{{#Wiki_filter:William E. Ide                                   Mail Station 7602 Palo Verde Nuclear        Vice President               TEL (623) 393-6116 P.O. Box 52034 Generating Station        Nuclear Production            FAX (623) 393-6077 Phoenix, AZ 85072-2034 035-00704-WEI/SMM June 11,2002 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station P1-37 Washington, DC 20555
{{#Wiki_filter:Palo Verde Nuclear Generating Station William E. Ide Vice President Nuclear Production TEL (623) 393-6116 FAX (623) 393-6077 Mail Station 7602 P.O. Box 52034 Phoenix, AZ 85072-2034 035-00704-WEI/SMM June 11,2002 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station P1-37 Washington, DC 20555  


==Dear Sirs:==
==Dear Sirs:==
==Subject:==
==Subject:==
Palo Verde Nuclear Generating Station (PVNGS)
Palo Verde Nuclear Generating Station (PVNGS)
Line 25: Line 24:
By copy of this letter, Arizona Public Service Company is also forwarding the Monthly Operating Reports to the Regional Administrator, NRC Region IV and the NRC Resident Inspector.
By copy of this letter, Arizona Public Service Company is also forwarding the Monthly Operating Reports to the Regional Administrator, NRC Region IV and the NRC Resident Inspector.
If you have any questions, please contact Sue Meyer at (602) 250-3078.
If you have any questions, please contact Sue Meyer at (602) 250-3078.
Sincerely, WEI/SMM/cj
Sincerely, WEI/SMM/cj  


==Enclosures:==
==Enclosures:==
MAY 2002 Monthly Operating Reports cc:     E. W. Merschoff                             (all w/enclosures)
MAY 2002 Monthly Operating Reports cc:
J. H. Moorman INPO Records Center Utility Data Institute
E. W. Merschoff J. H. Moorman INPO Records Center Utility Data Institute (all w/enclosures)


NRC MONTHLY OPERATING DATA REPORT DOCKET NO.:             50-528 UNIT NAME:              PVNGS-1 DATE:                    06/07/02 COMPLETED BY:            S. M. Meyer TELEPHONE:              (602) 250-3078 Repo rting Period:             May 2002
NRC MONTHLY OPERATING DATA REPORT DOCKET NO.:
: 1. Design Electrical Rating (Net MWe):     1265
UNIT NAME:
: 2. Maximum Dependable Capacity (Net MWe):         1243 Unit 1 Generating Statistics                  This Month            Yr. to Date        Cumulative
DATE:
: 3. Hours Reactor was Critical                                            744.0              3,624.0        109,855.1
COMPLETED BY:
: 4. Hours Generator was On-Line                                          744.0              3,624.0        108,511.6
TELEPHONE:
: 5. Unit Reserve Shutdown Hours                                              0.0                  0.0              0.0
Repo 50-528 PVNGS-1 06/07/02 S. M. Meyer (602) 250-3078 rting Period:
: 6. Net Electrical Energy Generated (MWh)                              934,298          4,570,566        130,534,124 UNIT SHUTDOWNS Outage                     Method of Duration                Shutting Down               Cause and Corrective Action 3
May 2002
No.      Date        Type 1    Hours      Reason 2        Reactor                  to Prevent Occurrence No reactor shutdowns occurred during the month of May 2002.
: 1.
1                2 F-Forced          Reason:                                        3 Method:
Design Electrical Rating (Net MWe):
S-Scheduled        A-Equipment Failure (Explain)                     1-Manual B-Maintenance or Test                             2-Manual Trip / Scram C-Refueling                                       3-Automatic Trip / Scram D-Regulatory Restriction                         4-Continuation E-Operator Training / License Examination         5-Other-(Explain)
1265
F-Administrative G-Operational Error (Explain)
: 2.
H-Other (Explain)
Maximum Dependable Capacity (Net MWe):
: 3.
: 4.
: 5.
6.
1243 UNIT SHUTDOWNS No.
Date Outage Duration Type 1 Hours Reason 2 Method of Shutting Down Reactor3 Cause and Corrective Action to Prevent Occurrence No reactor shutdowns occurred during the month of May 2002.
2Reason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training / License Examination F-Administrative G-Operational Error (Explain)
H-Other (Explain) 3Method:
1-Manual 2-Manual Trip / Scram 3-Automatic Trip / Scram 4-Continuation 5-Other-(Explain)


