA insertion have been established, and all CEA positions are monitored and  
 
controlled during power operation to ensure that the  
 
reactivity limits, ejected CEA worth, and SDM limits are  
 
preserved.  
 
The shutdown CEAs are arranged into groups that are radially symmetric. Therefore, movement of the shutdown CEAs does  
 
not introduce radial asymmetries in the core power  
 
distribution. The shutdown and regulating CEAs provide the  
 
required reactivity worth for immediate reactor shutdown  
 
upon a reactor trip.  
 
The design calculations are performed with the assumption that the shutdown CEAs are withdrawn prior to the regulating  
 
CEAs. The shutdown CEAs can be fully withdrawn without the  
 
core going critical. The shutdown CEAs are controlled  
 
manually by the Control Room operator. During normal unit  
 
operation, the shutdown CEAs are fully withdrawn. The  
 
shutdown CEAs must be completely withdrawn from the core  
 
prior to withdrawing any regulating CEAs during an approach  
 
to criticality. The shutdown CEAs are left in this position until the reactor is shut down. They affect core power, burnup distribution, and add negative reactivity to shut  
 
down the reactor upon receipt of a reactor trip signal.  
 
Shutdown CEA Insertion Limits B 3.1.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-2 Revision 38 APPLICABLE Accident analysis assumes that the shutdown CEAs are fully  SAFETY ANALYSES withdrawn any time the reactor is critical. This ensures that:  a. The minimum SDM is maintained; and  
Shutdown CEA Insertion Limits B 3.1.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-2 Revision 38 APPLICABLE Accident analysis assumes that the shutdown CEAs are fully  SAFETY ANALYSES withdrawn any time the reactor is critical. This ensures that:  a. The minimum SDM is maintained; and  
: b. The potential effects of a CEA ejection accident are limited to acceptable limits. Control element assemblies are considered fully withdrawn at 129 inches.
: b. The potential effects of a CEA ejection accident are limited to acceptable limits.
On a reactor trip, all CEAs (shutdown and regulating), except the most reactive CEA, are assumed to insert into the core. The shutdown and regulating CEAs shall be at or above their insertion limits and available to insert the required amount of negative reactivity on a reactor trip signal. The regulating CEAs may be partially inserted in the core as allowed by LCO 3.1.6. The shutdown CEA insertion limit is established to ensure that a sufficient amount of negative reactivity is available to shut down the reactor and maintain the required SDM (see LCO 3.1.1) following a reactor trip from full power. The combination of regulating CEAs and shutdown CEAs (less the most reactive CEA, which is assumed to be fully withdrawn) is sufficient to take the reactor from full power conditions at rated temperature to zero power, and to maintain the required SDM at rated no load temperature (Reference 1, Sections 3.2 and 3.4). The shutdown CEA insertion limit also limits the reactivity worth of an ejected shutdown CEA.
Control element assemblies are considered fully withdrawn at 129 inches.
The acceptance criteria for addressing shutdown CEA, as well as regulating CEA insertion limits and inoperability or misalignment, are that:  a. There be no violation of:  
 
: 1. SAFDLs, or  2. RCS pressure boundary damage; and  b. The core remains subcritical after accident transients.
On a reactor trip, all CEAs (shutdown and regulating),
As such, the shutdown CEA insertion limits affect safety analyses involving core reactivity, ejected CEA worth, and SDM (Reference 1, Section 14.1.2).
except the most reactive CEA, are assumed to insert into the  
Shutdown CEA Insertion Limits B 3.1.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-3 Revision 38  The shutdown CEA insertion limits satisfy 10 CFR 50.36(c)(2)(ii), Criterion 2. LCO The shutdown CEAs must be within their insertion limits any time the reactor is critical or approaching criticality.
 
This ensures that a sufficient amount of negative reactivity is available to shut down the reactor and maintain the required SDM following a reactor trip. APPLICABILITY The shutdown CEAs must be within their insertion limits, with the reactor in MODEs 1 and 2. The Applicability in MODE 2 begins anytime any regulating CEA is not fully inserted. This ensures that a sufficient amount of negative reactivity is available to shut down the reactor and maintain the required SDM following a reactor trip. In MODE 3, 4, 5, or 6, the shutdown CEAs are fully inserted in the core and contribute to the SDM. Refer to LCO 3.1.1 for SDM requirements in MODEs 3, 4, and 5. Limiting Condition for Operation 3.9.1 ensures adequate SDM in MODE 6.
core. The shutdown and regulating CEAs shall be at or above  
This LCO has been modified by a Note indicating the LCO requirement is suspended during SR 3.1.4.4. This SR verifies the freedom of the CEAs to move, and requires the shutdown CEAs to move below the LCO limits, which would normally violate the LCO. ACTIONS A.1  When one shutdown CEA is withdrawn  121.5 inches and < 129 inches, the accumulated times the shutdown CEAs have been withdrawn within this range must be verified. The Completion Time for this action is once within 4 hours and 24 hours thereafter. Operation is allowed for 7 consecutive days and a total of 14 days per 365 days. The peaking factors may not be outside required limits when one shutdown CEA is misaligned; therefore, continued operation is allowed. Since the power distribution limits are being maintained via the LCOs of Technical Specification Section 3.2, any out-of-limit peaking factor conditions will require entry into the Actions of the appropriate Section 3.2 LCO(s). The limits on consecutive days and total days in this condition reflect that the core may be approaching the acceptable limits placed on operation with Shutdown CEA Insertion Limits B 3.1.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-4 Revision 38 flux patterns outside those assumed in the long-term burnup assumptions. Therefore, operation in this condition cannot continue and the CEA is required to be restored per Action B. The accumulated times are required to be verified once within 4 hours to determine which accumulated time limit is more limiting. The periodic Completion Time of 24 hours after the initial completion within 4 hours is adequate to ensure that the accumulated time limits are not exceeded.
 
B.1  Prior to entering this condition, the shutdown CEAs were fully withdrawn or all but one shutdown CEA was withdrawn  129 inches. If one shutdown CEA is withdrawn  121.5 inches and < 129 inches for > 7 days per occurrence or > 14 days per 365 days, or one shutdown CEA withdrawn < 121.5 inches, or two or more shutdown CEAs withdrawn < 129 inches, the out-of-limit CEAs must be restored to within limits within 2 hours. The Completion Time of 2 hours reflects that the power distribution limits may be outside required limits and that the core may be approaching the acceptable limits placed on operation within flux patterns outside those assumed in the long-term burnup assumptions.
their insertion limits and available to insert the required  
The CEA(s) must be restored to within limits within 2 hours. The 2-hour total Completion Time allows the operator adequate time to adjust the CEA(s) in an orderly manner.
 
C.1  When Required Action A.1 or B.1 cannot be met or completed within the required Completion Time, a controlled shutdown should be commenced. The allowed Completion Time of 6 hours is reasonable, based on operating experience, for reaching MODE 3 from full power conditions in an orderly manner and without challenging plant systems. SURVEILLANCE SR 3.1.5.1 REQUIREMENTS Verification that the shutdown CEAs are within their insertion limits prior to an approach to criticality ensures that when the reactor is critical, or being taken critical, the shutdown CEAs will be available to shut down the Shutdown CEA Insertion Limits B 3.1.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-5 Revision 55  reactor, and the required SDM will be maintained following a reactor trip. This SR and Frequency ensure that the shutdown CEAs are withdrawn before the regulating CEAs are withdrawn during a unit startup.
amount of negative reactivity on a reactor trip signal. The  
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
REFERENCES 1. UFSAR  2. 10 CFR 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Plants" Regulating CEA Insertion Limits B 3.1.6 B 3.1  REACTIVITY CONTROL SYSTEMS B 3.1.6  Regulating Control Element Assembly (CEA) Insertion Limits BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-1 Revision 43 BACKGROUND The insertion limits of the regulating CEAs are initial assumptions in all safety analyses that assume CEA insertion upon reactor trip. The insertion limits directly affect core power distributions, assumptions of available SDM, and initial reactivity insertion rate. The applicable criteria for these reactivity and power distribution design requirements are Reference 1, Appendix 1C, Criteria 27, 29, 30, and 31, and Reference 2.
regulating CEAs may be partially inserted in the core as  
Limits on regulating CEA insertion have been established, and all CEA positions are monitored and controlled during power operation to ensure that the power distribution and reactivity limits defined by the design power peaking, ejected CEA worth, reactivity insertion rate, and SDM limits are preserved.
 
The regulating CEA groups operate with a predetermined amount of position overlap, in order to approximate a linear relation between CEA worth and CEA position (integral CEA worth). The regulating CEA groups are withdrawn and operate in a predetermined sequence. The group sequence and overlap limits are specified in the COLR. Regulating CEAs are considered to be fully withdrawn when withdrawn to at least 129.0 inches.
allowed by LCO 3.1.6. The shutdown CEA insertion limit is  
The regulating CEAs are used for precise reactivity control of the reactor. The positions of the regulating CEAs are manually controlled. They are capable of adding reactivity very quickly (compared to borating or diluting).
 
The power density at any point in the core must be limited to maintain SAFDLs, including limits that preserve the criteria specified in Reference 2. Together, LCOs 3.1.6, 3.2.4, and LCO 3.2.5 provide limits on control component operation and on monitored process variables to ensure the core operates within the LHR (LCO 3.2.1); and Total Integrated Radial Peaking Factor (rTF) (LCO 3.2.3) limits in the COLR. Operation within the LHR limits given in the COLR prevents power peaks that would exceed the loss of coolant accident (LOCA) limits derived by the Emergency Core Cooling Regulating CEA Insertion Limits B 3.1.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-2 Revision 43 System analysis. Operation within the rTF limit given in the COLR prevents departure from nucleate boiling (DNB) during a loss of forced reactor coolant flow accident. In addition to the LHR and rTF limits, certain reactivity limits are preserved by regulating CEA insertion limits. The regulating CEA insertion limits also restrict the ejected CEA worth to the values assumed in the safety analysis and preserve the minimum required SDM in MODEs 1 and 2.
established to ensure that a sufficient amount of negative  
The regulating CEA insertion and alignment limits are process variables that together characterize and control the three-dimensional power distribution of the reactor core.
 
Additionally, the regulating bank insertion limits control the reactivity that could be added in the event of a CEA ejection accident, and the shutdown and regulating bank insertion limits ensure the required SDM is maintained.
reactivity is available to shut down the reactor and  
Operation within the subject LCO limits will prevent fuel cladding failures that would breach the primary fission product barrier and release fission products to the reactor coolant in the event of a LOCA, loss of flow, ejected CEA, or other accident requiring termination by a Reactor Protective System trip function. APPLICABLE The fuel cladding must not sustain damage as a result of SAFETY ANALYSES normal operation (Condition I) and AOOs (Condition II). The acceptance criteria for the regulating CEA insertion, ASI, rTF, LHR, and AZIMUTHAL POWER TILT (Tq) LCOs are such as to preclude core power distributions from occurring that would violate the following fuel design criteria:  a. During a large break LOCA, the peak cladding temperature must not exceed a limit of 2200&deg;F (Reference 2);  b. During a loss of forced reactor coolant flow accident, there must be at least a 95% probability at a 95%
 
confidence level (the 95/95 DNB criterion) that the hot fuel rod in the core does not experience a DNB condition; Regulating CEA Insertion Limits B 3.1.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-3 Revision 43  c. During an ejected CEA accident, the energy input to the fuel must not exceed accepted limits (Reference 1, Section 14.3); and  d. The CEAs must be capable of shutting down the reactor with a minimum required SDM, with the highest worth CEA stuck fully withdrawn, Reference 1, Appendix 1C, Criterion 29. Regulating CEA position, ASI, rTF, LHR, and Tq are process variables that together characterize and control the three-dimensional power distribution of the reactor core.
maintain the required SDM (see LCO 3.1.1) following a  
Fuel cladding damage does not normally occur when the core is operated outside these LCOs during normal operation.
 
However, fuel cladding damage could result if an accident or AOO occurs with simultaneous violation of one or more of these LCOs. Changes in the power distribution can cause increased power peaking and corresponding increased local LHRs.
reactor trip from full power. The combination of regulating  
The SDM requirement is ensured by limiting the regulating and shutdown CEA insertion limits, so that the allowable inserted worth of the CEAs is such that sufficient reactivity is available to shut down the reactor to hot zero power. SHUTDOWN MARGIN assumes the maximum worth CEA remains fully withdrawn upon trip (Reference 1, Section 3.4).
 
The most limiting SDM requirements for MODEs 1 and 2 conditions at BOC are determined by the requirements of several transients, e.g., Loss of Flow, Seized Rotor, Boron Dilution, etc. However, the most limiting SDM requirements for MODEs 1 and 2 at EOC come from the SLB and Excess Load transients. The requirements of the SLB and Excess Load events at EOC for both the full power and no load conditions are significantly larger than those of any other event at that time in cycle.
CEAs and shutdown CEAs (less the most reactive CEA, which is  
To verify that adequate SDMs are available throughout the cycle to satisfy the changing requirements, calculations are performed at both BOC and EOC. It has been determined that calculations at these two times in cycle a are sufficient since the differences between available SDMs and the Regulating CEA Insertion Limits B 3.1.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-4 Revision 43 limiting SDM requirements are the smallest at these times in a cycle. The measurement of CEA bank worth performed as part of the Startup Testing Program demonstrates that the core has the expected shutdown capability. Consequently, adherence to LCOs 3.1.5 and 3.1.6 provides assurance that the available SDM at any time in a cycle will exceed the limiting SDM requirements at that time in a cycle.
 
Operation at the insertion limits or ASI limits may approach the maximum allowable linear heat generation rate or peaking factor, with the allowed Tq present. Operation at the insertion limit may also indicate the maximum ejected CEA worth could be equal to the limiting value in fuel cycles that have sufficiently high ejected CEA worths.
assumed to be fully withdrawn) is sufficient to take the  
The regulating and shutdown CEA insertion limits ensure that safety analyses assumptions for reactivity insertion rate, SDM, ejected CEA worth, and power distribution peaking factors are preserved (Reference 1, Section 3.4).
 
The regulating CEA insertion limits satisfy 10 CFR 50.36(c)(2)(ii), Criterion 2. LCO The limits on regulating CEAs sequence, overlap, and physical insertion, as defined in the COLR, must be maintained because they serve the function of preserving power distribution, ensuring that the SDM is maintained, ensuring that ejected CEA worth is maintained, and ensuring adequate negative reactivity insertion on trip. The overlap between regulating banks provides more uniform rates of reactivity insertion and withdrawal and is imposed to maintain acceptable power peaking during regulating CEA motion.
reactor from full power conditions at rated temperature to  
The power-dependent insertion limit (PDIL) alarm circuit is required to be OPERABLE for notification that the CEAs are outside the required insertion limits. The PDIL alarm circuit required to be OPERABLE receives its signal from the reed switch position indication system. When the PDIL alarm circuit is inoperable, the verification of CEA positions is increased to ensure improper CEA alignment is identified before unacceptable flux distribution occurs.
 
Regulating CEA Insertion Limits B 3.1.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-5 Revision 43 APPLICABILITY The regulating CEA sequence, overlap, and physical insertion limits shall be maintained with the reactor in MODEs 1 and 2. These limits must be maintained, since they preserve the assumed power distribution, ejected CEA worth, SDM, and reactivity rate insertion assumptions. Applicability in MODEs 3, 4, and 5 is not required, since neither the power distribution nor ejected CEA worth assumptions would be exceeded in these MODEs. SHUTDOWN MARGIN is preserved in MODEs 3, 4, and 5 by adjustments to the soluble boron concentration.
zero power, and to maintain the required SDM at rated no  
This LCO has been modified by a Note indicating the LCO requirement is suspended during SR 3.1.4.4. This SR verifies the freedom of the CEAs to move, and requires the regulating CEAs to move below the LCO limits, which would normally violate the LCO. ACTIONS A.1 and A.2  Operation beyond the transient insertion limit may result in a loss of SDM and excessive peaking factors. The transient insertion limit should not be violated during normal operation; this violation, however, may occur during transients when the operator is manually controlling the CEAs in response to changing plant conditions. When the regulating groups are inserted beyond the transient insertion limits, actions must be taken to either withdraw the regulating groups beyond the limits or to reduce THERMAL POWER to less than or equal to that allowed for the actual CEA insertion limit. Two hours provides a reasonable time to accomplish this, allowing the operator to deal with current plant conditions while limiting peaking factors to acceptable levels.
 
B.1 and B.2  If the CEAs are inserted between the long-term steady state insertion limits and the transient insertion limits for intervals > 4 hours per 24 hour period, and the short-term steady state insertions are exceeded, peaking factors can develop that are of immediate concern (Reference 1, Chapter 14).
load temperature (Reference 1, Sections 3.2 and 3.4). The  
Regulating CEA Insertion Limits B 3.1.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-6 Revision 43  Verifying the short-term steady state insertion limits are not exceeded ensures that the peaking factors that do develop are within those allowed for continued operation.
 
Fifteen minutes provides adequate time for the operator to verify if the short-term steady state insertion limits are exceeded. Experience has shown that rapid power increases in areas of the core, in which the flux has been depressed, can result in fuel damage, as the LHR in those areas rapidly increases. Restricting the rate of THERMAL POWER increases to 5% RTP per hour, following CEA insertion beyond the long-term steady-state insertion limits, ensures the power transients experienced by the fuel will not result in fuel failure.
shutdown CEA insertion limit also limits the reactivity  
C.1  With the regulating CEAs inserted between the long-term steady state insertion limit and the transient insertion limit, and with the core approaching the 5 EFPD per 30 EFPD or 14 EFPD per 365 EFPD limits, the CEAs must be returned to within the long-term steady state insertion limits, or the core must be placed in a condition in which the abnormal fuel burnup cannot continue. A Completion Time of 2 hours is allotted to return the CEAs to within the long-term steady state insertion limits.
 
The required Completion Time of 2 hours from initial discovery of a regulating CEA group outside the limits until its restoration to within the long-term steady state limits, shown on the figures in the COLR, allows sufficient time for borated water to enter the RCS from the chemical addition and makeup systems, and to cause the regulating CEAs to withdraw to the acceptable region. It is reasonable to continue operation for 2 hours after it is discovered that the 5-day or 14-day EFPD limit has been exceeded. This Completion Time is based on limiting the potential xenon redistribution, the low probability of an accident, and the steps required to complete the action.
worth of an ejected shutdown CEA.  
D.1  When the PDIL alarm circuit is inoperable, performing SR 3.1.6.1 within 1 hour and once per 4 hours thereafter Regulating CEA Insertion Limits B 3.1.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-7 Revision 55  ensures improper CEA alignments are identified before unacceptable flux distributions occur.
 
