{{#Wiki_filter: | {{#Wiki_filter: UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 February 11, 2013 Mr. William R. Gideon Vice President | ||
Progress Energy | |||
H. B. Robinson Steam Electric Plant, Unit 2 | |||
Mr. William Vice President Progress Energy H. B. Robinson Steam Electric Plant, Unit 2 3581 West Entrance Rd Hartsville, SC 29550 | 3581 West Entrance Rd | ||
Hartsville, SC 29550 SUBJECT: H. B. ROBINSON STEAM ELECTRIC PLANT - NOTIFICATION OF LICENSED | |||
SUBJECT: H. B. ROBINSON STEAM ELECTRIC PLANT - NOTIFICATION OF LICENSED OPERATOR INITIAL EXAMINATION 05000261/2013301 | OPERATOR INITIAL EXAMINATION 05000261/2013301 | ||
Dear Mr. Gideon: In a telephone conversation on January 30, 2013, between Mr. Jeffery L. Smith, Senior | |||
In a telephone conversation on January 30, 2013, between Mr. Jeffery L. Smith, Senior Operations Instructor, and Mr. Richard S. Baldwin, Chief Examiner, arrangements were made for the administration of licensing examinations at H. B. Robinson Steam Electric Plant. The operating test is scheduled to be administered during the week July 29, 2013. The written examination is scheduled to be administered the week of August 5, 2013. The on-site preparatory week is scheduled for the week of July 8, 2013. | Operations Instructor, and Mr. Richard S. Baldwin, Chief Examiner, arrangements were made for the administration of licensing examinations at H. B. Robinson Steam Electric Plant. The operating test is scheduled to be administered during the week July 29, 2013. The written examination is scheduled to be administered the week of August 5, 2013. The on-site preparatory week is scheduled for the week of July 8, 2013. | ||
As agreed during the telephone conversation meeting, your staff will prepare both the operating test and written examination based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The U.S. Nuclear Regulatory Commission (NRC) regional office will discuss with your staff any changes that might be necessary before the examinations are administered. Your staff has also agreed to make copies of all examination materials that are necessary for administering the examination. | As agreed during the telephone conversation meeting, your staff will prepare both the operating | ||
test and written examination based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The U.S. Nuclear Regulatory Commission (NRC) regional office will discuss with your staff any changes that might be necessary before the examinations are administered. Your staff has also agreed to make copies of all examination materials that are necessary for administering the examination. | |||
To meet the above schedule, it will be necessary for your staff to furnish the operating test outline by May 15, 2013. Mr. Baldwin will provide a written examination outline to your staff by February 8, 2013. The operating test, written examination, and the supporting reference materials identified in Attachment 3 to ES-201 will be due by June 14, 2013. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized representative of the facility licensee shall approve the outline, examination, and test before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use. | |||
To meet the above schedule, it will be necessary for your staff to furnish the operating test outline by May 15, 2013. Mr. Baldwin will provide a written examination outline to your staff by February 8, 2013. The operating test, written examination, and the supporting reference | |||
We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Any delay in receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled. In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final. | materials identified in Attachment 3 to ES-201 will be due by June 14, 2013. Pursuant to Title | ||
10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized | |||
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered. To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications, medical certifications, and waiver requests (if any) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date. | representative of the facility licensee shall approve the outline, examination, and test before | ||
they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use. | |||
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget (OMB) under approval number 3150-0018, which expires on February 28, 2013. The public reporting burden for this collection of information is estimated to average 500 hours per response, including the time for reviewing instructions, gathering and maintaining the data needed, writing the examinations, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503. | We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Any delay in | ||
receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled. | |||
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number. | W. Gideon 2 In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and | ||
to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final. | |||
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the Public Electronic Reading Room). Thank you for your cooperation in this matter. Mr. Smith has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Baldwin at (404) 997-4642, (Internet E-mail: Richard.Baldwin@nrc.gov), or me at (404) 997-4436, (Internet E-mail: Mark.Franke@nrc.gov). | |||
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered. To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications, medical certifications, and waiver | |||
Sincerely,/RA/ Mark E. Franke, Chief Operations Branch 2 Division of Reactor Safety Docket No.: 50-261 License No.: DPR-23 | requests (if any) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date. | ||
cc: (See Page 4) Thank you for your cooperation in this matter. Mr. Smith has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Baldwin at (404) 997-4642, (Internet E-mail: Richard.Baldwin@nrc.gov), or me at (404) 997-4436, (Internet E-mail: Mark.Franke@nrc.gov). | This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget (OMB) under approval number 3150-0018, which expires on February 28, 2013. The public reporting burden for this collection of information is estimated to average | ||
500 hours per response, including the time for reviewing instructions, gathering and maintaining | |||
Sincerely,/RA/ Mark E. Franke, Chief Operations Branch 2 Division of Reactor Safety Docket No.: 50-261 License No.: DPR-23 | the data needed, writing the examinations, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including | ||
suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer, Office of Information | |||
and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, | |||
Washington, DC 20503. | |||
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number. | |||
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its | |||
enclosures will be available electronically for public inspection in the NRC Public Document | |||
Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the Public Electronic Reading Room). | |||
W. Gideon 3 Thank you for your cooperation in this matter. Mr. Smith has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Baldwin at (404) 997-4642, (Internet E-mail: Richard.Baldwin@nrc.gov), or me at (404) 997-4436, (Internet E-mail: Mark.Franke@nrc.gov). Sincerely, | |||
/RA/ Mark E. Franke, Chief | |||
Operations Branch 2 | |||
Division of Reactor Safety Docket No.: 50-261 License No.: DPR-23 | |||
cc: (See Page 4) | |||
W. Gideon 3 Thank you for your cooperation in this matter. Mr. Smith has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Baldwin at (404) 997-4642, (Internet E-mail: Richard.Baldwin@nrc.gov), or me at (404) 997-4436, (Internet E-mail: Mark.Franke@nrc.gov). Sincerely, | |||
/RA/ Mark E. Franke, Chief | |||
Operations Branch 2 | |||
Division of Reactor Safety Docket No.: 50-261 License No.: DPR-23 | |||
cc: (See Page 4) | cc: (See Page 4) | ||
xG PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE xG NON-SENSITIVE ADAMS: xG Yes ACCESSION NUMBER:_________________________ xG SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRS RII:DRS SIGNATURE RA RA NAME BALDWIN FRANKE DATE 2/11/2013 2/11/2013 2/ /2013 2/ /2013 2/ /2013 2/ /2013 2/ /2013 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: G:\OLEXAMS\ROBINSON EXAMINATIONS\INITIAL EXAM - 2013-301\ROBINSON 2103-301 INITIAL EXAM 120 DAY LETTER (RSB).DOCX | |||
W. Gideon 4 cc: Division of Radiological Health | |||
TN Dept. of Environment & Conservation 401 Church Street Nashville, TN 37243-1532 | |||
Donald W. Barker | |||
Manager, Nuclear Oversight | |||
H. B. Robinson Steam Electric Plant, Unit 2 Progress Energy Electronic Mail Distribution | |||
J. W. (Bill) Pitesa | |||
Senior Vice President Nuclear Operations Duke Energy Corporation | |||
Electronic Mail Distribution | |||
Lara S. Nichols Deputy General Counsel Duke Energy Corporation | |||
Electronic Mail Distribution | |||
M. Christopher Nolan | |||
Director - Regulatory Affairs General Office Duke Energy Corporation | |||