==SUMMARY==
==SUMMARY==
NRC MONTHLY OPERATING DATA REPORT DOCKET NO.:             50-529 UNIT NAME:              PVNGS-2 DATE:                    06/07/02 COMPLETED BY:            S. M. Meyer TELEPHONE:              (602) 250-3078 Reporting Period:               May 2002
: Unit 1 Generating Statistics This Month Yr. to Date Cumulative Hours Reactor was Critical 744.0 3,624.0 109,855.1 Hours Generator was On-Line 744.0 3,624.0 108,511.6 Unit Reserve Shutdown Hours 0.0 0.0 0.0 Net Electrical Energy Generated (MWh) 934,298 4,570,566 130,534,124 1F-Forced S-Scheduled
: 1. Design Electrical Rating (Net MWe):     1265
 
: 2. Maximum Dependable Capacity (Net MWe):         1243 Unit 2 Generating Statistics                  This Month            Yr. To Date    ]    Cumulative
NRC MONTHLY OPERATING DATA REPORT DOCKET NO.:
: 3. Hours Reactor was Critical                                            744.0              2,874.0          108,775.5
UNIT NAME:
: 4. Hours Generator was On-Line                                          744.0              2,845.6          107,443.6
DATE:
: 5. Unit Reserve Shutdown Hours                                              0.0                  0.0                0.0
COMPLETED BY:
: 6. Net Electrical Energy Generated (MWh)                              938,659          3,548,561        130,473,072 UNIT SHUTDOWNS Outage                     Method of Duration                Shutting Down             Cause and Corrective Action 2                3 No.      Date        Type 1    Hours      Reason          Reactor                    to Prevent Occurrence No reactor shutdowns occurred during the month of May 2002.
TELEPHONE:
2                                                3 1
50-529 PVNGS-2 06/07/02 S. M. Meyer (602) 250-3078 Reporting Period:
F-Forced          Reason:                                          Method:
May 2002
S-Scheduled        A-Equipment Failure (Explain)                     1-Manual B-Maintenance or Test                             2-Manual Trip / Scram C-Refueling                                       3-Automatic Trip / Scram D-Regulatory Restriction                         4-Continuation E-Operator Training / License Examination         5-Other-(Explain)
: 1.
F-Administrative G-Operational Error (Explain)
Design Electrical Rating (Net MWe):
H-Other (Explain)
1265
: 2.
Maximum Dependable Capacity (Net MWe):
: 3.
: 4.
: 5.
6.
UNIT SHUTDOWNS Outage Duration Type 1 Hours Reason 2 Method of Shutting Down Reactor3 Cause and Corrective Action to Prevent Occurrence No reactor shutdowns occurred during the month of May 2002.
2Reason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training / License Examination F-Administrative G-Operational Error (Explain)
H-Other (Explain) 3Method:
1-Manual 2-Manual Trip / Scram 3-Automatic Trip / Scram 4-Continuation 5-Other-(Explain)


==SUMMARY==
==SUMMARY==
NRC MONTHLY OPERATING DATA REPORT DOCKET NO.:             50-530 UNIT NAME:              PVNGS-3 DATE:                    06/07/02 COMPLETED BY:            S. M. Meyer TELEPHONE:              (602) 250-3078 Reporting Period:             May 2002
: 1243 Unit 2 Generating Statistics This Month Yr. To Date ] Cumulative Hours Reactor was Critical 744.0 2,874.0 108,775.5 Hours Generator was On-Line 744.0 2,845.6 107,443.6 Unit Reserve Shutdown Hours 0.0 0.0 0.0 Net Electrical Energy Generated (MWh) 938,659 3,548,561 130,473,072 No.
: 1. Design Electrical Rating (Net MWe):     1269
Date 1 F-Forced S-Scheduled
: 2. Maximum Dependable Capacity (Net MWe):           1247 Unit 3 Generating Statistics                    This Month          Yr. to Date        Cumulative
 