E.1  When a Required Action cannot be completed within the required Completion Time, a controlled shutdown should be commenced. The allowed Completion Time of 6 hours is reasonable, based on operating experience, for reaching MODE 3 from full power conditions in an orderly manner and without challenging plant systems. SURVEILLANCE SR 3.1.6.1 REQUIREMENTS With the PDIL alarm circuit OPERABLE, verification of each regulating CEA group position is sufficient to detect CEA positions that may approach the acceptable limits, and to provide the operator with time to undertake the Required Action(s) should the sequence or insertion limits be found to be exceeded. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
The acceptance criteria for addressing shutdown CEA, as well as regulating CEA insertion limits and inoperability or  
SR 3.1.6.2  Verification of the accumulated time of CEA group insertion between the long-term steady state insertion limits and the transient insertion limits ensures the cumulative time limits are not exceeded. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
SR 3.1.6.3  Demonstrating the PDIL alarm circuit OPERABLE verifies that the PDIL alarm circuit is functional. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. REFERENCES 1. UFSAR  2. 10 CFR 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Plants" 10 CFR 50.46 STE-SDM B 3.1.7 B 3.1  REACTIVITY CONTROL SYSTEMS B 3.1.7  Special Test Exception (STE)-SHUTDOWN MARGIN (SDM)
misalignment, are that:  a. There be no violation of:  
: 1. SAFDLs, or  2. RCS pressure boundary damage; and  b. The core remains subcritical after accident transients.  
 
As such, the shutdown CEA insertion limits affect safety analyses involving core reactivity, ejected CEA worth, and  
 
SDM (Reference 1, Section 14.1.2).  
 
Shutdown CEA Insertion Limits B 3.1.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-3 Revision 38  The shutdown CEA insertion limits satisfy 10 CFR 50.36(c)(2)(ii), Criterion 2.
LCO The shutdown CEAs must be within their insertion limits any time the reactor is critical or approaching criticality.
 
This ensures that a sufficient amount of negative reactivity  
 
is available to shut down the reactor and maintain the required SDM following a reactor trip.
APPLICABILITY The shutdown CEAs must be within their insertion limits, with the reactor in MODEs 1 and 2. The Applicability in  
 
MODE 2 begins anytime any regulating CEA is not fully  
 
inserted. This ensures that a sufficient amount of negative  
 
reactivity is available to shut down the reactor and  
 
maintain the required SDM following a reactor trip. In  
 
MODE 3, 4, 5, or 6, the shutdown CEAs are fully inserted in  
 
the core and contribute to the SDM. Refer to LCO 3.1.1 for  
 
SDM requirements in MODEs 3, 4, and 5. Limiting Condition  
 
for Operation 3.9.1 ensures adequate SDM in MODE 6.  
 
This LCO has been modified by a Note indicating the LCO requirement is suspended during SR 3.1.4.4. This SR  
 
verifies the freedom of the CEAs to move, and requires the  
 
shutdown CEAs to move below the LCO limits, which would normally violate the LCO.
ACTIONS A.1  When one shutdown CEA is withdrawn  121.5 inches and  
< 129 inches, the accumulated times the shutdown CEAs have been withdrawn within this range must be verified. The  
 
Completion Time for this action is once within 4 hours and  
 
24 hours thereafter. Operation is allowed for 7 consecutive  
 
days and a total of 14 days per 365 days. The peaking  
 
factors may not be outside required limits when one shutdown  
 
CEA is misaligned; therefore, continued operation is  
 
allowed. Since the power distribution limits are being  
 
maintained via the LCOs of Technical Specification  
 
Section 3.2, any out-of-limit peaking factor conditions will  
 
require entry into the Actions of the appropriate  
 
Section 3.2 LCO(s). The limits on consecutive days and  
 
total days in this condition reflect that the core may be  
 
approaching the acceptable limits placed on operation with Shutdown CEA Insertion Limits B 3.1.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-4 Revision 38 flux patterns outside those assumed in the long-term burnup assumptions. Therefore, operation in this condition cannot  
 
continue and the CEA is required to be restored per Action  
 
B. The accumulated times are required to be verified once  
 
within 4 hours to determine which accumulated time limit is  
 
more limiting. The periodic Completion Time of 24 hours after the initial completion within 4 hours is adequate to ensure that the accumulated time limits are not exceeded.  
 
B.1  Prior to entering this condition, the shutdown CEAs were fully withdrawn or all but one shutdown CEA was withdrawn  129 inches. If one shutdown CEA is withdrawn  121.5 inches and  
< 129 inches for  
> 7 days per occurrence or > 14 days per 365 days, or one shutdown CEA withdrawn  
< 121.5 inches, or two or more shutdown CEAs withdrawn  
< 129 inches, the out-of-limit CEAs must be restored to within limits within 2 hours. The Completion Time of  
 
2 hours reflects that the power distribution limits may be  
 
outside required limits and that the core may be approaching  
 
the acceptable limits placed on operation within flux  
 
patterns outside those assumed in the long-term burnup  
 
assumptions.  
 
The CEA(s) must be restored to within limits within 2 hours.
The 2-hour total Completion Time allows the operator  
 
adequate time to adjust the CEA(s) in an orderly manner.  
 
C.1  When Required Action A.1 or B.1 cannot be met or completed within the required Completion Time, a controlled shutdown  
 
should be commenced. The allowed Completion Time of 6 hours  
 
is reasonable, based on operating experience, for reaching  
 
MODE 3 from full power conditions in an orderly manner and without challenging plant systems.
SURVEILLANCE SR 3.1.5.1 REQUIREMENTS Verification that the shutdown CEAs are within their insertion limits prior to an approach to criticality ensures  
 
that when the reactor is critical, or being taken critical,  
 
the shutdown CEAs will be available to shut down the Shutdown CEA Insertion Limits B 3.1.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-5 Revision 55  reactor, and the required SDM will be maintained following a reactor trip. This SR and Frequency ensure that the  
 
shutdown CEAs are withdrawn before the regulating CEAs are  
 
withdrawn during a unit startup.  
 
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
REFERENCES 1. UFSAR  2. 10 CFR 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Plants"  
 
Regulating CEA Insertion Limits B 3.1.6 B 3.1  REACTIVITY CONTROL SYSTEMS  
 
B 3.1.6  Regulating Control Element Assembly (CEA) Insertion Limits  
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-1 Revision 43 BACKGROUND The insertion limits of the regulating CEAs are initial assumptions in all safety analyses that assume CEA insertion  
 
upon reactor trip. The insertion limits directly affect  
 
core power distributions, assumptions of available SDM, and initial reactivity insertion rate. The applicable criteria for these reactivity and power distribution design  
 
requirements are Reference 1, Appendix 1C, Criteria 27, 29,  
 
30, and 31, and Reference 2.  
 
Limits on regulating CEA insertion have been established, and all CEA positions are monitored and controlled during  
 
power operation to ensure that the power distribution and  
 
reactivity limits defined by the design power peaking,  
 
ejected CEA worth, reactivity insertion rate, and SDM limits  
 
are preserved.  
 
The regulating CEA groups operate with a predetermined amount of position overlap, in order to approximate a linear  
 
relation between CEA worth and CEA position (integral CEA  
 
worth). The regulating CEA groups are withdrawn and operate  
 
in a predetermined sequence. The group sequence and overlap  
 
limits are specified in the COLR. Regulating CEAs are  
 
considered to be fully withdrawn when withdrawn to at least  
 
129.0 inches.  
 
The regulating CEAs are used for precise reactivity control of the reactor. The positions of the regulating CEAs are  
 
manually controlled. They are capable of adding reactivity  
 
very quickly (compared to borating or diluting).  
 
The power density at any point in the core must be limited to maintain SAFDLs, including limits that preserve the criteria specified in Reference 2. Together, LCOs 3.1.6, 3.2.4, and LCO 3.2.5 provide limits on control component  
 
operation and on monitored process variables to ensure the  
 
core operates within the LHR (LCO 3.2.1); and Total Integrated Radial Peaking Factor (
rTF) (LCO 3.2.3) limits in the COLR. Operation within the LHR limits given in the COLR prevents power peaks that would exceed the loss of coolant  
 
accident (LOCA) limits derived by the Emergency Core Cooling Regulating CEA Insertion Limits B 3.1.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-2 Revision 43 System analysis. Operation within the rTF limit given in the COLR prevents departure from nucleate boiling (DNB) during a loss of forced reactor coolant flow accident. In addition to the LHR and rTF limits, certain reactivity limits are preserved by regulating CEA insertion limits.
The regulating CEA insertion limits also restrict the  
 
ejected CEA worth to the values assumed in the safety  
 
analysis and preserve the minimum required SDM in MODEs 1  
 
and 2.
The regulating CEA insertion and alignment limits are process variables that together characterize and control the  
 
three-dimensional power distribution of the reactor core.
 
Additionally, the regulating bank insertion limits control  
 
the reactivity that could be added in the event of a CEA  
 
ejection accident, and the shutdown and regulating bank  
 
insertion limits ensure the required SDM is maintained.  
 
Operation within the subject LCO limits will prevent fuel cladding failures that would breach the primary fission  
 
product barrier and release fission products to the reactor  
 
coolant in the event of a LOCA, loss of flow, ejected CEA,  
 
or other accident requiring termination by a Reactor Protective System trip function.
APPLICABLE The fuel cladding must not sustain damage as a result of SAFETY ANALYSES normal operation (Condition I) and AOOs (Condition II). The acceptance criteria for the regulating CEA insertion, ASI, rTF, LHR, and AZIMUTHAL POWER TILT (T q) LCOs are such as to preclude core power distributions from occurring that would violate the following fuel design criteria:  a. During a large break LOCA, the peak cladding temperature must not exceed a limit of 2200&deg;F (Reference 2);  b. During a loss of forced reactor coolant flow accident, there must be at least a 95% probability at a 95%  
 
confidence level (the 95/95 DNB criterion) that the hot  
 
fuel rod in the core does not experience a DNB  
 
condition; Regulating CEA Insertion Limits B 3.1.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-3 Revision 43  c. During an ejected CEA accident, the energy input to the fuel must not exceed accepted limits (Reference 1,  
 
Section 14.3); and  d. The CEAs must be capable of shutting down the reactor with a minimum required SDM, with the highest worth CEA  
 
stuck fully withdrawn, Reference 1, Appendix 1C, Criterion 29.
Regulating CEA position, ASI, rTF, LHR, and T q are process variables that together characterize and control the three-dimensional power distribution of the reactor core.  
 
Fuel cladding damage does not normally occur when the core is operated outside these LCOs during normal operation.
 
However, fuel cladding damage could result if an accident or  
 
AOO occurs with simultaneous violation of one or more of these LCOs. Changes in the power distribution can cause increased power peaking and corresponding increased local  
 
LHRs.
The SDM requirement is ensured by limiting the regulating and shutdown CEA insertion limits, so that the allowable  
 
inserted worth of the CEAs is such that sufficient  
 
reactivity is available to shut down the reactor to hot zero  
 
power. SHUTDOWN MARGIN assumes the maximum worth CEA  
 
remains fully withdrawn upon trip (Reference 1,  
 
Section 3.4).  
 
The most limiting SDM requirements for MODEs 1 and 2 conditions at BOC are determined by the requirements of  
 
several transients, e.g., Loss of Flow, Seized Rotor, Boron Dilution, etc. However, the most limiting SDM requirements for MODEs 1 and 2 at EOC come from the SLB and Excess Load transients. The requirements of the SLB and Excess Load events at EOC for both the full power and no load conditions are significantly larger than those of any other event at  
 
that time in cycle.
 
To verify that adequate SDMs are available throughout the cycle to satisfy the changing requirements, calculations are  
 
performed at both BOC and EOC. It has been determined that  
 
calculations at these two times in cycle a are sufficient  
 
since the differences between available SDMs and the Regulating CEA Insertion Limits B 3.1.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-4 Revision 43 limiting SDM requirements are the smallest at these times in a cycle. The measurement of CEA bank worth performed as  
 
part of the Startup Testing Program demonstrates that the  
 
core has the expected shutdown capability. Consequently,  
 
adherence to LCOs 3.1.5 and 3.1.6 provides assurance that  
 
the available SDM at any time in a cycle will exceed the limiting SDM requirements at that time in a cycle.  
 
Operation at the insertion limits or ASI limits may approach the maximum allowable linear heat generation rate or peaking  
 
factor, with the allowed T q present. Operation at the insertion limit may also indicate the maximum ejected CEA  
 
worth could be equal to the limiting value in fuel cycles  
 
that have sufficiently high ejected CEA worths.  
 
The regulating and shutdown CEA insertion limits ensure that safety analyses assumptions for reactivity insertion rate,  
 
SDM, ejected CEA worth, and power distribution peaking  
 
factors are preserved (Reference 1, Section 3.4).  
 
The regulating CEA insertion limits satisfy 10 CFR 50.36(c)(2)(ii), Criterion 2.
LCO The limits on regulating CEAs sequence, overlap, and physical insertion, as defined in the COLR, must be  
 
maintained because they serve the function of preserving  
 
power distribution, ensuring that the SDM is maintained,  
 
ensuring that ejected CEA worth is maintained, and ensuring  
 
adequate negative reactivity insertion on trip. The overlap  
 
between regulating banks provides more uniform rates of reactivity insertion and withdrawal and is imposed to maintain acceptable power peaking during regulating CEA  
 
motion.
The power-dependent insertion limit (PDIL) alarm circuit is required to be OPERABLE for notification that the CEAs are  
 
outside the required insertion limits. The PDIL alarm  
 
circuit required to be OPERABLE receives its signal from the  
 
reed switch position indication system. When the PDIL alarm  
 
circuit is inoperable, the verification of CEA positions is  
 
increased to ensure improper CEA alignment is identified before unacceptable flux distribution occurs.  
 
Regulating CEA Insertion Limits B 3.1.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-5 Revision 43 APPLICABILITY The regulating CEA sequence, overlap, and physical insertion limits shall be maintained with the reactor in MODEs 1  
 
and 2. These limits must be maintained, since they preserve  
 
the assumed power distribution, ejected CEA worth, SDM, and  
 
reactivity rate insertion assumptions. Applicability in  
 
MODEs 3, 4, and 5 is not required, since neither the power distribution nor ejected CEA worth assumptions would be exceeded in these MODEs. SHUTDOWN MARGIN is preserved in  
 
MODEs 3, 4, and 5 by adjustments to the soluble boron  
 
concentration.  
 
This LCO has been modified by a Note indicating the LCO requirement is suspended during SR 3.1.4.4. This SR  
 
verifies the freedom of the CEAs to move, and requires the  
 
regulating CEAs to move below the LCO limits, which would  
 
normally violate the LCO.
ACTIONS A.1 and A.2  Operation beyond the transient insertion limit may result in a loss of SDM and excessive peaking factors. The transient  
 
insertion limit should not be violated during normal  
 
operation; this violation, however, may occur during  
 
transients when the operator is manually controlling the  
 
CEAs in response to changing plant conditions. When the  
 
regulating groups are inserted beyond the transient  
 
insertion limits, actions must be taken to either withdraw  
 
the regulating groups beyond the limits or to reduce THERMAL  
 
POWER to less than or equal to that allowed for the actual  
 
CEA insertion limit. Two hours provides a reasonable time  
 
to accomplish this, allowing the operator to deal with current plant conditions while limiting peaking factors to acceptable levels.  
 
B.1 and B.2  If the CEAs are inserted between the long-term steady state insertion limits and the transient insertion limits for  
 
intervals > 4 hours per 24 hour period, and the short-term  
 
steady state insertions are exceeded, peaking factors can  
 
develop that are of immediate concern (Reference 1,  
 
Chapter 14).  
 
Regulating CEA Insertion Limits B 3.1.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-6 Revision 43  Verifying the short-term steady state insertion limits are not exceeded ensures that the peaking factors that do  
 
develop are within those allowed for continued operation.
 
Fifteen minutes provides adequate time for the operator to  
 
verify if the short-term steady state insertion limits are  
 
exceeded.
Experience has shown that rapid power increases in areas of the core, in which the flux has been depressed, can result  
 
in fuel damage, as the LHR in those areas rapidly increases.
Restricting the rate of THERMAL POWER increases to 5% RTP per hour, following CEA insertion beyond the long-term  
 
steady-state insertion limits, ensures the power transients  
 
experienced by the fuel will not result in fuel failure.  
 
C.1  With the regulating CEAs inserted between the long-term steady state insertion limit and the transient insertion  
 
limit, and with the core approaching the 5 EFPD per 30 EFPD  
 
or 14 EFPD per 365 EFPD limits, the CEAs must be returned to  
 
within the long-term steady state insertion limits, or the  
 
core must be placed in a condition in which the abnormal  
 
fuel burnup cannot continue. A Completion Time of 2 hours  
 
is allotted to return the CEAs to within the long-term  
 
steady state insertion limits.  
 
The required Completion Time of 2 hours from initial discovery of a regulating CEA group outside the limits until  
 
its restoration to within the long-term steady state limits,  
 
shown on the figures in the COLR, allows sufficient time for  
 
borated water to enter the RCS from the chemical addition  
 
and makeup systems, and to cause the regulating CEAs to  
 
withdraw to the acceptable region. It is reasonable to  
 
continue operation for 2 hours after it is discovered that  
 
the 5-day or 14-day EFPD limit has been exceeded. This Completion Time is based on limiting the potential xenon redistribution, the low probability of an accident, and the  
 
steps required to complete the action.  
 
D.1  When the PDIL alarm circuit is inoperable, performing SR 3.1.6.1 within 1 hour and once per 4 hours thereafter Regulating CEA Insertion Limits B 3.1.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-7 Revision 55  ensures improper CEA alignments are identified before unacceptable flux distributions occur.  
 
