{{#Wiki_filter: | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511 June 11, 2015 | ||
Mr. Michael R. Chisum | Mr. Michael R. Chisum | ||
| Line 80: | Line 80: | ||
ML15162A965 SUNSI Review By: MJW ADAMS: Yes No Sensitive Non-Sensitive Non-Publicly Available Publicly Available Keyword NRC-002 OFFICE DRS/EB1/RI: C: NAME MWilliams TFarnholtz SIGNATURE /RA/ email /RA/ DATE 6/10/15 6/11/15 | |||
Letter to Michael Chisum from Thomas Farnholtz dated June 11, 2015 SUBJECT: WATERFORD STEAM ELECTRIC STATION, UNIT 3 - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND | Letter to Michael Chisum from Thomas Farnholtz dated June 11, 2015 SUBJECT: WATERFORD STEAM ELECTRIC STATION, UNIT 3 - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND | ||
PERMANENT PLANT MODIFICATIONS INSPECTION (05000382/2015007) AND REQUEST FOR INFORMATION | PERMANENT PLANT MODIFICATIONS INSPECTION (05000382/2015007) AND REQUEST FOR INFORMATION | ||
| Line 114: | Line 98: | ||
Regional Counsel (Karla.Fuller@nrc.gov) | Regional Counsel (Karla.Fuller@nrc.gov) | ||
Congressional Affairs Officer (Jenny.Weil@nrc.gov) Technical Support Assistant (Loretta.Williams@nrc.gov) RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov) | Congressional Affairs Officer (Jenny.Weil@nrc.gov) Technical Support Assistant (Loretta.Williams@nrc.gov) RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov) | ||
RIV/ETA: OEDO (Michael.Waters@nrc.gov) | RIV/ETA: OEDO (Michael.Waters@nrc.gov) | ||
}} | }} | ||
Revision as of 04:02, 11 June 2018
| ML15162A965 | |
| Person / Time | |
|---|---|
| Site: | Waterford |
| Issue date: | 06/11/2015 |
| From: | Thomas Farnholtz Region 4 Engineering Branch 1 |
| To: | Chisum M R Entergy Operations |
| M. Williams | |
| References | |
| IR 2015007 | |
| Download: ML15162A965 (6) | |
See also: IR 05000382/2015007
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511 June 11, 2015
Mr. Michael R. Chisum
Site Vice President Entergy Operations, Inc. 17265 River Road
Killona, LA 70057-0751
SUBJECT: WATERFORD STEAM ELECTRIC STATION, UNIT 3 - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS INSPECTION (05000382/2015007) AND REQUEST FOR INFORMATION
Dear Mr. Chisum:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC) staff will conduct the baseline inspection of changes, tests, experiments, and permanent plant modifications at your Waterford Steam Electric Station, Unit 3, from August 10-28, 2015. The inspection will consist of three reactor inspectors from the NRC's Region IV office for two
weeks. The inspection will be conducted in accordance with the NRC Inspection Procedure 71111.17T, "Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications."
Experience has shown that this inspection is resource intensive for both the NRC inspectors and your staff. In order to minimize the impact to your onsite resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. Please note that the documents are requested to be provided by August 3, 2015. Upon review of these documents, the inspectors will select additional documentation for review upon arrival. It is important that all of these documents are up-to-date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection. We have discussed the schedule for these inspection activities with your staff and understand
that our regulatory contact for this inspection will be Leia Milste of your licensing organization. If
there are any questions about this inspection or the material requested, please contact the lead
inspector, Megan Williams, by telephone at 817-200-1076 or by e-mail at
megan.williams@nrc.gov. This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995. (44 U.S.C. 3501 et seq.) Existing information collection
requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
M. Chisum - 2 - In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Sincerely,
/RA/
Thomas R. Farnholtz, Chief Engineering Branch 1
Division of Reactor Safety
Docket: 50-382 License: NPF-38
Enclosure: Evaluations of Changes, Tests, and Experiments
and Permanent Plant Modifications Inspection Request for Information
Electronic Distribution to Waterford Steam Electric Station, Unit 3
- 1 - Enclosure Request for Information Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications Inspection Waterford Steam Electric Station, Unit 3
Inspection Report: 05000382/2015007
Inspection Dates: August 10-28, 2015
Inspection Procedure: IP 71111.17T, "Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications" Lead Inspector: Megan Williams, Reactor Inspector
Information Requested for the In-Office Preparation Week
The following information should be sent to the Region IV office in hard copy or electronic format (preferred) by August 3, 2015, to the attention of Megan Williams. We request that you
categorize the documents in your response with the numbered list below. If only hard copies of
the requested documents are available or if the electronic format is too large, please inform the
lead inspector and provide the documents on the first day of the onsite inspection. Also, the
inspectors will select specific items from the information requested below and request from your staff additional documents needed during the onsite inspection weeks. We ask that the specific items requested be available and ready for review on the first day of inspection. If you have any questions regarding this information request, please contact the lead inspector as soon as
possible.