: 3. Hours Reactor was Critical                                            744.0            3,624.0        105,047.7
NRC MONTHLY OPERATING DATA REPORT DOCKET NO.:
: 4. Hours Generator was On-Line                                            744.0            3,624.0          104,059.9
UNIT NAME:
: 5. Unit Reserve Shutdown Hours                                              0.0                  0.0              0.0
DATE:
: 6. Net Electrical Energy Generated (MWh)                              946,336          4,624,689        126,994,139 UNIT SHUTDOWNS Outage                     Method of Duration                Shutting Down               Cause and Corrective Action 2                3 No.      Date        Type1      Hours      Reason          Reactor                    to Prevent Occurrence No reactor shutdowns occurred during the month of May 2002.
COMPLETED BY:
2                                                3 1
TELEPHONE:
F-Forced          Reason:                                          Method:
50-530 PVNGS-3 06/07/02 S. M. Meyer (602) 250-3078 Reporting Period:
S-Scheduled        A-Equipment Failure (Explain)                     1-Manual B-Maintenance or Test                             2-Manual Trip / Scram C-Refueling                                       3-Automatic Trip / Scram D-Regulatory Restriction                         4-Continuation E-Operator Training / License Examination         5-Other-(Explain)
May 2002
F-Administrative G-Operational Error (Explain)
: 1.
H-Other (Explain)
Design Electrical Rating (Net MWe):
1269
: 2.
Maximum Dependable Capacity (Net MWe):
1247
: 3.
: 4.
: 5.
6.
UNIT SHUTDOWNS Outage Duration Type1 Hours Reason 2 Method of Shutting Down Reactor 3
Cause and Corrective Action to Prevent Occurrence No reactor shutdowns occurred during the month of May 2002.
2Reason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training / License Examination F-Administrative G-Operational Error (Explain)
H-Other (Explain) 3Method:
1-Manual 2-Manual Trip / Scram 3-Automatic Trip / Scram 4-Continuation 5-Other-(Explain)


==SUMMARY==
==SUMMARY==
                                                            }}
: Unit 3 Generating Statistics This Month Yr. to Date Cumulative Hours Reactor was Critical 744.0 3,624.0 105,047.7 Hours Generator was On-Line 744.0 3,624.0 104,059.9 Unit Reserve Shutdown Hours 0.0 0.0 0.0 Net Electrical Energy Generated (MWh) 946,336 4,624,689 126,994,139 No.
Date 1F-Forced S-Scheduled}}

Latest revision as of 17:54, 16 January 2025

May 2002 Monthly Operating Report for Palo Verde Nuclear Generating Station
ML021710157
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 06/11/2002
From: Ide W
Arizona Public Service Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
035-00704-WEI/SMM
Download: ML021710157 (4)


Text

Palo Verde Nuclear Generating Station William E. Ide Vice President Nuclear Production TEL (623) 393-6116 FAX (623) 393-6077 Mail Station 7602 P.O. Box 52034 Phoenix, AZ 85072-2034 035-00704-WEI/SMM June 11,2002 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station P1-37 Washington, DC 20555

Dear Sirs:

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Units 1, 2, and 3 Docket Nos. STN 50-528/5291530 Monthly Operating Reports for MAY 2002 Enclosed are the Monthly Operating Reports for MAY 2002, prepared and submitted pursuant to Specification 5.6.4 of Appendix A, (Technical Specifications) to the PVNGS Units 1, 2, and 3 Operating Licenses.