E.1  When a Required Action cannot be completed within the required Completion Time, a controlled shutdown should be commenced. The allowed Completion Time of 6 hours is reasonable, based on operating experience, for reaching  
 
MODE 3 from full power conditions in an orderly manner and without challenging plant systems.
SURVEILLANCE SR 3.1.6.1 REQUIREMENTS With the PDIL alarm circuit OPERABLE, verification of each regulating CEA group position is sufficient to detect CEA positions that may approach the acceptable limits, and to  
 
provide the operator with time to undertake the Required  
 
Action(s) should the sequence or insertion limits be found  
 
to be exceeded. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
SR 3.1.6.2  Verification of the accumulated time of CEA group insertion between the long-term steady state insertion limits and the  
 
transient insertion limits ensures the cumulative time  
 
limits are not exceeded. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
SR 3.1.6.3  Demonstrating the PDIL alarm circuit OPERABLE verifies that the PDIL alarm circuit is functional. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
REFERENCES 1. UFSAR  2. 10 CFR 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Plants" 10 CFR 50.46 STE-SDM B 3.1.7 B 3.1  REACTIVITY CONTROL SYSTEMS  
 
B 3.1.7  Special Test Exception (STE)-SHUTDOWN MARGIN (SDM)  
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-1 Revision 2 BACKGROUND The primary purpose of the SDM STE is to permit relaxation of existing LCOs to allow the performance of certain PHYSICS TESTS. These tests are constructed to determine the CEA worth.
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-1 Revision 2 BACKGROUND The primary purpose of the SDM STE is to permit relaxation of existing LCOs to allow the performance of certain PHYSICS TESTS. These tests are constructed to determine the CEA worth.
Reference 1, Appendix B, Section XI requires that a test program be established to ensure that structures, systems, and components will perform satisfactorily in service. All functions necessary to ensure that specified design conditions are not exceeded during normal operation and AOOs must be tested. Testing is required as an integral part of the design, fabrication, construction, and operation of the power plant. Requirements for notification of the Nuclear Regulatory Commission, for the purpose of conducting tests and experiments, are specified in Reference 1, 10 CFR 50.59.
Reference 1, Appendix B, Section XI requires that a test program be established to ensure that structures, systems,  
 
and components will perform satisfactorily in service. All  
 
functions necessary to ensure that specified design  
 
conditions are not exceeded during normal operation and AOOs must be tested. Testing is required as an integral part of  
 
the design, fabrication, construction, and operation of the  
 
power plant. Requirements for notification of the Nuclear  
 
Regulatory Commission, for the purpose of conducting tests  
 
and experiments, are specified in Reference 1, 10 CFR 50.59.  
 
The key objectives of a test program (Reference 2) are to:  a. Ensure that the facility has been adequately designed;  b. Validate the analytical models used in design and analysis;  c. Verify assumptions used for predicting plant response;  
The key objectives of a test program (Reference 2) are to:  a. Ensure that the facility has been adequately designed;  b. Validate the analytical models used in design and analysis;  c. Verify assumptions used for predicting plant response;  
: d. Ensure that installation of equipment in the facility has been accomplished in accordance with the design; and  e. Verify that operating and emergency procedures are adequate.
: d. Ensure that installation of equipment in the facility has been accomplished in accordance with the design;  
To accomplish these objectives, testing is required prior to initial criticality, after each refueling shutdown, and during startup, low power operation, power ascension, and at power operation. The PHYSICS TESTS requirements for reload fuel cycles ensure that the operating characteristics of the core are consistent with the design predictions, and that the core can be operated as designed (Reference 3, Section 13.4).
 
PHYSICS TESTS procedures are written and approved in accordance with an established process. The procedures STE-SDM B 3.1.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-2 Revision 2 include all information necessary to permit a detailed execution of testing required to ensure that the design intent is met. PHYSICS TESTS are performed in accordance with these procedures, and test results are independently reviewed prior to continued power escalation and long- term power operation. Examples of PHYSICS TESTS include determination of critical boron concentration, CEA group worths, reactivity coefficients, flux symmetry, and core power distribution. APPLICABLE It is acceptable to suspend certain LCOs for PHYSICS TESTS SAFETY ANALYSES because fuel damage criteria are not exceeded. Even if an accident occurs during PHYSICS TESTS with one or more LCOs suspended, fuel damage criteria are preserved because adequate limits on power distribution and shutdown capability are maintained during PHYSICS TESTS.
and  e. Verify that operating and emergency procedures are adequate.  
Reference 2 defines the requirements for initial testing of the facility, including PHYSICS TESTS. Requirements for reload fuel cycle PHYSICS TESTS are defined in the UFSAR Reference 3, Section 13.4. Although these PHYSICS TESTS are generally accomplished within the limits of all LCOs, conditions may occur when one or more LCOs must be suspended to make completion of PHYSICS TESTS possible or practical.
 
This is acceptable as long as the fuel design criteria are not violated. As long as the LHR remains within its limit, fuel design criteria are preserved.
To accomplish these objectives, testing is required prior to initial criticality, after each refueling shutdown, and  
In this test, the following LCOs are suspended:  a. LCO 3.1.1; and  b. LCO 3.1.6. Therefore, this LCO places limits on the minimum amount of CEA worth required to be available for reactivity control when CEA worth measurements are performed.
 
The individual LCOs cited above govern SDM CEA group height, insertion, and alignment. Additionally, the LCOs governing RCS flow, reactor inlet temperature, and pressurizer pressure contribute to maintaining DNB parameter limits. The initial condition criteria for accidents sensitive to core power distribution are preserved by the LHR and DNB STE-SDM B 3.1.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-3 Revision 43  parameter limits. The criteria for the LOCA are specified in Reference 2, 10 CFR 50.46. The criteria for the loss of forced reactor coolant flow accident are specified in Reference 3, Chapter 14. Operation within the LHR limit preserves the LOCA criteria; operation within the DNB parameter limits preserves the loss of flow criteria. Surveillance tests are conducted as necessary to ensure that LHR and DNB parameters remain within limits during PHYSICS TESTS. Performance of these SRs allows PHYSICS TESTS to be conducted without decreasing the margin of safety.
during startup, low power operation, power ascension, and at  
Requiring that shutdown reactivity equivalent to at least the highest estimated CEA worth (of those CEAs actually withdrawn) be available for trip insertion from the OPERABLE CEA provides a high degree of assurance that shutdown capability is maintained for the most challenging postulated accident, a stuck CEA. When LCO 3.1.1 is suspended, there is not the same degree of assurance during this test that the reactor would always be shut down if the highest worth CEA was stuck out and calculational uncertainties or the estimated highest CEA worth was not as expected (the single failure criterion is not met). This situation is judged acceptable, however, because SAFDLs are still met. The risk of experiencing a stuck CEA and subsequent criticality is reduced during this PHYSICS TESTS exception by the Surveillance Requirements; and by ensuring that shutdown reactivity is available, equivalent to the reactivity worth of the estimated highest worth withdrawn CEA (Reference 3, Chapter 3).
 
PHYSICS TESTS include measurement of core parameters or exercise of control components that affect process variables. Among the process variables involved are total integrated radial peaking factor, Tq and ASI, which represent initial condition input (power peaking) to the accident analysis. Also involved are the shutdown and regulating CEAs, which affect power peaking and are required for shut down of the reactor. The limits for these variables are specified for each fuel cycle in the COLR.
power operation. The PHYSICS TESTS requirements for reload  
As described in LCO 3.0.7, compliance with STE LCOs is optional and, therefore, no criteria of 10 CFR STE-SDM B 3.1.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-4 Revision 43 50.36(c)(2)(ii) apply. Special Test Exception LCOs provide flexibility to perform certain operations by appropriately modifying requirements of other LCOs. A discussion of the criteria satisfied for the other LCOs is provided in their respective Bases. LCO This LCO provides that a minimum amount of CEA worth is immediately available for reactivity control when CEA worth measurement tests are performed. The STE is required to permit the periodic verification of the actual versus predicted worth of the regulating and shutdown CEAs. The SDM requirements of LCO 3.1.1, the shutdown CEA insertion limits of LCO 3.1.5, and the regulating CEA insertion limits of LCO 3.1.6 may be suspended. APPLICABILITY This LCO is applicable in MODEs 2 and 3. Although CEA worth testing is conducted in MODE 2, sufficient negative reactivity is inserted during the performance of these tests to result in temporary entry into MODE 3. Because the intent is to immediately return to MODE 2 to continue CEA worth measurements, the STE allows limited operation to 6 consecutive hours in MODE 3, as indicated by the Note, without having to borate to meet the SDM requirements of LCO 3.1.1. ACTIONS A.1  With any CEA not fully inserted and less than the minimum required reactivity equivalent available for insertion, or with all CEAs inserted and the reactor subcritical by less than the reactivity equivalent of the highest worth CEA, restoration of the minimum SDM requirements must be accomplished by increasing the RCS boron concentration. The boration flow rate shall be  40 gpm and the boron concentration shall be  2300 ppm boric acid solution or equivalent. The required Completion Time of immediately is required to meet the assumptions of the safety analysis. It is assumed that boration will be continued until the SDM requirements are met.
 
STE-SDM B 3.1.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-5 Revision 55 SURVEILLANCE SR 3.1.7.1 REQUIREMENTS Verification of the position of each partially or fully withdrawn full-length or part-length CEA is necessary to ensure that the minimum negative reactivity requirements for insertion on a trip are preserved. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. SR 3.1.7.2  Prior demonstration that each CEA to be withdrawn from the core during PHYSICS TESTS is capable of full insertion, when tripped from at least a 50% withdrawn position, ensures that the CEA will insert on a trip signal. The Frequency ensures that the CEAs are OPERABLE prior to reducing SDM to less than the limits of LCO 3.1.1.
fuel cycles ensure that the operating characteristics of the core are consistent with the design predictions, and that the core can be operated as designed (Reference 3, Section 13.4).  
The SR is modified by a Note that allows the SR to not be performed during initial power escalation following a refueling outage if SR 3.1.4.6 has been met during that refueling outage. This allows the CEA drop time test, which also proves the CEAs are trippable, to be credited for this SR. REFERENCES 1. 10 CFR Part 50  2. Regulatory Guide 1.68, Revision 2, Initial Test Programs for Water-Cooled Nuclear Power Plants,"
 
August 1978  3. UFSAR STE-MODEs 1 and 2 B 3.1.8 B 3.1  REACTIVITY CONTROL SYSTEMS B 3.1.8  Special Test Exceptions (STE)-MODEs 1 and 2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-1 Revision 2 BACKGROUND The primary purpose of these MODEs 1 and 2 STEs is to permit relaxation of existing LCOs to allow the performance of certain PHYSICS TESTS. These tests are conducted to determine specific reactor core characteristics. Reference 1, Appendix B, Section XI requires that a test program be established to ensure that structures, systems, and components will perform satisfactorily in service. All functions necessary to ensure that specified design conditions are not exceeded during normal operation and AOOs must be tested. Testing is required as an integral part of the design, fabrication, construction, and operation of the power plant. Requirements for notification of the Nuclear Regulatory Commission, for the purpose of conducting tests and experiments, are specified in Reference 1, 10 CFR 50.59.
PHYSICS TESTS procedures are written and approved in accordance with an established process. The procedures STE-SDM B 3.1.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-2 Revision 2 include all information necessary to permit a detailed execution of testing required to ensure that the design  
 
intent is met. PHYSICS TESTS are performed in accordance  
 
with these procedures, and test results are independently  
 
reviewed prior to continued power escalation and long- term  
 
power operation. Examples of PHYSICS TESTS include determination of critical boron concentration, CEA group worths, reactivity coefficients, flux symmetry, and core power distribution.
APPLICABLE It is acceptable to suspend certain LCOs for PHYSICS TESTS SAFETY ANALYSES because fuel damage criteria are not exceeded. Even if an accident occurs during PHYSICS TESTS with one or more LCOs  
 
suspended, fuel damage criteria are preserved because  
 
adequate limits on power distribution and shutdown  
 
capability are maintained during PHYSICS TESTS.  
 
Reference 2 defines the requirements for initial testing of the facility, including PHYSICS TESTS. Requirements for  
 
reload fuel cycle PHYSICS TESTS are defined in the UFSAR Reference 3, Section 13.4. Although these PHYSICS TESTS are generally accomplished within the limits of all LCOs,  
 
conditions may occur when one or more LCOs must be suspended  
 
to make completion of PHYSICS TESTS possible or practical.
 
This is acceptable as long as the fuel design criteria are  
 
not violated. As long as the LHR remains within its limit, fuel design criteria are preserved.  
 
In this test, the following LCOs are suspended:  a. LCO 3.1.1; and  b. LCO 3.1.6.
Therefore, this LCO places limits on the minimum amount of CEA worth required to be available for reactivity control  
 
when CEA worth measurements are performed.  
 
The individual LCOs cited above govern SDM CEA group height, insertion, and alignment. Additionally, the LCOs governing RCS flow, reactor inlet temperature, and pressurizer pressure contribute to maintaining DNB parameter limits.
The initial condition criteria for accidents sensitive to  
 
core power distribution are preserved by the LHR and DNB STE-SDM B 3.1.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-3 Revision 43  parameter limits. The criteria for the LOCA are specified in Reference 2, 10 CFR 50.46. The criteria for the loss of  
 
forced reactor coolant flow accident are specified in  
 
Reference 3, Chapter 14. Operation within the LHR limit  
 
preserves the LOCA criteria; operation within the DNB  
 
parameter limits preserves the loss of flow criteria.
Surveillance tests are conducted as necessary to ensure that LHR and DNB parameters remain within limits during PHYSICS  
 
TESTS. Performance of these SRs allows PHYSICS TESTS to be  
 
conducted without decreasing the margin of safety.  
 
Requiring that shutdown reactivity equivalent to at least the highest estimated CEA worth (of those CEAs actually  
 
withdrawn) be available for trip insertion from the OPERABLE  
 
CEA provides a high degree of assurance that shutdown  
 
capability is maintained for the most challenging postulated  
 
accident, a stuck CEA. When LCO 3.1.1 is suspended, there  
 
is not the same degree of assurance during this test that  
 
the reactor would always be shut down if the highest worth  
 
CEA was stuck out and calculational uncertainties or the  
 
estimated highest CEA worth was not as expected (the single  
 
failure criterion is not met). This situation is judged  
 
acceptable, however, because SAFDLs are still met. The risk  
 
of experiencing a stuck CEA and subsequent criticality is  
 
reduced during this PHYSICS TESTS exception by the  
 
Surveillance Requirements; and by ensuring that shutdown  
 
reactivity is available, equivalent to the reactivity worth  
 
of the estimated highest worth withdrawn CEA (Reference 3,  
 
Chapter 3).  
 
PHYSICS TESTS include measurement of core parameters or exercise of control components that affect process  
 
variables. Among the process variables involved are total integrated radial peaking factor, T q and ASI, which represent initial condition input (power peaking) to the  
 
accident analysis. Also involved are the shutdown and  
 
regulating CEAs, which affect power peaking and are required  
 
for shut down of the reactor. The limits for these  
 
variables are specified for each fuel cycle in the COLR.  
 
As described in LCO 3.0.7, compliance with STE LCOs is optional and, therefore, no criteria of 10 CFR STE-SDM B 3.1.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-4 Revision 43 50.36(c)(2)(ii) apply. Special Test Exception LCOs provide flexibility to perform certain operations by appropriately  
 
modifying requirements of other LCOs. A discussion of the  
 
criteria satisfied for the other LCOs is provided in their respective Bases.
LCO This LCO provides that a minimum amount of CEA worth is immediately available for reactivity control when CEA worth  
 
measurement tests are performed. The STE is required to  
 
permit the periodic verification of the actual versus  
 
predicted worth of the regulating and shutdown CEAs. The  
 
SDM requirements of LCO 3.1.1, the shutdown CEA insertion  
 
limits of LCO 3.1.5, and the regulating CEA insertion limits of LCO 3.1.6 may be suspended.
APPLICABILITY This LCO is applicable in MODEs 2 and 3. Although CEA worth testing is conducted in MODE 2, sufficient negative  
 
reactivity is inserted during the performance of these tests  
 
to result in temporary entry into MODE 3. Because the  
 
intent is to immediately return to MODE 2 to continue CEA  
 
worth measurements, the STE allows limited operation to  
 
6 consecutive hours in MODE 3, as indicated by the Note,  
 
without having to borate to meet the SDM requirements of LCO 3.1.1.
ACTIONS A.1  With any CEA not fully inserted and less than the minimum required reactivity equivalent available for insertion, or  
 
with all CEAs inserted and the reactor subcritical by less  
 
than the reactivity equivalent of the highest worth CEA,  
 
restoration of the minimum SDM requirements must be  
 
accomplished by increasing the RCS boron concentration. The boration flow rate shall be  40 gpm and the boron concentration shall be  2300 ppm boric acid solution or equivalent. The required Completion Time of immediately is  
 
required to meet the assumptions of the safety analysis. It  
 
is assumed that boration will be continued until the SDM requirements are met.
STE-SDM B 3.1.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-5 Revision 55 SURVEILLANCE SR 3.1.7.1 REQUIREMENTS Verification of the position of each partially or fully withdrawn full-length or part-length CEA is necessary to  
 
ensure that the minimum negative reactivity requirements for insertion on a trip are preserved. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
SR 3.1.7.2  Prior demonstration that each CEA to be withdrawn from the core during PHYSICS TESTS is capable of full insertion, when  
 
tripped from at least a 50% withdrawn position, ensures that  
 
the CEA will insert on a trip signal. The Frequency ensures  
 
that the CEAs are OPERABLE prior to reducing SDM to less  
 
than the limits of LCO 3.1.1.  
 
The SR is modified by a Note that allows the SR to not be performed during initial power escalation following a  
 
refueling outage if SR 3.1.4.6 has been met during that  
 
refueling outage. This allows the CEA drop time test, which  
 
also proves the CEAs are trippable, to be credited for this SR. REFERENCES 1. 10 CFR Part 50  2. Regulatory Guide 1.68, Revision 2, Initial Test Programs for Water-Cooled Nuclear Power Plants,"  
 
August 1978  3. UFSAR  
 
STE-MODEs 1 and 2 B 3.1.8 B 3.1  REACTIVITY CONTROL SYSTEMS  
 
B 3.1.8  Special Test Exceptions (STE)-MODEs 1 and 2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-1 Revision 2 BACKGROUND The primary purpose of these MODEs 1 and 2 STEs is to permit relaxation of existing LCOs to allow the performance of certain PHYSICS TESTS. These tests are conducted to  
 
determine specific reactor core characteristics.
Reference 1, Appendix B, Section XI requires that a test program be established to ensure that structures, systems,  
 
and components will perform satisfactorily in service. All  
 
functions necessary to ensure that specified design  
 
conditions are not exceeded during normal operation and AOOs must be tested. Testing is required as an integral part of  
 
the design, fabrication, construction, and operation of the  
 
power plant. Requirements for notification of the Nuclear  
 
Regulatory Commission, for the purpose of conducting tests  
 
and experiments, are specified in Reference 1, 10 CFR 50.59.  
 