1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations. 2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) performed since the last triennial modification inspection that did not result in an evaluation. 3. A list with descriptions of all 10 CFR 50.59 evaluations performed the last triennial modification inspection that did not result in an application for license amendment. 4. A list with descriptions of all corrective action documents related to 10 CFR 50.59 screenings and evaluations since the last triennial modification inspection. 5. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations, including qualification dates. 6. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or evaluations, including qualification dates. 7. Procedure(s) for implementing permanent plant modifications.
- 2 - 8. A list with descriptions of all permanent plant modifications since the last triennial modification inspection. 9. A list with descriptions of all corrective action documents related to permanent plant modifications since the last triennial modification inspection. 10. Current revisions of the Technical Specifications and Bases and the Updated Final Safety Analysis Report. Note: Descriptions should be brief but of sufficient detail to ensure that inspectors can
determine the safety and/or risk significance of the screenings, evaluations, and modifications.
Note: For this inspection, permanent plant modifications include permanent plant changes, design changes, set point changes, procedure changes, equivalency evaluations, suitability analyses, calculations, and commercial grade dedications.
Inspector Contact Information:
Megan Williams Ron Kopriva Wayne Sifre
Reactor Inspector Reactor Inspector Reactor Inspector
817-200-1076 817-200-1104 817-200-1193
megan.williams@nrc.gov ron.kopriva@nrc.gov wayne.sifre@nrc.gov
Mailing Address:
U.S. NRC, Region IV Attn: Megan Williams 1600 East Lamar Blvd.
Arlington, TX 76011-4125
ML15162A965 SUNSI Review By: MJW ADAMS: Yes No Sensitive Non-Sensitive Non-Publicly Available Publicly Available Keyword NRC-002 OFFICE DRS/EB1/RI: C: NAME MWilliams TFarnholtz SIGNATURE /RA/ email /RA/ DATE 6/10/15 6/11/15
Letter to Michael Chisum from Thomas Farnholtz dated June 11, 2015 SUBJECT: WATERFORD STEAM ELECTRIC STATION, UNIT 3 - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND
PERMANENT PLANT MODIFICATIONS INSPECTION (05000382/2015007) AND REQUEST FOR INFORMATION
Distribution Regional Administrator (Marc.Dapas@nrc.gov) Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)
DRP Director (Troy.Pruett@nrc.gov)
DRP Deputy Director (Ryan.Lantz@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov) DRS Deputy Director (Jeff.Clark@nrc.gov) Senior Resident Inspector (Frances.Ramirez@nrc.gov)
Resident Inspector (Chris.Speer@nrc.gov)
WAT Administrative Assistant (Linda.Dufrene@nrc.gov)
Branch Chief, DRP/D (Geoffrey.Miller@nrc.gov) Senior Project Engineer, DRP/D (Bob.Hagar@nrc.gov) Project Engineer, DRP/D (Brian.Parks@nrc.gov)
Project Engineer, DRP/D (Jan.Tice@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Michael.Orenak@nrc.gov) Team Leader, DRS/TSS (Don.Allen@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov) Technical Support Assistant (Loretta.Williams@nrc.gov) RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)
RIV/ETA: OEDO (Michael.Waters@nrc.gov)