By copy of this letter, Arizona Public Service Company is also forwarding the Monthly Operating Reports to the Regional Administrator, NRC Region IV and the NRC Resident Inspector.

If you have any questions, please contact Sue Meyer at (602) 250-3078.

Sincerely, WEI/SMM/cj

Enclosures:

MAY 2002 Monthly Operating Reports cc:

E. W. Merschoff J. H. Moorman INPO Records Center Utility Data Institute (all w/enclosures)

NRC MONTHLY OPERATING DATA REPORT DOCKET NO.:

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

Repo 50-528 PVNGS-1 06/07/02 S. M. Meyer (602) 250-3078 rting Period:

May 2002

1.

Design Electrical Rating (Net MWe):

1265

2.

Maximum Dependable Capacity (Net MWe):

3.
4.
5.

6.

1243 UNIT SHUTDOWNS No.

Date Outage Duration Type 1 Hours Reason 2 Method of Shutting Down Reactor3 Cause and Corrective Action to Prevent Occurrence No reactor shutdowns occurred during the month of May 2002.

2Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training / License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain) 3Method:

1-Manual 2-Manual Trip / Scram 3-Automatic Trip / Scram 4-Continuation 5-Other-(Explain)

SUMMARY

Unit 1 Generating Statistics This Month Yr. to Date Cumulative Hours Reactor was Critical 744.0 3,624.0 109,855.1 Hours Generator was On-Line 744.0 3,624.0 108,511.6 Unit Reserve Shutdown Hours 0.0 0.0 0.0 Net Electrical Energy Generated (MWh) 934,298 4,570,566 130,534,124 1F-Forced S-Scheduled

NRC MONTHLY OPERATING DATA REPORT DOCKET NO.:

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

50-529 PVNGS-2 06/07/02 S. M. Meyer (602) 250-3078 Reporting Period:

May 2002

1.

Design Electrical Rating (Net MWe):

1265

2.

Maximum Dependable Capacity (Net MWe):

3.
4.
5.

6.

UNIT SHUTDOWNS Outage Duration Type 1 Hours Reason 2 Method of Shutting Down Reactor3 Cause and Corrective Action to Prevent Occurrence No reactor shutdowns occurred during the month of May 2002.

2Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training / License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain) 3Method:

1-Manual 2-Manual Trip / Scram 3-Automatic Trip / Scram 4-Continuation 5-Other-(Explain)

SUMMARY

1243 Unit 2 Generating Statistics This Month Yr. To Date ] Cumulative Hours Reactor was Critical 744.0 2,874.0 108,775.5 Hours Generator was On-Line 744.0 2,845.6 107,443.6 Unit Reserve Shutdown Hours 0.0 0.0 0.0 Net Electrical Energy Generated (MWh) 938,659 3,548,561 130,473,072 No.

Date 1 F-Forced S-Scheduled

NRC MONTHLY OPERATING DATA REPORT DOCKET NO.:

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

50-530 PVNGS-3 06/07/02 S. M. Meyer (602) 250-3078 Reporting Period:

May 2002

1.

Design Electrical Rating (Net MWe):

1269

2.

Maximum Dependable Capacity (Net MWe):

1247

3.
4.
5.

6.

UNIT SHUTDOWNS Outage Duration Type1 Hours Reason 2 Method of Shutting Down Reactor 3

Cause and Corrective Action to Prevent Occurrence No reactor shutdowns occurred during the month of May 2002.

2Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training / License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain) 3Method:

1-Manual 2-Manual Trip / Scram 3-Automatic Trip / Scram 4-Continuation 5-Other-(Explain)

SUMMARY

Unit 3 Generating Statistics This Month Yr. to Date Cumulative Hours Reactor was Critical 744.0 3,624.0 105,047.7 Hours Generator was On-Line 744.0 3,624.0 104,059.9 Unit Reserve Shutdown Hours 0.0 0.0 0.0 Net Electrical Energy Generated (MWh) 946,336 4,624,689 126,994,139 No.

Date 1F-Forced S-Scheduled