The key objectives of a test program (Reference 2) are to:  a. Ensure that the facility has been adequately designed;  b. Validate the analytical models used in design and analysis;  c. Verify assumptions used for predicting plant response;  
The key objectives of a test program (Reference 2) are to:  a. Ensure that the facility has been adequately designed;  b. Validate the analytical models used in design and analysis;  c. Verify assumptions used for predicting plant response;  
: d. Ensure that installation of equipment in the facility has been accomplished in accordance with design; and  e. Verify that operating and emergency procedures are adequate.
: d. Ensure that installation of equipment in the facility has been accomplished in accordance with design; and  e. Verify that operating and emergency procedures are adequate.  
To accomplish these objectives, testing is required prior to initial criticality, after each refueling shutdown, and during startup, low power operation, power ascension, and at power operation. The PHYSICS TESTS requirements for reload fuel cycles ensure that the operating characteristics of the core are consistent with the design predictions, and that the core can be operated as designed (Reference 3, Section 13.4). PHYSICS TESTS procedures are written and approved in accordance with established formats. The procedures include all information necessary to permit a detailed execution of STE-MODEs 1 and 2 B 3.1.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-2 Revision 43  testing required to ensure that design intent is met. PHYSICS TESTS are performed in accordance with these procedures and test results are approved prior to continued power escalation and long-term power operation.
 
Examples of PHYSICS TESTS include determination of critical boron concentration, CEA group worths, reactivity coefficients, flux symmetry, and core power distribution. APPLICABLE It is acceptable to suspend certain LCOs for PHYSICS TESTS SAFETY ANALYSES because fuel damage criteria are not exceeded. Even if an accident occurs during a PHYSICS TESTS with one or more LCOs suspended, fuel damage criteria are preserved because the limits on power distribution and shutdown capability are maintained during PHYSICS TESTS.
To accomplish these objectives, testing is required prior to initial criticality, after each refueling shutdown, and  
Reference 3, Section 13.4 defines the requirements for initial testing of the facility, including PHYSICS TESTS.
 
Although these PHYSICS TESTS are generally accomplished within the limits of all LCOs, conditions may occur when one or more LCO must be suspended to make completion of PHYSICS TESTS possible or practical. This is acceptable as long as the fuel design criteria are not violated. As long as the LHR remains within its limit, fuel design criteria are preserved.
during startup, low power operation, power ascension, and at  
In this test, the following LCOs are suspended:  LCO 3.1.3; LCO 3.1.4; LCO 3.1.5; LCO 3.1.6; LCO 3.2.3; and LCO 3.2.4.
 
The safety analysis (Reference 3, Section 13.4) places limits on allowable THERMAL POWER during PHYSICS TESTS and requires the LHR and the DNB parameter to be maintained within limits.
power operation. The PHYSICS TESTS requirements for reload  
The individual LCOs governing CEA group height, insertion and alignment, ASI, rTF, and Tq preserve the LHR limits. Additionally, the LCOs governing RCS flow, reactor inlet temperature (Tc), and pressurizer pressure contribute to maintaining DNB parameter limits. The initial condition criteria for accidents sensitive to core power distribution are preserved by the LHR and DNB parameter limits. The criteria for the LOCA are specified in Reference 1, 10 CFR 50.46. The criteria for the loss of forced reactor STE-MODEs 1 and 2 B 3.1.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-3 Revision 43 coolant flow accident are specified in Reference 1, 10 CFR 50.46. Operation within the LHR limit preserves the LOCA criteria; operation within the DNB parameter limits preserves the loss of flow criteria.
 
During PHYSICS TESTS, one or more of the LCOs that normally preserve the LHR and DNB parameter limits may be suspended. The results of the accident analysis are not adversely impacted, however, if LHR and DNB parameters are verified to be within their limits while the LCOs are suspended.
fuel cycles ensure that the operating characteristics of the  
Therefore, SRs are placed as necessary to ensure that LHR and DNB parameters remain within limits during PHYSICS TESTS. Performance of these SRs allows PHYSICS TESTS to be conducted without decreasing the margin of safety.
 
PHYSICS TESTS include measurement of core parameters or exercise of control components that affect process variables. Among the process variables involved are rTF, Tq, and ASI, which represent initial condition input (power peaking) to the accident analysis. Also involved are the shutdown and regulating CEAs, which affect power peaking and are required for shut down of the reactor. The limits for these variables are specified for each fuel cycle in the COLR.
core are consistent with the design predictions, and that the core can be operated as designed (Reference 3, Section 13.4).
As described in LCO 3.0.7, compliance with STE LCOs is optional and, therefore, no criteria of 10 CFR 50.36(c)(2)(ii) apply. Special Test Exception LCOs provide flexibility to perform certain operations by appropriately modifying requirements of other LCOs. A discussion of the criteria satisfied for the other LCOs is provided in their respective Bases. LCO This LCO permits individual CEAs to be positioned outside of their normal group heights and insertion limits during the performance of PHYSICS TESTS, such as those required to:  a. Measure CEA worth;  
PHYSICS TESTS procedures are written and approved in accordance with established formats. The procedures include  
: b. Determine the reactor stability index and damping factor under xenon oscillation conditions;  c. Determine power distributions for nonnormal CEA configurations; STE-MODEs 1 and 2 B 3.1.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-4 Revision 43  d. Measure rod shadowing factors; and  e. Measure temperature and power coefficients.
 
The requirements of LCO 3.1.3, LCO 3.1.4, LCO 3.1.5, LCO 3.1.6, LCO 3.2.3, and LCO 3.2.4 may be suspended during the performance of PHYSICS TESTS, provided THERMAL POWER is restricted to test power plateau, which shall not exceed 85% RTP. APPLICABILITY This LCO is applicable in MODEs 1 and 2 because the reactor must be critical at various THERMAL POWER levels to perform the PHYSICS TESTS described in the LCO section. Limiting the test power plateau to < 85% RTP ensures that LHRs are maintained within acceptable limits. ACTIONS A.1  If THERMAL POWER exceeds the test power plateau, THERMAL POWER must be reduced to restore the additional thermal margin provided by the reduction. The 15-minute Completion Time ensures that prompt action shall be taken to reduce THERMAL POWER to within acceptable limits.
all information necessary to permit a detailed execution of STE-MODEs 1 and 2 B 3.1.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-2 Revision 43  testing required to ensure that design intent is met.
B.1 and B.2  If Required Action A.1 cannot be completed within the required Completion Time, PHYSICS TESTS must be suspended within 1 hour, and the reactor must be brought to MODE 3. Allowing 1 hour for suspending PHYSICS TESTS allows the operator sufficient time to change any abnormal CEA configuration back to within the limits of LCO 3.1.4, LCO 3.1.5, and LCO 3.1.6. Bringing the reactor to MODE 3 within 6 hours increases thermal margin and is consistent with the Required Actions of the power distribution LCOs.
PHYSICS TESTS are performed in accordance with these  
The required Completion Time of 6 hours is adequate for performing a controlled shutdown from full power conditions in an orderly manner and without challenging plant systems, and is consistent with power distribution LCO Completion Times.
 
STE-MODEs 1 and 2 B 3.1.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-5 Revision 55 SURVEILLANCE SR 3.1.8.1 REQUIREMENTS  Verifying that THERMAL POWER is equal to or less than that allowed by the test power plateau, as specified in the PHYSICS TESTS procedure and required by the safety analysis, ensures that adequate LHR and DNB parameter margins are maintained while LCOs are suspended. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. REFERENCES 1. 10 CFR Part 50  2. Regulatory Guide 1.68, Revision 2, Initial Test Programs for Water-Cooled Nuclear Power Plants,"
procedures and test results are approved prior to continued  
 
power escalation and long-term power operation.  
 
Examples of PHYSICS TESTS include determination of critical boron concentration, CEA group worths, reactivity  
 
coefficients, flux symmetry, and core power distribution.
APPLICABLE It is acceptable to suspend certain LCOs for PHYSICS TESTS SAFETY ANALYSES because fuel damage criteria are not exceeded. Even if an accident occurs during a PHYSICS TESTS with one or more LCOs  
 
suspended, fuel damage criteria are preserved because the  
 
limits on power distribution and shutdown capability are  
 
maintained during PHYSICS TESTS.  
 
Reference 3, Section 13.4 defines the requirements for initial testing of the facility, including PHYSICS TESTS.
 
Although these PHYSICS TESTS are generally accomplished  
 
within the limits of all LCOs, conditions may occur when one  
 
or more LCO must be suspended to make completion of PHYSICS  
 
TESTS possible or practical. This is acceptable as long as  
 
the fuel design criteria are not violated. As long as the  
 
LHR remains within its limit, fuel design criteria are  
 
preserved.  
 
In this test, the following LCOs are suspended:  LCO 3.1.3; LCO 3.1.4; LCO 3.1.5; LCO 3.1.6; LCO 3.2.3; and LCO 3.2.4.  
 
The safety analysis (Reference 3, Section 13.4) places limits on allowable THERMAL POWER during PHYSICS TESTS and requires the LHR and the DNB parameter to be maintained  
 
within limits.  
 
The individual LCOs governing CEA group height, insertion and alignment, ASI, rTF, and Tq preserve the LHR limits.
Additionally, the LCOs governing RCS flow, reactor inlet temperature (T c), and pressurizer pressure contribute to maintaining DNB parameter limits. The initial condition  
 
criteria for accidents sensitive to core power distribution are preserved by the LHR and DNB parameter limits. The criteria for the LOCA are specified in Reference 1,  
 
10 CFR 50.46. The criteria for the loss of forced reactor STE-MODEs 1 and 2 B 3.1.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-3 Revision 43 coolant flow accident are specified in Reference 1, 10 CFR 50.46. Operation within the LHR limit preserves the  
 
LOCA criteria; operation within the DNB parameter limits  
 
preserves the loss of flow criteria.  
 
During PHYSICS TESTS, one or more of the LCOs that normally preserve the LHR and DNB parameter limits may be suspended.
The results of the accident analysis are not adversely  
 
impacted, however, if LHR and DNB parameters are verified to  
 
be within their limits while the LCOs are suspended.
 
Therefore, SRs are placed as necessary to ensure that LHR  
 
and DNB parameters remain within limits during PHYSICS  
 
TESTS. Performance of these SRs allows PHYSICS TESTS to be  
 
conducted without decreasing the margin of safety.  
 
PHYSICS TESTS include measurement of core parameters or exercise of control components that affect process variables. Among the process variables involved are rTF, Tq, and ASI, which represent initial condition input (power peaking) to the accident analysis. Also involved are the  
 
shutdown and regulating CEAs, which affect power peaking and  
 
are required for shut down of the reactor. The limits for  
 
these variables are specified for each fuel cycle in the  
 
COLR.
As described in LCO 3.0.7, compliance with STE LCOs is optional and, therefore, no criteria of 10 CFR  
 
50.36(c)(2)(ii) apply. Special Test Exception LCOs provide  
 
flexibility to perform certain operations by appropriately  
 
modifying requirements of other LCOs. A discussion of the  
 
criteria satisfied for the other LCOs is provided in their respective Bases.
LCO This LCO permits individual CEAs to be positioned outside of their normal group heights and insertion limits during the  
 
performance of PHYSICS TESTS, such as those required to:  a. Measure CEA worth;  
: b. Determine the reactor stability index and damping factor under xenon oscillation conditions;  c. Determine power distributions for nonnormal CEA configurations; STE-MODEs 1 and 2 B 3.1.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-4 Revision 43  d. Measure rod shadowing factors; and  e. Measure temperature and power coefficients.  
 
The requirements of LCO 3.1.3, LCO 3.1.4, LCO 3.1.5, LCO 3.1.6, LCO 3.2.3, and LCO 3.2.4 may be suspended during the performance of PHYSICS TESTS, provided THERMAL POWER is restricted to test power plateau, which shall not exceed  
 
85% RTP.
APPLICABILITY This LCO is applicable in MODEs 1 and 2 because the reactor must be critical at various THERMAL POWER levels to perform  
 
the PHYSICS TESTS described in the LCO section. Limiting  
 
the test power plateau to < 85% RTP ensures that LHRs are maintained within acceptable limits.
ACTIONS A.1  If THERMAL POWER exceeds the test power plateau, THERMAL POWER must be reduced to restore the additional thermal  
 
margin provided by the reduction. The 15-minute Completion  
 
Time ensures that prompt action shall be taken to reduce  
 
THERMAL POWER to within acceptable limits.  
 
B.1 and B.2  If Required Action A.1 cannot be completed within the required Completion Time, PHYSICS TESTS must be suspended within 1 hour, and the reactor must be brought to MODE 3.
Allowing 1 hour for suspending PHYSICS TESTS allows the  
 
operator sufficient time to change any abnormal CEA  
 
configuration back to within the limits of LCO 3.1.4,  
 
LCO 3.1.5, and LCO 3.1.6. Bringing the reactor to MODE 3  
 
within 6 hours increases thermal margin and is consistent  
 
with the Required Actions of the power distribution LCOs.
 
The required Completion Time of 6 hours is adequate for  
 
performing a controlled shutdown from full power conditions  
 
in an orderly manner and without challenging plant systems,  
 
and is consistent with power distribution LCO Completion Times.
STE-MODEs 1 and 2 B 3.1.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-5 Revision 55 SURVEILLANCE SR 3.1.8.1 REQUIREMENTS  Verifying that THERMAL POWER is equal to or less than that allowed by the test power plateau, as specified in the  
 
PHYSICS TESTS procedure and required by the safety analysis,  
 
ensures that adequate LHR and DNB parameter margins are maintained while LCOs are suspended. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
REFERENCES 1. 10 CFR Part 50  2. Regulatory Guide 1.68, Revision 2, Initial Test Programs for Water-Cooled Nuclear Power Plants,"  
 
August 1978  3. UFSAR}}
August 1978  3. UFSAR}}

Revision as of 20:22, 30 June 2018

Calvert Cliffs, Units 1 and 2 - Technical Specification Bases, Revisions 49 Through 55. Part 4 of 12
ML15257A196
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 09/04/2015
From:
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML15257A190 List:
References
Download: ML15257A196 (49)


Text

SDM B 3.1.1 B 3.1 REACTIVITY CONTROL SYSTEMS

B 3.1.1 SHUTDOWN MARGIN (SDM)

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-1 Revision 2 BACKGROUND The reactivity control systems must be redundant and capable of holding the reactor core subcritical when shut down under

cold conditions, in accordance with Reference 1, Appendix 1C, Criteria 27, 29, and 30. Maintenance of the SDM ensures that postulated reactivity events will not

damage the fuel. SHUTDOWN MARGIN requirements provide

sufficient reactivity margin to ensure that acceptable fuel

design limits will not be exceeded for normal shutdown and

anticipated operational occurrences (AOOs). As such, the

SDM defines the degree of subcriticality that would be

obtained immediately following the insertion of all control

element assemblies (CEAs), assuming the single CEA of

highest reactivity worth is fully withdrawn.

The system design requires that two independent reactivity control systems be provided, and that one of these systems

be capable of maintaining the core subcritical under cold

conditions. These requirements are provided by the use of

movable CEAs and soluble boric acid in the Reactor Coolant

System (RCS). The CEA System provides the SDM during power

operation and is capable of making the core subcritical

rapidly enough to prevent exceeding acceptable fuel damage

limits, assuming that the CEA of highest reactivity worth

remains fully withdrawn.

The soluble boron system can compensate for fuel depletion during operation and all xenon burnout reactivity changes,

and maintain the reactor subcritical under cold conditions.

During power operation, SDM control is ensured by operating with the shutdown CEAs fully withdrawn and the regulating

CEAs within the limits of Limiting Condition for Operation (LCO) 3.1.6. When the unit is in the shutdown and refueling MODEs, the SDM requirements are met by means of adjustments to the RCS boron concentration.

APPLICABLE The minimum required SDM is assumed as an initial condition SAFETY ANALYSIS in safety analysis. The safety analysis (Reference 1, Section 3.4) establishes a SDM that ensures specified acceptable fuel design limits (SAFDLs) are not exceeded for SDM B 3.1.1 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-2 Revision 43 normal operation and AOOs, with the assumption of the highest worth CEA stuck out following a reactor trip. For

MODE 5, the primary safety analysis that relies on the SDM

limit is the boron dilution analysis.

The acceptance criteria for the SDM requirements are that SAFDLs are maintained. This is done by ensuring that: a. The reactor can be made subcritical from all operating conditions, transients, and Design Basis Events; b. The reactivity transients associated with postulated accident conditions are controllable within acceptable

limits (departure from nucleate boiling ratio [DNBR],

fuel centerline temperature limit AOOs, and an

acceptable energy deposition for the CEA ejection

accident [Reference 1, Chapter 14]); and c. The reactor will be maintained sufficiently subcritical to preclude inadvertent criticality in the shutdown

condition.

The most limiting accident for the SDM requirements are based on a main steam line break (MSLB) or an Excess Load event (with failure of an MSIV to close), as described in the accident analysis (Reference 1, Chapter 14). The

increased steam flow causes an increased energy removal from the affected steam generator, and consequently the RCS.

This results in a reduction of the reactor coolant

temperature. The resultant coolant shrinkage causes a

reduction in pressure. In the presence of a negative

moderator temperature coefficient (MTC), this cooldown

causes an increase in core reactivity. As RCS temperature

decreases, the severity of the event decreases. The most limiting MSLB, with respect to potential fuel damage before

a reactor trip occurs, is a guillotine break of a main steam

line outside containment, initiated at the end of core life.

Following the MSLB or Excess Load event, a post-trip return to power may occur; however, no fuel damage occurs as a

result of the post-trip return to power, and THERMAL POWER

does not violate the Safety Limit (SL) requirement of

SL 2.1.1. The limiting Excess Load event with respect to potential return-to-power after reactor trip is the opening of all steam dump and bypass valves at full power with failure of an MSIV to close.