Electronic Mail Distribution | |||
Mike Glover Director Site Operations H. B. Robinson Steam Electric Plant | |||
Electronic Mail Distribution | |||
Richard Keith Holbrook | |||
Operations Manager H. B. Robinson Steam Electric Plant Electronic Mail Distribution | |||
Sandra Threatt, Manager | |||
Nuclear Response and Emergency Environmental Surveillance Bureau of Land and Waste Management | |||
Department of Health and Environmental | |||
Control | |||
Electronic Mail Distribution | |||
Sharon Wheeler Manager, Support Services | |||
H B Robinson Steam Electric Plant | |||
Electronic Mail Distribution Brian C. McCabe | |||
Manager, Nuclear Oversight Shearon Harris Nuclear Power Plant Progress Energy | |||
Electronic Mail Distribution | |||
Richard Hightower | |||
Supervisor Licensing/Regulatory Programs Progress Energy | |||
Electronic Mail Distribution | |||
Joseph W. Donahue Vice President Nuclear Oversight | |||
Progress Energy | |||
Electronic Mail Distribution | |||
David T. Conley Senior Counsel | |||
Legal Department | |||
Progress Energy | |||
Electronic Mail Distribution | |||
John H. O'Neill, Jr. Shaw, Pittman, Potts & Trowbridge | |||
2300 N. Street, NW | |||
Washington, DC 20037-1128 | |||
Richard Haynes Director, Division of Waste Management | |||
Bureau of Land and Waste Management | |||
S.C. Department of Health and | |||
Environmental Control | |||
Electronic Mail Distribution Thomas Cosgrove | |||
Plant General Manager | |||
H.B. Robinson Steam Electric Plant, Unit 2 | |||
Progress Energy Electronic Mail Distribution | |||
Donna B. Alexander | |||
Manager, Nuclear Regulatory Affairs | |||
(interim) | |||
Progress Energy Electronic Mail Distribution | |||
(cc cont'd - See Page 5) | |||
W. Gideon 5 (cc cont'd) Robert P. Gruber | |||
Executive Director Public Staff - NCUC 4326 Mail Service Center | |||
Raleigh, NC 27699-4326 | |||
W. Lee Cox, III | |||
Section Chief Radiation Protection Section N.C. Department of Environmental | |||
Commerce & Natural Resources | |||
Electronic Mail Distribution | |||
Greg Kilpatrick Operations Manager | |||
H.B. Robinson Steam Electric Plant, Unit 2 | |||
Progress Energy | |||
Electronic Mail Distribution Mark Yeager | |||
Division of Radioactive Waste Mgmt. | |||
S.C. Department of Health and | |||
Environmental Control | |||
Electronic Mail Distribution Public Service Commission | |||
State of South Carolina | |||
P.O. Box 11649 | |||
Columbia, SC 29211 Chairman | |||
North Carolina Utilities Commission | |||
Electronic Mail Distribution | |||
Henry Curry Training Manager H.B. Robinson Steam Electric Plant, Unit 2 | |||
Progress Energy | |||
Electronic Mail Distribution | |||
Senior Resident Inspector U.S. Nuclear Regulatory Commission | |||
H. B. Robinson Steam Electric Plant | |||
2112 Old Camden Rd | |||
Hartsville, SC 29550 | |||
Christos Kamilaris Manager, Support Services | |||
H.B. Robinson Steam Electric Plant, Unit 2 Progress Energy Electronic Mail Distribution | |||
John W. Flitter | |||
Director of Electric & Gas Regulation | |||
South Carolina Office of Regulatory Staff Electronic Mail Distribution | |||
Letter to William R. Gideon from Mark E. Franke dated February 11, 2013. | |||
SUBJECT: H. B. ROBINSON STEAM ELECTRIS PLANT - NOTIFICATION OF LICENSED OPERATOR INITIAL EXAMINATION 05000261/2013301 | |||
Distribution: RIDSNRRDIRS | |||
PUBLIC | |||
RidsNrrPMRobinson Resource | |||
}} | }} |
Revision as of 07:19, 28 March 2018
ML13045A843 | |
Person / Time | |
---|---|
Site: | Robinson |
Issue date: | 02/11/2013 |
From: | Franke M E Division of Reactor Safety II |
To: | Gideon W R Progress Energy Co |
References | |
Download: ML13045A843 (7) | |
See also: IR 05000261/2013301
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 February 11, 2013 Mr. William R. Gideon Vice President
Progress Energy
H. B. Robinson Steam Electric Plant, Unit 2
3581 West Entrance Rd
Hartsville, SC 29550 SUBJECT: H. B. ROBINSON STEAM ELECTRIC PLANT - NOTIFICATION OF LICENSED
OPERATOR INITIAL EXAMINATION 05000261/2013301
Dear Mr. Gideon: In a telephone conversation on January 30, 2013, between Mr. Jeffery L. Smith, Senior
Operations Instructor, and Mr. Richard S. Baldwin, Chief Examiner, arrangements were made for the administration of licensing examinations at H. B. Robinson Steam Electric Plant. The operating test is scheduled to be administered during the week July 29, 2013. The written examination is scheduled to be administered the week of August 5, 2013. The on-site preparatory week is scheduled for the week of July 8, 2013.