SDM B 3.1.1 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-3 Revision 43 In addition to the limiting MSLB transient, the SDM requirement for MODEs 3 and 4 must also protect against an

uncontrolled CEA withdrawal from a hot zero power or low

power condition, and a CEA ejection.

In the boron dilution analysis, the required SDM defines the reactivity difference between an initial subcritical boron

concentration and the corresponding critical boron

concentration. These values, in conjunction with the

configuration of the RCS and the assumed dilution flow rate,

directly affect the results of the analysis. This event is

most limiting at the beginning of core life when critical

boron concentrations are highest.

The withdrawal of CEAs from hot zero power or low power conditions adds reactivity to the reactor core, causing both

the core power level and heat flux to increase with

corresponding increases in reactor coolant temperatures and

pressure. The withdrawal of CEAs also produces a time-

dependent redistribution of core power.

The uncontrolled CEA withdrawal transient is terminated by the Variable High Power Trip. In all cases, power level, RCS pressure, linear heat rate (LHR), and the DNBR do not

exceed allowable limits.

SHUTDOWN MARGIN satisfies 10 CFR 50.36(c)(2)(ii),

Criterion 2.

LCO The MSLB (or the Excess Load event) and the boron dilution accidents (Reference 1, Chapter 14) are the most limiting analyses that establish the SDM value of the LCO. For MSLB

accidents (or the Excess Load event), if the LCO is violated, there is a potential to exceed the DNBR limit and

to exceed the acceptance criteria given in Reference 1,

Chapter 14. For the boron dilution accident, if the LCO is

violated, the minimum required time assumed for operator

action to terminate dilution may no longer be applicable.

Because both initial RCS level and the dilution flow rate

also significantly impact the boron dilution event in MODE 5

with pressurizer level < 90 inches from the bottom of the SDM B 3.1.1 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-4 Revision 43 pressurizer, the LCO also includes limits for these parameters during these conditions.

SHUTDOWN MARGIN is a core physics design condition that can be ensured through CEA positioning (regulating and shutdown

CEA) in MODEs 1 and 2 and through the soluble boron concentration in all other MODEs.

APPLICABILITY In MODEs 3, 4, and 5, the SDM requirements are applicable to provide sufficient negative reactivity to meet the

assumptions of the safety analyses discussed above. In

MODEs 1 and 2, SDM is ensured by complying with LCOs 3.1.5

and 3.1.6. In MODE 6, the shutdown reactivity requirements are given in LCO 3.9.1.

ACTIONS A.1, A.2, and A.3 With non-borated water sources of > 88 gpm available, while the unit is in MODE 5 with the pressurizer level

< 90 inches, the consequences of a boron dilution event may

exceed the analysis results. Therefore, action must be

initiated immediately to reduce the potential for such an

event. To accomplish this, Required Action A.1 requires

immediate suspension of positive reactivity additions.

However, since Required Action A.1 only reduces the

potential for the event and does not eliminate it, immediate action must also be initiated to increase the SDM to compensate for the non-borated water sources (Required

Action A.2). Finally, Required Action A.3 requires periodic

verification, once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, that the SDM increase is

maintained sufficient to compensate for the additional

sources of non-borated water. Required Action A.1 is

modified by a Note indicating that the suspension of

positive reactivity additions is not required if SDM has

been sufficiently increased to compensate for the additional

sources of non-borated water. The immediate Completion Time

reflects the urgency of the corrective actions. The

periodic Completion Time of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is considered

reasonable, based on other administrative controls available

and operating experience.

SDM B 3.1.1 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-5 Revision 27 B.1 and B.2 With the RCS level at or below the bottom of the hot leg nozzles, while the unit is in MODE 5 with the pressurizer

level < 90 inches, the consequences of a boron dilution

event may exceed the analysis results. Therefore, action

must be initiated immediately to reduce the potential for such an event. To accomplish this, Required Action B.1 requires immediate suspension of operations involving positive reactivity additions that could result in loss of the required SDM. Suspending positive reactivity additions that could result in failure to meet the minimum SDM limit is required to assure continued safe operation.

Introduction of coolant inventory must be from sources that have boron concentration greater than that required in the RCS for the minimum SDM. This may result in an overall reduction in RCS boron concentration, but provides an acceptable margin to maintaining subcritical operation.

Introduction of temperature changes including temperature increases when operating with a positive MTC must also be evaluated to ensure they do not result in a loss of the required SDM. However, since Required Action B.1 only reduces the potential for the event and does not eliminate

it, immediate action must also be initiated to increase the

RCS level to above the bottom of the hot leg nozzles

(Required Action B.2). The immediate Completion Time

reflects the urgency of the corrective actions.

C.1 If the SDM requirements are not met for reasons other than addressed in Condition A or B, boration must be initiated

promptly. A Completion Time of immediately is required to

meet the assumptions of the safety analysis. It is assumed

that boration will be continued until the SDM requirements

are met.

In the determination of the required combination of boration flow rate and boron concentration, there is no unique

requirement that must be satisfied. Since it is imperative

to raise the boron concentration of the RCS as soon as

possible, the boron concentration should be a highly

concentrated solution, such as that normally found in the

boric acid storage tank or the refueling water tank. The SDM B 3.1.1 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-6 Revision 55 operator should borate with the best source available for the plant conditions. However, as a minimum, the boration flow rate shall be 40 gpm and the boron concentration shall be 2300 ppm boric acid solution or equivalent.

Assuming that a value of 1% k/k must be recovered and a boration flow rate of 40 gpm from the boric acid storage tank, it is possible to increase the boron concentration of

the RCS by 100 ppm in approximately 15 minutes. If an inverse boron worth of 100 ppm/% k/k is assumed, this combination of parameters will increase the SDM by 1% k/k. These boration parameters of 40 gpm and 100 ppm represent

typical values and are provided for the purpose of offering a specific example.

SURVEILLANCE SR 3.1.1.1 REQUIREMENTS SHUTDOWN MARGIN is verified by performing a reactivity balance calculation, considering the listed reactivity

effects: a. RCS boron concentration;

b. CEA positions;
c. RCS average temperature;
d. Fuel burnup based on gross thermal energy generation;
e. Xenon concentration;
f. Samarium concentration; and
g. Isothermal temperature coefficient.

Using the isothermal temperature coefficient accounts for Doppler reactivity in this calculation because the reactor is subcritical and the fuel temperature will be changing at the same rate as the RCS.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.1.1.2 and SR 3.1.1.3 These Surveillance Requirements (SRs) periodically verify the significant assumptions of a boron dilution event are SDM B 3.1.1 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.1-7 Revision 55 maintained. A non-borated water source of 88 gpm allows for only one charging pump to be capable of injection during

these conditions since each charging pump is capable of an

injection rate of 46 gpm. Each SR is modified by a Note

indicating that it is only required when the unit is in

MODE 5 with the pressurizer level < 90 inches. Since the applicable conditions for the SR may be attained while already in MODE 5, each SR is provided with a Frequency of

once within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> after achieving MODE 5 with pressurizer

level < 90 inches. This provides a short period of time to

verify compliance after the conditions are attained.

Additionally, each SR must be completed once each 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

after the initial verification. The Frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

is considered reasonable, in view of other administrative controls available and operating experience.

REFERENCES 1. Updated Final Safety Analysis Report (UFSAR)

Reactivity Balance B 3.1.2 B 3.1 REACTIVITY CONTROL SYSTEMS

B 3.1.2 Reactivity Balance

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-1 Revision 2 BACKGROUND According to Reference 1

, Appendix 1C, Criteria 27, 29, and 30, reactivity shall be controllable, such that, subcriticality is maintained under cold conditions, and acceptable fuel design limits are not exceeded during normal operation and AOOs. Therefore, reactivity balance is used as a measure of the predicted versus measured core reactivity during power operation. The periodic

confirmation of core reactivity is necessary to ensure that

Design Basis Accident (DBA) and transient safety analyses

remain valid. A large reactivity difference could be the

result of unanticipated changes in fuel, CEA worth, or operation at conditions not consistent with those assumed in the predictions of core reactivity, and could potentially

result in a loss of SDM or violation of acceptable fuel

design limits. Comparing predicted versus measured core

reactivity validates the nuclear methods used in the safety

analysis and supports the SDM demonstrations (LCO 3.1.1

) in ensuring the reactor can be brought safely to cold, subcritical conditions.

When the reactor core is critical or in normal power operation, a reactivity balance exists and the net

reactivity is zero. A comparison of predicted and measured

reactivity is convenient under such a balance, since

parameters are being maintained relatively stable under

steady state power conditions. The positive reactivity

inherent in the core design is balanced by the negative

reactivity of the control components, thermal feedback,

neutron leakage, and materials in the core that absorb

neutrons, such as burnable absorbers producing zero net

reactivity. Excess reactivity can be inferred from the

critical boron curve, which provides an indication of the soluble boron concentration in the RCS versus cycle burnup.

Periodic measurement of the RCS boron concentration for comparison with the predicted value with other variables

fixed (such as CEA height, temperature, pressure, and power)

provides a convenient method of ensuring that core

reactivity is within design expectations, and that the

calculational models used to generate the safety analysis

are adequate.

Reactivity Balance B 3.1.2 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-2 Revision 2 In order to achieve the required fuel cycle energy output, the uranium enrichment in the new fuel loading and in the

fuel remaining from the previous cycle provides excess positive reactivity beyond that required to sustain steady state operation throughout the cycle. When the reactor is critical at hot full power, the excess positive reactivity is compensated by burnable absorbers (if any), CEAs,

whatever neutron poisons (mainly xenon and samarium) are

present in the fuel, and the RCS boron concentration.

When the core is producing THERMAL POWER, the fuel is being depleted and excess reactivity is decreasing. As the fuel

depletes, the RCS boron concentration is reduced to decrease

negative reactivity and maintain constant THERMAL POWER.

The critical boron curve is based on steady state operation

at RATED THERMAL POWER (

RTP). Therefore, deviations from the predicted critical boron curve may indicate deficiencies in the design analysis, deficiencies in the calculational models, or abnormal core conditions, and must be evaluated.

APPLICABLE Accurate prediction of core reactivity is either an explicit SAFETY ANALYSES or implicit assumption in the accident analysis evaluations.

Most accident evaluations (Reference 1, Section 14.1

) are, therefore, dependent upon accurate evaluation of core reactivity. In particular, SDM and reactivity transients,

such as CEA withdrawal accidents or CEA ejection accidents,

are very sensitive to accurate prediction of core

reactivity. These accident analysis evaluations rely on

computer codes that have been qualified against available test data, operating plant data, and analytical benchmarks.

Monitoring reactivity balance additionally ensures that the

nuclear methods provide an accurate representation of the

core reactivity.

Design calculations and safety analyses are performed for each fuel cycle for the purpose of predetermining reactivity

behavior and the RCS boron concentration requirements for

reactivity control during fuel depletion.

The comparison between measured and predicted initial core reactivity provides a normalization for calculational models

used to predict core reactivity. If the measured and Reactivity Balance B 3.1.2 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-3 Revision 2 predicted RCS boron concentrations for identical core conditions at beginning

-of-cycle (BOC) do not agree, the assumptions used in the reload cycle design analysis or the calculational models used to predict soluble boron

requirements may not be accurate. If reasonable agreement

between measured and predicted core reactivity exists at BOC, the prediction may be normalized to the measured boron concentration. Thereafter, any significant deviations in the measured boron concentration from the predicted critical

boron curve that develop during fuel depletion may be an

indication that the calculational model is not adequate for

core burnups beyond BOC, or that an unexpected change in

core conditions has occurred.

The normalization of predicted RCS boron concentration to the measured value is typically performed after reaching RTP

following startup from a refueling outage, with the CEAs in

their normal positions for power operation. The

normalization is performed at BOC conditions, so that core

reactivity relative to predicted values can be continually

monitored and evaluated as core conditions change during the

cycle.

The reactivity balance satisfies 10 CFR 50.36(c)(2)(ii),

Criterion 2.

LCO The reactivity balance limit is established to ensure plant operation is maintained within the assumptions of the safety

analyses. Large differences between actual and predicted

core reactivity may indicate that the assumptions of the DBA and transient analyses are no longer valid, or that the uncertainties in the nuclear design methodology are larger

than expected. A limit on the reactivity balance of

+/- 1% k/k has been established, based on engineering judgment. A 1% deviation in reactivity from that predicted

is larger than expected for normal operation and should

, therefore

, be evaluated.

When measured core reactivity is within 1% k/k of the predicted value at steady state thermal conditions, the core

is considered to be operating within acceptable design

limits. Since deviations from the limit are normally

detected by comparing predicted and measured steady state Reactivity Balance B 3.1.2 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-4 Revision 2 RCS critical boron concentrations, the difference between measured and predicted values would be approximately 100 ppm

(depending on the boron worth) before the limit is reached.

These values are well within the uncertainty limits for analysis of boron concentration samples, so that spurious violations of the limit due to uncertainty in measuring the

RCS boron concentration are unlikely.

APPLICABILITY The limits on core reactivity must be maintained during MODE 1 because a reactivity balance must exist when the

reactor is critical or producing THERMAL POWER. As the fuel

depletes, core conditions are changing, and confirmation of

the reactivity balance ensures the core is operating as

designed. This Specification does not apply in MODE 2

because enough operating margin exists to limit the effects

of a reactivity anomaly, and THERMAL POWER is low enough

( 5% RTP) such that reactivity anomalies are unlikely to occur. This Specification does not apply in MODEs 3, 4, and 5 because the reactor is shut down and the reactivity balance is not changing.

In MODE 6, fuel loading results in a continually changing core reactivity. Boron concentration requirements

(LCO 3.9.1

) ensure that fuel movements are performed within the bounds of the safety analysis. A SDM demonstration is required during the first startup following operations that

could have altered core reactivity (e.g., fuel movement, or CEA replacement, or shuffling).

ACTIONS A.1 and A.2 Should an anomaly develop between measured and predicted core reactivity, an evaluation of the core design and safety

analysis must be performed. Core conditions are evaluated

to determine their consistency with input to design

calculations. Measured core and process parameters are

evaluated to determine that they are within the bounds of

the safety analysis, and safety analysis calculational

models are reviewed to verify that they are adequate for

representation of the core conditions. The required

Completion Time of 7 days is based on the low probability of

a DBA occurring during this period, and allows sufficient Reactivity Balance B 3.1.2 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-5 Revision 2 time to assess the physical condition of the reactor and to complete the evaluation of the core design and safety analysis.

Following evaluations of the core design and safety analysis, the cause of the reactivity anomaly may be resolved. If the cause of the reactivity anomaly is a mismatch in core conditions at the time of RCS boron

concentration sampling, a recalculation of the RCS boron concentration requirements may be performed to demonstrate that core reactivity is behaving as expected. If an

unexpected physical change in the condition of the core has

occurred, it must be evaluated and corrected, if possible.

If the cause of the reactivity anomaly is in the calculation

technique, the calculational models must be revised to provide more accurate predictions. If any of these results are demonstrated, and it is concluded that the reactor core

is acceptable for continued operation, the boron letdown curve may be renormalized, and power operation may continue.

If operational restrictions or additional SRs are necessary

to ensure the reactor core is acceptable for continued

operation, they must be defined.

The required Completion Time of 7 days is adequate for preparing whatever operating restrictions or SRs may be required to allow continued reactor operation.

B.1 If the core reactivity cannot be restored to within the 1% k/k limit, the plant must be brought to a MODE in which the LCO does not apply. To achieve this status, the plant

must be brought to at least MODE 2 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. The

allowed Completion Time is reasonable, based on operating

experience, for reaching MODE 2 from full power conditions in an orderly manner and without challenging plant systems.

SURVEILLANCE SR 3.1.2.1 REQUIREMENTS Core reactivity is verified by periodic comparisons of measured and predicted RCS boron concentrations. The

comparison is made considering that other core conditions are fixed or stable

, including CEA position, moderator Reactivity Balance B 3.1.2 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.2-6 Revision 3 temperature, fuel temperature, fuel depletion, xenon concentration, and samarium concentration. The SR is

performed prior to entering MODE 1 as an initial check on

core conditions and design calculations at BOC and every

31 days after 60 effective full power days (EFPD). The SR

is modified by two Notes. The Note in the SR column indicates that the normalization of predicted core reactivity to the measured value may take place within the first 60 EFPD after each fuel loading. This allows sufficient time for core conditions to reach steady state,

but prevents operation for a large fraction of the fuel

cycle without establishing a benchmark for the design

calculations. The required subsequent Frequency of 31 EFPD

following the initial 60 EFPD, after entering MODE 1, is

acceptable, based on the slow rate of core changes due to

fuel depletion and the presence of other indicators

(e.g., quadrant power tilt ratio, etc.) for prompt

indication of an anomaly. The Frequency Note, "only

required after 60 EFPD after each fuel loading," is added to the Frequency column to allow this.

REFERENCES 1. UFSAR

MTC B 3.1.3 B 3.1 REACTIVITY CONTROL SYSTEMS

B 3.1.3 Moderator Temperature Coefficient (MTC)

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-1 Revision 29 BACKGROUND The MTC relates a change in core reactivity to a change in reactor coolant temperature. A positive MTC means that

reactivity increases with increasing moderator temperature;

conversely, a negative MTC means that reactivity decreases with increasing moderator temperature. The reactor is designed to operate with a negative MTC over a large range

of fuel cycle operation. Therefore, a coolant temperature

increase will cause a reactivity decrease, so that the

coolant temperature tends to return toward its initial

value. Reactivity increases that cause a coolant

temperature increase will thus be self limiting, and stable

power operation will result.

Moderator temperature coefficient values are predicted at selected burnups during the safety evaluation analysis and

are confirmed to be acceptable by measurements.

Reload cores are designed so that the MTC is less positive than that allowed by the LCO. The actual value of the MTC is dependent on core characteristics, such as fuel loading and

reactor coolant soluble boron concentration. The core

design may require additional fixed distributed poisons

(burnable poison) to yield an MTC at the BOC within the

range analyzed in the plant accident analysis. The end-of-

cycle (EOC) MTC is also limited by the requirements of the

accident analysis. Fuel cycles that are designed to achieve

high burnups or that have changes to other characteristics

are evaluated to ensure that the MTC does not exceed the EOC limit. APPLICABLE The acceptance criteria for the specified MTC are:

SAFETY ANALYSES

a. The MTC values must remain within the bounds of those used in the accident analysis (Reference 1,

Section 14.2.2); and b. The MTC must be such that inherently stable power operations result during normal operation and during

accidents, such as overheating and overcooling events.

MTC B 3.1.3 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-2 Revision 43 Reference 1, Section 14.1.2 contains analyses of accidents that result in both overheating and overcooling of the

reactor core. Moderator temperature coefficient is one of

the controlling parameters for core reactivity in these

accidents. Both the most positive value and most negative

value of the MTC are important to safety, and both values must be bounded. Values used in the analyses consider worst-case conditions, such as very large soluble boron

concentrations, to ensure the accident results are bounding.

Accidents that cause core overheating, either by decreased heat removal or increased power production, must be

evaluated for results when the MTC is positive. Reactivity

accidents that cause increased power production include the

CEA withdrawal and CEA ejection transient s from either zero or full THERMAL POWER. The limiting overheating event relative to plant response is based on the maximum

difference between core power and steam generator heat

removal during a transient. The most limiting event with

respect to a positive MTC is a CEA ejection accident from full power (Reference 1, Section 14.

13). Accidents that cause core overcooling must be evaluated for results when the MTC is most negative. The event that

produces the most rapid cooldown of the RCS, and is

therefore the most limiting event with respect to the

negative MTC, is a steam line break (SLB) event. Following

the reactor trip for the postulated EOC SLB event, the large

moderator temperature reduction combined with the large

negative MTC may produce reactivity increases that are as

much as the shutdown reactivity. When this occurs, a

substantial fraction of core power is produced with all CEAs

inserted, except the most reactive one, which is assumed

withdrawn. Even if the reactivity increase produces slightly subcritical conditions, a large fraction of core power may be produced through the effects of subcritical

neutron multiplication.

Moderator temperature coefficient values are bounded in reload safety evaluations assuming steady state conditions

at BOC, peak RCS boron, and EOC. A 2/3 core burnup MTC

measurement is conducted and the measured value may be MTC B 3.1.3 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-3 Revision 29 extrapolated to project the EOC value, in order to confirm reload design predictions.

The MTC satisfies 10 CFR 50.36(c)(2)(ii), Criterion 2.

LCO Limiting Condition for Operation 3.1.3 requires the MTC to be within specified limits of the Core Operating Limits

Report (COLR), with the maximum positive limit specified in

Figure 3.1.3-1, to ensure the core operates within the

assumptions of the accident analysis. During the reload

core safety evaluation, the MTC is analyzed to determine

that its values remain within the bounds of the original

accident analysis during operation. The limit on a positive

MTC ensures that core overheating accidents will not violate

the accident analysis assumptions. The negative MTC limit

for EOC specified in the COLR ensures that core overcooling

accidents will not violate the accident analysis

assumptions.

Moderator temperature coefficient is a core physics parameter determined by the fuel and fuel cycle design and

cannot be easily controlled once the core design is fixed.

During operation, therefore, the LCO can only be ensured

through measurement. The surveillance checks at BOC and

2/3 core burnup provide confirmation that the MTC is behaving as anticipated, so that the acceptance criteria are met. APPLICABILITY In MODE 1, the limits on the MTC must be maintained to ensure that any accident initiated from THERMAL POWER

operation will not violate the design assumptions of the

accident analysis. In MODE 2, the limits must also be

maintained to ensure startup accidents, such as the

uncontrolled CEA or group withdrawal, will not violate the

assumptions of the accident analysis. In MODEs 3, 4, 5,

and 6, this LCO is not applicable, since no DBAs using the

MTC as an analysis assumption are initiated from these

MODEs. However, the variation of the MTC, with temperature

in MODEs 3, 4, and 5 for DBAs initiated in MODEs 1 and 2, is

accounted for in the accident analysis. The variation of

the MTC, with temperature assumed in the safety analysis, is

accepted as valid once the BOC and 2/3 core burnup measurements are used for normalization.

MTC B 3.1.3 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-4 Revision 29 ACTIONS A.1 Moderator temperature coefficient is a function of the fuel and fuel cycle designs, and cannot be controlled directly

once the designs have been implemented in the core. If MTC

exceeds its limits, the reactor must be placed in MODE 3.

This eliminates the potential for violation of the accident analysis bounds. The associated Completion Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />

is reasonable, considering the probability of an accident

occurring during the time period that would require an MTC

value within the LCO limits, and the time for reaching

MODE 3 from full power conditions in an orderly manner and without challenging plant systems.

SURVEILLANCE SR 3.1.3.1 and SR 3.1.3.2 REQUIREMENTS The SRs for measurement of the MTC at the beginning and 2/3 core burnup of each fuel cycle provide for confirmation of the limiting MTC values. The MTC varies with boron concentration during fuel cycle operation

. The MTC becomes more negative as the RCS boron concentration is reduced

. The requirement for measurement prior to entering MODE 1 after each fuel loading satisfies the confirmatory check on the most positive (least negative) MTC value. The requirement for measurement, within 7 EFPD of initially reaching an equilibrium condition with THERMAL POWER 90% RTP, and within 7 EFPD of reaching 2/3 core burnup, satisfies the confirmatory check of the most negative MTC value. The 2/3 core burnup measurement is performed at any THERMAL POWER, so that the projected EOC MTC may be evaluated before the reactor actually reaches the EOC condition. Moderator temperature coefficient values may be

extrapolated and compensated to permit direct comparison to

the specified MTC limits.

Surveillance Requirement 3.1.3.2 is modified by a Note, which indicates that if the extrapolated MTC is more

negative than the EOC COLR limit, the SR may be repeated,

and that shutdown must occur prior to exceeding the minimum

allowable boron concentration at which MTC is projected to

exceed the lower limit. An engineering evaluation is MTC B 3.1.3 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.3-5 Revision 29 performed if the extrapolated value of MTC exceeds the Specification limits.

REFERENCES 1. UFSAR

CEA Alignment B 3.1.4 B 3.1 REACTIVITY CONTROL SYSTEMS

B 3.1.4 Control Element Assembly (CEA) Alignment

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-1 Revision 2 BACKGROUND The OPERABILITY (e.g., trippability) of the shutdown and regulating CEAs is an initial assumption in all safety

analyses that assume CEA insertion upon reactor trip.

The applicable criteria for these reactivity and power distribution design requirements are found in Reference 1, Appendix 1C, Criteria 6, 27, 29, and 30, and Reference 2.

Mechanical or electrical failures may cause a CEA to become inoperable or to become misaligned from its group. Control element assembly inoperability or misalignment may cause increased power peaking, due to the asymmetric reactivity

distribution and a reduction in the total available CEA

worth for reactor shutdown. Therefore, CEA alignment and

OPERABILITY are related to core operation in design power

peaking limits and the core design requirement of a minimum

SDM.

Limits on CEA alignment and OPERABILITY have been established, and all CEA positions are monitored and

controlled during power operation to ensure that the power

distribution and reactivity limits defined by the design

power peaking and SDM limits are preserved.

Control element assemblies are moved by their control element drive mechanisms (CEDMs). Each CEDM moves its CEA

one step (approximately 3/4-inch) at a time.

The CEAs are arranged into groups that are radially symmetric. Therefore, movement of the CEA groups do not

introduce radial asymmetries in the core power distribution.

The shutdown and regulating CEAs provide the required reactivity worth for immediate reactor shutdown upon a reactor trip. The regulating CEAs also provide reactivity

(power level) control during normal operation and

transients.

The axial position of shutdown and regulating CEAs is indicated by two separate and independent systems, which are CEA Alignment B 3.1.4 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-2 Revision 2 the Plant Computer CEA Position Indication System and the Reed Switch Position Indication System.

The Plant Computer CEA Position Indication System counts the commands sent to the CEA gripper coils from the CEDM Control

System that moves the CEAs. There is a one step counter for each CEA. Individual CEAs in a group all receive the same signal to move and should, therefore, all be at the same

position indicated by the group step counter for that group.

Plant Computer CEA Position Indication System is considered

highly precise (+/- 1 step or +/- 3/4-inch). If a CEA does not move one step for each command signal, the step counter will

still count the command and incorrectly reflect the position

of the CEA.

The Reed Switch Position Indication System provides a highly accurate indication of actual CEA position, but at a lower

precision than the step counters. This system is based on

inductive analog signals from a series of reed switches

spaced along a tube with a center-to-center distance of 1.5 inches, which is two steps. To increase the reliability

of the system, there are redundant reed switches at each position.

APPLICABLE Control element assembly misalignment accidents are SAFETY ANALYSES analyzed in the safety analysis (Reference 1, Sections 14.2, 14.11, and 14.13). The accident analysis defines CEA misoperation as any event, with the exception of sequential

group withdraws, which could result from a single

malfunction in the reactivity control systems. For example, CEA misalignment may be caused by a malfunction of the CEDM, CEDM Control System, or by operator error. A stuck CEA may be caused by mechanical jamming of the CEA fingers or of the

gripper. A dropped CEA could be caused by an electrical

failure in the CEA coil power programmers.

The acceptance criteria for addressing CEA inoperability/

misalignment are that: a. There shall be no violations of:

1. SAFDLs, or 2. RCS pressure boundary integrity; and CEA Alignment B 3.1.4 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-3 Revision 2 b. The core must remain subcritical after accidents or transients.

Two types of misalignment are distinguished in the safety analysis (Reference 1, Appendix 1C). The first type of misalignment occurs if one CEA fails to insert upon a reactor trip and remains stuck fully withdrawn. This condition requires an evaluation to determine that

sufficient reactivity worth is held in the remaining CEAs to

meet the SDM requirement with the maximum worth CEA stuck

fully withdrawn. If a CEA is stuck in the fully withdrawn

position, its worth is added to the SDM requirement, since

the safety analysis does not take two stuck CEAs into

account. The second type of misalignment occurs when one

CEA drops partially or fully into the reactor core. This

event causes an initial power reduction followed by a return

toward the original power, due to positive reactivity feedback from the negative MTC. Increased peaking during the power increase may result in excessive local LHRs (Reference 1, Section 14.14).

None of the above CEA misoperations will result in an automatic reactor trip. In the case of the full-length CEA drop, a prompt decrease in core average power and a

distortion in radial power are initially produced, which,

when conservatively coupled, result in a local power and

heat flux increase, and a decrease in DNBR parameters.

The results of the CEA misoperation analysis show that, during the most limiting misoperation events, no violations

of the SAFDLs, fuel centerline temperature, or RCS pressure

occur.

Control element assembly alignment satisfies 10 CFR 50.36(c)(2)(ii), Criteria 2 and 3.

LCO The limits on shutdown and regulating CEA alignments ensure that the assumptions in the safety analysis will remain

valid. The requirements on OPERABILITY ensure that upon

reactor trip, the CEAs will be available and will be

inserted to provide enough negative reactivity to shut down

the reactor. The OPERABILITY requirements also ensure that CEA Alignment B 3.1.4 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-4 Revision 43 the CEA banks maintain the correct power distribution and CEA alignment.

The requirement is to maintain the CEA alignment to within 7.5 inches between any CEA and its group.

Failure to meet the requirements of this LCO may produce unacceptable power peaking factors and LHRs, or unacceptable

SDMs, all of which may constitute initial conditions inconsistent with the safety analysis.

APPLICABILITY The requirements on CEA OPERABILITY and alignment are applicable in MODEs 1 and 2 because these are the only MODEs

in which neutron (or fission) power is generated, and the

OPERABILITY (e.g., trippability) and alignment of CEAs have

the potential to affect the safety of the plant. In

MODEs 3, 4, 5, and 6, the alignment limits do not apply

because the CEAs are bottomed, and the reactor is shut down

and not producing fission power. In the shutdown MODEs, the

OPERABILITY of the shutdown and regulating CEAs has the

potential to affect the required SDM, but this effect can be

compensated for by an increase in the boron concentration of

the RCS. See LCO 3.1.1 for SDM in MODEs 3, 4, and 5, and

LCO 3.9.1 for boron concentration requirements during refueling.

ACTIONS A.1 and B.1 A CEA may become misaligned, yet remain trippable. In this condition, the CEA can still perform its required function

of adding negative reactivity should a reactor trip be

necessary.

If one or more regulating or shutdown CEAs are misaligned by

> 7.5 inches and 15 inches but trippable, or one CEA is misaligned by > 15 inches but trippable, continued operation

in MODEs 1 and 2 may continue, provided CEA alignment is restored within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> for CEAs misaligned 15 inches and within the time specified in the COLR for CEAs misaligned

> 15 inches. (The maximum time provided in the COLR is 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.)

CEA Alignment B 3.1.4 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-5 Revision 43 Regulating and shutdown CEA alignment is restored by either aligning the misaligned CEA(s) to within 7.5 inches of its

group or aligning the misaligned CEAs group to within

7.5 inches of the misaligned CEA.

Xenon redistribution in the core starts to occur as soon as a CEA becomes misaligned. Restoring CEA alignment ensures acceptable power distributions are maintained. For small misalignments ( 15 inches) of the CEAs, there is: a. A small effect on the time-dependent, long-term power distributions relative to those used in generating LCOs

and limiting safety system settings setpoints; b. A negligible effect on the available SDM; and

c. A small effect on the ejected CEA worth used in the accident analysis.

With a large CEA misalignment (

> 15 inches), however, this misalignment would cause distortion of the core power

distribution. This distortion may, in turn, have a

significant effect on the time-dependent, long-term power

distributions relative to those used in generating LCOs and

limiting safety system settings setpoints.

The effect on the available SDM and the ejected CEA worth used in the accident analysis remains small.

Therefore, this condition is limited to a single CEA misalignment, while still allowing time for recovery.

In both cases, the allowed time period is sufficient to: a. Identify cause of a misaligned CEA; b. Take appropriate corrective action to realign the CEAs; and c. Minimize the effects of xenon redistribution.

If a CEA is untrippable, it is not available for reactivity insertion during a reactor trip. With an untrippable CEA,

meeting the insertion limits of LCOs 3.1.5 and 3.1.6 does

not ensure that adequate SDM exists. Condition F must be

entered.

CEA Alignment B 3.1.4 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-6 Revision 37 C.1 and C.2 If any CEA is not restored to within its alignment limits within the Completion Time provided in Required Action A.1

or B.1, an additional 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> is allowed to restore CEA alignment, provided THERMAL POWER is reduced 70% RTP.

Prompt action must be taken to reduce THERMAL POWER, and the reduction must be completed within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. Reducing THERMAL POWER ensures acceptable power distributions are maintained

during the additional time provided to restore alignment.

The Completion Times are acceptable based on the reasons

provided in the Bases for Required Actions A.1 and B.1.

D.1, D.2.1, and D.2.2 The CEA motion inhibit permits CEA motion within the requirements of LCO 3.1.6, and prevents regulating CEAs from

being misaligned from other CEAs in the group.

Performing SR 3.1.4.1 within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> thereafter is considered acceptable, in view of other

information continuously available to the operator in the

Control Room.

With the CEA motion inhibit inoperable, a Completion Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> is allowed for restoring the CEA motion inhibit to

OPERABLE status, or fully withdrawing the CEAs in groups 3

and 4, and withdrawing all CEAs in group 5 to < 5%

insertion.

Withdrawal of the CEAs to the positions required in Required Action D.2.2 provides additional assurance that core

perturbations in local burnup, peaking factors, and SDM will

not be more adverse than the Conditions assumed in the

safety analyses and LCO setpoint determination (Reference 1,

Chapter 14).

The 6-hour Completion Time takes into account Required Action D.1, the protection afforded by the CEA deviation

circuits, and other information continuously available to

the operator in the Control Room, so that during actual CEA

motion, deviations can be detected.

CEA Alignment B 3.1.4 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-7 Revision 55 Required Action D.2.2 is modified by a Note indicating that performing this Required Action is not required when in

conflict with Required Actions A.1, B.1, C.2, or E.1.

E.1 When the CEA deviation circuit is inoperable, performing SR 3.1.4.1 within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> thereafter ensures improper CEA alignments are identified before

unacceptable flux distributions occur. The specified

Completion Times take into account other information

continuously available to the operator in the Control Room,

so that during CEA movement, deviations can be detected, and

the protection provided by the CEA inhibit and deviation

circuit is not required.

F.1 If any Required Action and associated Completion Time of Condition C, Condition D, or Condition E is not met, one or

more regulating or shutdown CEAs are untrippable, two or

more CEAs are misaligned by > 15 inches, the unit is

required to be brought to MODE 3. By being brought to

MODE 3, the unit is brought outside the MODE of

applicability. Continued operation is not allowed in the

case of more than one CEA misaligned from any other CEA in

its group by > 15 inches, or one or more CEAs untrippable.

This is because these cases could result in a loss of SDM

and power distribution and a loss of safety function,

respectively.

When a Required Action cannot be completed within the required Completion Time, a controlled shutdown should be

commenced. The allowed Completion Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> is

reasonable, based on operating experience, for reaching

MODE 3 from full power conditions in an orderly manner and without challenging plant systems.

SURVEILLANCE SR 3.1.4.1 REQUIREMENTS Verification is required that individual CEA positions are within 7.5 inches (indicated reed switch positions) of all

other CEAs in the group within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> of any CEA movement of

> 7.5 inches. The CEA position verification after each CEA Alignment B 3.1.4 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-8 Revision 55 movement of

> 7.5 inches ensure that the CEAs in that group are properly aligned at the time when CEA misalignments are

most likely to have occurred. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.1.4.2 Demonstrating the CEA motion inhibit OPERABLE verifies that the CEA motion inhibit is functional, even if it is not

regularly operated. The verification shall ensure that the

motion inhibit circuit maintains the CEA group overlap and

sequencing requirements of LCO 3.1.6, and prevents any

regulating CEA from being misaligned from all other CEAs in its group by

> 7.5 inches (indicated position). The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.1.4.3 Demonstrating the CEA deviation circuit is OPERABLE verifies the circuit is functional. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.1.4.4 Verifying each CEA is trippable would require that each CEA be tripped. In MODEs 1 and 2, tripping each CEA would

result in radial or axial power tilts or oscillations.