As agreed during the telephone conversation meeting, your staff will prepare both the operating
test and written examination based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The U.S. Nuclear Regulatory Commission (NRC) regional office will discuss with your staff any changes that might be necessary before the examinations are administered. Your staff has also agreed to make copies of all examination materials that are necessary for administering the examination.
To meet the above schedule, it will be necessary for your staff to furnish the operating test outline by May 15, 2013. Mr. Baldwin will provide a written examination outline to your staff by February 8, 2013. The operating test, written examination, and the supporting reference
materials identified in Attachment 3 to ES-201 will be due by June 14, 2013. Pursuant to Title
10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized
representative of the facility licensee shall approve the outline, examination, and test before
they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Any delay in
receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled.
W. Gideon 2 In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and
to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final.
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered. To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications, medical certifications, and waiver
requests (if any) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget (OMB) under approval number 3150-0018, which expires on February 28, 2013. The public reporting burden for this collection of information is estimated to average
500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time for reviewing instructions, gathering and maintaining
the data needed, writing the examinations, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including
suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer, Office of Information
and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget,
Washington, DC 20503.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
enclosures will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the Public Electronic Reading Room).
W. Gideon 3 Thank you for your cooperation in this matter. Mr. Smith has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Baldwin at (404) 997-4642, (Internet E-mail: Richard.Baldwin@nrc.gov), or me at (404) 997-4436, (Internet E-mail: Mark.Franke@nrc.gov). Sincerely,
/RA/ Mark E. Franke, Chief
Operations Branch 2
Division of Reactor Safety Docket No.: 50-261 License No.: DPR-23
cc: (See Page 4)
W. Gideon 3 Thank you for your cooperation in this matter. Mr. Smith has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Baldwin at (404) 997-4642, (Internet E-mail: Richard.Baldwin@nrc.gov), or me at (404) 997-4436, (Internet E-mail: Mark.Franke@nrc.gov). Sincerely,
/RA/ Mark E. Franke, Chief
Operations Branch 2
Division of Reactor Safety Docket No.: 50-261 License No.: DPR-23
cc: (See Page 4)
xG PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE xG NON-SENSITIVE ADAMS: xG Yes ACCESSION NUMBER:_________________________ xG SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRS RII:DRS SIGNATURE RA RA NAME BALDWIN FRANKE DATE 2/11/2013 2/11/2013 2/ /2013 2/ /2013 2/ /2013 2/ /2013 2/ /2013 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: G:\OLEXAMS\ROBINSON EXAMINATIONS\INITIAL EXAM - 2013-301\ROBINSON 2103-301 INITIAL EXAM 120 DAY LETTER (RSB).DOCX