Therefore, individual CEAs are exercised to provide increased confidence that all CEAs continue to be trippable,

even if they are not regularly tripped. A movement of

7.5 inches is adequate to demonstrate motion without

exceeding the alignment limit when only one CEA is being

moved. For the purposes of performing the CEA operability

test, if the CEA has an inoperable position indicator

channel, the alternate indication system (pulse counter or

voltage dividing network) will be used to monitor position.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. Between required performances of SR 3.1.4.4, if a CEA(s)is discovered to be immovable, but remains trippable and aligned, the CEA is

considered to be OPERABLE. At any time, if a CEA(s) is

immovable, a determination of the trippability (OPERABILITY)

of the CEA(s) must be made, and appropriate action taken.

CEA Alignment B 3.1.4 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.4-9 Revision 55 SR 3.1.4.5 Performance of a CHANNEL FUNCTIONAL TEST of each reed switch position transmitter channel ensures the channel is OPERABLE

and capable of indicating CEA position over the entire

length of the CEA's travel. A successful test of the

required contact(s) of a channel relay may be performed by the verification of the change of state of a single contact of the relay. This clarifies what is an acceptable CHANNEL

FUNCTIONAL TEST of a relay. This is acceptable because all

of the other required contacts of the relay are verified by

other Technical Specification tests at least once per

refueling interval with applicable extensions. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.1.4.6 Verification of CEA drop times determined that the maximum CEA drop time permitted is consistent with the assumed drop

time used in that safety analysis (Reference 1, Chapter 14).

Control element assembly drop time is measured from the time

when electrical power is interrupted to the CEDM until the

CEA reaches its 90% insertion position, from a fully withdrawn position, with Tave 515°F and all reactor coolant pumps operating. Measuring drop times prior to reactor

criticality, after reactor vessel head removal, ensures that

reactor internals and CEDM will not interfere with CEA

motion or drop time, and that no degradation in these

systems has occurred that would adversely affect CEA motion

or drop time. Individual CEAs whose drop times are greater

than safety analysis assumptions are not OPERABLE. This SR

is performed prior to criticality, based on the need to

perform this SR under the conditions that apply during a

unit outage and because of the potential for an unplanned

unit transient if the SR were performed with the reactor at power. REFERENCES 1. UFSAR 2. 10 CFR 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Plants"

Shutdown CEA Insertion Limits B 3.1.5 B 3.1 REACTIVITY CONTROL SYSTEMS

B 3.1.5 Shutdown Control Element Assembly (CEA) Insertion Limits

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-1 Revision 2 BACKGROUND The insertion limits of the shutdown CEAs are initial assumptions in all safety analyses that assume CEA insertion

upon reactor trip. The insertion limits directly affect

core power distributions and assumptions of available SDM, ejected CEA worth, and initial reactivity insertion rate.

The applicable criteria for these reactivity and power distribution design requirements are in Reference 1, Appendix 1C, Criteria 6, 27, 28, 29, and 30, and Reference 2. Limits on shutdown CEA insertion have been established, and all CEA positions are monitored and

controlled during power operation to ensure that the

reactivity limits, ejected CEA worth, and SDM limits are

preserved.

The shutdown CEAs are arranged into groups that are radially symmetric. Therefore, movement of the shutdown CEAs does

not introduce radial asymmetries in the core power

distribution. The shutdown and regulating CEAs provide the

required reactivity worth for immediate reactor shutdown

upon a reactor trip.

The design calculations are performed with the assumption that the shutdown CEAs are withdrawn prior to the regulating

CEAs. The shutdown CEAs can be fully withdrawn without the

core going critical. The shutdown CEAs are controlled

manually by the Control Room operator. During normal unit

operation, the shutdown CEAs are fully withdrawn. The

shutdown CEAs must be completely withdrawn from the core

prior to withdrawing any regulating CEAs during an approach

to criticality. The shutdown CEAs are left in this position until the reactor is shut down. They affect core power, burnup distribution, and add negative reactivity to shut

down the reactor upon receipt of a reactor trip signal.

Shutdown CEA Insertion Limits B 3.1.5 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-2 Revision 38 APPLICABLE Accident analysis assumes that the shutdown CEAs are fully SAFETY ANALYSES withdrawn any time the reactor is critical. This ensures that: a. The minimum SDM is maintained; and

b. The potential effects of a CEA ejection accident are limited to acceptable limits.

Control element assemblies are considered fully withdrawn at 129 inches.

On a reactor trip, all CEAs (shutdown and regulating),

except the most reactive CEA, are assumed to insert into the

core. The shutdown and regulating CEAs shall be at or above

their insertion limits and available to insert the required

amount of negative reactivity on a reactor trip signal. The

regulating CEAs may be partially inserted in the core as

allowed by LCO 3.1.6. The shutdown CEA insertion limit is

established to ensure that a sufficient amount of negative

reactivity is available to shut down the reactor and

maintain the required SDM (see LCO 3.1.1) following a

reactor trip from full power. The combination of regulating

CEAs and shutdown CEAs (less the most reactive CEA, which is

assumed to be fully withdrawn) is sufficient to take the

reactor from full power conditions at rated temperature to

zero power, and to maintain the required SDM at rated no

load temperature (Reference 1, Sections 3.2 and 3.4). The

shutdown CEA insertion limit also limits the reactivity

worth of an ejected shutdown CEA.

The acceptance criteria for addressing shutdown CEA, as well as regulating CEA insertion limits and inoperability or

misalignment, are that: a. There be no violation of:

1. SAFDLs, or 2. RCS pressure boundary damage; and b. The core remains subcritical after accident transients.

As such, the shutdown CEA insertion limits affect safety analyses involving core reactivity, ejected CEA worth, and

SDM (Reference 1, Section 14.1.2).

Shutdown CEA Insertion Limits B 3.1.5 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-3 Revision 38 The shutdown CEA insertion limits satisfy 10 CFR 50.36(c)(2)(ii), Criterion 2.

LCO The shutdown CEAs must be within their insertion limits any time the reactor is critical or approaching criticality.

This ensures that a sufficient amount of negative reactivity

is available to shut down the reactor and maintain the required SDM following a reactor trip.

APPLICABILITY The shutdown CEAs must be within their insertion limits, with the reactor in MODEs 1 and 2. The Applicability in

MODE 2 begins anytime any regulating CEA is not fully

inserted. This ensures that a sufficient amount of negative

reactivity is available to shut down the reactor and

maintain the required SDM following a reactor trip. In

MODE 3, 4, 5, or 6, the shutdown CEAs are fully inserted in

the core and contribute to the SDM. Refer to LCO 3.1.1 for

SDM requirements in MODEs 3, 4, and 5. Limiting Condition

for Operation 3.9.1 ensures adequate SDM in MODE 6.

This LCO has been modified by a Note indicating the LCO requirement is suspended during SR 3.1.4.4. This SR

verifies the freedom of the CEAs to move, and requires the

shutdown CEAs to move below the LCO limits, which would normally violate the LCO.

ACTIONS A.1 When one shutdown CEA is withdrawn 121.5 inches and

< 129 inches, the accumulated times the shutdown CEAs have been withdrawn within this range must be verified. The

Completion Time for this action is once within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> and

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> thereafter. Operation is allowed for 7 consecutive

days and a total of 14 days per 365 days. The peaking

factors may not be outside required limits when one shutdown

CEA is misaligned; therefore, continued operation is

allowed. Since the power distribution limits are being

maintained via the LCOs of Technical Specification Section 3.2, any out-of-limit peaking factor conditions will

require entry into the Actions of the appropriate

Section 3.2 LCO(s). The limits on consecutive days and

total days in this condition reflect that the core may be

approaching the acceptable limits placed on operation with Shutdown CEA Insertion Limits B 3.1.5 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-4 Revision 38 flux patterns outside those assumed in the long-term burnup assumptions. Therefore, operation in this condition cannot

continue and the CEA is required to be restored per Action

B. The accumulated times are required to be verified once

within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to determine which accumulated time limit is

more limiting. The periodic Completion Time of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after the initial completion within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> is adequate to ensure that the accumulated time limits are not exceeded.

B.1 Prior to entering this condition, the shutdown CEAs were fully withdrawn or all but one shutdown CEA was withdrawn 129 inches. If one shutdown CEA is withdrawn 121.5 inches and

< 129 inches for

> 7 days per occurrence or > 14 days per 365 days, or one shutdown CEA withdrawn

< 121.5 inches, or two or more shutdown CEAs withdrawn

< 129 inches, the out-of-limit CEAs must be restored to within limits within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. The Completion Time of

2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> reflects that the power distribution limits may be

outside required limits and that the core may be approaching

the acceptable limits placed on operation within flux

patterns outside those assumed in the long-term burnup

assumptions.

The CEA(s) must be restored to within limits within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.

The 2-hour total Completion Time allows the operator

adequate time to adjust the CEA(s) in an orderly manner.

C.1 When Required Action A.1 or B.1 cannot be met or completed within the required Completion Time, a controlled shutdown

should be commenced. The allowed Completion Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />

is reasonable, based on operating experience, for reaching

MODE 3 from full power conditions in an orderly manner and without challenging plant systems.

SURVEILLANCE SR 3.1.5.1 REQUIREMENTS Verification that the shutdown CEAs are within their insertion limits prior to an approach to criticality ensures

that when the reactor is critical, or being taken critical,

the shutdown CEAs will be available to shut down the Shutdown CEA Insertion Limits B 3.1.5 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.5-5 Revision 55 reactor, and the required SDM will be maintained following a reactor trip. This SR and Frequency ensure that the

shutdown CEAs are withdrawn before the regulating CEAs are

withdrawn during a unit startup.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

REFERENCES 1. UFSAR 2. 10 CFR 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Plants"

Regulating CEA Insertion Limits B 3.1.6 B 3.1 REACTIVITY CONTROL SYSTEMS

B 3.1.6 Regulating Control Element Assembly (CEA) Insertion Limits

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-1 Revision 43 BACKGROUND The insertion limits of the regulating CEAs are initial assumptions in all safety analyses that assume CEA insertion

upon reactor trip. The insertion limits directly affect

core power distributions, assumptions of available SDM, and initial reactivity insertion rate. The applicable criteria for these reactivity and power distribution design

requirements are Reference 1, Appendix 1C, Criteria 27, 29,

30, and 31, and Reference 2.

Limits on regulating CEA insertion have been established, and all CEA positions are monitored and controlled during

power operation to ensure that the power distribution and

reactivity limits defined by the design power peaking,

ejected CEA worth, reactivity insertion rate, and SDM limits

are preserved.

The regulating CEA groups operate with a predetermined amount of position overlap, in order to approximate a linear

relation between CEA worth and CEA position (integral CEA

worth). The regulating CEA groups are withdrawn and operate

in a predetermined sequence. The group sequence and overlap

limits are specified in the COLR. Regulating CEAs are

considered to be fully withdrawn when withdrawn to at least

129.0 inches.

The regulating CEAs are used for precise reactivity control of the reactor. The positions of the regulating CEAs are

manually controlled. They are capable of adding reactivity

very quickly (compared to borating or diluting).

The power density at any point in the core must be limited to maintain SAFDLs, including limits that preserve the criteria specified in Reference 2. Together, LCOs 3.1.6, 3.2.4, and LCO 3.2.5 provide limits on control component

operation and on monitored process variables to ensure the

core operates within the LHR (LCO 3.2.1); and Total Integrated Radial Peaking Factor (

rTF) (LCO 3.2.3) limits in the COLR. Operation within the LHR limits given in the COLR prevents power peaks that would exceed the loss of coolant

accident (LOCA) limits derived by the Emergency Core Cooling Regulating CEA Insertion Limits B 3.1.6 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-2 Revision 43 System analysis. Operation within the rTF limit given in the COLR prevents departure from nucleate boiling (DNB) during a loss of forced reactor coolant flow accident. In addition to the LHR and rTF limits, certain reactivity limits are preserved by regulating CEA insertion limits.

The regulating CEA insertion limits also restrict the

ejected CEA worth to the values assumed in the safety

analysis and preserve the minimum required SDM in MODEs 1

and 2.

The regulating CEA insertion and alignment limits are process variables that together characterize and control the

three-dimensional power distribution of the reactor core.

Additionally, the regulating bank insertion limits control

the reactivity that could be added in the event of a CEA

ejection accident, and the shutdown and regulating bank

insertion limits ensure the required SDM is maintained.

Operation within the subject LCO limits will prevent fuel cladding failures that would breach the primary fission

product barrier and release fission products to the reactor

coolant in the event of a LOCA, loss of flow, ejected CEA,

or other accident requiring termination by a Reactor Protective System trip function.

APPLICABLE The fuel cladding must not sustain damage as a result of SAFETY ANALYSES normal operation (Condition I) and AOOs (Condition II). The acceptance criteria for the regulating CEA insertion, ASI, rTF, LHR, and AZIMUTHAL POWER TILT (T q) LCOs are such as to preclude core power distributions from occurring that would violate the following fuel design criteria: a. During a large break LOCA, the peak cladding temperature must not exceed a limit of 2200°F (Reference 2); b. During a loss of forced reactor coolant flow accident, there must be at least a 95% probability at a 95%

confidence level (the 95/95 DNB criterion) that the hot

fuel rod in the core does not experience a DNB

condition; Regulating CEA Insertion Limits B 3.1.6 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-3 Revision 43 c. During an ejected CEA accident, the energy input to the fuel must not exceed accepted limits (Reference 1,

Section 14.3); and d. The CEAs must be capable of shutting down the reactor with a minimum required SDM, with the highest worth CEA

stuck fully withdrawn, Reference 1, Appendix 1C, Criterion 29.

Regulating CEA position, ASI, rTF, LHR, and T q are process variables that together characterize and control the three-dimensional power distribution of the reactor core.

Fuel cladding damage does not normally occur when the core is operated outside these LCOs during normal operation.

However, fuel cladding damage could result if an accident or

AOO occurs with simultaneous violation of one or more of these LCOs. Changes in the power distribution can cause increased power peaking and corresponding increased local

LHRs.

The SDM requirement is ensured by limiting the regulating and shutdown CEA insertion limits, so that the allowable

inserted worth of the CEAs is such that sufficient

reactivity is available to shut down the reactor to hot zero

power. SHUTDOWN MARGIN assumes the maximum worth CEA

remains fully withdrawn upon trip (Reference 1,

Section 3.4).

The most limiting SDM requirements for MODEs 1 and 2 conditions at BOC are determined by the requirements of

several transients, e.g., Loss of Flow, Seized Rotor, Boron Dilution, etc. However, the most limiting SDM requirements for MODEs 1 and 2 at EOC come from the SLB and Excess Load transients. The requirements of the SLB and Excess Load events at EOC for both the full power and no load conditions are significantly larger than those of any other event at

that time in cycle.

To verify that adequate SDMs are available throughout the cycle to satisfy the changing requirements, calculations are

performed at both BOC and EOC. It has been determined that

calculations at these two times in cycle a are sufficient

since the differences between available SDMs and the Regulating CEA Insertion Limits B 3.1.6 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-4 Revision 43 limiting SDM requirements are the smallest at these times in a cycle. The measurement of CEA bank worth performed as

part of the Startup Testing Program demonstrates that the

core has the expected shutdown capability. Consequently,

adherence to LCOs 3.1.5 and 3.1.6 provides assurance that

the available SDM at any time in a cycle will exceed the limiting SDM requirements at that time in a cycle.

Operation at the insertion limits or ASI limits may approach the maximum allowable linear heat generation rate or peaking

factor, with the allowed T q present. Operation at the insertion limit may also indicate the maximum ejected CEA

worth could be equal to the limiting value in fuel cycles

that have sufficiently high ejected CEA worths.

The regulating and shutdown CEA insertion limits ensure that safety analyses assumptions for reactivity insertion rate,

SDM, ejected CEA worth, and power distribution peaking

factors are preserved (Reference 1, Section 3.4).

The regulating CEA insertion limits satisfy 10 CFR 50.36(c)(2)(ii), Criterion 2.

LCO The limits on regulating CEAs sequence, overlap, and physical insertion, as defined in the COLR, must be

maintained because they serve the function of preserving

power distribution, ensuring that the SDM is maintained,

ensuring that ejected CEA worth is maintained, and ensuring

adequate negative reactivity insertion on trip. The overlap

between regulating banks provides more uniform rates of reactivity insertion and withdrawal and is imposed to maintain acceptable power peaking during regulating CEA

motion.

The power-dependent insertion limit (PDIL) alarm circuit is required to be OPERABLE for notification that the CEAs are

outside the required insertion limits. The PDIL alarm

circuit required to be OPERABLE receives its signal from the

reed switch position indication system. When the PDIL alarm

circuit is inoperable, the verification of CEA positions is

increased to ensure improper CEA alignment is identified before unacceptable flux distribution occurs.

Regulating CEA Insertion Limits B 3.1.6 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-5 Revision 43 APPLICABILITY The regulating CEA sequence, overlap, and physical insertion limits shall be maintained with the reactor in MODEs 1

and 2. These limits must be maintained, since they preserve

the assumed power distribution, ejected CEA worth, SDM, and

reactivity rate insertion assumptions. Applicability in

MODEs 3, 4, and 5 is not required, since neither the power distribution nor ejected CEA worth assumptions would be exceeded in these MODEs. SHUTDOWN MARGIN is preserved in

MODEs 3, 4, and 5 by adjustments to the soluble boron

concentration.

This LCO has been modified by a Note indicating the LCO requirement is suspended during SR 3.1.4.4. This SR

verifies the freedom of the CEAs to move, and requires the

regulating CEAs to move below the LCO limits, which would

normally violate the LCO.

ACTIONS A.1 and A.2 Operation beyond the transient insertion limit may result in a loss of SDM and excessive peaking factors. The transient

insertion limit should not be violated during normal

operation; this violation, however, may occur during

transients when the operator is manually controlling the

CEAs in response to changing plant conditions. When the

regulating groups are inserted beyond the transient

insertion limits, actions must be taken to either withdraw

the regulating groups beyond the limits or to reduce THERMAL

POWER to less than or equal to that allowed for the actual

CEA insertion limit. Two hours provides a reasonable time

to accomplish this, allowing the operator to deal with current plant conditions while limiting peaking factors to acceptable levels.

B.1 and B.2 If the CEAs are inserted between the long-term steady state insertion limits and the transient insertion limits for

intervals > 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period, and the short-term

steady state insertions are exceeded, peaking factors can

develop that are of immediate concern (Reference 1,

Chapter 14).