W. Gideon 4 cc: Division of Radiological Health
TN Dept. of Environment & Conservation 401 Church Street Nashville, TN 37243-1532
Donald W. Barker
Manager, Nuclear Oversight
H. B. Robinson Steam Electric Plant, Unit 2 Progress Energy Electronic Mail Distribution
J. W. (Bill) Pitesa
Senior Vice President Nuclear Operations Duke Energy Corporation
Electronic Mail Distribution
Lara S. Nichols Deputy General Counsel Duke Energy Corporation
Electronic Mail Distribution
M. Christopher Nolan
Director - Regulatory Affairs General Office Duke Energy Corporation
Electronic Mail Distribution
Mike Glover Director Site Operations H. B. Robinson Steam Electric Plant
Electronic Mail Distribution
Richard Keith Holbrook
Operations Manager H. B. Robinson Steam Electric Plant Electronic Mail Distribution
Sandra Threatt, Manager
Nuclear Response and Emergency Environmental Surveillance Bureau of Land and Waste Management
Department of Health and Environmental
Control
Electronic Mail Distribution
Sharon Wheeler Manager, Support Services
H B Robinson Steam Electric Plant
Electronic Mail Distribution Brian C. McCabe
Manager, Nuclear Oversight Shearon Harris Nuclear Power Plant Progress Energy
Electronic Mail Distribution
Richard Hightower
Supervisor Licensing/Regulatory Programs Progress Energy
Electronic Mail Distribution
Joseph W. Donahue Vice President Nuclear Oversight
Progress Energy
Electronic Mail Distribution
David T. Conley Senior Counsel
Legal Department
Progress Energy
Electronic Mail Distribution
John H. O'Neill, Jr. Shaw, Pittman, Potts & Trowbridge
2300 N. Street, NW
Washington, DC 20037-1128
Richard Haynes Director, Division of Waste Management
Bureau of Land and Waste Management
S.C. Department of Health and
Environmental Control
Electronic Mail Distribution Thomas Cosgrove
Plant General Manager
H.B. Robinson Steam Electric Plant, Unit 2
Progress Energy Electronic Mail Distribution
Donna B. Alexander
Manager, Nuclear Regulatory Affairs
(interim)
Progress Energy Electronic Mail Distribution
(cc cont'd - See Page 5)
W. Gideon 5 (cc cont'd) Robert P. Gruber
Executive Director Public Staff - NCUC 4326 Mail Service Center
Raleigh, NC 27699-4326
W. Lee Cox, III
Section Chief Radiation Protection Section N.C. Department of Environmental
Commerce & Natural Resources
Electronic Mail Distribution
Greg Kilpatrick Operations Manager
H.B. Robinson Steam Electric Plant, Unit 2
Progress Energy
Electronic Mail Distribution Mark Yeager
Division of Radioactive Waste Mgmt.
S.C. Department of Health and
Environmental Control
Electronic Mail Distribution Public Service Commission
State of South Carolina
P.O. Box 11649
Columbia, SC 29211 Chairman
North Carolina Utilities Commission
Electronic Mail Distribution
Henry Curry Training Manager H.B. Robinson Steam Electric Plant, Unit 2
Progress Energy
Electronic Mail Distribution
Senior Resident Inspector U.S. Nuclear Regulatory Commission
H. B. Robinson Steam Electric Plant
2112 Old Camden Rd
Hartsville, SC 29550
Christos Kamilaris Manager, Support Services
H.B. Robinson Steam Electric Plant, Unit 2 Progress Energy Electronic Mail Distribution
John W. Flitter
Director of Electric & Gas Regulation
South Carolina Office of Regulatory Staff Electronic Mail Distribution
Letter to William R. Gideon from Mark E. Franke dated February 11, 2013.
SUBJECT: H. B. ROBINSON STEAM ELECTRIS PLANT - NOTIFICATION OF LICENSED OPERATOR INITIAL EXAMINATION 05000261/2013301
Distribution: RIDSNRRDIRS
PUBLIC
RidsNrrPMRobinson Resource