Regulating CEA Insertion Limits B 3.1.6 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-6 Revision 43 Verifying the short-term steady state insertion limits are not exceeded ensures that the peaking factors that do

develop are within those allowed for continued operation.

Fifteen minutes provides adequate time for the operator to

verify if the short-term steady state insertion limits are

exceeded.

Experience has shown that rapid power increases in areas of the core, in which the flux has been depressed, can result

in fuel damage, as the LHR in those areas rapidly increases.

Restricting the rate of THERMAL POWER increases to 5% RTP per hour, following CEA insertion beyond the long-term

steady-state insertion limits, ensures the power transients

experienced by the fuel will not result in fuel failure.

C.1 With the regulating CEAs inserted between the long-term steady state insertion limit and the transient insertion

limit, and with the core approaching the 5 EFPD per 30 EFPD

or 14 EFPD per 365 EFPD limits, the CEAs must be returned to

within the long-term steady state insertion limits, or the

core must be placed in a condition in which the abnormal

fuel burnup cannot continue. A Completion Time of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />

is allotted to return the CEAs to within the long-term

steady state insertion limits.

The required Completion Time of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> from initial discovery of a regulating CEA group outside the limits until

its restoration to within the long-term steady state limits,

shown on the figures in the COLR, allows sufficient time for

borated water to enter the RCS from the chemical addition

and makeup systems, and to cause the regulating CEAs to

withdraw to the acceptable region. It is reasonable to

continue operation for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> after it is discovered that

the 5-day or 14-day EFPD limit has been exceeded. This Completion Time is based on limiting the potential xenon redistribution, the low probability of an accident, and the

steps required to complete the action.

D.1 When the PDIL alarm circuit is inoperable, performing SR 3.1.6.1 within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and once per 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> thereafter Regulating CEA Insertion Limits B 3.1.6 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.6-7 Revision 55 ensures improper CEA alignments are identified before unacceptable flux distributions occur.

E.1 When a Required Action cannot be completed within the required Completion Time, a controlled shutdown should be commenced. The allowed Completion Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> is reasonable, based on operating experience, for reaching

MODE 3 from full power conditions in an orderly manner and without challenging plant systems.

SURVEILLANCE SR 3.1.6.1 REQUIREMENTS With the PDIL alarm circuit OPERABLE, verification of each regulating CEA group position is sufficient to detect CEA positions that may approach the acceptable limits, and to

provide the operator with time to undertake the Required

Action(s) should the sequence or insertion limits be found

to be exceeded. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.1.6.2 Verification of the accumulated time of CEA group insertion between the long-term steady state insertion limits and the

transient insertion limits ensures the cumulative time

limits are not exceeded. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.1.6.3 Demonstrating the PDIL alarm circuit OPERABLE verifies that the PDIL alarm circuit is functional. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

REFERENCES 1. UFSAR 2. 10 CFR 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Plants" 10 CFR 50.46 STE-SDM B 3.1.7 B 3.1 REACTIVITY CONTROL SYSTEMS

B 3.1.7 Special Test Exception (STE)-SHUTDOWN MARGIN (SDM)

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-1 Revision 2 BACKGROUND The primary purpose of the SDM STE is to permit relaxation of existing LCOs to allow the performance of certain PHYSICS TESTS. These tests are constructed to determine the CEA worth.

Reference 1, Appendix B,Section XI requires that a test program be established to ensure that structures, systems,

and components will perform satisfactorily in service. All

functions necessary to ensure that specified design

conditions are not exceeded during normal operation and AOOs must be tested. Testing is required as an integral part of

the design, fabrication, construction, and operation of the

power plant. Requirements for notification of the Nuclear

Regulatory Commission, for the purpose of conducting tests

and experiments, are specified in Reference 1, 10 CFR 50.59.

The key objectives of a test program (Reference 2) are to: a. Ensure that the facility has been adequately designed; b. Validate the analytical models used in design and analysis; c. Verify assumptions used for predicting plant response;

d. Ensure that installation of equipment in the facility has been accomplished in accordance with the design;

and e. Verify that operating and emergency procedures are adequate.

To accomplish these objectives, testing is required prior to initial criticality, after each refueling shutdown, and

during startup, low power operation, power ascension, and at

power operation. The PHYSICS TESTS requirements for reload

fuel cycles ensure that the operating characteristics of the core are consistent with the design predictions, and that the core can be operated as designed (Reference 3, Section 13.4).

PHYSICS TESTS procedures are written and approved in accordance with an established process. The procedures STE-SDM B 3.1.7 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-2 Revision 2 include all information necessary to permit a detailed execution of testing required to ensure that the design

intent is met. PHYSICS TESTS are performed in accordance

with these procedures, and test results are independently

reviewed prior to continued power escalation and long- term

power operation. Examples of PHYSICS TESTS include determination of critical boron concentration, CEA group worths, reactivity coefficients, flux symmetry, and core power distribution.

APPLICABLE It is acceptable to suspend certain LCOs for PHYSICS TESTS SAFETY ANALYSES because fuel damage criteria are not exceeded. Even if an accident occurs during PHYSICS TESTS with one or more LCOs

suspended, fuel damage criteria are preserved because

adequate limits on power distribution and shutdown

capability are maintained during PHYSICS TESTS.

Reference 2 defines the requirements for initial testing of the facility, including PHYSICS TESTS. Requirements for

reload fuel cycle PHYSICS TESTS are defined in the UFSAR Reference 3, Section 13.4. Although these PHYSICS TESTS are generally accomplished within the limits of all LCOs,

conditions may occur when one or more LCOs must be suspended

to make completion of PHYSICS TESTS possible or practical.

This is acceptable as long as the fuel design criteria are

not violated. As long as the LHR remains within its limit, fuel design criteria are preserved.

In this test, the following LCOs are suspended: a. LCO 3.1.1; and b. LCO 3.1.6.

Therefore, this LCO places limits on the minimum amount of CEA worth required to be available for reactivity control

when CEA worth measurements are performed.

The individual LCOs cited above govern SDM CEA group height, insertion, and alignment. Additionally, the LCOs governing RCS flow, reactor inlet temperature, and pressurizer pressure contribute to maintaining DNB parameter limits.

The initial condition criteria for accidents sensitive to

core power distribution are preserved by the LHR and DNB STE-SDM B 3.1.7 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-3 Revision 43 parameter limits. The criteria for the LOCA are specified in Reference 2, 10 CFR 50.46. The criteria for the loss of

forced reactor coolant flow accident are specified in

Reference 3, Chapter 14. Operation within the LHR limit

preserves the LOCA criteria; operation within the DNB

parameter limits preserves the loss of flow criteria.

Surveillance tests are conducted as necessary to ensure that LHR and DNB parameters remain within limits during PHYSICS

TESTS. Performance of these SRs allows PHYSICS TESTS to be

conducted without decreasing the margin of safety.

Requiring that shutdown reactivity equivalent to at least the highest estimated CEA worth (of those CEAs actually

withdrawn) be available for trip insertion from the OPERABLE

CEA provides a high degree of assurance that shutdown

capability is maintained for the most challenging postulated

accident, a stuck CEA. When LCO 3.1.1 is suspended, there

is not the same degree of assurance during this test that

the reactor would always be shut down if the highest worth

CEA was stuck out and calculational uncertainties or the

estimated highest CEA worth was not as expected (the single

failure criterion is not met). This situation is judged

acceptable, however, because SAFDLs are still met. The risk

of experiencing a stuck CEA and subsequent criticality is

reduced during this PHYSICS TESTS exception by the

Surveillance Requirements; and by ensuring that shutdown

reactivity is available, equivalent to the reactivity worth

of the estimated highest worth withdrawn CEA (Reference 3,

Chapter 3).

PHYSICS TESTS include measurement of core parameters or exercise of control components that affect process

variables. Among the process variables involved are total integrated radial peaking factor, T q and ASI, which represent initial condition input (power peaking) to the

accident analysis. Also involved are the shutdown and

regulating CEAs, which affect power peaking and are required

for shut down of the reactor. The limits for these

variables are specified for each fuel cycle in the COLR.

As described in LCO 3.0.7, compliance with STE LCOs is optional and, therefore, no criteria of 10 CFR STE-SDM B 3.1.7 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-4 Revision 43 50.36(c)(2)(ii) apply. Special Test Exception LCOs provide flexibility to perform certain operations by appropriately

modifying requirements of other LCOs. A discussion of the

criteria satisfied for the other LCOs is provided in their respective Bases.

LCO This LCO provides that a minimum amount of CEA worth is immediately available for reactivity control when CEA worth

measurement tests are performed. The STE is required to

permit the periodic verification of the actual versus

predicted worth of the regulating and shutdown CEAs. The

SDM requirements of LCO 3.1.1, the shutdown CEA insertion

limits of LCO 3.1.5, and the regulating CEA insertion limits of LCO 3.1.6 may be suspended.

APPLICABILITY This LCO is applicable in MODEs 2 and 3. Although CEA worth testing is conducted in MODE 2, sufficient negative

reactivity is inserted during the performance of these tests

to result in temporary entry into MODE 3. Because the

intent is to immediately return to MODE 2 to continue CEA

worth measurements, the STE allows limited operation to

6 consecutive hours in MODE 3, as indicated by the Note,

without having to borate to meet the SDM requirements of LCO 3.1.1.

ACTIONS A.1 With any CEA not fully inserted and less than the minimum required reactivity equivalent available for insertion, or

with all CEAs inserted and the reactor subcritical by less

than the reactivity equivalent of the highest worth CEA,

restoration of the minimum SDM requirements must be

accomplished by increasing the RCS boron concentration. The boration flow rate shall be 40 gpm and the boron concentration shall be 2300 ppm boric acid solution or equivalent. The required Completion Time of immediately is

required to meet the assumptions of the safety analysis. It

is assumed that boration will be continued until the SDM requirements are met.

STE-SDM B 3.1.7 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.7-5 Revision 55 SURVEILLANCE SR 3.1.7.1 REQUIREMENTS Verification of the position of each partially or fully withdrawn full-length or part-length CEA is necessary to

ensure that the minimum negative reactivity requirements for insertion on a trip are preserved. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.1.7.2 Prior demonstration that each CEA to be withdrawn from the core during PHYSICS TESTS is capable of full insertion, when

tripped from at least a 50% withdrawn position, ensures that

the CEA will insert on a trip signal. The Frequency ensures

that the CEAs are OPERABLE prior to reducing SDM to less

than the limits of LCO 3.1.1.

The SR is modified by a Note that allows the SR to not be performed during initial power escalation following a

refueling outage if SR 3.1.4.6 has been met during that

refueling outage. This allows the CEA drop time test, which

also proves the CEAs are trippable, to be credited for this SR. REFERENCES 1. 10 CFR Part 50 2. Regulatory Guide 1.68, Revision 2, Initial Test Programs for Water-Cooled Nuclear Power Plants,"

August 1978 3. UFSAR

STE-MODEs 1 and 2 B 3.1.8 B 3.1 REACTIVITY CONTROL SYSTEMS

B 3.1.8 Special Test Exceptions (STE)-MODEs 1 and 2 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-1 Revision 2 BACKGROUND The primary purpose of these MODEs 1 and 2 STEs is to permit relaxation of existing LCOs to allow the performance of certain PHYSICS TESTS. These tests are conducted to

determine specific reactor core characteristics.

Reference 1, Appendix B,Section XI requires that a test program be established to ensure that structures, systems,

and components will perform satisfactorily in service. All

functions necessary to ensure that specified design

conditions are not exceeded during normal operation and AOOs must be tested. Testing is required as an integral part of

the design, fabrication, construction, and operation of the

power plant. Requirements for notification of the Nuclear

Regulatory Commission, for the purpose of conducting tests

and experiments, are specified in Reference 1, 10 CFR 50.59.

The key objectives of a test program (Reference 2) are to: a. Ensure that the facility has been adequately designed; b. Validate the analytical models used in design and analysis; c. Verify assumptions used for predicting plant response;

d. Ensure that installation of equipment in the facility has been accomplished in accordance with design; and e. Verify that operating and emergency procedures are adequate.

To accomplish these objectives, testing is required prior to initial criticality, after each refueling shutdown, and

during startup, low power operation, power ascension, and at

power operation. The PHYSICS TESTS requirements for reload

fuel cycles ensure that the operating characteristics of the

core are consistent with the design predictions, and that the core can be operated as designed (Reference 3, Section 13.4).

PHYSICS TESTS procedures are written and approved in accordance with established formats. The procedures include

all information necessary to permit a detailed execution of STE-MODEs 1 and 2 B 3.1.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-2 Revision 43 testing required to ensure that design intent is met.

PHYSICS TESTS are performed in accordance with these

procedures and test results are approved prior to continued

power escalation and long-term power operation.

Examples of PHYSICS TESTS include determination of critical boron concentration, CEA group worths, reactivity

coefficients, flux symmetry, and core power distribution.

APPLICABLE It is acceptable to suspend certain LCOs for PHYSICS TESTS SAFETY ANALYSES because fuel damage criteria are not exceeded. Even if an accident occurs during a PHYSICS TESTS with one or more LCOs

suspended, fuel damage criteria are preserved because the

limits on power distribution and shutdown capability are

maintained during PHYSICS TESTS.

Reference 3, Section 13.4 defines the requirements for initial testing of the facility, including PHYSICS TESTS.

Although these PHYSICS TESTS are generally accomplished

within the limits of all LCOs, conditions may occur when one

or more LCO must be suspended to make completion of PHYSICS

TESTS possible or practical. This is acceptable as long as

the fuel design criteria are not violated. As long as the

LHR remains within its limit, fuel design criteria are

preserved.

In this test, the following LCOs are suspended: LCO 3.1.3; LCO 3.1.4; LCO 3.1.5; LCO 3.1.6; LCO 3.2.3; and LCO 3.2.4.

The safety analysis (Reference 3, Section 13.4) places limits on allowable THERMAL POWER during PHYSICS TESTS and requires the LHR and the DNB parameter to be maintained

within limits.

The individual LCOs governing CEA group height, insertion and alignment, ASI, rTF, and Tq preserve the LHR limits.

Additionally, the LCOs governing RCS flow, reactor inlet temperature (T c), and pressurizer pressure contribute to maintaining DNB parameter limits. The initial condition

criteria for accidents sensitive to core power distribution are preserved by the LHR and DNB parameter limits. The criteria for the LOCA are specified in Reference 1,

10 CFR 50.46. The criteria for the loss of forced reactor STE-MODEs 1 and 2 B 3.1.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-3 Revision 43 coolant flow accident are specified in Reference 1, 10 CFR 50.46. Operation within the LHR limit preserves the

LOCA criteria; operation within the DNB parameter limits

preserves the loss of flow criteria.

During PHYSICS TESTS, one or more of the LCOs that normally preserve the LHR and DNB parameter limits may be suspended.

The results of the accident analysis are not adversely

impacted, however, if LHR and DNB parameters are verified to

be within their limits while the LCOs are suspended.

Therefore, SRs are placed as necessary to ensure that LHR

and DNB parameters remain within limits during PHYSICS

TESTS. Performance of these SRs allows PHYSICS TESTS to be

conducted without decreasing the margin of safety.

PHYSICS TESTS include measurement of core parameters or exercise of control components that affect process variables. Among the process variables involved are rTF, Tq, and ASI, which represent initial condition input (power peaking) to the accident analysis. Also involved are the

shutdown and regulating CEAs, which affect power peaking and

are required for shut down of the reactor. The limits for

these variables are specified for each fuel cycle in the

COLR.

As described in LCO 3.0.7, compliance with STE LCOs is optional and, therefore, no criteria of 10 CFR

50.36(c)(2)(ii) apply. Special Test Exception LCOs provide

flexibility to perform certain operations by appropriately

modifying requirements of other LCOs. A discussion of the

criteria satisfied for the other LCOs is provided in their respective Bases.

LCO This LCO permits individual CEAs to be positioned outside of their normal group heights and insertion limits during the

performance of PHYSICS TESTS, such as those required to: a. Measure CEA worth;

b. Determine the reactor stability index and damping factor under xenon oscillation conditions; c. Determine power distributions for nonnormal CEA configurations; STE-MODEs 1 and 2 B 3.1.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-4 Revision 43 d. Measure rod shadowing factors; and e. Measure temperature and power coefficients.

The requirements of LCO 3.1.3, LCO 3.1.4, LCO 3.1.5, LCO 3.1.6, LCO 3.2.3, and LCO 3.2.4 may be suspended during the performance of PHYSICS TESTS, provided THERMAL POWER is restricted to test power plateau, which shall not exceed

85% RTP.

APPLICABILITY This LCO is applicable in MODEs 1 and 2 because the reactor must be critical at various THERMAL POWER levels to perform

the PHYSICS TESTS described in the LCO section. Limiting

the test power plateau to < 85% RTP ensures that LHRs are maintained within acceptable limits.

ACTIONS A.1 If THERMAL POWER exceeds the test power plateau, THERMAL POWER must be reduced to restore the additional thermal

margin provided by the reduction. The 15-minute Completion

Time ensures that prompt action shall be taken to reduce

THERMAL POWER to within acceptable limits.

B.1 and B.2 If Required Action A.1 cannot be completed within the required Completion Time, PHYSICS TESTS must be suspended within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, and the reactor must be brought to MODE 3.

Allowing 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> for suspending PHYSICS TESTS allows the

operator sufficient time to change any abnormal CEA

configuration back to within the limits of LCO 3.1.4,

LCO 3.1.5, and LCO 3.1.6. Bringing the reactor to MODE 3

within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> increases thermal margin and is consistent

with the Required Actions of the power distribution LCOs.

The required Completion Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> is adequate for

performing a controlled shutdown from full power conditions

in an orderly manner and without challenging plant systems,

and is consistent with power distribution LCO Completion Times.

STE-MODEs 1 and 2 B 3.1.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.1.8-5 Revision 55 SURVEILLANCE SR 3.1.8.1 REQUIREMENTS Verifying that THERMAL POWER is equal to or less than that allowed by the test power plateau, as specified in the

PHYSICS TESTS procedure and required by the safety analysis,

ensures that adequate LHR and DNB parameter margins are maintained while LCOs are suspended. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

REFERENCES 1. 10 CFR Part 50 2. Regulatory Guide 1.68, Revision 2, Initial Test Programs for Water-Cooled Nuclear Power Plants,"

August 1978 3. UFSAR